Loading...
HomeMy WebLinkAbout2313C CCO 03.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER CSA 30 & 32 WELL SITE IMPROVEMENTS AND CHANGE ORDER NO. 3 MANGANESE TREATMENT JULY 30, 2025 COUNTY SERVICE AREAS 30 & 32 EL PORVENIR & CANTUA CREEK PAGE 1 OF 1 COUNTY OF FRESNO WESTSIDE GROUNDWATER PROJECT STATE WATER RESOURCES CONTROL BOARD— PROJECT NUMBER: 1000359-005C CONTRACT NO. 23-13-C TO: SYBLON REID CONTRACTORS: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), 56 -WORKING DAYS will be added to the contract time for the First Order of Work. The completion date for the First Order of Work is July 24, 2025. GRANT A TIME EXTENSION: This change was requested by the contractor. Grant a time extension of 56 working days to the First Order of Work, Submittals due to the Departments review and approval time exceeding the 10 working days (contract requirements) for several different submittals. The time extensions shall apply according to Section 8-1.07B, "Time Adjustments," of the Special Provisions. NET COST THIS CHANGE ORDER: $0.00 (NO COST) NET TIME EXTENSION THIS CHANGE ORDER: 56 -WORKING DAYS (FIRST ORDER OF WORK) JAMES DREWS, Resident Engineer APPROVAL RECOMMENDED: SYBLON REID CONTRACTORS 0, - 0 Contractor MANDEEP S. SEKHON, PE Construction Engineer wiCG scoK- By APPROVED BY: Digitally signed by Steve Steve White White President,Syblon Reid Construction Inc.,Partner Date:2025.07.31 Title 09:48:53-07'00' STEVEN E. WHITE, Director Jul 30,2025 Public Works and Planning Accepted Date: Date: Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.