HomeMy WebLinkAbout2326C CCO 05.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 5
CONTRACT NO. 23-26-C JULY 25, 2025
PAGE 1 OF 2
TO: WEST VALLEY CONSTRUCTON COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
INCREASE ITEMS AT UNIT BID PRICES
This change was proposed by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, increase
items at the unit bid prices. These bid items are being adjusted per the actual field placement.
Increased Items:
Total
Item Description Unit Quantity Price Amount (0/.) TOTAL
No. (0/6)
2-16A Water Meter Box(1324) EA 42.00 $550.00 $23,100.00 2,100.00 4,300.0
Replacement
2-16B Water Meter Box Lid EA 1.00 225.29 225.29 20.00 0.00
(1336) Replacement
2-25B Water Meter Box Lid EA 18.00 153.15 2,756.70 163.64 (23.68)
(B30) Replacement
2-28A Water Meter Box Lid EA 1.00 108.00 108.00 9.09 50.00
(1316) Replacement
5 Water Meter EA 50.00 120.00 6,000.00 200.00 275.00
Replacement
6 Water Meter Box EA 1.00 465.00 465.00 8.33 (87.00)
Replacement
15 Water Meter Box Lid EA 4.00 113.00 452.00 14.81 (20.51)
(1316) Replacement
20 Water Meter Box Lid (139) EA 2.00 92.00 184.00 4.55 228.57
Replacement
23 Water Meter Retrofit EA 4.00 113.00 452.00 9.76 9.76
24 Water Meter Box Lid (139) EA 1.00 92.00 92.00 4.35 20.00
Replacement
25 Water Meter Box Lid EA 1.00 140.00 140.00 100.00 (96.00)
(1324) Replacement
27 Water Meter Retrofit EA 3.00 113.00 339.00 4.48 4.48
TOTAL INCREASES: $34,313.99
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 5
CONTRACT NO. 23-26-C JULY 25, 2025
PAGE 2OF2
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
NET COST THIS CHANGE ORDER: $34,313.99 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
.Po6utyS��uc�c.�ee�
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
West Valley Construction Co., Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
Assistant Vice President Steve White White
Date:2025.08.25
Title 10:16:39-07'00'
Steven E. White, Director
Aug 18,2025 Public Works and Planning
Accepted Date:
Date:
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.