HomeMy WebLinkAbout19-05-C AGEE CONSTRUCTION CORP CCO 2.pdfCOUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
OUTSIDE CANAL ON RUSSELL AVENUE CHANGE ORDER NO. 02
BRIDGE REPLACEMENT JUNE 10, 2020
FEDERAL PROJECT NUMBER: BRLS-5942 (195) PAGE 1 OF 4
CONTRACT NO. 19-05-C
__ Contractor
__ Auditor Controller
__ Business Office
__ Board
__ Const. Management
__ RE/Arch
__ Design.
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
TO: AGEE CONSTRUCTION CORPORATION:
Make the following changes to the plans and specifications or do the following work not included in the plans
and specifications for this contract.
PART I: INCREASE, DECREASE, AND ELIMINATE BID ITEMS AT UNIT PRICES
Increased Items:
Item
No. Quantity Unit (%) Description
Unit Price Total
Amount
Total
%
20 149.14 CY 13.81 Roadway Excavation
(Temporary Detour Roadway)
$155.00 $23,116.70 13.81
25 12.50 CY 25.00 Excavation (Soft Spots –
Permanent Roadway)
$105.00 $1,312.50 25.00
41 666.75 SY 30.58 Geogrid Soil Reinforcing
(Temporary Overburden and
Drainage)
$6.80 $4,533.90 30.58
44 48.50 TON 1.52 Aggregate Sub-Base
(Permanent Roadway)
$27.00 $1,309.50 1.52
46 166.50 TON 7.33 Aggregate Base (Permanent
Roadway)
$32.00 $5,328.00 7.33
48 114.24 TON 7.89 Asphalt Concrete (Type A –
Permanent Roadway)
$100.00 $11,424.00 7.89
52 58.00 LF 22.92 Asphalt Concrete Dike (Type
C)
$15.00 $870.00 22.92
62 2.00 LF 4.35 24” RGRCP – CLASS III $240.00 $480.00 4.35
64 9.00 SY 0.81 Geocomposite Drainage
Blanket
$24.00 $216.00 0.81
66 6.00 LF 7.14 10” Flume Downdrains $36.00 $216.00 7.14
75 118.00 SY 12.33 RSP Fabric (Outside Canal
Modifications)
$6.00 $708.00 12.33
TOTAL INCREASE: $49,514.60
Decreased Items:
Item
No. Quantity Unit (%) Description @ Price
Total
Amount
Total
%
2 20,632.40 $ 206.32 Supplemental Work (Payment
Adjustments for Price Index
$1.00 $20,632.40 -206.32
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
OUTSIDE CANAL ON RUSSELL AVENUE CHANGE ORDER NO. 02
BRIDGE REPLACEMENT JUNE 10, 2020
FEDERAL PROJECT NUMBER: BRLS-5942 (195) PAGE 2 OF 4
CONTRACT NO. 19-05-C
__ Contractor
__ Auditor Controller
__ Business Office
__ Board
__ Const. Management
__ RE/Arch
__ Design.
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
Fluctuations)
18 296.00 SY 41.69 HDPE Canal Liner $40.00 $11,840.00 -41.69
28 102.67 CY 7.39 Structure Excavation
(Retaining Wall)
$12.00 $1,232.04 -7.39
29 21.00 CY 7.19 Controlled Low Strength
Material
$205.00 $4,305.00 -66.13
40 634.00 SY 33.90 Geogrid Soil Reinforcing
(Temporary Detour Roadway)
$6.50 $4,121.00 -33.90
49 2.50 TON 22.73 Minor Hot Mix Asphalt $200.00 $500.00 -22.73
54 0.15 TON 15.00 Tack Coat $2,500.00 $375.00 -15.00
55 7.00 CY 2.59 Structural Concrete, Retaining
Wall
$780.00 $5,460.00 -2.59
59 3,597.14 LB 12.28 Bar Reinforcing Steel
(Retaining Wall)
$2.00 $7,194.28 -12.28
65 4,210.00 LF 10.85 Drainage Wick $2.50 $10,525.00 -10.85
74 40.00 SY 22.22 RSP (Irrigation Canal
Modifications)
$9.00 $360.00 -22.00
79 2.00 LF 1.45 Concrete Barrier (Type 60D) $170.00 $340.00 -1.45
80 376.00 LF 6.62 Paint Traffic Stripe $2.50 $940.00 -6.62
TOTAL DECREASE: $67,824.72
Bid Item No. 2 – Supplemental Work (Payment Adjustments for Price Index Fluctuations) is not
subject to the requirements in Section 9-1.06, “Changed Quantity Pay Adjustment,” of the Standard
Specifications, according to Section 9-1.24, “Supplemental Work (Payment Adjustments for Price
Index Fluctuations),” of the Special Provisions. According to Section 9-1.07, “Payment Adjustments
for Price Index Fluctuations,” of the Special Provisions and Standard Specifications, Bid Item No. 2,
“Supplemental Work (Payment Adjustments for Price Index Fluctuations),” will be reduced to reflect
the fluctuation in the California Statewide Crude Oil Index between the bid month and the month
asphalt products were used on the project.
Bid Item No. 18 – HDPE Canal Liner decreased by 41.69 percent because the temporary detours were
not constructed (included in Contract Change Order No.1). The contractor did not make a request for
adjustment to the unit price and the actual quantities were paid at the unit price at bid opening, resulting
in a decrease of $11,840.
Bid Item No. 41 – Geogrid Soil Reinforcing (Temporary Overburden and Drainage), increased by
30.58 percent to reflect the actual quantity placed. The increased quantity in excess of 125 percent of
the estimated quantity results in $827.90. Since the quantity in excess of 125 percent results in less
than $5,000, no adjustment to the unit bid price is made according to Section 9-1.06, “Changed
Quantity Payment Adjustments,” of the Standard Specifications. You did not request a price
adjustment.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
OUTSIDE CANAL ON RUSSELL AVENUE CHANGE ORDER NO. 02
BRIDGE REPLACEMENT JUNE 10, 2020
FEDERAL PROJECT NUMBER: BRLS-5942 (195) PAGE 3 OF 4
CONTRACT NO. 19-05-C
__ Contractor
__ Auditor Controller
__ Business Office
__ Board
__ Const. Management
__ RE/Arch
__ Design.
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
These changes do not affect the controlling activity. No time adjustment is warranted.
TOTAL COST PART I: A $18,310.12 DECREASE
TOTAL TIME EXTENSION PART I: ZERO WORKING DAYS
PART II: REMOVE ADDITIONAL SOFT SPOTS IN THE PERMANENT ROADWAY SUBBGRADE –
EXTRA WORK
The estimated quantity at bid opening for bid item No. 25, “Excavation (Soft Spots - Permanent
Roadway),” was 50 cubic yards; and a total volume of 340.80 cubic yards was excavated. Up to 125
percent of the bid quantity (62.50 cubic yards) is paid at the unit price of $105. According to Section 9-
1.06B, “Increases of More Than 25 Percent,” of the Standard Specifications, the quantity in excess of
125 percent of the bid quantity (278.30 cubic yard) is being paid as extra work at an adjusted unit price
of $8.26 (for labor and equipment only) determined according to Section 9-1.04, “Force Account,” of the
Standard Specifications. Materials are paid through bid item Nos. 22 and/or 34 The additional payment
is (278.30 cubic yard x $8.26 per cubic yard) $2,298.76. This amount will be paid as extra work.
These changes do not affect the controlling activity. No time adjustment is warranted.
TOTAL COST PART II: A $2,298.76 INCREASE
TOTAL TIME EXTENSION PART II: ZERO WORKING DAYS
PART III: ADJUST CONTRACT TIME
Six working days are added to the contract time for unsuitable weather conditions due to rain/wet subgrade
according to Section 8-1.07B, “Time Adjustments,” of the Special Provisions.
Weather Day Extension Summary
Weather Days Jan 9, 2020 1 working day
Jan 16, 2020 1 working day
Mar 16, 2020 1 working day
Mar 25, 2020 1 working day
Apr 6, 2020 1 working day
Apr 9, 2020 1 working day
Total Weather Days 6 working days
TOTAL COST PART III: $0.00 (NO COST)
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
OUTSIDE CANAL ON RUSSELL AVENUE CHANGE ORDER NO. 02
BRIDGE REPLACEMENT JUNE 10, 2020
FEDERAL PROJECT NUMBER: BRLS-5942 (195) PAGE 4 OF 4
CONTRACT NO. 19-05-C
__ Contractor
__ Auditor Controller
__ Business Office
__ Board
__ Const. Management
__ RE/Arch
__ Design.
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
TOTAL TIME EXTENSION PART III: SIX WORKING DAYS
NET COSTS THIS CHANGE ORDER: A $16,011.36 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: SIX WORKING DAYS
SUBMITTED BY:
_______________________________________
LAUREN PETTYJOHN, Resident Engineer
ACCEPTED BY: APPROVAL RECOMMENDED:
AGEE CONSTRUCTION CORPORATION _______________________________________
Contractor STEVE DEIS, GE
Construction Engineer
By: AUTHORIZED FOR PAYMENT BY:
Title: _______________________________________
STEVEN E. WHITE, Director
Public Works and Planning
Accepted Date: ____________________
Date: _________________________________
Lauren Pettyjohn (Jun 10, 2020 13:27 PDT)
Steve Deis (Jun 11, 2020 07:44 PDT)
Alan Dirlam (Jun 15, 2020 10:06 PDT)
Chief Estimator
Jun 15, 2020
Steven White (Jun 15, 2020 10:23 PDT)
Steven White
Jun 15, 2020