HomeMy WebLinkAbout2304C CCO 07.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7 FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025 CONTRACT NO. 23-04-C PAGE 1 OF 3 TO: AVISON CONSTRUCTION, INC.: Make the following change(s) to the plans and specifications or do work not in the plans and specifications for this contract. Because of the proposed change, 201 -WORKING DAYS will be granted to the allotted contract time. The revised date of completion for the Second Order of Work is October 10, 2025. PART I: INCREASE / DECREASE / ELIMINATE ITEMS AT UNIT PRICES Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item quantities to the actual quantities used. Increased Items: Item Total Total No. Description Unit Quantity Price Amount of/0) o„u) 27 Hot Mix Asphalt (Type A, 1/2" TON 10.63 $104.00 $1,105.52 8.79 8.79 Grading) 48 Paint HMA Dike (White) LF 1,864.00 1.00 1,864.00 981.05 981.05 53 Thermoplastic Traffic Stripe LF 200.00 2.00 400.00 3.06 3.06 (Detail 39) TOTAL INCREASE: $3,369.52 Decreased Items: Item Total Total No. Description Unit Quantity Price Amount o� ° 32 Place Type A '/2" Grading HMA SY 413.82 $18.00 $7,448.76 (51.73) (51.73) (Miscellaneous Area) 33 Tack Coat TON 1.14 1,000.00 1,140.00 (14.25) (14.25) 37 24—Inch Reinforced Concrete LF 3.00 185.00 555.00 (2.14) (2.14) Pipe (Class III, Rubber Gasket Joint) TOTAL DECREASE: $9,143.76 Eliminated Items: Item Total Total No. Description Unit Quantity Price Amount % °� 1 Supplemental Work (Payment $ 80,000.00 $1.00 $80,000.00 (100.00) (100.00) Adjustment for Price Index Fluctuations) _Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Mgmt therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7 FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025 CONTRACT NO. 23-04-C PAGE 2 OF 3 TOTAL DECREASE: $80,000.00 Since you did not incur any costs associated with these items, no payment will be made for these bid items. This work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART I: $85,774.24 DECREASE TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS PART II: GRANT A TIME EXTENSION Grant a time extension of 187 working days to the "Second Order of Work" due to long lead times for material delivery, PG&E connection delays, City of Fresno punch list inspections and repairs, and the Departments design & request for change order extra work, in accordance with Section 8-1.07B, "Time Adjustments," of the Special Provisions. Grant the contractor a thirteen-working day time extension for unsuitable working conditions due to the rain/wet surface conditions, and one working day for the new Juneteenth Holiday. Weather Day & Holiday Extension Summary/Reference Weather Day November 26, 2024 1 Working Day Weather Day November 27, 2024 1 Working Day Weather Day December 12, 2024 1 Working Day Weather Day December 24, 2024 1 Working Day Weather Day February 13, 2025 1 Working Day Weather Day February 14, 2025 1 Working Day Weather Day March 5, 2025 1 Working Day Weather Day March 6, 2025 1 Working Day Weather Day March 13, 2025 1 Working Day Weather Day March 14, 2025 1 Working Day Weather Day March 17, 2025 1 Working Day Weather Day April 1, 2025 1 Working Day Holiday June 19, 2025 1 Working Day Weather Day September 19, 2025 1 Working Day Total Weather Days 14 Working Days TOTAL COST PART II: ($0.00) NO COST TOTAL TIME EXTENSION PART II: 201 -WORKING DAYS Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Mgmt therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7 FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025 CONTRACT NO. 23-04-C PAGE 3 OF 3 NET COST THIS CHANGE ORDER: $85,774.24 DECREASE NET TIME EXTENSION THIS CHANGE ORDER: 201 -WORKING DAYS James Drews, Resident Engineer APPROVAL RECOMMENDED: AVISON CONSTRUCTION, INC. Contractor Mandeep S. Sekhon, PE Construction Engineer By APPROVED BY: Digitally signed by Steven Steven White White Project Manager Date:2025.11.03 Title 10:13:03-08'00' Steven E. White, Director Nov 3,2025 Public Works and Planning Accepted Date: Date: Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be _Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.Mgmt therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.