HomeMy WebLinkAbout2326C CCO 07.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7 CONTRACT NO. 23-26-C DECEMBER 10, 2025 PAGE 1 OF 5 TO: WEST VALLEY CONSTRUCTON COMPANY, INC.: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), 67 -WORKING DAYS will be added to the contract time. The revised date of completion for the contract is September 19, 2025. PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES This payment adjustment was proposed by the engineer. Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item quantities to the actual quantities used. Increased Items: Total Item Description Unit Quantity Price Amount o� TOTAL No. (0/0) 6 Water Meter Box EA 2.00 $465.00 $930.00 15.38 (85.00) Replacement 7 Water Meter Box EA 1.00 250.00 250.00 0.50 (99.50) Adjustment to Grade 9 Water Meter Retrofit EA 1.00 101.00 101.00 0.71 1.44 36 Permanent Trench TON 1.00 2,000.00 2,000.00 100.00 0.00 Resurfacing 42 Water Meter Retrofit EA 1.00 101.00 101.00 1.52 (29.47) 59 New Water Meter Box B3 EA 1.00 480.00 480.00 100.00 100.00 with Lid by Existing (B40) Box 60 Water Meter Box Steel EA 1.00 712.00 712.00 1.96 1.96 Lid Retrofit or New Lid 62 Water Meter Retrofit EA 2.00 101.00 202.00 0.65 (9.04) 65 Install Endpoint Only EA 31.00 75.00 2,325.00 310.00 310.00 2-16A Water Meter Box(B24) EA 3.00 550.00 1,650.00 6.82 4,600.00 Replacement 2-16B Water Meter Box Lid EA 1.00 225.29 225.29 16.67 16.67 (B36) Replacement 2-28A Water Meter Box Lid EA 25.00 108.00 2,700.00 208.33 362.50 (B16) Replacement 2-28C Water Meter Box Lid (B3) EA 1.00 79.00 79.00 50.00 200.00 Replacement Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of supervisors therefore the prices shown above. _Const.Management RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7 CONTRACT NO. 23-26-C DECEMBER 10, 2025 PAGE 2OF5 2-28D Water Meter Box(133) EA 1.00 448.63 448.63 50.00 200.00 Replacement TOTAL INCREASE: $12,203.92 Decrease Items: Total Item Description Unit Quantity Price Amount (%o) TOTAL No. .°� 1 Supplemental Work Allowance $ 27,180.04 $1.00 $27,180.04 (90.60) (90.60) 22 Install Endpoints Only EA 2.00 68.00 136.00 (66.67) (66.67) 63 Water Meter Box Lid (139) EA 2.00 97.00 194.00 (2.25) (58.57) Replacement 64 Water Meter Box Lid (B24) EA 33.00 145.00 4,785.00 (5.60) (30.50) Replacement 66 Water Meter Retrofit EA 34.00 125.00 4,250.00 (3.40) (3.40) 2-25B Water Meter Box Lid (B30) EA 9.00 153.15 1,378.35 (21.43) (13.16) Replacement 2-64C Water Meter Box Lid (133) EA 1.00 79.00 79.00 (50.00) (50.00) Replacement 2-64D Water Meter Box (133) EA 1.00 448.63 448.63 (50.00) (50.00) Replacement 2-64E Water Meter Box (B24) EA 56.00 550.00 30,800.00 (60.22) (60.22) Replacement 2-641 Bid Item No. 60 (Water Meter EA 1.00 712.00 712.00 (50.00) (50.00) Box Steel Lid Retrofit) TOTAL DECREASE: $69,963.02 Eliminated Items: Total Item Description Unit Quantity Price Amount ° TOTAL No. °\/0) 26 Install Endpoint Only EA 3.00 68.00 204.00 (100.00) (100.00) 2-64A Water Meter Box Lid (B16) EA 27.00 108.00 2,916.00 (100.00) (100.00) Replacement 2-64B Water Meter Box(B16) EA 1.00 465.00 465.00 (100.00) (100.00) Replacement 2-64F Water Meter Box Lid (B36) EA 2.00 225.26 450.58 (100.00) (100.00) Replacement 2-64G Water Meter Box(1336) EA 1.00 509.96 509.96 (100.00) (100.00) Replacement Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors therefore the prices shown above. _Const.Management RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7 CONTRACT NO. 23-26-C DECEMBER 10, 2025 PAGE 3OF5 2-64H Water Meter Box Lid (1330) EA 4.00 153.15 612.60 (100.00) (100.00) Replacement 2-64J B1017 Box EA 1.00 712.00 712.00 (100.00) (100.00) TOTAL DECREASE: $5,870.14 This change did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART I: $63,629.24 DECREASE TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS PART II: REPLACE A TWO-INCH WATER METER - EXTRA WORK This extra work was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace the two-inch water meter in WWD 41 F (Clubhouse Common Lot 2#150). Perform all work according to the Standard Specifications, Special Provisions, and/or manufacturer's recommendation, as directed by the engineer. Compensation for this work will be made as extra work at Force Account according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $623.28 increase. This amount will be paid through Bid Item No.1, Supplemental Work Allowance, with no net increase to the contract. This extra work did not impact the critical path for the project, so granting additional contract time was not warranted. TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 1) TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS PART III: SUSPENSION OF CONTRACT This suspension was requested by the contractor. Suspend the contract due to unsuitable weather conditions in the Shaver Lake area. This contract suspension is being made according to Section 8-1.06, "Suspensions," of the Special Provisions. The first day of the suspension of contract was March 24, 2025, and the suspension ended June 16, 2025. A total of 58-working days were granted to the allotted contract time. TOTAL COST PART III: $0.00 (NO COST) TOTAL TIME EXTENSION PART III: 58 -WORKING DAYS Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors therefore the prices shown above. _Const.Management RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7 CONTRACT NO. 23-26-C DECEMBER 10, 2025 PAGE 4OF5 PART IV: GRANT A TIME EXTENSION This time extension was requested by the contractor. Grant the contractor a 9-working days' time extension to the allotted contract time for unsuitable working conditions due to rain/wet conditions and fire, in accordance with Section 8-1.07B, "Time Adjustments," of the Special Provisions. Weather Day Summary/Reference Weather Day(Rain) February 4, 2025 1 Working Day Weather Day (Rain) February 13, 2025 1 Working Day Weather Day (Rain) March 5, 2025 1 Working Day Weather Day (Rain) March 17, 2025 1 Working Day Weather Days (Fire) September 15-19, 2025 5 Working Days Total Weather Days 9 Working Days TOTAL COST PART IV: $0.00 (NO COST) TOTAL TIME EXTENSION PART IV: NINE (9) -WORKING DAYS _Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 7 CONTRACT NO. 23-26-C DECEMBER 10, 2025 PAGE 5OF5 NET COST THIS CHANGE ORDER: $63,629.24 DECREASE NET TIME EXTENSION THIS CHANGE ORDER: 67 -WORKING DAYS .>?e6utyS�e.s,�uc,�.aa.L Robert Hendrickson, Resident Engineer APPROVAL RECOMMENDED: West Valley Construction Co.. Inc. Contractor Mandeep S. Sekhon, PE Construction Engineer B APPROVED BY: Steven Digitally signed by Steven White �— / White Date:2026.01.26 Title ee- �1� S T, l � Ir�p.�(yY� 14:11:13-08'00' Steven E. White, Director Public Works and Planning Accepted Date: Date: Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.