HomeMy WebLinkAbout2415C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE CHANGE ORDER NO. 3
REPLACEMENT JULY 23, 2025
CONTRACT NO. 24-15-C PAGE 1 OF 2
TO: DG CONSTRUCTON, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), SEVEN (7) -WORKING DAYS will be added to the contract timeline.
EXCAVATE WATERMAIN TRENCH TO ADDITOINAL 6-INCH DEPTH AND EXCAVATE A DRAINAGE
TRENCH — EXTRA WORK
This change was proposed by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, excavate the
watermain trench to an additional 6-inch depth between Sta. 10+00 and Sta. 10+50 (Flintridge Drive) to place
additional gravel bedding and excavate a drainage trench from the watermain alignment to the roadside
drainage ditch at Sta. 10+00 to dissipate the natural springs' water. Perform all work according to the
applicable sections of the Special Provisions and/or Standard Specifications, as directed by the Resident
Engineer. Payment for this work will be made as extra work at Force Account according to Section 9-1.03,
"Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $5,094.04 increase,
this amount will be paid through Bid Item No. 1, Supplemental Work with no net increase to the contract
amount.
Seven (7) working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments," of the Special Provisions.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices Shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE CHANGE ORDER NO. 3
REPLACEMENT JULY 23, 2025
CONTRACT NO. 24-15-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NO. 1)
NET TIME EXTENSION THIS CHANGE ORDER: SEVEN (7) -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
DG Construction, Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
President Steve White White
Date:2025.08.12
Title 10:45:46-07'00'
Steven E. White, Director
Accepted Date:
Jul 29,2025 Public Works and Planning
Date:
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business Office noted above, and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.