CONTRACT CHANGE ORDER
Project: DBH Olive Avenue Campus Remodel Contractor: BMY Construction Group, Inc.
Contract No.: 24-S-09 Address: 5485 E.Olive Ave., Fresno,CA 93727
Date: 2025-09-18
Architect: Barry Mast
Change Order No.: 1
Construction Contract Dollar Amount(as awarded on 2025-04-22) $17,687,000.00
Director's Change Order Limit: $210,000.00
Change Order Allowance $1,2389090.00
Construction Start Date(NTP Issued 2025-07-25): 2025-07-28
Contract Time(Working Days): 250
Original Construction Completion Date: 2026-07-28
Change Order Scope of Work:
PCO#001-Arc Flash Testing 8 Days $14,490.00
PCO#002-New Sprinker Heads and Trim 0 Days $3,563.91
Attachment(s):
Change Order Summary,Contractors PCO,Subcontractor's Price Proposal
Net Change Order Dollar Amount: $189053.91
Net Working Days: 1 8
Total Change Order Dollar Amount To Date $189053.91
Adjusted Contract Dollar Amount: $17,705,053.91
Director's Change Order Limit Balance: $191,946.09
Change Order Allowance Balance: $1,2209036.09
Total Adjusted Working Days To Date: 8
Adjusted Construction Completion Date: 2026-08-07
By signing acceptance of this Change Order, the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in this Change Order.
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 24-S-09,Article VI shall apply.
�y�Me�eirrrs�
Reviewed: BMY Construction Group, Inc. Dylan P.,ece rOs,Sep o.20 S1050 PD
General Contractor
Reviewed: Keith M. Eckert 11 �s�=
Kciti Fckrrt iScp lH.Ji JT PDT
Senior Engineering Technician, Project Manager
lamie Sylvester
Reviewed-Cleared for Approval Jamie Sylvester Jamie Sylvester(S,19,20250920147 PDT'.
Principal Accountant
Reviewed: Barry Mast 7D
Supervising Architect,Architect of Record
Reviewed: Mandeep Sekhon
Construction Division Engineer, Construction Manager
Reviewed: William M. Kettler
Deputy Director of Planning
/J OAN/'A/J�. /LNdif,O.�/
Reviewed: Bernard Jimenez Dernard n„ene=;SeP24.2� _1442I PI,
Planning&Resource Management Officer
seeveil White
Approved: Steven E. White Sten,Wh,—S,p 4,2025155413 PDT;
Director of Public Works and Planning
Approved: Ernest"Buddy"Mendes Not Applicable
Board of Supervisors, Chairman
CONTRACT CHANGE ORDER SUMMARY
Project: DBH Olive Avenue Campus Remodel
Change Order 'Wor
•. Days Potential Change Orders
1 2025-09-18 $18,053.91 $0.00 8 Includes PCO: 1,2
Totals $18,053.91 $0.00 8
Potential
Change Orders C $) redit Rejected Pending Adj. Da Description
1 1 $14,490.00 8 Arc Flash Study
2 1 $3,563.91 0 New Sprinker Heads and Trim
Totals $18,053.91 $0.00 $0.00 $0.00
CONSTRUCTION
GROUP INCORPORATED
August 12, 2025
The County of Fresno
Attn: Keith Eckert
2220 Tulare St
Fresno, CA 93721
Re: DBH Olive Ave. Campus Remodel
BMY JOB NO.23026
Subject: PCO#001 Arc Flash Report
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for the purpose of conducting arc
flash testing.
BMY is requesting that the County of Fresno issue a Change Order, adding $14,490.00 to the contract
price. In order to perform the work, BMY is requiring a time extension of 8 working days.
This PCO is valid for 30 days. Due to the unprecedented times in our industry, with volatile material
pricing and delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is
currently having supply issues. The cost of material is on a consistent rise, and it is not as readily
available, with lead times getting longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down, and get
materials and products.At this time, we need your assistance with timely approvals so we can minimize
project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further
information, please do not hesitate to contact me.
Respectfully,
Chris Prince
Project Engineer
CC: Dylan Medeiros
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559) 243-4200 • Fax (559) 222-2380
Lic No. 686178
PCO #001
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group,Inc. Project: 25007-DBH OLIVE AVENUE CAMPUS REMODEL
5485 East Olive Avenue 5555 E Olive Ave
Fresno,California 93727-2541 Fresno,California 93727
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #001 : CE #001 - Arc Flash Study
TO: The County of Fresno,Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 001 /0 CONTRACT: CONTRACT#24-S-09/BMY Project
#25007-DBH OLIVE AVENUE CAMPUS
REMODEL
REQUEST RECEIVED FROM: Cesar Moreno(Bergelectric Corp.) CREATED BY: Chris Prince(BMY Construction Group,
Inc.)
STATUS: Pending-In Review CREATED DATE: 7/24/2025
REFERENCE: PRIME CONTRACT #001 -July Approved PCO's
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: DBH Olive ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30 Days
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 8 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $14,490.00
POTENTIAL CHANGE ORDER TITLE: CE#001 -Arc Flash Study
CHANGE REASON: Client Request
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #001 - Arc Flash Study
Since the building hasn't been occupied for a long time, an arc flash study is required before any
electrical work can begin.
BMY is requiring a time extension of 8 working days.
ATTACHMENTS:
24SO9 PCO 001_0 Arch Flash Testing CR f
# Budget Code Description Amount
1 26-OOOO.S Electrical/BERG Arch Flash Study $13,800.00
Subtotal: $13,800.00
Fee(3.00%Applies to All Line Items): $414.00
Insurance(1.00%Applies to All Line Items): $138.00
Bond(1.00%Applies to All Line Items): $138.00
Grand Total: $14,490.00
BMY Construction Group,Inc. Page 1 of 2 Printed On:8/12/2025 02:53 PM
PCO #001
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:8/12/2025 02:53 PM
bBergelectric
Date: August 06,2025
Dylan Medeiros
BMY Construction Group Inc.
5485 E Olive Ave,
Fresno, CA, 93727
Project: DBH Olive Ave. Campus Remodel(PWS)
Berg Work Order# 132778
Customer Contract: N/A
Subject: Berg Change Order#001
Description: Existing Equipment Arc Flash Study
Dear Dylan Medeiros:
Enclosed is one copy of our cost breakdown sheets covering the electrical work for the subject change.
Please forward your approved change order adding $13,800.00 to our contract for the above referenced
change order and a 0 man day time extension.
See attached list of exclusions and clarifications.
The status of the work contained in this change order is:
Work on Hold Pending Direction
X Completed Work
Work in Progress
Time Extension Required
Written Notice To Proceed is Required
This proposal is based on the usual elements such as labor, materials, and normal markup and does not
include any amount for interference, disruptions, rescheduling, change in the sequence of work, delays
and/or associated acceleration. We expressly reserve the right to submit our request for any of these
items should we be faced with performing our work under any of these conditions. This change proposal
is limited to modifications involving our original scope of work. This cost proposal supercedes all
previously submitted cost proposals relating to this same work. This quote is valid for 30 calendar days
from the submission date and void thereafter. Work which may be required to complete this change order
which the work of other trades and/or not specifically itemized herein is not a part of this change
proposal. As Contractors,we reserve the right to correct our quote for errors or omissions.
Please reference the Berg change order number listed above when issuing a sub-contract modification for
this subject change.
Sincerely,
BERGELECTRIC CORPORATION
Cesar Moreno
Project Manager
Bergelectric Corp. Contractors & Engineers
11
August 6,2025
Project: DBH Olive Ave.Campus Remodel
5555 E.Olive Ave
Fresno, CA 93727
Subject: RFI 003/PR 01 Arc Flash Study
Scope of Change:
The attached proposal is based on RFI 003/PR 01 which asked Berg to provide a proposal for an arc flash
study for the existing equipment. The attached includes all sub and Berg costs for this study.
Clarifications:
1) See attached documentation for breakdown of costs for labor
Exclusions:
1) Overtime, Double time&shift work
2) Standard Contract Exclusions apply
Labor Adjustments
Foremen and General Forman.
■ Includes added plan review,field review of currently installed systems against prior plans, redesign
coordination, as built or red-line drawings,test and checkout, commissioning, as well as mark ups
for detailing and estimating coordination.
2. Recap sheet shows Per Diem at 100%for the percentage of the crew who is receiving Per Diem.
Material Adjustments:
1) Misc. Material is estimated at 3%of material cost to include materials that are not easily quantifiable to
include but not limited to augers, back brace, batteries, buckets, cleaning solvents,cutting oil, dies, drill
bits, eye protection,first aid (kit), garbage collectors (trash cans, bins, etc.), hacksaw blades, hand gloves,
hard hats, hoses, knockout seals, lubricant(WD-40), marking paint, material due to unforeseen and
routing changes (ie 4 sq pull boxes,couplings and routing changes, cuts,etc.), pulling soap, PVC
cement, rags,silicone, string,tape(electrical, marking, duct, masking),temporary supports (wood),
visqueen (plastic product protection),water&ice,tie wire,and zip ties. Due to the size,complexity, as
well as the production factor of this change the misc. material factor has not been included on this
change.
2) Small tool is estimated at 4%of labor cost to include tools that are commonly utilized on the project
and frequently need to be replaced due the repetitive use to include but not limited to: brooms,
brushes, burke bars, come-along, conduit benders,crowbar, digging bar, drill motors,forming stakes,
grinders, hammer, hand knockout sets, hand pipe cutters, hand saws, hand threader, hand truck, hand
wire bender, heater, heater—PVC, high voltage gloves and matts, loop wire insertion tool, measuring
tape, pick pipe wrench, power actuated tools, power cords and adapter,screw drivers,shovels, socket
sets, stud puncher,traffic control,vacuum,wire cutters,wire strippers, and wrenches.
• All change order requests are priced using industry standard Accubid 11 or higher version software.
750 W. Pinedale Avenue, Fresno CA 93711
Tel 559.860.2590 1 C10-85046
• Material costs are maintained and updated electronically to Accubid via TradeService;a Trimble
company. Material cost changes are automatically uploaded once a week to ensure current market
pricing is utilized.
• Submitted cost is valid for 30 days;after 30 days costs may be subject to change and will be revised as
necessary.
• The estimated material quantities are input into estimating software to establish the material costs and
labor hours. Material pricing has been adjusted to incorporate just-in-time deliveries due to storage
and handling limitations presented by the building site, crane/pick deliver requirements, and the lack of
material storage available on site. Basic material pricing is tracked via TradeService material pricing
software and labor hours are quantified through Accubid estimating software which references the
current year's NECA manual of labor units. Large equipment and/or major system changes are
forwarded to the respective vendor or manufacturer and a revised bill of material with associated pricing
is reissued.
• The above interpretation of the change in our scope of work is based solely on the documents as noted
above. Any additional electrical work necessitated by revisions to the architectural, structural,
mechanical, documents and drawings of this change if any,and not specifically noted on the
aforementioned documents are expressly excluded from the above listed interpretation. Further,this
change proposal pricing does not include any costs for changes in sequence, delays, disruptions,
rescheduling,time extensions or accelerations to the work and extended overhead beyond those
specific items as listed and priced in this proposal. Bergelectric Corp.expressly reserves the right to
compensation and notice of potential claim made,for any and all of the aforementioned costs and
related items noted as not being included in this cost proposal.
750 W. Pinedale Avenue, Fresno CA 93711
Tel 559.860.2590 1 C10-85046
bBergelectric
REQUEST FOR 11333 Sunrise Park Drive I Rancho Cordova,CA 195742
CHANGE ORDER
Dylan Medeiros Phone#: 559-417-8643 Project: DBH Olive Ave.Campus Remodel(PWS)
5485 E Olive Ave, Fax#: 5555 E Olive Ave.,Fresno,CA,93727
Fresno,CA,93727
P.M.: Moreno,Cesar Berg Work Order#: 132778
Berg C/O# 001
G.C.Ref.#
Description Existing Equipment Arc Flash Study Date:08/06/2025
Lump Sum Change Order
Sheet No. Material Pricing Sheets Material Cost Direct Labor Hours
1
2
3
4
5
6
7
8
9
10
Other Labor Costs Hours Rate Total Total Listed Material $0.00
TOTALS 0.00 $0.00 Misc.Material 1 3.00% $0.00
Sub-Total $0.00
Sales Tax 8.35% $0.00
Material Cost $0.00
Labor Costs
Direct Labor Hours 0.00
Multiply by Labor Rate
Direct Labor Cost $0.00
Other Labor Costs $0.00
Sub-Total $0.00
Mark-up15.00°/u $0.00
TOTALS $0.00
Job Expenses
Rental Costs TOTALS
Description Duration Unit Rate Total Total Rental Costs $0.00
Subtotal Total Material Costs $0.00
Rental Tax 8.35% $0.00 Total Job Expense $0.00
TOTALS $0.00 Sub-Total $0.00
Mark-up 15.00% $0.00
Subcontractor Costs Sub-Total $0.00
Subcontractor Total Total Subcontractor Cost $12 000.00
Power Engineering Experts $12,000.00 Mark-up 15.00% $1,800.00
Subcontractor Total $13,800.00
C.O.Sub-Total $13,800.00
Bond 1 0.00% $0.00
TOTALS $12,000.00 SELLING PRICE $13,800.00
The listed price is good for 30 Day
Comments:We request a time extension of 0 days.
CONSTRUCTION
GROUP INCORPORATED
September 8, 2025
The County of Fresno
Attn: Keith Eckert
2220 Tulare St
Fresno, CA 93721
Re: DBH Olive Ave. Campus Remodel
BMY JOB NO.25007
Subject: PCO#002 Exterior Sprinkler Heads and Trim
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for new exterior fire sprinkler
heads and trim.
BMY is requesting that the County of Fresno issue a Change Order, adding $3,563.91 to the contract
price. In order to perform the work, BMY is requiring a time extension of 0 working days.
This PCO is valid for 30 days. Due to the unprecedented times in our industry, with volatile material
pricing and delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is
currently having supply issues. The cost of material is on a consistent rise, and it is not as readily
available, with lead times getting longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down, and get
materials and products.At this time, we need your assistance with timely approvals so we can minimize
project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further
information, please do not hesitate to contact me.
Respectfully,
Chris Prince
Project Engineer
CC: Dylan Medeiros
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559) 243-4200 • Fax (559) 222-2380
Lic No. 686178
= PCO #002
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group, Inc. Project:25007-DBH OLIVE AVENUE CAMPUS REMODEL
5485 East Olive Avenue 5555 E Olive Ave
Fresno,California 93727-2541 Fresno,California 93727
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #002: CE #005 - New Sprinkler
Heads and Trim
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 002/0 CONTRACT: CONTRACT#24-S-09/BMY Project
#25007-DBH OLIVE AVENUE CAMPUS
REMODEL
REQUEST RECEIVED FROM: Josh Johnson(Johnson Fire Protection) CREATED BY: Chris Prince(BMY Construction Group,
Inc.)
STATUS: Pending-In Review CREATED DATE: 9/8/2025
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: DBH Olive ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30 Days
WILL EXPIRE AFTER:
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $3,563.91
POTENTIAL CHANGE ORDER TITLE: CE#005-New Sprinkler Heads and Trim
CHANGE REASON: Existing Condition
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#005-New Sprinkler Heads and Trim
We are highly recommending that the sprinklers be changed due to excessive corrosion due to the exterior environment. Frankly the sprinklers are far
worse than the trim.At the next 5-year inspection they will most likely fail as a result and require changing anyway.Would be far cheaper to do it during
the construction phase than when the facility is up and running.
In Addition,OSFM states that when a sprinkler is removed for any reason it cannot be re-installed.All of the existing heads will be subject to this as all
heads require removal to replace the sprinkler trim.
ATTACHMENTS:
24SO9 PCO 002_0 Fire Sprinkler CP.pdf
# I Budget Code Description Amount
1 21-OOOO.S Fire Sprinklers/JOHNSON New Heads and Trim $3,394.20
Subtotal: $3,394.20
Fee(3.00%Applies to All Line Items): $101.83
Insurance(1.00%Applies to All Line Items): $33.94
Bond(1.00%Applies to All Line Items): $33.94
Grand Total: $3,563.91
BMY Construction Group, Inc. Page 1 of 2 Printed On:9/8/2025 10:45 AM
PCO #002
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:9/8/2025 10:45 AM
JOHNSON 732 N. Elko Street
Visalia, Ca 93291
FIRE (559)651-1882
PROTECTION >eptember 1st 202!
Change Order Request Change Order# 1
To: BMY Construction Group REQUEST TYPE
5485 E. Olive Ave CHANGE ORDER ✓
Fresno, CA EXTRA WORK
BACK CHARGE
OTHER
Contact: PM &SUPERINTENDENT
Project: DBH TI Summary PER OWNER REQUEST, ADD THE EXTERIOR
FRESNO, CA OVERHANGS SPRINKLERS TO DRAWINGS AND
CHANGE TO NEW HEADS AND TRIM
Labor
Hours
Foreman 1 8.00 $125.00 $1,000.00
Journeyman 1 0.00 $105.00 $0.00
Apprentice 8.00 $95.00 $760.00
Labor Total $1,760.00
Materials
Item Quantity Cost per
PI pe 0.00 $0.00 $0.00
Fittings 0 $0.00 $0.00
Alum Trim 64 $7.13 $456.32
Sprinklers 64 $12.88 $824.32
Material Total $1,280.64
Lift Equipment Days Cost per day
0 0 $0.00 $0.00
0 0 $0.00 $0.00
Lift Total $0.00
Supervision &Admin Costs $45.00
Subtotal $3,085.64
OH/Prof $308.56
Total Change Order Amount: $ 3,394.20