HomeMy WebLinkAbout2415C CCO 04.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE CHANGE ORDER NO. 4
REPLACEMENT SEPTEMBER 11, 2025
CONTRACT NO. 24-15-C PAGE 1 OF 2
TO: DG CONCTRUCTION, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
PART I: ADJUST COMPENSATION FOR THE USE OF PEA GRAVEL INSTEAD OF SAND FOR PIPE
BEDDING
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, use 3/8"-1/2"
pea gravel as the placement for bedding in the bottom of trench instead of sand bedding to place 6-inch HDPE
pipe on Flintridge Road and Cordwood Road. Payment for the additional cost will be paid at an agreed unit
price of$35.00 per ton for the difference of cost of pea-gravel ($52.00 per ton pea-gravel)to sand ($17.00 per
ton) being placed, according to Section 9-1.03, "Payment Scope," of the Special Provisions. A total of 66.86
tons of 3/8"-1/2" pea gravel was delivered to the job site; the additional compensation resulted in (66.86 tons x
$35.00 per ton = $2,340.10). This amount covers trucking, labor, and placing material. Total compensation for
this work resulted in a $2,340.10 increase, this amount will be paid through Bid Item No. 1, Supplemental Work
with no net increase to the contract amount.
This work did not impact the critical path for the project, so granting additional contract time was not warranted
TOTAL COST PART I: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: EXCAVATE SEWER LATERAL AND REPAIR—EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, excavate the
sewer lateral at Sta. 18+90 (Cordwood Road) to repair a broken sewer lateral. Perform all work according to
the applicable sections of the Special Provisions and/or Standard Specifications, as directed by the Resident
Engineer. Payment for this work will be made as extra work at Force Account according to Section 9-1.03,
"Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $2,902.38 increase,
this amount will be paid through Bid Item No. 1, Supplemental Work with no net increase to the contract
amount.
Two (2) working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments," of the Project Specifications.
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE CHANGE ORDER NO. 4
REPLACEMENT SEPTEMBER 11, 2025
CONTRACT NO. 24-15-C PAGE 2 OF 2
TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART II: TWO (2) -WORKING DAYS
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NO. 1)
NET TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
�o6ontyYutc�C.�ae�
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
DG Construction, Inc. 04�-�ak'
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By a � APPROVED BY:
Digitally signed by Steve
President Steve White White
Date:2025.09.23
Title 14:38:32-07'00'
Steven E. White, Director
Accepted Date:
Sep 16,2025 Public Works and Planning
Date:
_Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors rites shown above.
_Const.Management p
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.