HomeMy WebLinkAbout2407C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
EAST REEDLEY BRIDGE REPLACEMENTS CHANGE ORDER NO. 2
REEDLEY MAIN CANAL BRIDGE REPLACEMENT ON ENGLEHART APRIL 23, 2025
AVENUE: BRLO-5942(239) PAGE 1 OF 4
TRAVERS CREEK BRIDGE REPLACEMENT ON LINCOLN AVENUE: BRLO-5942(226)
TRAVERS CREEK BRIDGE REPLACEMENT ON PARLIER AVENUE: BRLO-5942(227)
CONTRACT NO. 24-07-C
TO: CAL VALLEY CONSTRUCTION, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
INCREASE/DECREASE/ELEMINATE ITEMS AT UNIT BID PRICES
This compensation adjustment was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Item(s):
Item Total Total
No. Description Unit Quantity Price Amount
22 Hot Mix Asphalt (Type A) TON 0.41 $150.00 $61.50 0.10 0.10
23 Minor Hot Mix Asphalt TON 1.00 300.00 300.00 8.33 8.33
24 Cold Plane Asphalt Concrete SQYD 18.88 11.00 207.68 12.59 12.59
Pavement
50 Rolled Erosion Control SQFT 1,616.00 2.00 3,232.00 118.82 118.82
Product (Netting)
52 Survey Monument Well EA 1.00 2,000.00 2,000.00 100.00 100.00
66 Hot Mix Asphalt (Type A) TON 30.70 150.00 4,605.00 8.08 8.08
67 Minor Hot Mix Asphalt TON 5.73 160.00 916.80 8.19 8.19
68 Cold Plane Asphalt Concrete SQYD 119.90 11.00 1,318.90 17.63 17.63
Pavement
69 Minor Concrete CY 1.00 1,750.00 1,750.00 33.33 33.33
71 Rock Slope Protection (1501b, CY 94.70 400.00 37,880.00 16.61 16.61
Class III, Method B)
72 Rock Slope Protection Fabric SQYD 536.04 6.00 3,216.24 289.75 289.75
(Class 8)
73 Pavement Marker EA 2.00 16.00 32.00 4.00 4.00
(Retroreflective)
75 4" Yellow Thermoplastic LF 3.00 16.00 48.00 0.52 0.52
Traffic Striping (Detail 5,22)
103 Remove Yellow Painted LF 59.00 25.00 1,475.00 33.71 33.71
Traffic Stripe (Hazardous
Waste)
104 Relocate Fence LF 70.00 48.00 3,360.00 116.67 116.67
Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified, and will accept as full payment therefore the
Board of Supervisors prices shown above.
_Const.Management
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
EAST REEDLEY BRIDGE REPLACEMENTS CHANGE ORDER NO. 2
REEDLEY MAIN CANAL BRIDGE REPLACEMENT ON ENGLEHART APRIL 23, 2025
AVENUE: BRLO-5942(239) PAGE 2 OF 4
TRAVERS CREEK BRIDGE REPLACEMENT ON LINCOLN AVENUE: BRLO-5942(226)
TRAVERS CREEK BRIDGE REPLACEMENT ON PARLIER AVENUE: BRLO-5942(227)
CONTRACT NO. 24-07-C
122 Fence LF 1.00 82.00 82.00 6.67 6.67
124 Pavement Marker EA 10.00 16.00 160.00 55.56 55.56
(Retroreflective)
126 4" White Thermoplastic Traffic LF 306.00 12.00 3,672.00 102.00 102.00
Striping (Detail 27B)
127 4" White Thermoplastic Traffic LF 125.00 16.00 2,000.00 71.43 71.43
Striping (Detail 22)
TOTAL INCREASE: $66,317.12
Decreased Item(s):
Item Total Total
No. Description Unit Quantity Price Amount o� o�
12 Temporary High-Visibility Fence LF 120.00 $14.00 $1,680.00 (46.15) (46.15)
13 Remove Yellow Painted Traffic LF 107.00 25.00 2,675.00 (22.53) (22.53)
Stripe (Hazardous Waste)
25 Minor Concrete CY 7.50 2,200.00 16,500.00 (93.75) (93.75)
27 Pavement Marker(Retroreflective) EA 10.00 16.00 160.00 (50.00) (50.00)
29 4" White Thermoplastic Traffic LF 20.00 12.00 240.00 (2.27) (2.27)
Striping (Detail 27B)
30 4" Yellow Thermoplastic Traffic LF 124.00 16.00 1,984.00 (21.75) (21.75)
Striping (Detail 5,22)
31 Thermoplastic Pavement Marking SQFT 1.00 20.00 20.00 (5.26) (5.26)
58 Temporary High-Visibility Fence LF 160.00 12.00 1,920.00 (22.22) (22.22)
95 Rolled Erosion Control Product SQFT 139.00 2.00 278.00 (9.59) (9.59)
(Netting)
102 Temporary High-Visibility Fence LF 230.00 12.00 2,760.00 (53.49) (53.49)
112 Hot Mix Asphalt (Type A) TON 16.68 150.00 2,502.00 (5.38) (5.38)
113 Minor Hot Mix Asphalt TON 4.80 240.00 1,152.00 (21.82) (21.82)
116 Minor Concrete CY 5.50 2,000.00 11,000.00 (91.67) (91.67)
TOTAL DECREASE: $42,871.00
Contractor We, the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
EAST REEDLEY BRIDGE REPLACEMENTS CHANGE ORDER NO. 2
REEDLEY MAIN CANAL BRIDGE REPLACEMENT ON ENGLEHART APRIL 23, 2025
AVENUE: BRLO-5942(239) PAGE 3 OF 4
TRAVERS CREEK BRIDGE REPLACEMENT ON LINCOLN AVENUE: BRLO-5942(226)
TRAVERS CREEK BRIDGE REPLACEMENT ON PARLIER AVENUE: BRLO-5942(227)
CONTRACT NO. 24-07-C
Eliminated Item(s):
Item Total
No. Description Unit Quantity Price Amount ,(0/6) Total
4 AID Inspection Fee $ 1,000.00 $1.00 $1,000.00 (100.00) (100.00)
7 Lead Compliance Plan LS 1.00 1,000.00 1,000.00 (100.00) (100.00)
16 Relocate Roadside Sign EA 1.00 275.00 275.00 (100.00) (100.00)
46 AID Inspection Fee $ 1,000.00 1.00 1,000.00 (100.00) (100.00)
53 Lead Compliance Plan LS 1.00 500.00 500.00 (100.00) (100.00)
90 Temporary Water LS 1.00 50,000.00 50,000.00 (100.00) (100.00)
Diversion System
91 AID Inspection Fee $ 1,000.00 1.00 1,000.00 (100.00) (100.00)
97 Lead Compliance Plan LS 1.00 1,000.00 1,000.00 (100.00) (100.00)
114 Cold Plane Asphalt SQYD 10.00 150.00 1,500.00 (100.00) (100.00)
Concrete Pavement
TOTAL DECREASE: $57,275.00
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor approved,that we will provide all equipment,furnish all materials, except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
EAST REEDLEY BRIDGE REPLACEMENTS CHANGE ORDER NO. 2
REEDLEY MAIN CANAL BRIDGE REPLACEMENT ON ENGLEHART APRIL 23, 2025
AVENUE: BRLO-5942(239) PAGE 4 OF 4
TRAVERS CREEK BRIDGE REPLACEMENT ON LINCOLN AVENUE: BRLO-5942(226)
TRAVERS CREEK BRIDGE REPLACEMENT ON PARLIER AVENUE: BRLO-5942(227)
CONTRACT NO. 24-07-C
NET COST THIS CHANGE ORDER: $33,828.88 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
Cal Valley Construction, Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
chrli 6rl�fw
By Chri,Grimm(May 2,202515:46PDT) APPROVED BY:
Digitally signed by Steve
Operations Manager Steve White White
Date:2025.05.05
Title 12:27:41-07'00'
Steven E. White, Director
May 2,2025 Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors prices shown above.
_Const.Management
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.