HomeMy WebLinkAbout2418C CCO 03 - REVISED.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
GOLDEN STATE BOULEVARD PHASE 2 CHANGE ORDER NO. 03
DRAPER STREET TO CLAYTON AVENUE OCTOBER 20, 2025
STATE PROJECT NUMBER: SB1 LPPL-5942(307) PAGE 1 OF 4
CONTRACT NO. 24-18-C
TO: DON BERRY CONSTRUCTION, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 20 -WORKING DAYS will be added to the allotted contract time.
PART I: INSTALL K-MARKERS AT BETHEL AVENUE INTERSECTON— EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install K-
markers at Bethel Avenue intersection as per the attached revised Plan Sheet 76B, as directed by the
engineer. Perform all work in accordance with Section 82, "Signs and Markers," of the Standard Specifications
and Special Provisions. Compensation for the materials will be made at an agreed price of$1,237.50, in
accordance with Section 9-1.03, "Payment Scope," of the Standard Specifications and Special Provisions. This
agreed price includes compensation for all labor, materials, equipment, traffic, incidentals, overheads,
markups, and profits, no additional compensation will be made thereafter. This amount will be paid through Bid
Item No. 3, Supplemental Work, with no net increase to the contract.
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: $0.00 (PAID IN BID ITEM NO. 3)
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: INSTALL ACCESSIBLE PEDESTRIAN SIGNALS (APS)AT GOLDEN STATE BOULEVARD
AND MERCED STREET INTERSECTION — EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install a total of
four(4) additional APS units at the Golden State Boulevard and Merced Street intersection. Perform all work in
accordance with Section 86-1.02T, "Accessible Pedestrian Signals," of the Standard Specifications and Special
Provisions. Compensation for the materials will be made at an agreed price of$7,920, in accordance with
Section 9-1.03, "Payment Scope," of the Standard Specifications and Special Provisions. This agreed price
includes compensation for all labor, materials, equipment, traffic, incidentals, overheads, markups, and profits,
no additional compensation will be made thereafter. This amount will be paid through Bid Item No. 3,
Supplemental Work, with no net increase to the contract.
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors therefore the prices shown above.
_Const.Management
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
GOLDEN STATE BOULEVARD PHASE 2 CHANGE ORDER NO. 03
DRAPER STREET TO CLAYTON AVENUE OCTOBER 20, 2025
STATE PROJECT NUMBER: SB1 LPPL-5942(307) PAGE 2 OF 4
CONTRACT NO. 24-18-C
TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 3)
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: REMOVE AND REPLACE EXISITING STRIPING AT TEMPERANCE AVENUE INTERSECTION
— EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, blackout the
existing striping at the Temperance Avenue intersection which was placed in Phase 1 of the Golden State
Boulevard Project and place new striping to match the current project striping. Perform all work in accordance
with Section 84, "Markings," of the Standard Specifications and Special Provisions. Compensation for the
additional striping will be made at the unit bid prices of the pertaining bid items (shown below), compensation
for the removal of the existing striping (includes sealing of the surface) will be made at the agreed unit prices;
$0.81 per linear foot for Details 12, 25, 39, and 39A, in accordance with Section 9-1.03, "Payment Scope," of
the Standard Specifications and Special Provisions.
Increased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount NO NO
54 4" White 2-Coat Paint Traffic LF 856.00 $0.70 $569.29 5.30 31.89
Striping (Detail 8, 12, 27B, 38, $599.20
38A)
55 6" White 2-Coat Paint Traffic LF 451.00 0.78 351.78 36.20
Striping (Detail 39, 39A) 1.88
57 4" Yellow 2-Coat Paint Traffic LF 1,550.00 1.30 2,015.00 13.03 37.25
Striping (Detail 21, 22, 24, 25, 29,
31, 32)
TOTAL INCREASE: $2,92698 $2,965.98
A total of 2,568 linear feet of Details 12, 25, 39, and 39A were blacked out, compensation resulted in (2,568 x
0.81 = 2,080.08) $2,080.08.
$2,965.98
Total compensation for the additional striping resulted in $2� 6.98, this amount will be paid through Bid Item
Nos. 54, 55, and 57. Total compensation for the removal of the existing striping resulted in $2,080.08, this
amount will be paid through Bid Item No. 3, Supplemental Work with no net increase to the contract.
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
—Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
GOLDEN STATE BOULEVARD PHASE 2 CHANGE ORDER NO. 03
DRAPER STREET TO CLAYTON AVENUE OCTOBER 20, 2025
STATE PROJECT NUMBER: SB1 LPPL-5942(307) PAGE 3 OF 4
CONTRACT NO. 24-18-C
$2,965.98 INCREASE
TOTAL COST PART III: $2,926.98 tNGRE S
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
PART IV: GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant a time extension of 20-working days to the "Second Order of Work" due to the long lead time for
the traffic signal equipment delivery. This time extension is being granted according to Section 8-1.07B,
"Time Adjustments," of the Standard Specifications.
TOTAL COST PART IV: $0.00 (NO COST)
TOTAL TIME EXTENSION PART IV: 20 -WORKING DAYS
PART V: REVISE PROJECT PLANS (SELMA REGION)
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace Plan
Sheet 77A with the attached revised Plan Sheet 77B. The revision included in this revised plan sheet adds a
total of six (6) roadside signs, including R6-2, R1-2, R3(CA)(40), R9-3, and R2-1(40). Perform all work in
accordance with Section 82, "Signs and Markers," of the Standard Specifications and Special Provisions.
Compensation for the additional roadside signs will be made at unit bid prices of the pertaining bid items
(shown below), and compensation for the additional mobilization will be made at agreed price of$605,
according to Section 9-1.03, "Payment Scope," of the Standard Specifications and Special Provisions.
These changes did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
Increased Items:
Item Total Total
No. Description Unit Quantity Price Amount o�
51 Roadside Sign EA 6.00 $450.00 $2,700.00 35.29 35.29
TOTAL INCREASE: $2,700.00
Total compensation for the additional roadside signs resulted in $2,700.00, this amount will be paid through Bid
Item No. 51. Compensation for the additional mobilization, $605 will be made through Bid Item No. 3,
Supplemental Work, with no net increase to the contract.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
AMENDED
COUNTY OF FRESNO Steven Digitally signed by
CONSTRUCTION MANAGEMENT Steven White
CONTRACT CHANGE ORDER white Date:
20222:41 .01.21
GOLDEN STATE BOULEVARD PHASE 2 CHANGE ORDER NO. 03
DRAPER STREET TO CLAYTON AVENUE OCTOBER 20, 2025
STATE PROJECT NUMBER: SB1 LPPL-5942(307) PAGE 4 OF 4
CONTRACT NO. 24-18-C
TOTAL COST PART V: $2,700.00 INCREASE
TOTAL TIME EXTENSION PART V: ZERO (0) -WORKING DAYS
$5,665.98 INCREASE
NET COST THIS CHANGE ORDER: $6,62e 98 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 20 -WORKING DAYS
a k�'�
Jersephene Vang, Resident Engineer
APPROVAL RECOMMENDED:
Don Berry Construction, Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
T�IZO,Dea o��
By APPROVED BY:
Steven Digitally signed by
Dan Dorval-CFO SEC Steven White
� White Date:2025.11.03
Title 08:47:01 -08'00'
Steven E. White, Director
Oct 29,2025 Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials, except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
I1PE K(OM?-1N)
GSB-SB1'+57.79 63.50'Lt
• CONFORM TO E'st
CL67 M * a a
'(6112--1h) 7` RI-1 •
CONFORM TO Exist STRIPING �j'�� • yy u ts1 CUSTOM •
R�r 1 I7YPf K(OMW
R81 n x x
• '.
I iz las ?T � Fr +�
2'
sY� II I,I 1T •1- long son ■� I. i
$SB-5'B1"+59. 3082'Lt 21 .a 12' 1s'
1 'GSB-SBI"-ta1E ---1P----rz' li CSB-SB1'+60.69�0.03'R!
43
CONFD T CONFORM 70 EdM STRIPYNC R•1 z1 �I-1-1 r Enbt STRONG GOLDEN STARS BLVII
ti5B-SB1"+61.17 30.99'Rt
a4 x.SB-NB1'UIIE 1't CONFORM TO Eriat STRIPING Y 1
12' i 1Y' 12' y IS' rr • ---12'
1S'12 yT ----------
11TT''P BY
J I I��1� �3 1T 4• 25 � 4
p I jrz�1 ■ .l9 PS Ite�- I ipll 12
g3 - W3-1 A s7➢ • C l TO Exist STRIPIN
as
G
AHEW) •WIO-5 R•1 I 1-1
•W10-5P •
1-6(Rt) 0WIO-51
• •W10-5PI
W10-2
CITY OF KINGSBURG
GOLDEN STATE BLVD
SCALE 1'=40'
J3�
k
w
J
a
g�
3
noTE RECORD DRAWING PROJECT-PHASE 2 csB of DEPARTNIENTOFPUBLICWORKSANDPLANNING
DESIGNED:—THIAHORNER REBIDENTENGINEER DOTE ' , , D\ /,/DD,)
ERIK CHIN . 1zn�rza]a ECONOMC DEVELOPMEGOLDEN STATE NT AND �NDRIEDA 4LS4t INFRASIRUCTUREIMPROVEMENTS ` SIGNAGEAND STRIPING
KA■5TH MAS DATE �GOLDEN BTATEBOULEVARD FOP � pgpy�NG NO.83� SHEET NO.]BSI TOTAL 10B
85B-SB1"+65b0 93./0'Lt
70 E'at 511NPING
'SS-Sal"+82.0
FORM 70 Exist SIRAPW
Y.SB-SB)'+49.29 9306'Lt TSB-SB2"+28.00 8323'Lt
• CONFORM TO&W S7R/P ONfORM TO Eriet STRIPING
R28E G
• • 70 Exist SO6PdVG
• • • • R81 4 4 G
RpBE�(Cp) R28�fG7 R2 R28E • � / 8
�11 r I I.ioh CONFORM TO Fist S7R/P/NG .n 1
�lis r, I �I ss fs a K fT f TO Exist 5�`7MPM�G r� i r7ni
fa f2 '•MN fa' I I
f2• G.SB-SBt'Lm�a—— fa. —— ,=-S82.—WE— I
189+00 (&j 190+00 191+00 r >+00 193+00 nfft• � 7+00 19+ 199+
O GOLDEN STATE BLVD GOLDEN SPATE BLVD
�rygp•ns' 'TSB-t•t'GNE rr•a s•uw 2:.
189300_ 190+-00-f: fTfY fs -0 193+00 �.9-9+D0- �.95+D0- �.46+D0- fY roa�nn /aoAnr
II fr f2• fY I I
Iffi L�j I� � JB 53 .Y .M � • ffi �' �)��]7ry''
W10-•2Rt :ia�) fT .m *_ J SAS I V Iial I
RI-2
R6 I
GT N10-2 Lt c.
CONFORM RJ Exist STRIPING W10-1
R6-3
o ' CITY OF MNGSBURG
GOLDEN STATE BLVD
SGLE. 1"_40'
—J x R2-190 `t
LYM'FORM/D _ * I\irll F/ 70 Exist SIR/PING • u x I x f: f��- R2-1 40
Exi2t-57R�/VLG M
I �
\ llfDiSON
� g�Z � fa. R3G GOLIIEN SPAT�.lL
fs• - + 1 'se-cLz•Lam 2s $
v 359+00 �- 362.o- 365+00
_ w � __ ut °f•
x fa a
12
tq 4
b"SB-CL2" 6S 3 6' f •m Mum *' 0 *G e ffi
� R GIdSl�l
m�
CITY OF SELMA 'x$
GOLDEN STATE BLVD
' SGLE. 1'=40'
R
nsTE RECORD DRAWING PROJECT-PHASE 2 �csap DFPAR721ENTOFPUBLICWORKSANDPLANNING
g DE9GNED:OyNTHIA HORNER RESIDENT ENGINEER DOTE , . ' GOLDEN STATE CORRIDOR-ECONOMI COD
LOPMENTAND SIGNAGE AND STRIPING
OHRIINFRASIRUCTU EIMPRO EMENTS
CHECI�D'.EDOARNORIEDA MARKTRONAI 9UPERVIBING ENGINEER 64TE �P GDLDEN BTATE BdJ—RD wA11R —AINON0.833 .—N..P9 TOTAL 10B