HomeMy WebLinkAbout2304C CCO 06.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 6 FEDERAL PROJECT NUMBER: CML-5942(293) JUNE 17, 2025 CONTRACT NO. 23-04-C PAGE 1 OF 2 TO: AVISON CONSTRUCTION, INC.: Make the following change(s) to the plans and specifications or do work not in the plans and specifications for this contract. Because of the proposed change, THREE (3) -WORKING DAYS will be granted to the allotted contract time. PERFORM EXTRA WORK This extra work was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, perform the following extra work: • Sawcut approximately 1' from the edge of the pavement to excavate, grade, and compact subgrade to build and place a 3' wide x 250' long x 0.25' thick hot mix asphalt (HMA) shoulder extension and install approximately 250' of(Type E) HMA dike along the eastside of Fowler Avenue, south of Olive Avenue approximately between Sta. 95+40 to 97+90. The HMA dike shall have tapered openings installed to allow drainage at every 25'. The finished dike shall be painted white. Provide all labor, materials, equipment, and incidentals for completing this work. • Excavate and grade new drainage ditches to the dimensions shown in the revised drainage Sheet Nos. 1 & 2 (attached) at the northwest and southwest corner. The work includes installing check dams within the existing drainage ditch as depicted in the revised plan sheets. Provide all labor, materials, equipment, and incidentals for completing this work. Perform all work according to the applicable sections of the Standard Specifications and the Special Provisions. Payment for this work will be made as extra work at an agreed lumpsum price of$31,000, according to Section 9-1.03, "Payment Scope," of the Special Provisions. This amount will be paid as extra work. Three (3) working days will be added to the contract time for the above referenced extra work, in accordance with Section 8-1.07B, "Time Adjustments," of the Project Specifications. Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.Mgmt therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 6 FEDERAL PROJECT NUMBER: CML-5942(293) JUNE 17, 2025 CONTRACT NO. 23-04-C PAGE 2 OF 2 NET COST THIS CHANGE ORDER: $31,000 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: THREE (3) -WORKING DAYS James Drews, Resident Engineer APPROVAL RECOMMENDED: AVISON CONSTRUCTION, INC. 0.-�JX � Contractor Mandeep S. Sekhon, PE Construction Engineer By APPROVED BY: Digitally signed by Steve Project Manager Steve White White Date:2025.06.24 Title 13:55:55-07'00' Steven E. White, Director Jun 23'2025 Public Works and Planning Accepted Date: Date: Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials, except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Mgmt therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. Cut/Fill Summary � 1I Name Cut Factor Fill Factor 2d Area Cut Fill Net Surface Volume South 1.000 1.000 4485.33 Sq. Ft. 171.58 Cu. Yd. 0.00 Cu. Yd. 171.58 Cu. Yd.<Cut> Surface Volume North 1.000 1.000 3752.86 Sq. Ft. 47.53 Cu. Yd. 0.08 Cu. Yd. 47.45 Cu. Yd.<Cut> Totals 8238.19 Sq. Ft. 219.10 Cu. Yd. 0.08 Cu. Yd. 219.03 Cu. Yd.<Cut> CONSTRUCT CHECK DAMS EVERY 100FT FOR NEXT SOOFi NORT SURFACE VOLUME SOUTH(FOWLER) 96.3 CU.YD TOP OF DAM ELEVATION IS 6" ABOVE EXISTING FL TOTAL ALL SURFACES 315.4 CU.YD BUT CAN NOT BE HIGHER THEN EP ELEVATION LJ Q / FL 332.00 I+ STA. 99+39.92, -62.75 � I� GRADE BACKSLOPE jgpp PUS/ X _ 3:AT 6:1 TO DAYLIGHT FL 331.50 I STA. 99+12.91, -31.94 ( I FL 31.50 3STA. 98+75.40, -29.96� GRADE BACKSLOPE RAW P FL 331.80 AT 6:1 TO DAYLIGHT STA. 97+38+70, -24.88 FL 331.50 FL 331.80 STA. 98+48.36, -29.57 ) _ _ GRADE BACKSLOPE J STA. 97+94.63, -25.73 / I / `:b / - - - - AT 2:1 TO DAYLIGHT 33300 ---- 9.15 V9/ STA 99+4 - - - - - - - - -^ -FL 331.80 _ / / �- - �9`50" _ r 0.65 ,,. __.._��_/ STA. 9^+r,83'74. - / `° 32.50 - = �A - 332.50= +.y., i �y.. -- -- ��-3332.00 3 - /.. _ A 24 17 32 00 _332.00=-_- - - - -- - _ � 0 332.50 �o - �OP AT 6.1 TODAYLIGHT L P RADE FORES 0 E 332.00 _ _ _ _- - -332.00 - - - - 32.50 _--.vi -_ -�n __ _ -332.50=�ri `n _ ^�' - _ - 333.00- DAI Li�T _ _ - - 332.50-- -Q _ E) FL-- --- E __ _- - FL 331.50 CEP 333.00 - - _-_ E) EPHP FADE FORESLOPE STA. 99+26.90`/32.0o4 \ E) H � P FL 331.84 FL 331.80 AT 6:1 TO DAYLIGHTAV4 WAY 96+00 E) EP 97+00 STA. 97+10+72, -24.35 98+00 - -STA. 98+21.05, -25.78- 99+00 _ FL 331.80 GRADE FORESLOPE OL_IVE ABLE- - - - STA. 97+66.07, -25.24 AT 5:1 TO DAYLIGHT HORIZ 0 20' 40' - - 6"PVC Irrig. Valve 4t Wi n,; - -�' --- ' - ' F - - Row of Olive Trees -- -- -- - -- - - - - - - _- - - - -- CKFL _ -- - - - - - - - - - - - - ---- O, ---- - FL 330.70 ,5 ORb STA. 92+97.25, 29.69 90 37 91+00 __----OLIVE AVE �3 -- STA 9FL 0 3+025.71, 27.77 94+00 (E) E (E) H �,S - - - - - - (E) E -_-_-- --- - -- -- - _ p� (E) H (E) FL - - - - - FL 330.70 - -- - -_ _ - - - - -_ STA. 93+52.1 1,_28.13_ -- --OG 3,31.46 - OG 332.31 Q--- - __- Q BOG 331.40 E) EP AC D-y --- -- OG 332.36 - - FL 330.70 to( FL 330J0R STA. 90+45.14, 28.26 -" - " �I�N.. (E) PP PROTECT FL 3 A72 + IQ GRADE BACKSLOPE Row of Oleanders STA. 92+08.46, 28.38 �Q IN PLACE - - ��,�., �I <STA. 3+78.1�;35?TSF AT 2:1 TO DAYLIGHT FL 330.70 FL 330.70 FL 330.70 STA. 91+52.81, 28.81 FL 330.70 E Gob STA. 90+45.28, 34.39 STA. 92+75.41, 34.34 RADE TO DAYLIGHT FL 330.70 FL 330.70 STA. 92+08.45, 33.15 STA. 91+01.23, 28.86 STA. 91+52+80, 32.85 GRADE BACKSLOPE o AT 2:1 TO DAYLIGHT FL 330.70 AT 2:1 TO DAYLIGHT FL 330.70 FL 330.70 STA. 91+01.21, 32.53 STA. 92+97.40, 34.66 FL 33 . FL 330.70 STA. 92+45.88, 28.64 STA. 93+25.80, 34.76 STA. 93+52.04, 34.77 HORIZ 0 20' 40' DATE RECORD DRAWING SCALE ,Caw AlPROJECT �, CID DEPARTMENT OF PUBLIC WORKS AND PLANNING DESIGNED: EC 4-7-25 RESIDENT ENGINEER DATE ,yA FOWLER AVE&OLIVE AVE INTERSECTION DRAWN: EC 4-7-25 QyQ' .�� tSs �� IMPROVEMENT PROJECT OLIVE WEST DITCH EXHIBIT CHECKED: S.ARTAL 4-7-25 � SUPERVISING ENGINEER DATE S � ➢��� FORRIGHTOF WAV DATA AND ACCURATE ACCESS DETERMINATION,SEE DOCUMENTS IN THE DEPARTMENT OF PUBLIC WORKS AND PLANNING. ROAD NO. D0600 BRIDGE NO. N/A -PR��� DRAWING NO. 11302 SHEET NO. 1 TOTAL 2 OLIVE AVE _ (E) DIKE — (E) EP EL: 332.46 \" (E) EP EL: 332.44 (E) --- __ STA. 99+58.14, -95.01 Q Q e15 GB FL 332.08 I ss I STA. 99+50.15, -94.69 \ / FL 332.05 STA. 99+50.74, -79.70 i \ GRADE BACKSLOPE \ AND FORSLOPE AT 2:1 TO DAYLIGHT 1 FL 331.97 STA. 99+22.54, -52.55 1 a a, rn o FL 331.91 10 I STA. 98+97.24, -46.19 FL 331.91 4.> III 6> _ I STA. 98+97.25, -36.19 GRADE BACKSLOPE AT 4:1 OR FLATTER TO DAYLIGHT Q 4'7 ol 61 -GRADE FORESLOPE LJ \ AT 6:1 TO FL o III I I n O FL 331.91 o I E) HP STA. 98+07.23, -36.15 E) DIKE FL 331.91 4.�f ' STA. 98+07.23, -46.15 n L/ E) EP + 4 d rn 0 HORIZ 0 20' 40' I + ro m rn cif rn 2 J I o C/Gr el Drwy c� I Q G�' I I DATE RECORD DRAWING SCALE ,Caw 1 PROJECT �, coU DEPARTMENT OF PUBLIC WORKS AND PLANNING DESIGNED: EC 4-7-25 RESIDENT ENGINEER DATE �S 4, ��� ,y1 FOWLER AVE&OLIVE AVE INTERSECTION DRAWN: EC 4-7-25 IMPROVEMENT PROJECT ''' FOWLER SOUTH DITCH EXHIBIT CHECKED: S.ARTAL 4-7-26 v� SUPERVISING ENGINEER DATE S � ➢��� FOR RIGHT OF WAY DATA AND ACCURATE ACCESS DETERMINATION,SEE DOCUMENTS IN THE DEPARTMENT OF PUBLIC WORKS AND PLANNING. ROAD NO. D0600 BRIDGE NO. N/A PR��� DRAWING NO. 11302 SHEET NO. 2 TOTAL 2