HomeMy WebLinkAbout2415C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE
REPLACEMENT CHANGE ORDER NO. 2
CONTRACT NO. 24-15-C JUNE 12, 2025
PAGE 1 OF 2
TO: DG CONSTRUCTON, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), THREE (3) -WORKING DAYS will be added to the contract timeline.
REPLACE 2-INCH SDR 11 HDPE PIPE WITH 3-INCH SDR 11 HDPE PIPE
This change was proposed by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace all the
2-inch SDR 11 HDPE Pipe (total of 740 linear feet) with 3-inch HDPE SDR 11 HDPE pipe throughout the
project. This change also eliminates three (3) 2-inch gate vales assemblies (Bid Item No. 20) and adds three
(3) 3-inch gate vales assemblies (Bid Item No. 21). Compensation for the price difference in material for the
pipe will be made at an agreed lumpsum price of$791.43, and compensation for upsizing the three (3) valve
assemblies to 3-inch, will be adjusted in Bid Items No. 20 and 21 as shown below at the unit bid prices in
accordance with Section 9-1.03, "Payment Scope," of the Special Provisions.
Eliminated Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/6) °r/o
20 2" Gate Valve Assembly EA 3.00 $2,567.00 $7,701.00 100.00 100.00
TOTAL DECREASE: $7,701.00
Increased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/0) °�
21 3" Gate Valve Assembly EA 3.00 $2,794.00 $8,382.00 100.00 100.00
TOTAL INCREASE: $8,382.00
Total compensation adjustment resulted in an increase of$1,472.43, a portion of the total compensation
adjustment, $791.43 will be paid as extra work and the remaining $681.00 will be adjusted through Bid Item
Nos. 20 and 21.
Three (3)working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments," of the Special Provisions.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
_Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
CSA 1 TAMARACK WATER INFRASTRUCTURE
REPLACEMENT CHANGE ORDER NO. 2
CONTRACT NO. 24-15-C JUNE 12, 2025
PAGE 2OF2
NET COST THIS CHANGE ORDER: $1,472.43 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: THREE (3) -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
DG Construction, Inc. I 'AX��
Contractor Mandeep S. Sekhon, PE
q Construction Engineer
By � O APPROVED BY:
Digitally signed by Steve
PRESIDENT Steve White White
Date:2025.06.16
Title 16:30:01-07'00'
Steven E. White, Director
Accepted Date:
Jun 16,2025 Public Works and Planning
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified, and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.