HomeMy WebLinkAbout2326C CCO 07.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7
CONTRACT NO. 23-26-C DECEMBER 10, 2025
PAGE 1 OF 5
TO: WEST VALLEY CONSTRUCTON COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 67 -WORKING DAYS will be added to the contract time. The revised
date of completion for the contract is September 19, 2025.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES
This payment adjustment was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Total
Item Description Unit Quantity Price Amount o� TOTAL
No. (0/0)
6 Water Meter Box EA 2.00 $465.00 $930.00 15.38 (85.00)
Replacement
7 Water Meter Box EA 1.00 250.00 250.00 0.50 (99.50)
Adjustment to Grade
9 Water Meter Retrofit EA 1.00 101.00 101.00 0.71 1.44
36 Permanent Trench TON 1.00 2,000.00 2,000.00 100.00 0.00
Resurfacing
42 Water Meter Retrofit EA 1.00 101.00 101.00 1.52 (29.47)
59 New Water Meter Box B3 EA 1.00 480.00 480.00 100.00 100.00
with Lid by Existing (B40)
Box
60 Water Meter Box Steel EA 1.00 712.00 712.00 1.96 1.96
Lid Retrofit or New Lid
62 Water Meter Retrofit EA 2.00 101.00 202.00 0.65 (9.04)
65 Install Endpoint Only EA 31.00 75.00 2,325.00 310.00 310.00
2-16A Water Meter Box(B24) EA 3.00 550.00 1,650.00 6.82 4,600.00
Replacement
2-16B Water Meter Box Lid EA 1.00 225.29 225.29 16.67 16.67
(B36) Replacement
2-28A Water Meter Box Lid EA 25.00 108.00 2,700.00 208.33 362.50
(B16) Replacement
2-28C Water Meter Box Lid (B3) EA 1.00 79.00 79.00 50.00 200.00
Replacement
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of supervisors therefore the prices shown above.
_Const.Management
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7
CONTRACT NO. 23-26-C DECEMBER 10, 2025
PAGE 2OF5
2-28D Water Meter Box(133) EA 1.00 448.63 448.63 50.00 200.00
Replacement
TOTAL INCREASE: $12,203.92
Decrease Items:
Total
Item Description Unit Quantity Price Amount (%o) TOTAL
No. .°�
1 Supplemental Work Allowance $ 27,180.04 $1.00 $27,180.04 (90.60) (90.60)
22 Install Endpoints Only EA 2.00 68.00 136.00 (66.67) (66.67)
63 Water Meter Box Lid (139) EA 2.00 97.00 194.00 (2.25) (58.57)
Replacement
64 Water Meter Box Lid (B24) EA 33.00 145.00 4,785.00 (5.60) (30.50)
Replacement
66 Water Meter Retrofit EA 34.00 125.00 4,250.00 (3.40) (3.40)
2-25B Water Meter Box Lid (B30) EA 9.00 153.15 1,378.35 (21.43) (13.16)
Replacement
2-64C Water Meter Box Lid (133) EA 1.00 79.00 79.00 (50.00) (50.00)
Replacement
2-64D Water Meter Box (133) EA 1.00 448.63 448.63 (50.00) (50.00)
Replacement
2-64E Water Meter Box (B24) EA 56.00 550.00 30,800.00 (60.22) (60.22)
Replacement
2-641 Bid Item No. 60 (Water Meter EA 1.00 712.00 712.00 (50.00) (50.00)
Box Steel Lid Retrofit)
TOTAL DECREASE: $69,963.02
Eliminated Items:
Total
Item Description Unit Quantity Price Amount ° TOTAL
No. °\/0)
26 Install Endpoint Only EA 3.00 68.00 204.00 (100.00) (100.00)
2-64A Water Meter Box Lid (B16) EA 27.00 108.00 2,916.00 (100.00) (100.00)
Replacement
2-64B Water Meter Box(B16) EA 1.00 465.00 465.00 (100.00) (100.00)
Replacement
2-64F Water Meter Box Lid (B36) EA 2.00 225.26 450.58 (100.00) (100.00)
Replacement
2-64G Water Meter Box(1336) EA 1.00 509.96 509.96 (100.00) (100.00)
Replacement
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of supervisors therefore the prices shown above.
_Const.Management
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7
CONTRACT NO. 23-26-C DECEMBER 10, 2025
PAGE 3OF5
2-64H Water Meter Box Lid (1330) EA 4.00 153.15 612.60 (100.00) (100.00)
Replacement
2-64J B1017 Box EA 1.00 712.00 712.00 (100.00) (100.00)
TOTAL DECREASE: $5,870.14
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: $63,629.24 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: REPLACE A TWO-INCH WATER METER - EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace
the two-inch water meter in WWD 41 F (Clubhouse Common Lot 2#150). Perform all work according to
the Standard Specifications, Special Provisions, and/or manufacturer's recommendation, as directed by
the engineer. Compensation for this work will be made as extra work at Force Account according to
Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted
in a $623.28 increase. This amount will be paid through Bid Item No.1, Supplemental Work Allowance,
with no net increase to the contract.
This extra work did not impact the critical path for the project, so granting additional contract time was not
warranted.
TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: SUSPENSION OF CONTRACT
This suspension was requested by the contractor.
Suspend the contract due to unsuitable weather conditions in the Shaver Lake area. This contract
suspension is being made according to Section 8-1.06, "Suspensions," of the Special Provisions. The
first day of the suspension of contract was March 24, 2025, and the suspension ended June 16, 2025.
A total of 58-working days were granted to the allotted contract time.
TOTAL COST PART III: $0.00 (NO COST)
TOTAL TIME EXTENSION PART III: 58 -WORKING DAYS
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of supervisors therefore the prices shown above.
_Const.Management
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7
CONTRACT NO. 23-26-C DECEMBER 10, 2025
PAGE 4OF5
PART IV: GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant the contractor a 9-working days' time extension to the allotted contract time for unsuitable working
conditions due to rain/wet conditions and fire, in accordance with Section 8-1.07B, "Time Adjustments," of the
Special Provisions.
Weather Day Summary/Reference
Weather Day(Rain) February 4, 2025 1 Working Day
Weather Day (Rain) February 13, 2025 1 Working Day
Weather Day (Rain) March 5, 2025 1 Working Day
Weather Day (Rain) March 17, 2025 1 Working Day
Weather Days (Fire) September 15-19, 2025 5 Working Days
Total Weather Days 9 Working Days
TOTAL COST PART IV: $0.00 (NO COST)
TOTAL TIME EXTENSION PART IV: NINE (9) -WORKING DAYS
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7
CONTRACT NO. 23-26-C DECEMBER 10, 2025
PAGE 5OF5
NET COST THIS CHANGE ORDER: $63,629.24 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 67 -WORKING DAYS
.>?e6utyS�e.s,�uc,�.aa.L
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
West Valley Construction Co.. Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
B APPROVED BY:
Steven Digitally signed by
Steven White
�— / White Date:2026.01.26
Title ee- �1� S T, l � Ir�p.�(yY� 14:11:13-08'00'
Steven E. White, Director
Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.