HomeMy WebLinkAbout2305C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
WATERWORKS DISTRICT 41 SHAVER LAKE CHANGE ORDER NO. 1
HYDROPNEUMATIC TANK REPLACEMENT OCTOBER 16, 2025
CONTRACT NO. 23-05-C PAGE 1 OF 2
TO: SHAVER LAKE CONSTRUCTION, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 222 -WORKING DAYS will be added to the contract time for the First
Order of Work. The revised completion date is November 4, 2024, for the First Order of Work. 17 -WORKING
DAYS will be added to the contract time for the Second Order of Work. The revised completion date is July 11,
2025, for the Second Order of Work.
PART I: INSTALL ANCHOR BOLTS RE-DESIGN— EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install the re-
design of the hydropneumatic tank anchor bolts. Perform all work according to the applicable sections of the
Special Provisions and/or Standard Specifications, as directed by the Resident Engineer. Payment for this
work will be made at agreed lumpsum amount of$873.79according to Section 9-1.03, "Payment Scope," of the
Special Provisions. This agreed price includes all materials, labor, equipment, and markups and profits, no
additional compensation will be made thereafter. This amount will be paid through Bid Item No. 1,
Supplemental Work with no net increase to the contract amount.
A time extension of 17-working days will be added to the "Second Order of Work" for the above referenced
extra work, in accordance with Section 8-1.07B, "Time Adjustments," of the Special Provisions.
TOTAL COST PART I: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART I: 17 -WORKING DAYS (SECOND ORDER OF WORK)
PART II: GRANT A TIME EXTENSION (FIRST ORDER OF WORK)
This time extension was requested by the contractor.
Grant a time extension of 222-working days to the "First Order of Work" due to the additional time
required for the submittals process and long-lead items. This time extension is being granted according
to Section 8-1.07B, "Time Adjustments," of the Special Provisions.
TOTAL COST PART II: $0.00 (NO COST)
TOTAL TIME EXTENSION PART IL 222 -WORKING DAYS (FIRST ORDER OR WORK)
PART III: DECREASE ITEMS AT UNIT PRICES
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
WATERWORKS DISTRICT 41 SHAVER LAKE CHANGE ORDER NO. 1
HYDROPNEUMATIC TANK REPLACEMENT OCTOBER 16, 2025
CONTRACT NO. 23-05-C PAGE 2 OF 2
Decreased Item:
Item Total Total
No. Description Unit Quantity Price Amount (0/6) °�2
1 Supplemental Work $ 4,126.21 $1.00 $4,126.21 (82.52) (82.52)
TOTAL DECREASE: $4,126.21
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART III: $4,126.21 DECREASE
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
NET COST THIS CHANGE ORDER: $4,126.21 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 17 -WORKING DAYS (SECOND ORDER OR WORK)
NET TIME EXTENSION THIS CHANGE ORDER: 222 -WORKING DAYS (FIRST ORDER OR WORK)
AZUL ARIAS, Resident Engineer
APPROVAL RECOMMENDED:
SHAVER LAKE CONSTRUCTION
Contractor MANDEEP S. SEKHON, PE
Construction Engineer
Ru UalY
By Bill Blair(Oct 21,2025 14:04:59 PDT) APPROVED BY:
Digitally signed by Steven
Owner Steven White atle:2025.10.21
Title 15:54:36-07'00'
STEVEN E. WHITE, Director
Oct 21,2025 Public Works and Planning
Accepted Date:
Date:
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.