HomeMy WebLinkAbout2214C CCO 33.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 33 MISSION ST TO AMERICAN AVE OCTOBER 2, 2025 CONTRACT NO. 22-14-C PAGE 1 OF 2 TO: YARBS GRADING AND PAVING, INC: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time. REPAIR SINKHOLE AT TODD AND WHITSON STREETS INTERSECTION This change was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, repair the sinkhole found near the south median nose of Todd and Whitson Streets intersection. This work includes saw cutting the existing asphalt pavement around the sinkhole, exploratory excavation and necessary repairs to the damaged utilities, if needed, backfilling and compacting, and placing hot mix asphalt to match the existing thickness. Perform all work according to the applicable sections of the Standard Specifications and/or Special Provisions. Compensation for this work will be made at force account at time and material basis in accordance with Section 9-1.03, "Payment Scope," of the Standard Specifications and Special Provisions. Total compensation resulted in $9,799.82, this amount will be paid as extra work. These changes did not impact the critical path for the project, therefore, granting additional contract time was not warranted. _Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors Const.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 33 MISSION ST TO AMERICAN AVE OCTOBER 2, 2025 CONTRACT NO. 22-14-C PAGE 2 OF 2 NET COST THIS CHANGE ORDER: A $9,799.82 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS Jersephene Vang, Resident Engineer APPROVAL RECOMMENDED: YARBS GRADING AND PAVING, INC. (�"or`'' Contractor Mandeep S. Sekhon, PE Construction Engineer By TroyYarr ugh(Oc[D1.z02510:• 13PDT) APPROVED BY: Digitally signed by Steve 10/24/2025 Steve White le Date:Date:2025.10.24 Title 14:52:39-07'00' Steven E. White, Director Accepted Date: Oct 24,2025 Public Works and Planning Date: ---LAC Ernest Buddy Mend s, Chairman Board of Supervisors Date: A'-3- Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Ccnst.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.