Loading...
HomeMy WebLinkAbout1807C CCO 09 Chairmans Approval.pdf 3-25-2� COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO COUNTY WESTSIDE GROUNDWATER PROJECT CHANGE ORDER NO. 9 EL PORVENIR(CSA 30)&CANTUA CREEK(CSA 32) JANUARY 30, 2025 PILOT HOLE TESTING AND PRODUCTION WELL CONSTRUCTION PAGE 1 OF 3 DRINKING WATER STATE REVOLVING FUND PROJECT NO: 1000359-005C CONTRACT NO. 18-07-C TO: ZIM INDUSTRIES, INC.: Make the following change(s)to the plans and specifications or do work not in the plans and specifications for this contract. Because of the proposed change(s),ZERO(0)-WORKING DAYS will be granted to the allotted contract time. PERFORM VARIOUS EXTRA WORK This extra work was request by the engineer and/or the contractor. Perform the referenced below various extra work in accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications. Upsize Pumps(Total Four) and Increase the Pumps' Setting Depths: • Upsize two(2) pumps from 20 HP to 30 HP; increase the pumps setting depth from 756 feet to 1197 feet; and utilize 3-inch Schedule 80 mild steel with heavy couplings in lieu of the Schedule 40 steel with standard couplings at County Service Area(CSA) 30, El Porvenir. • Upsize two(2) pumps from 40 HP to 50 HP; increase the pumps setting depth from 630 feet to 798 feet; and utilize 4-inch Schedule 80 mild steel with heavy couplings in lieu of the Schedule 40 steel with standard couplings at CSA 32, Cantua Creek. • Contactor's proposed cost for this work is$96,787.00 (see attached Exhibits A and B). Electrical Materials Cost Adiustment: • Adjust compensation for electrical materials costs' increase due to delays caused by the Covid- 19 pandemic and subsequent supply chain disruptions, and changes to the original project scope due to actual field conditions. • Contactor's proposed cost for the increased materials' is $55,929.37(see attached Exhibit C). Electrical Design Modifications: • Upsize wiring and soft starters to comply with the upsized pumps at CSA 30, El Porvenir, and CSA 32, Cantua Creek. • Contactor's proposed cost for this work is $10,480.70 (see attached Exhibit D). contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business orrice noted above,and perform all services necessary For the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. _RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and riling a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO COUNTY WESTSIDE GROUNDWATER PROJECT CHANGE ORDER NO. 9 EL PORVENIR(CSA 30)&CANTUA CREEK(CSA 32) JANUARY 30,2025 PILOT HOLE TESTING AND PRODUCTION WELL CONSTRUCTION PAGE 2 OF 3 DRINKING WATER STATE REVOLVING FUND PROJECT NO: 1000359-005C CONTRACT NO. 18-07-C Install Level Probes for Each Pump: • Install a total of four(4)low level cutout probes and relays(one(1)for each pump)to automatically shut off the pump if the water level drops to 50 feet above the pump bowls and to trigger a warning if the water level rises to 350 feet above the pump bowls. • Contactor's proposed cost for this work is $8,120(see attached Exhibit E). Install Future Pressure Switch Conduits: • Install at total of four(4)%-inch PVC conduits from the controller to the well head with the steel reinforcement support post, one at each well for the future pressure switches. • Contactor's proposed cost for this work is $5,065.87(see attached Exhibit F). Perform all work according to the applicable sections of the Standard Specifications, Special Provisions, and/or any other Specifications included in the contract documents Sum of contractor's proposals = $176,382.94. The negotiated lump-sum price for all above referenced extra work is$125,000.This negotiated price includes the offset of the liquidated damages caused by contractor's delays. Compensation for all above referenced extra work will be made at a lumpsum agreed price of$125,000 according to Section 9-1.03, "Payment Scope," of the Special Provisions. This agreed lumpsum price includes compensation for all labor,equipment, materials, tools, incidentals, markups, and profit. No additional compensation will be made.This amount will be paid as extra work. Time extensions were addressed in Contract Change Order No. 8, and no further time extensions will be granted. Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors _const.Management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO COUNTY WESTSIDE GROUNDWATER PROJECT CHANGE ORDER NO. 9 EL PORVENIR(CSA 30)&CANTUA CREEK(CSA 32) JANUARY 30,2025 PILOT HOLE TESTING AND PRODUCTION WELL CONSTRUCTION PAGE 3 OF 3 DRINKING WATER STATE REVOLVING FUND PROJECT NO: 1000359-005C CONTRACT NO. 18-07-C NET COST THIS CHANGE ORDER: $125,000 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO(0)-WORKING DAYS Jason Ahumada, Resident Engineer APPROVAL RECOMMENDED: Zlm Industries, Inc. Contractor Mandeep S. Sekhon, PE Construction Engineer By r APPROVED BY: Digitally signed by Estimator/PM Steve White�20 02,03 -idle 09:35:09-08,00, Jan 31,2025 Steven E.White, Director Public Works and Planning Accepted Date: Date: Ernest Buddy Mend , Chairman Board of Supervisors Date: 3 as ada S' ATTEST: BERNICE E.SEIDEL Clerk of the Board of Supervisors County of Fresno,State of California By Deputy _Contractor we,the above signed contractor,have given careful consideration to the change proposed and hereby agree,If _Auditor Controller this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Me noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors therefore the prices shown above. _Const.Management _RE/Arch. _Design if the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. FOR ACCOUNTING PURPOSES ORG: 9172 FUND: 0820 SUBCLASS: 16000 ACCOUNT: 8400 PROGRAM: 91293 Exhibit A Sekhon, Mandeep From: Wes Zimmerer <wes@zimindustries.com> Sent: Friday, December 13,2024 3:29 PM To: Sekhon, Mandeep; Curt Zimmerer; Robert Zimmerer Cc: Ahumada,Jason;Artal, Sebastian;Singleton, Richard; Evy Irlas-Mucino; Boyd Subject: RE: 1807C Fresno County Westside Ground Water Project-All Change Orders Attachments: Pump column submittals and request for pump change order.pdf, Exhibit 9.pdf; 1807C Fresno County Westside Groundwater Project- Extra Work WCDs 1, 2, and 3;PCO Electrical Material Cost Adjustments.pdf, PCO Electrical Design Modifications.pdf, PCO Level Probes.pdf, PCO Future Pressure Switch Conduit.pdf CAUTIONM - EXTERNAL EMAIL-THINK BEFORE YOU CLICK Report Suspicious Mandeep, Please find attached the proposed change orders related to pump equipment design updates(submitted March 20,2023), additional water pipe fittings(agreed to$6,000 subcontractor price August 15,2023),and various electrical adjustments, including larger HP soft starters and wire sizes,material cost adjustments, level probes, and future pressure switch conduit(submitted July 23,2024). These proposals reflect adjustments necessitated by changes in project conditions and design. Below is a summary of the proposed change orders: De_sclip_tton Date Amoito t Pump equipment design changes 3/20/2023 $96,787.00 °'2023 $;see.GG IPaid in CCO 06 Electrical material cost adjustments 7/23/2024 $55,929.37 Electrical design modifications 7/23/2024 $10,480.70 Level probes 7/23/2024 $8,120.00 Future pressure switch conduit 7/23/2024 $5,065.87 Total $+&3 Z8 9^ Regards, lRevised total = $176,382.94 Wes Zimmerer Negotiated lump-sum for all PCOs = $125,000 Estimator/P.M. Zim Indu3triC-s, Inc. 4532 E Jefferson Ave. Fresno, CA 93725 Phone(559)834-1551 Fax(559)834-5156 The information contained in this electronic transmission is intended only for the personal and confidential use of the designated addressee indicated,and is intended to be privileged and/or confidential.If the reader of this electronic transmission is not the intended recipient or addressee,you are hereby notified that you have received this electronic transmission in error,and that any review,dissemination,distribution or copying of this electronic transmission or any of the information contained herein,in any manner whatsoever,is strictly prohibited. If you receive this electronic transmission in error,please notify the sender immediately. Thankyou. 1 From:Sekhon, Mandeep<msekhon@fresnocountyca.gov> Sent:Tuesday, December 10,2024 8:58 AM To:Wes Zimmerer<wes@zimindustries.com>;Curt Zimmerer<curt@zimindustries.com>; Robert Zimmerer <bob@zimindustries.com> Cc:Ahumada,Jason<jahumada@fresnocountyca.gov>;Artal,Sebastian<sartal@fresnocountyca.gov>;Singleton, Richard <risingleton@fresnocountyca.gov> Subject: 1807C Fresno County Westside Ground Water Project-All Change Orders CAUTION:This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. Wes, As we discussed over the phone a couple of days ago, please submit all proposed change orders for us to consider for payment. Please note that this will be the final change order,which requires Board's approval.Originally,we were scheduled to take this item to the Board on January 7, 2025,however,we have surpassed the time to submit documents in advance and will have to push this date further back. Please submit all proposed change orders to us asap. Thanks Mandeep S. Sekhon, PEA Construction Engineer Department of Public Works and Planning I Construction V r' 2220 Tulare Street,7`h Floor, Fresno,CA 93721 Office: (559)600-7883 Cell:(559)250-7967 Vour input matters!Customer Service smvev. 2 Exhibit B 4532 E.Jefferson Ave. • Fresno, CA 93725 Ph. (559) 834-1551 • FAX (559) 834-5156 www.zimindustries.com March16,2023 County of Fresno Department of Public Works and Planning/Construction 2220 Tulare Street, 711'Floor Fresno,California 93723 Subject:Contract 18-07-C Fresno County Westside Groundwater Project 2—pumps&motors with 4-inch schedule80 steel column pipe x 798 feet located at CSA32 Cantua Creek 2—pumps&motors with 3-inch schedule80 steel column pipe x 1197 feet located at CSA30 El Porvenir Dear AJ/Mandeep, Below are Zim Industries, Inc.'s responses and answers to your follow-up questions regarding the above referenced pumps. 1) The County of Fresno is looking for a guarantee that the threaded coupler will not fail. Over the past several weeks we have been researching the recommended hang weights for 3-inch and 4-inch schedule 80 drop pipe equipped with the largest weight capacity couplings that are available in the pipe industry. We have requested from all of our pump suppliers their recommended maximum pump setting and hang weights utilizing both 3-inch and 4-inch schedule 80 mild steel pipe and 3K full heavy couplings and none of them were able to provide Us with this data. There has been a substantial change in both the depth of these four pump settings and the weight of these four pumps located at El Porvenir and Cantua Creek. There are several conditions that have changed since this project was originally bid including: 1)deeper pump settings on all four pumps;2) different larger capacity and longer submersible pump bowls; 3) different larger capacity submersible motors;4)thicker drop pipe/column pipe changing From schedule 40 to schedule 80 mild steel piping; 5) thicker couplings on both the 3-inch and 4-inch schedule 80 steel pipe; and 6) heavier total pump, motor and column water weights due to these required changes to meet these changes in the pumping conditions. The first chart(Exhibit 1) included in the attachments is a chart displaying the maximum suggested pump setting from Grundfos utilizing schedule 40 standard T&C Steel Pipe with standard couplings is 1250 feet for 3-inch I.D. pipe and 1100 feet for 4-inch I.D.pipe. A second chart(Exhibit 2) included in this attachment is from the Grundfos Engineering Manual displaying the pipe data for both 3-inch I.D. and 4-inch I.D.schedule 40 and schedule 80 pipe, but does not display a maximum suggested pump setting. The third thru fifth attached PDF files contains a summary of the calculated weights of both the 3-inch and 4-inch pumps including the water weight of the pumps with pump column pipe full of water for the following three pump designs: 1)the four pumps as originally specified and set to the originally contracted depths of 756 feet at El Porvenir and 630 feet at Cantua Creek utilizing schedule 40 mild steel column pipe and standard couplings as originally contracted(Exhibit 3);2)the four pumps that would be required to be set at the new required depths of 1197 feet at El Porvenir and 798 feet at Cantua Creek in order to meet the changes in the pumping conditions utilizing schedule 40 mild steel pipe and standard couplings(Exhibit 4); and 3) )the four pumps currently proposed to be set at the required depths of 1197 feet at El Porvenir and 798 feet at Cantua Creek in order to meet the changes in the pumping conditions utilizing schedule 80 mild steel pipe and heavy couplings(Exhibit 5). As stated above,we have had several conversations over the past several weeks with ail of our pump suppliers regarding the maximum recommended pump settings utilizing both schedule 40 black mild steel pipe with standard couplings for the 3-inch and 4-inch column pipe for these four pumps;and schedule 80 black mild steel pipe with heavy couplings for the 3-inch and 4-inch column pipe for these four pumps. Because no manufacturer or supplier was able to provide us with a recommended maximum hang weight or recommended maximum pump setting utilizing 3-inch and 4-inch schedule 80 mild steel pipe with heavy couplings to set these four pumps,we have calculated the estimated pump weights and compared these weights to the calculated joint strength of the 3-inch and 4-inch schedule 80 mild steel pipe with heavy couplings. In Exhibit#3,we have calculated the estimated pump weights of these four originally specified and contracted pumps full of water in order to display the total pump weights of the originally specified schedule 40 steel pipe pump settings. The estimated pump weight of each of the two 3-inch pumps full of water at CSA 30 set to a depth of 756 feet and specified utilizing 3-inch schedule 40 steel pipe and standard couplings is 11,118 pounds;and the estimated pump weight of each of the two 4-inch pumps full of water at CSA 32 set at 630 feet and specified utilizing 4-inch schedule 40 steel pipe and standard couplings is 13,606 pounds. The Grundfos chart(Exhibit 41)recommends that the maximum 3-inch pump setting utilizing schedule 40 mild steel pipe and standard couplings is 1250 feet or approximately I 18,387 pounds(14.71 pounds/foot x 1250 feet). The Grundfos chart also recommends that the maximum 4-inch pump setting utilizing schedule 40 mild steel pipe and standard couplings is 1100 feet or approximately 23,760 pounds(21.60 pounds,/foot x 1100 feet). Based upon these calculated pump i weights and Grundfos chart recommendations,all four originally specified and contracted pumps being set at their originally specified settings could be installed without any concern of their respective pump weights. All four pump total weights set at these originally contracted pump settings are less than 60% of the maximum recommended hang weights utilizing schedule 40 mild steel pipe and standard couplings. Additionally,(in Exhibit#4)we have calculated the estimated pump weights of these four pumps full of i water to assess whether the originally specified schedule 40 steel pipe with standard couplings will still work for these required new deeper required actual pump settings. The estimated pump weight of each of the two 3-inch mild steel pipe pumps full of water at CSA 30 set at 1197 feet and specified utilizing 3- inch schedule 40 steel pipe and standard couplings is 17,325 pounds;and the estimated pump weight of each of the two 4-inch schedule 40 mild steel pipe pumps full of water at CSA 32 set at 798 feet and specified utilizing 4-inch schedule 40 steel pipe and standard couplings is 16,736 pounds. The maximum setting utilizing 3-inch schedule 40 steel pipe and standard couplings is 1250 feet; and the maximum setting utilizing 4-inch schedule 40 steel pipe and standard couplings is 1100 feet. The two 3-inch schedule 40 mild steel pipe pumps at CSA 30 with settings of 1197 feet weigh 17,325 pounds and are at 9S%of the maximum weight limits of 18,387 pounds for utilizing schedule 40 steel pipe with standard couplings;and the two 4-inch schedule 40 mild steel pipe pumps at CSA 32 with settings of 798 feet weigh 16,736 pounds and are at 71%of the maximum weight limits of 23,760 pounds for utilizing schedule 40 steel pipe and standard couplings. Despite the fact that the total pump weights of these specified pumps utilizing schedule 40 pipe with standard couplings will stay below their respective maximum setting thresholds,we do not recommend utilizing schedule 40 mild steel pipe with standard couplings on these deep pump settings because both the schedule 40 pipe and the thinner wall standard couplings tend to flex and egg shape when these amounts of weight are hung from them. When the pipe and/or couplings flex and become egg shaped,there is a good chance that the threads won't hold, the pipe will slip out of the coupling,and the pump will be dropped. This potential joint failure could occur during both our initial installation or in the future when the pump is pulled for maintenance, rehabilitation or repair of either the well or the pump. Instead,on these four deep pump settings,we recommend that Fresno County utilizes schedule 80 mild steel pipe with heavy couplings because both the schedule 80 mild steel pipe and the heavy couplings are thicker and will not flex or become egg shaped when holding the pump weights of these deep pump settings. Furthermore,as discussed during our meeting on November 16, 2022,the thicker material of the schedule 80 steel pipe and heavy couplings will provide additional expected longevity for these four pumps. Finally, (in Exhibit#5)we have calculated the estimated pump weights of these four pumps full of water to display the weights of the required pumps set at the required deeper pump settings utilizing schedule 80 mild steel pipe with heavy couplings. The estimated pump weight of each of the two 3-inch pumps full of water at CSA 30 set at 1197 feet and specified utilizing 3-inch schedule 80 steel pipe and heavy couplings is 20,118 pounds;and the estimated pump weight of each of the two 4-inch pumps full of water at CSA 32 set at 798 feet and specified utilizing 4-inch schedule 80 steel pipe and heavy couplings is 19,655 pounds. We then calculated the joint strengths of 4-inch ID and 3-inch ID schedule 80 mild steel pipe with heavy couplings utilizing a safety factor of 3. Exhibit#6 displays the recommended maximum weight setting utilizing 3-inch schedule 80 steel pipe and heavy couplings is 23,138 pounds or 1376 feet(23,138 pounds /16.81 pounds per foot);and Exhibit#7 displays the recommended maximum weight setting utilizing 4- inch schedule 80 steel pipe and heavy couplings is 23,273 pounds or 944 feet(23,272 pounds/24.63 pounds per foot). The two 3-inch schedule 80 mild steel pipe pumps at CSA 30 with settings of 1197 feet weigh 20,118 pounds and are at 87%of the maximum weight limits of 23,138 pounds for utilizing schedule 80 steel pipe and heavy couplings; and the two 4-inch schedule 80 mild steel pipe pumps at CSA 32 with settings of 798 feet weigh 19,655 pounds and are at 85%of the maximum weight limits of 23,273 pounds for utilizing schedule 80 steel pipe and heavy couplings. We recommend that the schedule 80 mild steel pipe with the heavy couplings be utilized on all four pumps because all four pumps have total pump weights well under the maximum recommended weight capacity of schedule 80 mild steel pipe with heavy couplings of approximately 23,000 pounds for all pumps utilizing either 3-inch or 4-inch mild steel pipe with heavy couplings. Because the maximum recommended weight capacity of schedule 80 mild steel pipe with heavy couplings has been calculated using a safety factor of 3,the actual maximum hang weight of schedule 80 mild steel pipe with heavy couplings utilizing either 3-inch or 4-inch mild steel pipe is approximately 69,000 pounds. In addition, because both the pipe thickness and the coupling thickness of schedule 80 mild steel pipe with heavy couplings is greater than the pipe thickness and coupling thickness of schedule 40 mild steel pipe with standard couplings,there is little to no chance that the schedule 80 mild steel pipe or heavy couplings will flex or become egg shaped during the pump installation at these new deeper settings. While we are confident that utilizing the schedule 80 mild steel pipe with heavy couplings to set these new deeper and larger required pumps and motors,Zim Industries,Inc.recommends that the County of Fresno have their engineering team review this data included in this email the attached PDF files. While Zim Industries, Inc. is the general contractor,we are not the design engineer and we have not been contracted to perform the duties of the design engineer for the County of Fresno on this project. With that being said, based on the above stated pump weights and calculated joint strengths of the 3-inch and 4-inch schedule 80 mild steel pipe with heavy couplings,we recommend that 3-inch and 4-inch schedule 80 mild steel pipe with heavy couplings be utilized to set these four pumps on this project. 2) The County of Fresno is looking for proof of AIS certification See the attached Exhibit 8 containing the proof of American Iron and Steek Certification of the 3-inch ID and 4-inch ID schedule 80 mild steel pipe materials from our pump supplier. 3) The County of Fresno is asking that Zim Industries will split the cost of the purposed change order 50/50. The revised pricing of Zim Industries, Inc.'s cost proposal to furnish and install the four pumps utilizing 3- inch and 4-inch schedule 80 mild steel pipe with heavy couplings at the deeper pump settings required for CSA 30 and CSA 32 to meet the changes in pump,motor and pumping conditions is attached as Exhibit 9. Below is a summary of our revised proposals. Description of Work Original Bid Revised Bid Change Order Request CSA 32—Cantua Creek Well 1 $73,750.00 $112,218.16 $38,468.16 CSA 32—Cantua Creek Well 2 $73,750.00 $112,218.16 $38,468.16 CSA 30—El Porvenir Well 1 $78,720.00 $ 88,645.34 $ 9,925.34 CSA 30—El Porvenir Well 2 $78,720.00 $ 88,645.34 9,925,34 Total revised Change Order Request Amount $96,787.00 The change in conditions of the required pump, motor,column pipe and pump setting has required nearly every component of these four pumps to both change and increase in quantity from when we contracted this work. Zim Industries, Inc.disagrees with the County of Fresno's request to split these cost increases equally between Zim Industries, Inc. and the County of Fresno. All of these proposed pump cost increases are due to the fact that pumps are being set deeper,and the pump components are being increased in size,weight and footages to meet the change in the pumping conditions of these four wells. These proposed cost increases are summarized below because of these following pump component changes and quantity increases: 1)the pump settings went from 756 feet to 1197 feet on the two pumps located at CSA 30; and 2)the pump settings went from 630 feet to 798 feet on the two pumps located at CSA 32;3)the submersible pump bowl changed from 15 stages to 25 stages on the two pumps located at CSA 30;4)the submersible pump bowl changed from 11 stages to 23 stages on the two pumps located at CSA 32; 5)the submersible motor changed from 20 HP to 30 HP on the two pumps located at CSA 30;6)the submersible motor changed from 40 HP to 50 HP on the two pumps located at CSA 32;7)the column pipe changed from 756 feet of 3-inch coated schedule 40 mild steel pipe with standard couplings to 1197 feet of 3-inch schedule 80 mild steel pipe with heavy couplings on the two pumps located at CSA 30; 8)the column pipe changed from 630 feet of 4-inch coated schedule 40 mild steel pipe standard couplings to 798 feet of 4-inch schedule 80 mild steel pipe with heavy couplings on the two pumps located at CSA 32;9)the number of 3-inch diameter check valves changed from 4 each to 6 each on the two pumps located at CSA 30; 10)the number of 4-inch diameter check valves changed from 3 each to 4 each on the two pumps located at CSA 32;11)the submersible cable changed from 1000 feet of 6/3 Flat Jacket Cable to 1500 feet of 2/3 Flat Jacket Cable on the two pumps located at CSA 30; 12)the submersible cable changed from 1000 feet of 4/3 Flat Jacket Cable to 1000 feet of 2/3 Flat Jacket Cable on the two pumps located at CSA 32; 13)the footage of#14 wire changed from 2000 feet to 3000 feet on the two pumps located at CSA 30; 14)the pump airline changed from 756 feet of 1%"schedule 80 PVC airline to 1200 feet of l"stainless steel airline on the two pumps located at CSA 30;and 15)the pump airline changed from 630 feet of 1%" schedule 80 PVC airline to 800 feet of%"stainless steel airline on the two pumps located at CSA 32. We respectfully request that the County of Fresno approve our request for this contract price increase to compensate Zim Industries, Inc.for the pump changes, motor changes and pump setting changes required to meet the change in pumping conditions of the two wells at CSA 30 and the two wells at CSA 32. We have contacted our pump supplier for lead times on the remaining 3-inch and 4-inch mild steel schedule 80 drop pipe with heavy couplings for these four pumps(two pumps at CSA 32 and two pumps at CSA 30)and the lead times for manufacturing and delivery is 10 to 12 weeks. We have ordered all of the other pump components included in our proposal except for the 3-inch and 4-inch schedule 80 mild steel:drop pipe with heavy couplings. Once we have the County of Fresno's approval for utilizing this schedule 80 mild steel material with heavy couplings for both the 3-inch and 4-inch pump settings,we will proceed with ordering it from our supplier and finalize our work schedule. We look forward to finalizing the pump designs of these four pumps,ordering the 3-inch and 4-inch schedule 80 mild steel column pipe with heavy couplings and completing this project as soon as possible. Sincerely, 1 Curt B.Zim4rer President Exhibit C =T/A/ mounn rm9 wlcl 4532 E,Jefferson Ave. • Fresno, CA 93725 Ph. (559) 834-1551 • FAX (559) 834-5156 www.zimindustries.com July 23, 2024 County of Fresno Department of Public Works and Planning/Construction 2220 Tulare Street, 7"'Floor Fresno,CA 93723 RE: Fresno County Westside Groundwater Project(1807C)Electrical Material Cost Adjustments Dear AJ/Mandeep, Zim Industries, Inc. proposes a change order to address the unforeseen escalation in electrical material costs incurred between 2020 and 2022. The Covid-19 pandemic and subsequent supply chain disruptions resulted in significant delays and increases in material costs, which have had a profound impact on our operations. The delays in finalizing the pump equipment designs, combined with these industry-wide challenges, resulted in significantly higher costs for electrical conduit and wire by the time final designs were confirmed. Extended lead times and fluctuating prices due to the pandemic disrupted our procurement and planning. Suppliers could not offer reliable delivery schedules or pricing, and challenges in retaining and training our workforce further complicated our operations. These disruptions severely affected our ability to manage costs and schedules, contributing to increased electrical material costs. After the pump tests,it was evident that new pump equipment designs were required. This resulted in new pump designs with larger horsepower motors and, in turn, electrical design modifications, consisting of larger horsepower soft starters and larger wire sizes. Delays in finalizing these modifications,combined with ongoing industry-wide issues, resulted in a significant increase in electrical material costs. Attached, please find the documentation from our electrical subcontractor and their supplier outlining the additional costs for conduit and wire incurred during this period. Components with minimal cost increases have been excluded. Our proposed adjustment,with a 15%markup and bond cost,amounts to$55,929.37. If you have any questions or need further information, please do not hesitate to contact Bob Zimrnerer or me at (559)834-1551. We appreciate your consideration and look forward to your response. Sincerely, Wes Zimmerer Zim Industries, Inc. EL PORVENIR CSA.30 PVC CONDUIT CONDUCTORS GROUND CONDUCTORS CONOVR CONDUIT CONDwT C NOL'IT QUANTITY OAiGINAI WNAL PAEIENI N1RE SY!11E LEER TOTAL VA-AL ORiOUAL PRESENT ON AN11TY OAWwAL ORWIIAL GNEIEIiT CALLOUT SIZE TYPE OUANINTY wIEET CONpUR COST lSTENOEO A EAlES10E0 SSZ£ TYPE OF VCIRES FEET Of W:Rl COST EXTENDED PCOSTT ENTENDLO 512E OIN FEET WIRE COST ME- ICOSTi ESTf NCED ...AUN Ff0.I0UT IT OPE CONOUCTOAS P!0.lpOT COST P[RRUN PER FOOT COST COST H]W0A S�1R" PVC 1 110 f0.11 Nf.10 51L3 ti31.S0 S ilO1N ] ]10 f111 NN20 SifO II.GIAO I 1M N]S M]20 10:9 N]DODO 11R' PVC iO.el 391.13 {]]! t3t].TS 3 }NHN i ]TS 5111 i31].T. Si.90 Il.tlt.W I TSS 30.l{ {SSW 30,tf 311.]] N]WOC 11` PVC f021 iT13 I]]]f S THHN ] fO.i6 i]ZIO {p.T1 tT1.1p IS u talf f313 1f9.30 N 10000 L+' PVC f ID.]f 31.lf 11.0 ESS 12 TNHII 1 30 {0.1! 13A. 1EW 13 f0.13 2190 SILO Ill:AsTN s Ln n.o.1.J1 w1p w.0 UTR" PVC 113 39i1s .1:3 T]S3 z InnN ] ]}1 Sf.D if ll.i3 N.CR.SJ l0 SO31 IT L40 L.N Pvc v w.v rnnN In of i0.]1 `13 inNNi 2 lO.tS 3}Jp ti I0.13 Y9.Oi L�C000 1N- 5 3011 fl]3 fflE3 Ix THNII 3 13 30.1! iZ2! tJ.I: +11�] 13 50.13 f1.30 Ia.:J 1].00 PVC I 40 L. 1 i>_J] {31.:0 IS 1MNN 10 30.1S f11W Lp.]I f]1.Oi tt W 0.1! f110 1p.la 1)W L]C]f A PVC 93 NSi fi).4] 11.31 llll if 1] TMNM i ]1! f0.13 f12S3 30.]0 IfIN 12 113 f0.1/ ilSi! SaJO i1110 L]C]1 D PYC 3011 f]I33 il.]3 113).f0 11 iHNN 30.13 f]S.W /1}O.W fI Ii0 30.1E t1T.N f0.]0 )]SOJ L]CJIC >N- CVC f!0 Af.30 fIrilJ IS TNNN I30 D.1] !].ID fI 1f0 l0.13 IILW 13W L]0010 1- ]3 WT 1-1 0.15 13 O.1S Tl.I! 1-11 C]vvvA I" PVC 1I! ' vOB PVC 13T5 f011 LS}.}Sv it 1NMN ] 40 30.11 5330 .]..1 III<J 1 >S f0.13 ]1]0 f._[ [I l0 C JOUDC PVC - wl C 1001A PVC 111 31.00 3113.00 Ei 11 14 THHN 3 3a11 i](10 a]}.60 11 133 0.!I 113.W 010 PVC IS 3).13 11 TN-' i tall N.N {0.]1 11120 14 c]001 C PVC I 113 511E 3!,0 ROPE 1IS 010 PVC S:I.00 11 T1111!i MIT 2311p t!]30 W i1S0 C]C01E PV< 3 SILO 14 TNHII !v SC.If [S10 101 11.1E I'll APICf0.31 OPE RC SiWp i' PVC 11] A. ITS 6 3' GV< Sl.vOcl OPE if! ORIGVIALLY QUOTED TOTAL Of CONOUR: it.lf].30 ORRIAALLY ......... is S+i JS ORIGWALLY 3}!WN it CE3W O0.IGwALLT 3191.Of fs1I1J OWALLY QUOTED TOTAL OF MAL' iS,1N.]0 WOTFO QUOTED UOTEO OMMALLY QUOTE[]TOTAL OF ONO.MAE: ..F.' TOTAL OF ORIGINALLY QUOTED MATERIAL' NAT." PR£SEIIT TOTAL CO ST OF CONDLYI: 11,34E OS PAEIENT TOTAL COSTOFD 0 WIRE: /1...... TOTAL COST DIFFERENCE FOR CANTUA CREEK PROJECT:$G,G79.10 FRESf111 TOTAL COST OI UITC-L 11]L9.13 CANTUA CREEK CSA-32 PVC CONDUIT CONDUCTORS GROUND CONDUCTORS CDII.u1T CONDUIT CONOUR COIIDUIT pUNITRY ORIGINAL ORIGINAL ES EIIT PN ESCIIT NTRE WWE NUMBER TOTAL ORIGINAL ORGINAL igEf E11T PRESENT Gt10 DUANfRY ORIGINAL IN RNAL PRESENT vRE3Elli CALL OUT SIZE TYPE OUANIITY III PlET COST @]ll.xOED P COST E%TEND`. SQ! TYPE DP WIRCS fEET OF COST ![TCIIOEO OST E%TCIIOEO I. IN PffT COST !%f@HDlD COST E3I EIIOEO PfR UN PER FOOT COfT OR ROPE ONOURORf COST PlR RUH PER POOT OS( PER i00T COST X nwA 3' Pv 110 t1.00 111.N Na0 4:¢CJ TNHN lip ll.i] Np]p Nd1 fl.a)1.{0 { 1C0 4.It {f1.0a I121 H 12wI 1" PVC 1 IJp f1.00 -1 tJ JO Il.]4.pa IN TNMM ] 1)]a 11.11 f2,110.30 w.11 If.)T].0a 1 b0 30.{I nllN 1 111:9.1p H SIR.I 1" PVC t 110 i1.00 N,TIP as IN 1NNN i 1]3a 11.)! 3;Ill3p wf1 f3.3T1.00 JN i¢II i11AN N Ii00D 3" PVC 1 !00 {I.00 ilw,pa 3100 I1.p000a 1N iMNN l 1S)0 SI.I) I3.))I.IO Sl.fl 36.CIfAO I 1114 30.61 AI1.t0 MJ 01 PVC PVC I.l 5111*1.1 12TY fa,01 I 110 TNHN 11.19 {fa1S0 it,l)l.10 130 {}lS0 it.:] 11).4 1.U3 1 l}1P t]YI.fS I TMHN f196.{p Md0 {0]1 )!N N 1111A 1" PVC NO.CO ills 4e3]p 1➢il.N fp t0.{I 44.N H 13JIB 1' PVC 1 ab S1,N I= i!N II�TNCPI In TNHN 1 ]l11 a il.if i;IIf20 ls. . E 1 1 0 p.{I {ilASa SLSa NN.1 N I}:IC I- WG 1 Ib N.10 iabda 4.00 ILTwdJ 1.� iNH:1 1]fa {I.if fS,111.w {191 .."I RE 1 b0 b.N 3])1]O lalJ i1MAO H nJ1O 2' PYC 1 120 i1.00 3130.00 tape IJCJ TNHN l90 Si.i9 {f]LIa 11]S1.30 1 iN {Tf20 11_p 19l IP N)IIIE PVC SIT' SI9.{a 142.11 1HN'1 f2a1.00 13.9a 1l.00 1 50 1]7 i11S0 ]! Il.i] 11 11 1-1 31511 IN- 13.Lp PVC 11]JO 1p.15 1 ]J Sp.tf L]]p1B 1'J• PVC JS 10.]t 1155 - IS 120 p.11 I1.01 10 - 111a1C J/i- PVC I p 1.11 1,, 1 TNHN ?t9 1)SO LI:ppw 1 iMHN 110 f0A1 115]Sp I.N L u10e IS�p aa2. L TNNN w.0 ISN.w �uaat m11 n2a L-D Ll" PVC 11 S0.]1 p.)0 :1)1.[J IS TNHN t 11 f0.13 fIN➢a :JSp i/i1}.CO 13 IS I.It 531 d0 i0.:1 N31 L llwI I- PVC 1 It {0.]i 112! 111] 11 TNHN 4a 10.15 Ill.. {0.b 1111. IS 31 I. IISJ' 1a.11 f1AT L]200E la" PVC 1 )1 SI0.1! 11]] JJ) IS TXHN 2 w 1a.I3 f11.10 {O.b l]?C0 1 f0.1! ILTa 1.l fl.lf L 320SA PVC Ib SSLa 10 TXXN 210 1p23 4).]0 b.1 1111 ea II 1p11 nI.N )O.b L]2038 1' PVC fa.4 i1/1.6a TNNV 3011 i110.Cp 3J 31 IIIT.W 10 I30 i¢n fH➢a 1?SI 1.51 PVC 1p.4 119).60 11 THH:1 3 1a1: S1fI.aJ 1]e).CJ - 4A0a L 3 2 0 2D PVC w.l] 1191p C])IXIA l PVC 11 51.00 ROPES-;'. OPE NGNE NB 3 PVC 3p> NOO.pJ J;6fOJp ROI!HONE 1 CID 1.IR IVC 110 Nf.10 {1N.N 4 TNMN i 110 i0.t1 IS" III iSl.N 1{ IN SL11 lla:0 - C00 PVC ip.]1 SN.10 fa)) IJl.]! 11 i11XT1 i !Jp fJ.11 SSI.N f031 IS).N 11 Ila "I" 1+ PVC 1 tl0.10 ::a- ROPE NONE I PVC s1).J] ROPE NONE PVG 1.- SL1{¢b ROPE IID.. C aI.;. 11R PVC 1,I t021 31i10 111- 4 TNHN 2 S30.w I1 11 :!a If 1]0 f0.11 11Up 121 C]2G1C 1'a• PYC 1 30 1 p.11 1- It 1 1 111.J} 11 TNHN 1 SJ.11 ]0.11 i].a {I9_J 11 1 {p.11 4Ap Sa.J if.10 p10 PvC Ili ]I.11 ROPE NONE C]2p2w 38 C]10 C IC NMN1 3fp C] PV )p S0.14 3]:0 p33i]3A22.wfLp0 C-ID I?N I'll 1. 1WU1 1SJJ..3IJI 1Il1Al.tSaJ 1�1 {NI..J1J 1J:a {3SJ9l.{1wp0❑u i?v [n]]a]A )' PVG i1.0p 41➢I i1.11p.Op ROPE NOI:E YJ I.JI S' PVC Sap f1.pJ i3J0.0p {20PO.Oa ROPE NONE I. PVC IJlp aJ10.0a ROPE N11 IC InpB PVC 1p p f]Ja GS 1100a.N -PE ONE SCO PVC 1.TN.W ROPE 11011E ORIGINALLY OUOTED TOTAL OF COHOUIT: t1T11.10 O�Il.11].1a PR� AJTf.1. ORNi1DNLLLY f11.11.1p iCO35TIT l...i ORDiGI11aLLY t221J.11 PRESlNi t;SST 11 ORIGINALLY QUOTED TOTAL Of WIRE: 311,]I0.10 OUOTEO COST T!D UOT[O COST ORIGINALLY QUOTED TOTAL OF GND.N'I RE: 1].2N,Tt TOTAL OF ORIGINALLY QUOTED MATERIAL: f2),Ili.lS PRESENT TOTAL COST of C011UIT: IMIM11 P RESEIJIT TOTAL COST OP..M i=1.11a tC TOTAL COST DIFFERENCE FOR CANTUA CREEK PROJECT:S 41,GG3.92 iRESEIN TOTAL CasT OF ORD.VIIRE dN2] PRESEII I TOTAL COST OF MATERIAL 1N.1,A} Revised Conduit Prices (2022) INDEPENDENT Quotation 0 electric QUOTE DATE QUOTE NUMBER A Sonepar Company 03/31/2022 S105539329 INDEPENDENT ELECTRIC SUPPLY,INC 698 N LAVERNE AVE PAGE NO. FRESNO,CA 93727-6819 INDEPENDENT ELECTRIC SUPPLY,INC 559-486-7070 696 N LAVERNE AVE FRESNOFax 559-486-7081 5 9-486-707pg3727-6819 Fax 559-486a081 1 Of 2 QUOTE TO: SHIP TO: RE-BID PUMP STATIONS 117&284 INDUSTRIAL ELECTRIC-BARRY HALAJAI C/O 09 INDUSTRIAL ELECTRIC 4974 N. FRESNO STREET#290 6027 NORTH GLENN AVENUE FRESNO,CA 93726 FRESNO,CA 93704-1732 CUSTOMER NUMBER CUSTOMER PO NUMBER JOB NAME/RELEASE NUMBER ORDERED BY 169709 RE-BID PUMP STATIONS WRITER SHIP VIA TERMS SHIP DATE FREIGHTALLOWED Chris Salvo ND 30 Days 03/31/2022 No ORDER QTY DESCRIPTION UNIT PRICE EXT PRICE 100ft PVC .50 100.545/c 100.55 1/2-PVC-SCHED-40 CONDUIT $1.01/LF on 3/21 this was 75.00 per hundred 100ft PVC .75 119.693/c 119.69 3/4-PVC-SCHED-40 CONDUIT $1.19/LF on 3/21 90.00 per hundred 100ft PVC 1.0 193.097/c 193.10 1-IN-PVC-SCHED-40 CONDUIT $1.93/LF 3/2021 146.00/c 100ft PVC 1.25 252.949/c 252.95 1-1/4-PVC-SCHED-40 CONDUIT $2.53/LF 3/2021 161.20/c 100ft PVC 1.5 293.031/c 293.03 1-1/2-PVC-SCHED-40 CONDUIT $2.93/LF 3/2021 220.55/c 100ft PVC 2.0 365.695/c 365.70 2-IN-PVC-SCHED-40 CONDUIT $3.65/LF 3/2021 195.03/c 100ft PVC 2.5 573.825/c 573.83 2-1/2-PVC-SCHED-40 CONDUIT $5.74/LF 3/2021 378.00/c 100ft PVC 3.0 700.076/c 700.08 3-IN-PVC-SCHED-40 CONDUIT S7.00/LF 3/2021 475.75/c Continued on Next Page Subtotal S&H Charges Amount Due Pnnled By:CS3292 on 3131/2022 10:39:58 AM Revised Wire Prices (2022) INDEPENDENT Quotation electric QUOTE DATE QUOTE NUMBER 0 A Soncpar Company INDEPENDENT ELECTRIC SUPPLY,INC 698 N LAVERNE AVE FRESNO,CA 93727-6819 INDEPENDENT ELECTRIC SUPPLY,INC PAGE NO. 559-486-7070 698 N LAVERNE AVE FRESNO,793727-6819 Fax 559-486-7081 sfi 00 Fax 559A86-7081 1 Of 2 QUOTE TO: SHIP TO: 09 INDUSTRIAL ELECTRIC-SHOP INDUSTRIAL ELECTRIC-BARRY HALAJAI C/O 09 INDUSTRIAL ELECTRIC 4974 N. FRESNO STREET#290 4974 N.FRESNO STREET#290 FRESNO,CA 93726 FRESNO,CA 93726 CUSTOMER NUMBER CUSTOMER PO NUMBER JOB NAME/RELEASE NUMBER ORDERED BY 166510 INDUSTRIAL ELEC SHOP WRITER SHIP VIA TERMS SHIP DATE FREIGHT ALLOWED Chris Salvo ND 30 Days 04/08/2022 No ORDER QTY DESCRIPTION UNIT PRICE EXT PRICE 500ft WIC.THHN 12 STR BLK 50OR 218294/m 109.15 COPPER BUILDING WIRE $0.22/LF 120.00/m 6/2020 500ft WIC.THHN 10 STR BLK 50OR 333.840/m 166.92 COPPER BUILDING WIRE $0.33/LF 6/2020 155.00/m 100ft WIC.THHN 8 STR BLK MR 606.026/m 60.60 COPPER BUILDING WIRE $0.61/LF 6/2020 280.00/m 100ft WIC.THHN 6 STR BLK MR 932.407/m 93.24 COPPER BUILDING WIRE $0.93/LF 6/2020 475.00/m 100ft WIC.THHN 4 STR BLK MR 1426.869/m 142.69 COPPER BUILDING WIRE $1.43/LF 6/2020 695.00/m 100ft WIC.THHN 2 STR BLK MR 2252.676/m 225.27 COPPER BUILDING WIRE $2.25/LF 6/2020 955.75/m 100ft WIC.THHN 1 STR BLK MR 2518.998/m 251.90 COPPER BUILDING WIRE $2.52/LF 6/2020 1213.54/m 100ft WIC.THHN 1/0 STR BLK MR 3084.073/m 308.41 COPPER BUILDING WIRE $3.08/LF 6/2020 1457.14/m Continued on Next Page' Subtotal S&H Charges Amount Due Original Conduit and INDEPENDENT Wire Prices(2020) electric 0 A Sonepar company 8/17/2023 Re: 2020 Commodities Pricing Dear, Industrial Electric Per your request we have compiled 2020 commodities prices which are in the table below. Since 2020 the average material cost has increased significantly. Independent Electric Supply has experienced unprecedented pricing increases and lead time due to the impacts of Covid-19 and the resulting global supply chain crises our vendors are experiencing,which has affected many projects. We estimated on average the cost of material has increased from 25-30%since the beginning of 2022 and will continue to rise through 2023. nla S/100 LF S/1000 LF S/LF S/LF Size EMT PVC Size Wire Size PVC Size Wire 1/2 42 30.5 12 120.806 1/2 0.31 12 0.12 3/4 40.421 10 185 3/4 0.40 10 0.19 1 11 .928 33.098 8 247.483 1 0.33 8 0.25 1-1/4 22 53 43.831 6 381.22 1-1/4 0.44 6 0.38 1-1/2 235. 04 55.833 4 577.716 1-1/2 0.56 4 0.58 2 299. 79.25 2 1425.579 2 0.79 2 1.43 2.5 485.3 105 1/0 1632.041 2.5 1.05 1/0 1.63 3 587.76 120.46 2/0 2057.241 3 1.20 2/0 2.06 4 894.85 163.83 3/0 2972,862 4 1.64 3/0 2.97 4/0 3350.86 4/0 3.35 250mcm 3714.201 250mcm 3.74 400mcm 5645.504 400mcm 5.65 500mcm 8486.19 500mcm 8.49 Sincerely Gayne Alexander Branch Manager www.iesupply.com Exhibit D 4532 E.Jefferson Ave. • Fresno, CA 93725 Ph. (559) 834-1551 • FAX (559) 834-5156 -- www.zimindustries.com July 23,2024 County of Fresno Department of Public Works and Planning/Construction 2220 Tulare Street,7"' Floor Fresno,CA 93723 RE: Fresno County Westside Groundwater Project(1807C)Electrical Design Modifications DearAJ/Mandeep, Zim Industries, Inc. proposes a change order for electrical design modifications,consisting of larger horsepower soft starters and larger wire sizes. These modifications were required to suite the new pump equipment designs and are reflected in the following updates: 4/26/2022:CSA 32 pump specifications revised, upgrading motors from 40 HP to 50 HP. 0 9/1/2022:CSA 30 pump specifications revised, upgrading motors from 20 HP to 30 HP. 0 6/29/2023:CSA 30 wire sizes increased from ft4 to tf1,per response to the pump submittals. 0 1/28/2024:CSA 30 wire size increases confirmed, per response to RFI#4. 0 2/28/2024:CSA 32 wire sizes increased from#1/0 to#2/0 and CSA 30 wire sizes confirmed,per RFI#5 response. 0 3/25/2024:No further wire size changes, per response to RFI 46. Attached is documentation from our electrical subcontractor and their supplier outlining the cost implications,as well as the updates provided above and the revised plan and specification sheets reflecting these modifications. Including bond cost and a 15%markup, our proposal for these modifications amounts to$10,480.70. For questions or further clarification,please contact Bob Zimmerer or me at(559) 834-1551. Sincerely, Wes Zimmerer Zim Industries, Inc. Industrial Electric Company 4974 North Fresno Street#290 Fresno, California 93726 Ph 659 347-0644 Fax 559 347-0646 CONTRACTOR'S LICENSE No.:417084 Feburuary 9,2024 PROPOSAL COUNTY SERVICES AREA 30 AND 32 Zim Industries,Inc. COUNTY OF FRESNO 4532 E Jefferson Av UP SIZING OF CSA 30(30 HORSEPOWER) Fresno Ca. 93725 WELL PUMP MOTORS Phone(559)834-1551 Fax(559)834-5156 Cell:(559)351-3427 email: bob@zimindustries.com THANK YOU FOR THE OPPORTUNITY TO QUOTE THIS PROJECT WE WILL SUPPLY AND INSTALL THE FOLLOWING: EL PORVENIR CSA 30 This proposal is related to the submittal review dated October 31,2022,directing us to up size the the conductors and the Soft Starters from 20 Horsepower as per original plans to 30 Horsepower for each of the two we/1 pump motors located on the site. 2 30 HORSEPOWER SOFT STARTERS DIFFERENCE IN COST: $755.00 ea. $1,510.00 CSA 30 (WEST WELL) 720(3 x 240)APPROX.LINEAL FEET ORIGINAL #4 CONDUCTOR SIZE X 3 -$2.25 per ft. -$1,620.00 This price is being based on revised cost schedule 720(3 x 240)APPROX.LINEAL FEET ORIGINAL #I CONDUCTOR SIZE X 3 $3.61 per ft. $2,59910 240 APPROX.LINEAL FEET ORIGINAL N 8 CONDUCTOR SIZE X 1 -$0.79 per ft. -$189.60 This price is being based on revised cost schedule 240 APPROX.LINEAL FEET ORIGINAL #6 CONDUCTOR SIZE X 1 $1.01 per ft. $242.40 CSA 30 (EAST WELL) 840(3 x 280)APPROX.LINEAL FEET ORIGINAL #4 CONDUCTOR SIZE X 3 -$2.25 per ft. .$1,890.00 This price is being based on revised cost schedule 840(3 x 280)APPROX.LINEAL FEET ORIGINAL #1 CONDUCTOR SIZE X 3 $3.61 per ft. $3,032.40 280 APPROX.LINEAL FEET ORIGINAL #8 CONDUCTOR SIZE X 1 -$0.79 per ft. -$221.20 This price is being based on revised cost schedule 280 APPROX.LINEAL FEET ORIGINAL #6 CONDUCTOR SIZE X 1 $1.01 per ft. $282.80 ADDITIONAL COST: $3,746.00 MARK UP: 15% $561.90 TOTAL ADDITIONAL COST: $4,307.90 Page I of I Industrial Electric Company 4974 North Fresno Street#290 Fresno, California 93726 Ph 559 347-0644 Fax 559 347-0646 CONTRACTOR'S LICENSE No.:417084 April 5,2024 PROPOSAL COUNTY SERVICES AREA 30 AND 32 Zirn Industries,Inc. COUNTY OF FRESNO 4532 E Jefferson Av UP SIZING OF CSA 32(50 HORSEPOWER) Fresno,Ca. 93725 WELL PUMP MOTORS Phone(559)834-1551 Fax(559)834-5156 Cell:(559)351-3427 email: bob@zjmindustries.com THANK YOU FOR THE OPPORTUNITY TO QUOTE THIS PROJECT WE WILL SUPPLY AND INSTALL THE FOLLOWING: CANTUA CREEK CSA 32 This proposal is related to the submittal review dated October 31,2022,directing us to up size the the conductors and the Soft Starters from 40 Horsepower as per original plans to 50 Horsepower for each of the two well pump motors located on the site. 2 50 HORSEPOWER SOFT STARTERS DIFFERENCE IN COST; $1,245.00 ea. $2,490.00 (Difference in cost from original 40 Horse Power to 50 Horse Power) CSA 32 (WEST WELL) NO CHANGE FROM ORIGINAL DRAWINGS SHOWN ON REVISED DRAWINGS CSA 32 (EAST WELL) 4380(3 x 1,460)APPROX.LINEAL FEET ORIGINAL #4 CONDUCTOR SIZE X 3 -$3.98 per ft. -$117,43140 This price is being based on revised cost schedule 4380(3 x 280)APPROX.LINEAL FEET ORIGINAL #I CONDUCTOR SIZE X 3 $4.35 per ft. $19,053.00 ADDITIONAL COST: $4,110.60 MARK UP: 15% $616.59 TOTAL ADDITIONAL COST: $4,727.19 Page I of 1 County of Fresno Received 4/28/2022 Westside Groundwater Project Well Equipping E. All nnoteho|a and coatings in contact with potable water uhoU be ANS|/NGF-81 certified and comply with California AB 1953. PART 2PRODUCTS 2./ PUMP BASE A. Work shall be in conformance with Section 03 30 01 - Cast-in-Place Concrete, and with the details shown un the Plans. B. Vent piping and fittings shall be constructed as shown on the Plans and in conformance with Section 4OD50O—Pipe and Fiffingm. 22 WELL PUMP AND COLUMN PIPE A. Pump shall be of the submersible type including motor and power cable, discharge column, and well cap. B. Pump manufacturer shall supply five (5) compete set ofshop drawings, pump cun/es, installation and operating instrucdona, and pads list with the pump assembly and with compliance with Section 1.3' Submittals. These documents shall become the property of the Owner and aho|| be delivered to the Owner by Supplier upon completion of pump installation. C. Pump shall conform with all local and state sanitary and safety regulations, Pump and motor shall be capable of continuous operation. Pump and motor shall meet the following conditions: Pump Type Engineer approved Goulds or Engineer equal approved equal Maximum Speed Minimum Bowl Efficiency at Design 84% 77% Capacity'2 Well Pumping Facilities 432152-3 County of Fresno Received 4/26/2022 Westside Groundwater Project Well Equipping . Maximum Motor HP'2 - 50 1. Results of pilot hole testing will dictate final well pump design criteria for Well 2 in each community. For —� — biddiny.p^,;,or=s,:ge!heseya�ues for oumr s to beused in Well 2 for each community. 2. Final pump selection to be determined after receipt of Well 2 pu'm tests f results`— CSA 30 (EI Porvenir) Secondary Design Conditions Flow(gpm)' Total Head (ft)' Minimum Efficiency(%)' Notes: IY �rinai pul;p�elactie::c,b�cetor ir4 d-afteE,r_eio�o[1+14e�2rDU` terq� sit results CSA 32 Cantua Creek Secondary Design Conditions Flow(gpm) Total Head (ft) Minimum Efficiency(%) 80 1,000 65 140 899 78 170 795 77 220 546 64 D. The pump bowl assembly shall include bowls made of close-grained cast iron, free from blowholes, sand holes or other detrimental defects, with a tensile strength of 30,000 psi. Each intermediate bowl shall be constructed with a bearing. The bowl unit shall be capable of withstanding a hydrostatic pressure equal to twice the pressure at the rated capacity or 1.5 times the shutoff head, whichever is greater. E. Impellers should be the enclosed type, with sufficient skirt material thickness to enable repair and restoration of proper running clearances by installation of wear rings. The impeller shaft shall be made of 416 stainless steel. Each impeller shall be made of bronze, accurately machined and finished, and suitably balanced. Well Pumping Facilities 4321 52-4 gMresno_county of-13971139716004-weslside gw csa 30_321_docs1specs1bid package to specs143 21 52 well pumping facilities_rev20220413-doc County of Fresno Received 9/1/2022 Westside Groundwater Project Well Equipping E. All materials and coatings in contact with potable water shall be ANSI/NSF-61 certified and comply with California AB 1953. PART 2 PRODUCTS 2-1 PUMP BASE A. Work shall be in conformance with Section 03 30 01 - Cast-in-Place Concrete, and with the details shown on the Plans. B. Vent piping and fittings shall be constructed as shown on the Plans and in conformance with Section 40 05 00—Pipe and Fittings. 2.2 WELL PUMP AND COLUMN PIPE A. Pump shall be of the submersible type including motor and power cable, discharge column, and well cap. B. Pump manufacturer shall supply five (5) compete set of shop drawings, pump curves, installation and operating instructions, and parts list with the pump assembly and with compliance with Section 1.3, Submittals. These documents shall become the property of the Owner and shall be delivered to the Owner by Supplier upon completion of pump installation. C. Pump shall conform with all local and state sanitary and safety regulations. Pump and motor shall be capable of continuous operation. Pump and motor shall meet the following conditions: El Porvenir(CSA 30) Cantua Creek(CSA 32) Well 1&2 Wells 1&2 Pump Type � rankl'in Electric, Franklin Electric, Grundfos, v_1'Jiivtv.C.��^�.:.IIVO'Ur Engineer approved Goulds or Engineer approved equal equal •----ter, Maximum Speed 3,600 1,750 (rpm) Design Flow (gpm) 60 170 Design Head (ft) 1,154 1�� 795 Minimum Bowl Efficiency at Design 63% 77% Capacity'•2 �, , Well Pumping Facilities 4321 52-3 g;\fresno_counly of-13971139716004-westside gw csa 30_32\_docslspecs\bid package 1a specs143 21 52 well pumping facilities rev20220831.d0c County of Fresno Received 9/1/2022 Westside Groundwater Project Well Equipping Maximum Motor HP 30 50 CSA 30 (El Porvenir) Secondary Design Conditions Flow(gpm) Total Head (ft) Minimum Efficiency(%) 50 1,242 59 1 60 1,154 63 70 1.032 65 L80 879 64 CSA 32 Cantua Creek Secondary Design Conditions Flow(gpm) Total Head (ft) Minimum Efficiency(%) 80 1,000 65 140 899 78 170 795 77 220 546 64 D. The pump bowl assembly shall include bowls made of close-grained cast iron, free from blowholes, sand holes or other detrimental defects, with a tensile strength of 30,000 psi. Each intermediate bowl shall be constructed with a bearing. The bowl unit shall be capable of withstanding a hydrostatic pressure equal to twice the pressure at the rated capacity or 1.5 times the shutoff head, whichever is greater. Well Pumping Facilities 4321 52-4 g1resno_counly of-1397\139716004-westside gNe esa 30 321_docstspecslbid package to specs143 2152 well pumping facililies_rev20220831.doc ^Eg PLAN NOTES 4 S / B / e / PEuoNJ - - _ ��✓ENCJ��N�aiECRI�iNc RECORD DFAVnNG SCALE PROJECT w1m, DEPARTf Of PL'DUCIVOPJSAHD PL.£TGRDVRJECT FAa�EctR6CdNfW CAEEK,G [I�'j,Etj,� It Iz LE t I.AE 'a's --a PLAN NUM "J r---- ---I 67- E�k-I SINGLE LINE DIAGRAM a PEMMI RECOSO WLMMNG SCALE DEPARr.,fr,�roF"ucwoRKsAs�opL�N�,N-aI ELECTPJCALOeTAKS EL PORVEUIR i I 31 i I —j I T _ „ ` F— a i t . z i A 3 PMONI CSA 32 ELECTRICAL SfTE PLAN — CANTUA CREEK (SOUTH) E++c� EraiN�lrrc RECORD DRAWING SCALE PROTECT ff` DEPAWIle;'T OF H.'6LIC WORKS AND PLi1�.T:G n'ESrsroE CRaamvatERPRDxcr ,(P �' CSA 32 t C ICAL SITE PLAN ..... ..�. «, EL FGR�ErURRfsN1UA CTiEER.0 CANTUAtaERt EE (SOUTH) •-mad PLAN NOTES =O IF1 Y �^ ti' = ----_ _ �- PUZONI CSA 32 ELECTRICAL SITE PLAN — CANTUA CREEK tNORTHi EN�aarEcux�,INc RECORD DRA`MNG 6CAL.E PROTECT DEPARTMEVT OF PUBLIC\lbRl.S A_VU PIA­�G i•,ESTsioe cRo�un�AicR rRa:cr S CSA32 ELECTRICALSITE PLAN .v..n..��.a,n. Fl ocm�xmncnmwcREFK,G ,� CANTUA CREEK(NORTH) �� EEECtRM...u, �7- r--------------- vl�u 7" E43 -e.PLAN NOTES T SINGLE LINE DtAGRAM lx� �701E� RECORO OlftAAV4G --s-E 0, Of PUBLIC NVORKS R ELECTRICA DETALS CANTU�L CREEK FULL BOX TYMAL Z,7Z,7_ 7 'POST TOP ELECTROLIER.POLE&QASE-TYPrAL 12 001 000-L CONMETE 04CASED CONDUITS pEaOml �,L�rAL EatRPMENT MOUNTING DETAIL F��l TRENCH SECION---ttEr-AL- RECOFU)OMVANG LE PROJECT DEI INSIT��GAC�VATER MWECT MARZ MACREEK EL I I'M I -,mz�, EcluipmENT MOUNTING DETAIL 2012L- ............ E �E -I fEl U, Ef f I I gal TTT T �i E;L-� cl. FE, A-A DUPLEXER 'ANEL PEDESTAL DETAIL WELL PUMP CONTROL WIRING CILAGRAM EmaNEERINC,INC. RECORD OMMNG SCALE PR DEPART."E.N7 of i RMSWDIPL�NNING ELECIMCAL DETAILS EL PORVENIR AND CANWA CRM CA Exhibit E M MUOv N r,"3, mC 4532 E.Jefferson Ave. • Fresno, CA 93725 Ph. (559) 834-1551 • FAX (559) 834-5156 www.zimindustries.com July 23, 2024 County of Fresno Department of Public Works and Planning/Construction 2220 Tulare Street,71" Floor Fresno,CA 93723 RE: Fresno County Westside Groundwater Project(1807C) Level Probes Dear AJ/Mandeep, Zim Industries, Inc. proposes equipping each pump with level probes to enhance protection against running dry during low water levels, which can cause major damage or failure. During pump installation, we proactively included these level probes, attaching them to the column pipe; however,installation of a relay is still required. Implementing these level probes will provide the following benefits: o Automatically shut off the pump if the water level drops to 50 feet above the pump bowls. • Trigger a warning if the water level rises to 350 feet above the pump bowls,allowing for early intervention. These probes offer a direct and reliable method for monitoring water levels and can be combined with other protective measures,such as float switches or pressure sensors,ensuring comprehensive system protection. Attached is our subcontractor's proposal for these upgrades. Including bond cost and a 15%markup,our proposal amounts to$8,120.00. If you have any questions or need further clarification,please contact Bob Zimmerer or me at(559)834-1551. Sincerely, Wes Zimmerer Zim Industries, Inc. Industrial Electric Company 4974 North Fresno Street#290 Fresno,California 93726 Ph 559 347-0644 Fax 559 347-0646 CONTRACTOR'S LICENSE No.:417084 1120/2024 PROPOSAL ADDITION OF WELL LOW Zirn Irrigation CUT-OUT LEVEL SENSORS 4532 E Jefferson Av Fresno,Ca. 93725 Phone(559)834-1551 Fax(555)834-5156 Cell:(559)351-3427 email: bob@zimindustries.com THIS PROPOSAL IS FOR THE ADDITION OF(4)LEVEL LOW LEVEL CUT-OUT PROBES AND RELAYS.THIS INCLUDES INSTALLATION AND WIRING. THIS WILL PREVENT THE WELL PUMPS FROM OPERATING IF THE WATERDROPS TO(50) FEET ABOVE THE WELL PUMP. THERE IS A WARNING LEVEL THAT CAN BE SIGNALED AT 350 FEET ABOVE WELL PUMP. THIS IS FOR THE CONTROL OF THE RVSS ONLY.A PROVISION WILL BE AVAILABLE FOR A FUTURE PLC TIE-IN. 4 LOW LEVEL PROBES AND RELAYS,WIRING INCLUDED $1,750.00 ea. $7,000.00 Page 1 of I Exhibit F 4532 E.Jefierson Ave. • Fresno, CA 93725 Ph. (559) 834-1551 • FAX (559) 834-5156 www.zimindustries.com July 23, 2024 County of Fresno Department of Public Works and Planning/Construction 2220 Tulare Street,7"' Floor Fresno, CA 93723 RE: Fresno County Westside Groundwater Project(1807C) Future Pressure Switch Conduit Dear AJ/Mandeep, Zim Industries, Inc. requests a change order to install conduit for future pressure switches at CSA 30 and CSA 30. While pouring concrete to encase conduit, our subcontractor installed 3/4-inch conduit with steel reinforcement support post at the control box and well head manifold for future use. Attached is our subcontractor's proposal for the future pressure switch conduits and supports. Including bond cost and a 15% markup,our proposal amounts to$5,065.87. For any questions or further clarification, please contact Bob Zimmerer or me at(559) 834-1551. Sincerely, Wes Zimmerer Zim Industries, Inc. Industrial Electric Company 4974 North Fresno Street#290 Fresno,California 93726 Ph 559 347-0644 Fax 559 347-0646 CONTRACTOR'S LICENSE No.:417084 April 5,2024 PROPOSAL COUNTY SERVICES AREA 30 AND 32 Zim Irrigation COUNTY OF FRESNO 4532 E Jefferson Av ADDITIONAL CONDUIT ADDITION FOR Fresno,Ca. 93725 FUTURE PRESSURE SWITCHES BEFORE Phone(559)834-1551 CONCRETE ENCASEMENT Fax(5S9)834.5i56 Cell:(559)351.3427 email: bob@zimindustries-com THANK YOU FOR THE OPORTUNITY TO QUOTE THIS PROJECT WE WILL SUPPLY AND INSTALL THE FOLLOWING: EL PORVENIR / CANTUA CREEK GSA 30 AND 32 This proposal is for the cost of adding a 314 inch conduit system with steel reinforcement support post to be encased in concrete at the control box and at well head manifold. 4 STEEL"C"CHANNEL SUPPORTS $325.00 ea. $1,300.00 100 FEET 314 INCH PVC CONDUIT $1.33 per ft. $133.00 so FEET 3/4 INCH RIGID CONDUIT $3.25 per ft. $162.50 a 314 INCH MYERS HUBS $6.50 ea. $52.00 1 LOT MISC.MATERIAL $85.00 ea. $86.00 1 LOT CONCRETE $175.00 ea. $175.00 1 LOT EQUIPMENT CHARGE $150.00 ea. $150.00 12 LABOR $145.00 per hr. $1,740.00 ADDITIONAL COST: $3,797.50 MARK UP: 15% $569.63 TOTAL ADDITIONAL COST: $4,367.13 Page 7 of I