HomeMy WebLinkAbout2422C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
HOUGHTON CANAL AT CHATEAU FRESNO AVE TREE REMOVAL CHANGE ORDER NO. 1
N. CHATEAU FRESNO AVE, 0.5 MILES SOUTH OF BELMONT AVE APRIL 9, 2025
FEDERAL PROJECT NUMBER: BRLO-5942(237) PAGE 1 OF 2
CONTRACT NO. 24-22-C
TO: JULIAN TREE CARE, INC.:
Make the following changes to the plans and specifications or do work not included in the plans and
specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to
the contract time.
DECREASE ITEMS AT UNIT PRICES
This compensation adjustment was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Decreased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount
4 Remove Grapevines EA 8.0 $76.00 $608.00 (3.60) (3.60)
TOTAL DECREASE: $608.00
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified, and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
HOUGHTON CANAL AT CHATEAU FRESNO AVE TREE REMOVAL CHANGE ORDER NO. 1
N. CHATEAU FRESNO AVE, 0.5 MILES SOUTH OF BELMONT AVE APRIL 9, 2025
FEDERAL PROJECT NUMBER: BRLO-5942(237) PAGE 2 OF 2
CONTRACT NO. 24-22-C
NET COST THIS CHANGE ORDER: A $608.00 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
n
Je if Parks(Apr 9,2025 14:55 PDT)
Jennifer Parks, Resident Engineer
APPROVAL RECOMMENDED:
Julian Tree Care, Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By JuliananTr�Inc.(Apr11,202509:30PDT) APPROVED BY:
Digitally signed by Steve
CEO Steve White White
Date:2025.04.11
Title 10:47:05-07'00'
Steven E. White, Director
Apr 11,2025 Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices Shown above.
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.