HomeMy WebLinkAbout24S08 CCO 003 Stakeholders Set_SIGNED.pdf CO
County of Fresno
t Department of Public Works and Planning
O� O Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: DBH Olive Avenue Roof Replacement&Fagade Repairs
Contract No.: 24-S-08
Date: 2025-05-15
Contractor: Fortune-Ratliff General Contractor,Inc.
Architect: Robina Wright
Change Order No.: 003
Construction Contract Dollar Amount(BAI 73 2024-12-17) $3,165,830.00
Director's Change Order Limit: $170,791.50
Contract Time(Calendar Days): 137
Construction Start Date(NTP Issued 2025-03-05): 2025-03-05
Original Construction Completion Date: 2025-07-19
Change Order Scope of Work:
PCO#008-Damaged Plywood&Joist Replacement
PCO#009-RFI 16_0 Parapet Cap Flashing
Attachment(s):
Contractors PCO,Change Order Summary
Net Change Order Dollar Amount: $3,826.00
Net Calendar Days: 0
Total Change Order Dollar Amount To Date $100,925.00
Adjusted Contract Dollar Amount: $3,266,755.00
Director's Change Order Limit Balance: $69,866.50
Total Adjusted Calendar Days To Date: 10
Adjusted Construction Completion Date: 07/29/25
Reviewed-
Cleared for Jamie Sylvester Digitally signed by Jamie Sylvester
Approval Jamie Sylvester Date:2025.06.16 09:15:29-07'00'
Principal Accountant,Public Works&Planning
Digitally signed by Barry Mast
Reviewed: Barry Mast Date:2025.06.16 09:43:02-07'00'
Supervising Architect,Architect of Record
Reviewed: Keith M. Eckert 11 Keith Eckert 6.16.25
Senior Engineering Technician,Project Manager
Mandeep S. Sekhon Digitally signed by Mandeep S.Sekhon
Reviewed: Mandeep Sekhon . Date:2025.06.17 13:31:45-07'00'
Construction Division Engineer,Construction Manager
William M Kettler Digitally signed by William M.Kettler
M.Reviewed: William M. Kettler Date:2025.06.17 14:11:15-07'00'
Deputy Director of Planning
Bernard Jimenez Digitally signed by Bernard Jimenez
Reviewed: Bernard Jimenez Date:2025.06.18 08:01:30-07'00'
Planning&Resource Management Officer
Steve White Digitally signed by Steve White
Approved: Steven E. White Date:2025.06.18 08:15:41-07'00'
Director of Public Works and Planning
Approved: Buddy Mendes Not Applicable
Board of Supervisors, Chairman
Scan and forward Director Approved Copy to:
CAO Paul Nerland
PWP Business Office Jamie Sylvester
co County of Fresno
t Department of Public Works and Planning
O� O Development Services&Capital Projects Division
FR�S� Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: DBH Olive Avenue Roof Replacement&Facade Repairs
Contract No.: 24-S-08
Date: 2025-05-15
Contractor: Fortune-Ratliff General Contractor,Inc.
2485 East Olive Avenue
Fresno,CA 93727
(559)243-4200
Change Order No.: 003
Construction Contract Dollar Amount(BAI 73 2024-12-17) $3,165,830.00
Original Construction Completion Date: 2025-07-19
Change Order 003 is hereby approved by the County.
Scope of Work:
PCO#008-Damaged Plywood&Joist Replacement
PCO#009-RFI 160 Parapet Cap Flashing
Attachment(s):
Contractors PCO,Change Order Summary
Net Change Order Dollar Amount: $3,826.00
Net Calendar Days: 10
Adjusted Contract Dollar Amount: $3,266,755.00
Total Change Order Dollar Amount To Date: $100,925.00
Total Adjusted Calendar Days To Date: 10
Adjusted Construction Completion Date: 2025-07-29
Keith M.Eckert 11 Keith Eckert
Project Manager
Date: 5.16.25
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 24-S-08,Article VI shall apply.
Accepted By: Fortune-Ratliff General Contractor,Inc. Adam Myles
D ed by Adam Myles Authorized Signature
DN.C=US, 9
Adam IeS CN=Adam Mylesnerstliffwm,
Date:2025 05 16 09:18:25-07'00' Date: 5/1 6/2 5
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
hndaguerra9fresnocountyca.gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: DBH Olive Avenue Roof Replacement& Fapade Repairs
-1 Executed 1q". 1V0RWFC-redit1(F0Ws Description
Change Order
1 2025-03-21 $6,111.00 $0.00 0 Includes PCO#1,2,3
2 2025-04-23 $90,988.00 $0.00 10 Includes PCO#4.1,5,6.1,7
3 2025-05-15 $3,826.00 $0.00 0 Includes PCO#8,9
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
Totals $100,925.00 j $0.00 1 10
Proposed Executed
MLAdd
W
Change • • •
1 1 $2,003.00 0 Sheet metal flashing at soffit ASI-01
2 1 $1,824.00 0 RFI 090 Panel Patching
3 1 $2,284.00 0 ODU Platform per PR01 and RFI 12
4 $3,406.00 0 RFI 070 Roof Conduit Removal
4.1 2 $3,104.00 0 RFI 070 Roof Conduit Removal
5 2 $2,445.00 0 RFI 080 Expansion Joints
6 $26,902.00 5 RFI 14 0 Parapet Plywood Demo
6.1 2 $25,679.00 5 RFI 140 Parapet Plywood Demo
7 2 $59,760.00 5 Replacement of Roof Drains&Overflow Drains
8 3 $1,601.00 0 Damaged Plywood&Joist Replacement
9 3 $2,225.00 0 RFI 160 Parapet Cap Flashing
Totals $100,925.00 $0.00 $30,308.00 $0.00
FORTUNE/RATLIFF
` GENERAL CONTRACTORS, INC.
CA. LICENSE:496147
PCO# 8_0
DBH Olive Ave. Roof Replacement& Fagade Repairs Date: 5/1/2025
Fresno, CA.
Attn: Keith Eckert $739.00/ Daily Rate CP# 08
CC: Mandeep Sekhon Schedule Impact (Days): 0
Re: Damaged Plywood &Joist
Replacement-April 2025
Keith:
We herewith submit our Proposed Change Order to provide and install replacement of damaged plywood and joists
uncovered during existing roofing demolition per Absolute Urethane's attached proposals and previously approved
unit costs.This covers plywood &joist replacement for the month of April 2025. Costs for future plywood &joist
replacement will be submitted monthly.
SUB/SUPPLIER NAMES DESCRIPTION
Absolute Urethane Replace three (3)joists $ 450.00
Absolute Urethane Replace four(4) plywood sheets $ 1,040.00
SUB TOTAL $ - $ 1,490.00
Liability Insurance & BR 1.35% $ - $ 20.12
Subtotal SUB TOTAL $ - $ 1,510.12
P&P Bonds 1.00% $ - $ 15.10
Subtotal SUB TOTAL $ - $ 1,525.22
Fortune-Ratliff, Inc. OH & P 5% $ - $ 76.26
TOTAL CP $ - $ 1,601
Please review and advise as to the acceptance of this cost proposal. If you have any questions, please
do not hesitate to contact me.
Sincerely, Accepted by:
Keith Eckert, County of Fresno
By:
Adam Myles,Vice President Date:
352 W.Bedford#107,Fresno,CA. 93711 - P.O.Box 26944,Fresno,CA. 93729 - Phone:(559)432-1306 Fax:(559)432-2878
Absolute Change Order
6614 S Elm Ave
Fresno, CA 93706 Date Estimate#
3/12/2025 250053CO2
Name/Address Ship To
352 W.Bedford,#107 5555 E.Olive Ave
Fresno,CA 93711 Fresno,Ca 93727
P.O Box 26944
Fresno CA 93729
Project
DBH Olive Ave
Description Qty Rate Total
replacement of damaged or rotten 2x6x8 wood joist @$150 per 3 150.00 450.00
April joist replacement
Total $450.00
Absolute Change O rd e r
6614 S Elm Ave
Fresno, CA 93706 Date Estimate#
3/3/2025 250053COl
Name/Address Ship To
352 W.Bedford,#107 5555 E.Olive Ave
Fresno,CA 93711 Fresno,Ca 93727
P.O Box 26944
Fresno CA 93729
Project
DBH Olive Ave
Description Qty Rate Total
-Price to Remove,Dispose,and replace standard 5/8 plywood 4 260.00 1,040.00
sheathing @$260 per 4x8 sheet
April ply wood replacment
Total $1,040.00
FORTUNE/RATLIFF
` GENERAL CONTRACTORS, INC.
CA. LICFNSF 496147
PCO# 9_0
DBH Olive Ave. Roof Replacement& Fagade Repairs Date: 5/9/2025
Fresno, CA.
Attn: Keith Eckert $739.00/ Daily Rate CP# 09
CC: Mandeep Sekhon Schedule Impact:
Re: RFI 16_0 Response
Keith:
We herewith submit our Proposed Change Order to provide and install a continuous sheet metal cleat at the
parapet caps to allow for adequate slope per RFI 16 response.
SUB/SUPPLIER NAMES DESCRIPTION
Absolute Urethane Revised parapet cap cleat $ 2,070.00
SUB TOTAL $ - $ 2,070.00
Liability Insurance & BR 1.35% $ - $ 27.95
Subtotal SUB TOTAL $ - $ 2,097.95
P&P Bonds 1.00% $ - $ 20.98
Subtotal SUB TOTAL $ - $ 2,118.92
Fortune-Ratliff, Inc. OH & P 5% $ - $ 105.95
TOTAL CP $ - $ 2,225
Please review and advise as to the acceptance of this cost proposal. If you have any questions, please
do not hesitate to contact me.
Sincerely, Accepted by:
Keith Eckert, County of Fresno
By:
Adam Myles,Vice President Date:
352 W.Bedford#107,Fresno,CA. 93711 - P.O.Box 26944,Fresno,CA. 93729 - Phone:(559)432-1306 Fax:(559)432-2878
RFI NO.: 16 0
FORTUNE/RATLIFF DATE: 5/8/2025
GENERAL CONTRACTORS, INC.
CA.LICENSE 4.1 147
REQUEST FOR INFORMATION
TO Keith Eckert ATTN: Keith Eckert
Senior Engineering Technician CC: Barry Mast
The County of Fresno
Department of Public Works and Planning
F/R JOB#: 2408
PROJECT: DBH Olive Ave.Roof Replacement&Fagade Repairs PROJECT NO.:
KEY DESCRIPTION: Parapet Cap Flashing
DRAWING: H3/A-802,H10/A-802 SPECIFICATION:
ATTACHED SHEETS: ❑ YES OR ❑ NO
QUESTION: Details H3&H10 on sheet A-802 indicate an existing sloped nailer beneath the parapet cap flashing.There
is not an existing sloped nailer.The existing condition is a flat nailer without any slope. Please see attached photos and
advise.
Need Answer By: ASAP
ADDITIONAL COST: ® YES OR [-] NO
TIME DAYS
SUGGESTION: The sheet metal supplier has devised the attached detail to accomplish the proper slope.
Contractor Signature: CA,11 LZ 4- Project Superintendent
ATTACHED SHEETS: ❑ YES OR ❑ NO
REPLY: _
County Response (Barry Mast 2025-05-0q)
Proposed revised continuous cleat is acceptable as detailed below (see p. 5). verify that overlap on exterior
wall below parapet cap nailer is equal or greater than 1" as noted below.
Change Order Required: Z Yes or H No
Owner Representative Signature: Date:
Absolute Change Order
6614 S Elm Ave
Fresno, CA 93706 Date Estimate#
5/7/2025 250053CO3
Name/Address Ship To
352 W.Bedford,#107 5555 E.Olive Ave
Fresno,CA 93711 Fresno,Ca 93727
P.O Box 26944
Fresno CA 93729
Project
DBH Olive Ave
Description Qty Rate Total
change cleat to have kick up do to no slope on parapet 2,070.00 2,070.00
price difference in metal:$1,800.00 taxes included
x%15=$2,070.00
Total $2,070.00