HomeMy WebLinkAbout24S01 ECC Educational Building CCO 004 - signed.pdf coU� County of Fresno
Department of Public Works and Planning
Development Services&Capital Projects Division
Steven E.White, Director
O lsg O
�' FR 85 CONTRACT CHANGE ORDER
Project: ECC Educational Building Contractor: GC Builders
Contract No.24-S-01 D-24-640 Address: 3366 W.Sussex, Fresno,CA 93722
Date: 2025-11-17
Architect: Hoque Khan
Change Order No.: 4
Construction Contract Dollar Amount(as awarded on 2024-10-22) $2,753,499.00
Director's Change Order Limit: $150,175.00
Change Order Allowance $150,175.00
Construction Start Date(NTP Issued 2025-01-08): 2025-01-10
Original Contract Time(Calendar Days): 270
Original Construction Completion Date: 2025-10-07
Change Order Scope of Work:
PCO 10 Relocate Cameras 5 days $3,150.24
PCO 11.1 Relocate Electrical 2 days $2,418.01
PCO 12.2 Gutter Width Change 21 days $10,768.61
Attachment(s):
Change Order Summary,Contractors PCO,Subcontractor's Price Proposal
Net Change Order Dollar Amount: $16,336.86
Net Working Days: 1 28
Total Change Order Dollar Amount To Date $37,285.69
Adjusted Contract Dollar Amount: $27790,784.69
Director's Change Order Limit Balance: $112,889.31
Change Order Allowance Balance: $112,889.31
Total Adjusted Working Days To Date(Change Orders): 39
Adjusted Construction Completion Date: 2025-12-04
Approved Suspension of Contract(Calendar Days) 75
Revised Construction Completion Date(Suspension of Contract Days): 2026-02-17
By signing acceptance of this Change Order, the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in this Change Order.
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 24-S-01,Article Vl shall apply.
G& a dc- R4YL/3US
Reviewed: GC Builders Gerardo Campos(Dec 2,202508:49:02 PST)
General Contractor
it
Reviewed: Keith M. Eckert II Ke th Eckert(Dec 2,2025 09:12:44 PST)
Senior Engineering Technician,Project Manager
lamir3 S Ivy
Reviewed-Cleared for Approval Jamie Sylvester Jamie Sylveete,�Dec2,202510:48:03 PS)
Principal Accountant
Reviewed: Hoque Khan
Architect of Record
Reviewed: Mandeep Sekhon 04 "x-
Construction Division Engineer, Construction Manager
Reviewed: William M. Kettler -.
Deputy Director of Planning
13on��n 1 l lil�io
Reviewed: Bernard Jimenez eemad Ji--(Dec 3,20251P Oo ,
Pllannin/g,wt&R��eJsl^ource Management Officer
Approved: Steven E. White t—n EI/G/l aU20 5 51teP
Director of Public Works and Planning
Approved: Ernest"Buddy"Mendes Not Applicable
Board of Supervisors, Chairman
CHANGE ORDER SUMMARY
Project: ECC Educational Buildinq
lWate Add Credit Adj. Days Potential Change Orders Included
L Change Order
1 2025-06-17 $6,461.64 $0.00 2 Includes PCO: 1,2.1
2 2025-07-21 $15,689.98 -$3,340.59 7 Includes PCO:3,4,5,6.1,7
3 2025-09-12 $2,137.80 $0.00 2 Includes PCO:8,9.1
4 2025-11-17 $16,336.86 $0.00 28 Includes PCO: 10, 11.1, 12.2
Totals $40,626.28 -$3,340.59 39
Potential Executed
A.. Credit Rejected Pending
Change Orders CO#
1 1 $3,340.59 1 Relocate HVAC louver at South Elevation
2 $6,241.04 1 Additional Steel Support for RFI 57 Response
2.1 1 $3,121.05 1 Add Support at Entry Framing
3 2 $2,023.50 1 Electrical Work for Additional TV
4 2 $8,091.47 2 Reframe Roof at Restroom 06 and 07
5 2 $4,928.53 5 Reroute roof drain pipe at entry
6 $677.27 0 Power and Data to TV RFI 67
6.1 2 $646.48 0 Power and Data to TV RFI 67
7 2 -$3,340.59 -1 Relocate HVAC louver credit ref.PCO#001
8 3 $1,392.30 0 Permit Fees for Fire
9 $3,694.08 2 Addendum 6 Revised Domestic Water POC
9.1 3 $745.50 2 Addendum 6 Revised Domestic Water POC
10 4 $3,150.24 5 Relocate Cameras
11 $4,836.03 2 Relocate Electrical
11.1 4 $2,418.01 2 Relocate Electrical
12 $10,648.60 21 Gutter Width Change
12.1 $10,041.11 21 Gutter Width Change
12.2 4 $10,768.61 21 Gutter Width Change
13 $5,882.75 5 New UPS location
Totals $40,626.28 -$3,340.59 $36,138.13 $5,882.75
GERARDO CAMPOS
Gcis. BUILDERS
iK 933222
CORNO 010 CHANGE ORDER REQUEST
PROJECT: Environmental Compliance Center Ed Bldg Contract#:24-S-01
CONTRACTOR: GC Builders DATE 9/12/2025
ARCHITECT: Hoque Khan
OWNER: The County of Fresno
DESCRIPTION OF CHANGE: ASI 02 New camera locations
Per ASI 03, relocate cameras to new locations on the North, East, and South elevations.
TIME EXTENSION OF CHANGE: 5 Day(s)
Description Labor Material Equip Sub Total
Relocate Cameras $ 2,970.52
$
SUBTOTAL COR AMOUNT Subtotal $ 2,970.52
Contractor OH&P 5% $ 148.53
SUBTOTAL COR AMOUNT Subtotal $ 3,119.05
1%Bond Mark Up $ 31.19
TOTAL COR AMOUNT Totatj $ 3,150.24
�ef-"06 Coun�ios 9/12/2025
GC Builders Date
1 Stop Electric
Date Submitted: 1 9/1z/zozs
3410 N. Minden St.
Visalia CA. 93291 GC Builders
(559)636-0595 3366 W. Sussex Way Fresno, CA 93722 lInvoice # 25-65
License #991309 (559) 293-3459
LABOR COST DESCRIPTION OF WORK TO BE DONE
Hours Rate: Relocate 4 cameras to different areas.
MATERIAL ITEMS COST
Cate 5E $742.92
RJ45 connectors $101.01
Labor Cost $2,000.00
Description work completed
Material Cost $970.52
Notes and Comments
I hereby authorize you to preform such labor and materials you seem
deem advisable. A monthly service charge will be added after 30 days.
I agree to pay all attorney fees and court costs in the event of legal
Total Parts $843.93 action. Any bounce checks could be liable up to 3 times the amount of
check. I have read and agree to all terms and conditions of this
document
Mark up of Parts 15% $126.59
Other
Si nature: X
Labor $2,000.00
Thank you, Materials $970.52
Aaron Austin
(559)972-9850 C
uote good for 30 Da s Total $2,n[1 7 O■�
c° f Fr n
Countyo es o
` DEPARTMENT OF PUBLIC WORKS AND PLANNING
O� 1856O
STEVEN E.WHITE, DIRECTOR
Architect's Supplemental Instructions
Date: September 10, 2025
Instruction Number: ASI 03 - New Camera Locations
PROJECT: Fresno County Environmental Compliance Center Educational Building
1327 W. Dan Ronquillo Drive, Fresno, CA 93706
Contract No.: 24-S-01
ARCHITECT: Hoque Khan, Architect
CONTRACTOR: GC Builders
3366 W. Sussex
Fresno, CA 93722
The Contractor shall carry out the work in accordance with the following supplemental instructions without change in Contract Sum
or Contract Time. Proceeding with the work in accordance with these instructions indicates your acknowledgement that there will be
no change in the Contract Sum or Contract Time.
DESCRIPTION:
Refer to attached pages for New Camera Locations on the North, East, and South Elevations.
DEVELOPMENT SERVICES AND CAPITAL PROJECTS DIVISION
2220 Tulare Street,Sixth Floor/Fresno, California 93721 /Phone(559)600-5206/FAX(559)600-4548
The County of Fresno is an Equal Opportunity Employer
T
1
I I
NEW LOCATION
OF CAMERA
1 3274
�0
�❑ E
North Elevation
'I III II I� III
East Elevation
T 2 4
1 NEW LOCATION
OF CAMERA
�NEW LOCATION NEW LOCATION
OF CAMERA OF CAMERA
- - L
--- ;
0THIENIJH � Qiiiiii
1
� T
South Elevation
GERARDO CAMPOS
BUILDERS
„GCr3.
COR NO 011REB CHANGE ORDER REQUEST
PROJECT: Environmental Compliance Center Ed Bldg Contract#:24-S-01
CONTRACTOR: GC Builders DATE 10/31/2025
ARCHITECT: Hoque Khan
OWNER: The County of Fresno
DESCRIPTION OF CHANGE: Relocate Electrical in Conflict with the Gutter&Scupper
Relocate electrical conduits that were in conflict with the gutter and scupper. GCB has agreed to split the
original cost of$4,836.03 with the County,which makes the cost of the COR for the County $2,418.01 and
the cost for GCB at$2,418.02.
TIME EXTENSION OF CHANGE: 2 Day(s)
Description Labor Material Equip Sub Total
Relocate electrical due to rain gutters $ 2,560.14
Relocate conduit in conflict with welding brackets $ 2,000.00
SUBTOTAL COR AMOUNT Subtotal $ 4,560.14
Contractor OH&P 5% $ 228.01
SUBTOTAL COR AMOUNT Subtotal $ 4,788.15
1%Bond Mark Up $ 47.88
TOTAL COR AMOUNT I I TotaLl $ 4,836.03
GCB Cost $2,418.02
County Cosi $2,418.01
OwWV6 Camw 10/31/2025
GC Builders Date
1 Stop Electric
Date Submitted: 1 912 9 22 0 2 5
3410 N. Minden St.
Visalia CA. 93291 GC Builders
(559)636-0595 3366 W. Sussex Way Fresno, CA 93722 lInvoice # 25-66
License #991309 (559) 293-3459
LABOR COST DESCRIPTION OF WORK TO BE DONE
Hours Rate: Relocate conduit due to rain gutters
16 125.00 $2,000.00
MATERIAL ITEMS COST
wire $487.08
Labor Cost $2,000.00
Description work completed
Material Cost $560.14
Notes and Comments
I hereby authorize you to preform such labor and materials you seem
deem advisable. A monthly service charge will be added after 30 days.
I agree to pay all attorney fees and court costs in the event of legal
Total Parts $487.08 action. Any bounce checks could be liable up to 3 times the amount of
check. I have read and agree to all terms and conditions of this
document
Mark up of Parts 15% $73.06
Other
Si nature: X
Labor $2,000.00
Thank you, Materials $560.14
Aaron Austin
(559)972-9850
Dote good for 30 Da s Total $2,560.14
1 Stop Electric
Date Submitted: 1 9/19/zozs
3410 N. Minden St.
Visalia CA. 93291 GC Builders
(559)636-0595 3366 W. Sussex Way Fresno, CA 93722 lInvoice # 25-67
License #991309 (559) 293-3459
LABOR COST DESCRIPTION OF WORK TO BE DONE
Hours Rate: Relocate conduits in the way of welding brackets on
16 125.00 $2,000.00
MATERIAL ITEMS COST
Labor Cost $2,000.00
Description work completed
Material Cost $0.00
Notes and Comments
I hereby authorize you to preform such labor and materials you seem
deem advisable. A monthly service charge will be added after 30 days.
I agree to pay all attorney fees and court costs in the event of legal
Total Parts $0,001 action. Any bounce checks could be liable up to 3 times the amount of
check. I have read and agree to all terms and conditions of this
document
Mark up of Parts 15% $0.00
Other
Si nature: X
Labor $2,000.00
Thank you, Materials $0.00
Aaron Austin
(559)972-9850
uote goodfor 30Da s Total $2,000■oo
Kasey Earls
From: Eckert, Keith <keckert@fresnocountyca.gov>
Sent: Thursday, October 2, 2025 11:00 AM
To: Chris Giannetta; Kasey Earls
Cc: Sekhon, Mandeep; Gerardo Campos
Subject: ECC Cost for moving Conduits in conflict with gutter and Scuppers
Chris and Kasey,
Please send me cost for moving and relocating the Electrical conduits or boxes that were in conflict with the
gutter or scupper install as was discussed last week with design team.
Thankyou,
Keith Eckert
i
GERARDO CAMPOS
-,GCr3 BulL>J>;xs
UC 933222
COR NO 012.2 CHANGE ORDER REQUEST
PROJECT: Environmental Compliance Center Ed Bldg Contract#:24-S-01
CONTRACTOR: GC Builders DATE 11/5/2025
ARCHITECT: Hoque Khan
OWNER: The County of Fresno
DESCRIPTION OF CHANGE: Revised Gutter Size Width
Per RFI 73 response Drawing A, increase the width of the internal gutter from 8"to 16".
TIME EXTENSION OF CHANGE: 21 Day(s)
Description Labor Material Equip Sub Total
Increase Gutter Width $ 10,154.28
$
$
SUBTOTAL COR AMOUNT Subtotal $ 10,154.28
Contractor OH&P 5% 1 $ 507.71
SUBTOTAL COR AMOUNT Subtotal $ 10,661.99
1%Bond Mark Up $ 106.62
TOTAL COR AMOUNT Total $ 10,768.61
6 eVCW o Cct�nrios 11/5/2025
GC Builders Date
"WE BRING FUCTIONALITY&EXCEPTIONAL CRAFTSMANSHIP IN METAL TO LIFE"
SUBCONTRACT CHANGE-ORDER PROPOSAL
CCP# 5
24-112 Environmental Compliance Center
FOUR C'S CONSTRUCTION
1560 H.STREET,
FRESNO,CA 93721 CONSTBIICTION
CA LICENSE#:908294
DIR#:1000002824(EXP.06/30/25)
,PROPOSAL •• •
SUBMITTED DATE:10/17/2025 PLAN SET VERSION:
EXPIRATION DATE:10/31/2025 PLAN SET DATE:
TO:Kacey Earls FROM:Anthony Rios
• • Supply all labor,materials and equipment to complete the following scope of work.Scope of work is per specifications,plans and
manufacturer's recommendations.
Per request from GC Builders,Four C's Construction is providing revised pricing for the
internal gutter located at Grid Line B(GL-B)per Detail D8/A-8.9.The original proposal MATERIAL: $ 1,520.37
was based on an 8"wide internal gutter.This revised pricing reflects the increased gutter
width of 16",as indicated in Drawing A and RFI#73. LABOR: $ 7,309.44
The change in gutter width affects raw material usage,fabrication time,handling, EQUIPMENT: $ -
transportation,and field labor.
All other scope,including roof caps,finishes,and sequence of installation,remains JOB COST EXPENSES: $ -
unchanged from the original proposal.Gutter fabrication lead time remains 10 business
days from profile approval. OVERHEAD&PROFIT(%): $ 1,324.47
This cost represents the increase due solely to the change in gutter width from 8"to 16".
TOTAL SUM: $ 10,154.28
CLARIFICATIONS/CHANGES
ADDITIONAL CREW DAYS REQUIRED BEYOND SCHEDULE DUE TO THIS CHANGE ORDER:10
NOTE:ADDITIONAL CREW DAYS IS ESTIMATE BASED ON VARYING CREW SIZE
OF
THE EXPRESS TERMS,CONDITIONS,INCLUSIONS AND EXCLUSIONS OF THIS PROPOSAL SHALL BE INCORPORATED BY REFERENCE AS THOUGH SET FORTH AT LENGTH IN
ANY SUBCONTRACT TO BE EXECUTED BY THE RECIPIENT OF THIS PROPOSAL AND FOUR C'S.
ALL WORKMANSHIP IS WARRANTED FOR 1 YEAR UNLESS OTHERWISE NOTED.
FOUR CS RESERVES THE RIGHT THAT:
•IN THE EVENT OF SIGNIFICANT MATERIAL OR COMMODITY PRICE ESCALATION AFTER THE SUBMITTED DATE,TO EQUITABLY ADJUST ITS PRICE WHICH WILL BE RECONCILED
UPON CONTRACT EXECUTION.
•OUR PROPOSAL IS ALSO BASED ON INDUSTRY STANDARD MATERIAL AND EQUIPMENT DELIVERY LEAD TIMES AFTER APPROVAL.SIGNIFICANT SUPPLIER DELAYS IN
MATERIAL OR EQUIPMENT DELIVERY SCHEDULES SHALL BE AN EXCUSABLE DELAY AND THE PROJECT SCHEDULE WILL BE EQUITABLY ADJUSTED ACCORDINGLY.
•IN ADDITION,FOUR C'S CONTRACT TO PERFORM THE WORK SUBJECT TO THIS PROPOSAL WILL CONTAIN MUTUALLY AGREEABLE TERMS TO ADDRESS SIGNIFICANT
MATERIAL OR COMMODITY PRICE ESCALATION AND DELIVERY DELAYS THAT ARE NOT FORESEEN AT CONTRACT EXECUTION.
•FOUR C'S SHALL BE PROVIDED CLEAR AND UNINTERRUPTED ACCESS TO THE SITE WHERE ITS SCOPE OF WORK IS TO BE PERFORMED,AND ANY DELAY CAUSED BY THE
FAILURE TO PROVIDE SUCH ACCESS SHALL ENTITLE FOUR C'S TO AN EQUITABLE ADJUSTMENT IN THE CONTRACT PRICE AND THE CONTRACT TIME.
•ALL WORK SHALL BE PERFORMED DURING A STANDARD WORKWEEK AND DURING NORMAL WORKING HOURS,FOUR C'S SHALL BE ENTITLED TO AN EQUITABLE
ADJUSTMENT IN THE CONTRACT PRICE AND THE CONTRACT TIME.
•
•ANY SPECIAL SAFETY REQUIREMENTS(GC OR OWNER IMPOSED)BEYOND OSHA STANDARDS(STARE OR FEDERAL)ARE EXCLUDED&MAY
INCREASE OUR PROPOSAL PRICE DEPENDING ON HOW THEY APPLY TO OUR SCOPE OF WORK
•ELECTRICAL,PLUMBING,CONDENSATE DRAIN,ROOFING&CONCRETE
•WOOD/METAL FRAMING,WOOD/METAL BLOCKING&BACKING
•SAW CUTTING.CONCRETE CUTTING&CORING
•WINDOW GLAZING,FRAMES,ALUMINUM BREAKIBRAKE METALS,ALUMINUM TRIM,INFILL PANELS @ STOREFRONT/CURTAIN WALLS
•STAINLESS STEEL WORK
•ANY&ALL ELECTRICAL WORK
•FRAMING,BLOCKING,BACKING&FLEXIBLE FLASHING OF ANY KIND
•CONDUITS,WIRING,PIPING,MECHANICAL FLASHINGS,ROOFING LEAD,WEEP SCREEP OF ANY KIND
•ANYTHING NOT LISTED ABOVE IN INCLUSIONS,PERMITS,BONDS,FEES,ENGINEERING
•ACCESS DOORS,LOUVERS,ATTIC/EAVE/SOFFIT/WALL VENTS,BID BND RATE 2%
•ELECTRICAL,PLUMBING,CONDENSATE DRAIN,ROOFING&CONCRETE
•WEEKENDS&HOLIDAYS,WOOD NAILERS,DEMO,FLUID APPLIED
•COST FOR WAIVER(S)OF SUBROGATION($100.00 PER ENTITY NAMED),IF REQUIRED
"WE BRING FUCTIONALITY&EXCEPTIONAL CRAFTSMANSHIP IN METAL TO LIFE"
SUBCONTRACT CHANGE-ORDER PROPOSAL
24-112 Environmental Compliance Center
FOUR C'S CONSTRUCTION "Em
1560 H.STREET,
FRESNO,CA 93721
CA LICENSE#:908294 CONSTRUMON
DIR#: 1000002824(EXP.06/30/25)
PROPOSAL •- •
CHANGE ORDER NO.: 5 CHANGE CLARIFICATION: Internal Gutter
SUBMITTED DATE: 10/17/2025 PLAN SET VERSION:
EXPIRATION DATE: 10/31/2025 PLAN SET DATE:
TO: Kacey Earls FROM:Anthony Rios
• • Supply all labor,materials and equipment to complete the following scope of work.Scope of work is per specifications,plans
and manufacturer's recommendations.
SUBCONTRACTOR ITEMIZED BREAKDOWN OF WORK
DESCRIPTIONMATERIAL • AMOUNT
24ga Galy.Gutter W/Gutter Screen 1.00 1 $ 1.00 $ 950.00
Paint Additional 50sf 50.00 $ 6.50 $ 325.00
24ga Gutter Fabrication 70.00 $ 1.85 $ 129.50
rice change rom original gu ter price of 35 o 3
hich totals to $950 of increase cost per subcontractor.
SALE TAX 1 8.25% $ 115.87
TOTAL: $ 1,520.37
LABOR NO.HOURS RATE AMOUNT
PREP TIME/FIELD MEASUREMENTS $
SUPERVISION $
OT SUPERVISION $ -
FIELD WORK 48.00 $ 152.28 $ 7,309.44
OT FIELD WORK $ -
PRE-CONSTRUCTION/DRAFTING $
TRAVEL TIME $
TOTAL: $ 7,309.44
EQUIPMENT • DAYSIWEEKS RATE AMOUNT
Reach Fork I $
Fork Lift 10k
SALE TAX 8.25% $
TOTAL: $
JOB COST
DELIVERY/FREIGHT COST
ENGINEERING
TOTAL: $
TOTAL DIRECT COST $ 8,829.81
OVERHEAD/PROFIT 15% $ 1,324.47
CCP TOTAL:1 $ 10,154.28
SCHEDULEIMPACT
ADDITIONAL CREW DAYS REQUIRED 1 5
DUE TO THIS CHANGE-ORDER
NOTE:ADDITIONAL CREW DAYS IS ESTIMATE BASED ON
VARYING CREW SIZE.