HomeMy WebLinkAbout2304C CCO 07.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025
CONTRACT NO. 23-04-C PAGE 1 OF 3
TO: AVISON CONSTRUCTION, INC.:
Make the following change(s) to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the proposed change, 201 -WORKING DAYS will be granted to the allotted contract
time. The revised date of completion for the Second Order of Work is October 10, 2025.
PART I: INCREASE / DECREASE / ELIMINATE ITEMS AT UNIT PRICES
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total Total
No. Description Unit Quantity Price Amount of/0) o„u)
27 Hot Mix Asphalt (Type A, 1/2" TON 10.63 $104.00 $1,105.52 8.79 8.79
Grading)
48 Paint HMA Dike (White) LF 1,864.00 1.00 1,864.00 981.05 981.05
53 Thermoplastic Traffic Stripe LF 200.00 2.00 400.00 3.06 3.06
(Detail 39)
TOTAL INCREASE: $3,369.52
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount o� °
32 Place Type A '/2" Grading HMA SY 413.82 $18.00 $7,448.76 (51.73) (51.73)
(Miscellaneous Area)
33 Tack Coat TON 1.14 1,000.00 1,140.00 (14.25) (14.25)
37 24—Inch Reinforced Concrete LF 3.00 185.00 555.00 (2.14) (2.14)
Pipe (Class III, Rubber Gasket
Joint)
TOTAL DECREASE: $9,143.76
Eliminated Items:
Item Total Total
No. Description Unit Quantity Price Amount % °�
1 Supplemental Work (Payment $ 80,000.00 $1.00 $80,000.00 (100.00) (100.00)
Adjustment for Price Index
Fluctuations)
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025
CONTRACT NO. 23-04-C PAGE 2 OF 3
TOTAL DECREASE: $80,000.00
Since you did not incur any costs associated with these items, no payment will be made for these bid items.
This work did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: $85,774.24 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: GRANT A TIME EXTENSION
Grant a time extension of 187 working days to the "Second Order of Work" due to long lead times for material
delivery, PG&E connection delays, City of Fresno punch list inspections and repairs, and the Departments
design & request for change order extra work, in accordance with Section 8-1.07B, "Time Adjustments," of the
Special Provisions.
Grant the contractor a thirteen-working day time extension for unsuitable working conditions due to the rain/wet
surface conditions, and one working day for the new Juneteenth Holiday.
Weather Day & Holiday Extension Summary/Reference
Weather Day November 26, 2024 1 Working Day
Weather Day November 27, 2024 1 Working Day
Weather Day December 12, 2024 1 Working Day
Weather Day December 24, 2024 1 Working Day
Weather Day February 13, 2025 1 Working Day
Weather Day February 14, 2025 1 Working Day
Weather Day March 5, 2025 1 Working Day
Weather Day March 6, 2025 1 Working Day
Weather Day March 13, 2025 1 Working Day
Weather Day March 14, 2025 1 Working Day
Weather Day March 17, 2025 1 Working Day
Weather Day April 1, 2025 1 Working Day
Holiday June 19, 2025 1 Working Day
Weather Day September 19, 2025 1 Working Day
Total Weather Days 14 Working Days
TOTAL COST PART II: ($0.00) NO COST
TOTAL TIME EXTENSION PART II: 201 -WORKING DAYS
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 7
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 29, 2025
CONTRACT NO. 23-04-C PAGE 3 OF 3
NET COST THIS CHANGE ORDER: $85,774.24 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 201 -WORKING DAYS
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
AVISON CONSTRUCTION, INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steven
Steven White White
Project Manager Date:2025.11.03
Title 10:13:03-08'00'
Steven E. White, Director
Nov 3,2025 Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.