HomeMy WebLinkAbout19-09-C AGEE CONSTRUCTION CORP CCO 2.pdfCOUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO CANAL AT MCKINLEY AVENUE CHANGE ORDER NO. 02 BRIDGE REPLACMENT NOVEMBER 30, 2020 FEDERAL PROJECT NUMBER: BRLO-5942 (225) PAGE 1 OF 3 CONTRACT NO. 19-09-C __ Contractor __ Auditor Controller __ Business Office __ Board __ Const. Management __ RE/Arch. __ Design We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above. If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. TO: AGEE CONSTRUCTION CORPORATION.: Make the following changes to the plans and specifications or do the following work not included in the plans and specifications for this contract. Because of the change(s), ZERO WORKING DAYS will be added to the contract time. PART I: MODIFY SECTION 72-5.01 OF THE STANDARD SPECIFICATIONS Replace the second paragraph of Section 72-5.01 Slope Protection Standard Specifications with: Construct slope protection, gutter lining, and channel lining using shotcrete. This change does not impact the critical path for the project, so granting additional contract time was not warranted. TOTAL COST PART I: $0.00 (NO COST) TOTAL TIME EXTENSION PART I: ZERO WORKING DAYS PART II: MODIFY -ON PLAN SHEET NUMBER S-8 Replace Detail Section D-D, on Plan Sheet No. S-8 with Fresno Irrigation District (FID) Standard Detail 2-01 (attached) in order to incorporate construction joints and water stops at FID s request according to Section 4-1.05, Changes and Extra Work, of the Standard Specifications. Payment for this work will be made as extra work at an agreed lump sum price of $4,313.71 according to Section 9-1.03, Payment Scope, of the Special Provisions. This work did not impact the critical path for the project, so granting additional contract time was not warranted. TOTAL COST PART II: A $4,313.71 INCREASE TOTAL TIME EXTENSION PART II: ZERO WORKING DAYS COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO CANAL AT MCKINLEY AVENUE CHANGE ORDER NO. 02 BRIDGE REPLACMENT NOVEMBER 30, 2020 FEDERAL PROJECT NUMBER: BRLO-5942 (225) PAGE 2 OF 3 CONTRACT NO. 19-09-C __ Contractor __ Auditor Controller __ Business Office __ Board __ Const. Management __ RE/Arch. __ Design We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above. If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. PART III: INCREASE/DECREASE/ELIMINATE CONTRACT ITEMS AT UNIT PRICES Bid Item quantities in the Special Provisions are estimates only. This Part adjusts items to the actual quantities used. Increased Items: Item No. Description Unit Quantity Unit Price Total Amount (%) 44 Thick) LF 17.00 $300.00 $5,100.00 10.18 TOTAL INCREASE: $5,100 Decreased Items: Item No. Description Unit Quantity Unit Price Total Amount (%) 5 State Water Resources Control Board N.O.I. Fee LS 1.00 $516.00 $516.00 51.60 TOTAL DECREASE: $516 Eliminated Items: Item No.Description Unit Quantity Unit Price Total Amount (%) 46 Tapered Inlet EA 2.00 $400.00 $800.00 100.00 TOTAL DECREASE: $ 800.00 This change does not impact the critical path for the project, so granting additional contract time was not warranted. TOTAL COST PART III: A $3,784 INCREASE TOTAL TIME EXTENSION PART III: ZERO WORKING DAYS NET COST THIS CHANGE ORDER: AN $8,097.71 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO WORKING DAYS COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO CANAL AT MCKINLEY AVENUE CHANGE ORDER NO. 02 BRIDGE REPLACMENT NOVEMBER 30, 2020 FEDERAL PROJECT NUMBER: BRLO-5942 (225) PAGE 3 OF 3 CONTRACT NO. 19-09-C __ Contractor __ Auditor Controller __ Business Office __ Board __ Const. Management __ RE/Arch. __ Design We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above. If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. SUBMITTED BY: Jason Ahumada, Resident Engineer ACCEPTED BY: APPROVAL RECOMMENDED: By: AGEE CONSTRUCTION CORP. Steve Deis, GE Contractor Construction Engineer Title: AUTHORIZED FOR PAYMENT BY: Accepted Date: _______________________ Steven E. White, Director Public Works and Planning Date: