SCHEDULE
The schedule below is conceptual in nature. There are many variables outside of our
control that could impact the schedule, however a general schedule is provided.
Task Description Week of
Completion
1.Project Initiation / Review / Description 2
2.Public Scoping Process (NOP)
30 day public review
4
5-9
3.Admin Draft EIR
County review of Draft EIR
45-day public review
10
TBD
TBD
4.Final EIR TBD
5.Findings / SOC / Admin Record TBD