HomeMy WebLinkAbout1807C CCO02.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO COUNTY WESTSIDE GROUND WATER PROJECT CHANGE ORDER NO.2 EL PORVENIR(CSA 30) and CANTUA CREEK(CSA 32) CONTRACT NO. 18-07-C PILOT HOLE TESTING AND PRODUCTION JULY 31,2019 WELL CONSTRUCTION PAGE 1 OF 2 TO: ZIM INDUSTRIES INC.: You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. By reason of the proposed change, 37 WORKING days will be granted to the allotted contract time. PART I: GRANT TIME EXTENSION FOR WEATHER DAYS: Grant a time extension of five working days for unsuitable working conditions due to rain or wet surface conditions. Weather Day Extension SummarylReference Weather Day March 18 2019 1 Working Day Weather Day March 19 2019 1 Working Day Weather Day March 20 2019 1 Working Day Weather Day March 212019 1 Working Day Weather Day March 22 2019 1 Working Day Total Weather Days 5 Working Days TOTAL TIME EXTENSION PART 1: FIVE WORKING DAYS TOTAL COST PART 1: $0.09(NO COST) i PART It: GRANT TIME EXTENSION FOR PERMITTING PROCESS DELAYS: Grant a time extension of14 working days for delays caused in the permitting process. This time extension if granted in accordance with Section 8-1.07B,"Time Adjustments," of the project Special Provisions. TOTAL TIME EXTENSION PART 11: 14 WORKING DAYS TOTAL COST PART II: $0.00(NO COST) i PART III: GRANT TIME EXTENSION FOR WATER ACESS: Grant a time extension of three working days for delays cause by tack of available water supply. ThiS time extension if granted in accordance with Section 8-1.076, "Time Adjustments,"of the project Special Provisions. I TOTAL TIME EXTENSION PART III:THREE WORKING DAYS TOTAL COST PART 111: $0.00(NO COST) i i Cnnlrador..White We,!Ae tau-M(tnM wncraclo r,nave g1VOR WfOtW Ct)r151ACratl Dr:to the change plppQSCd dnd nereQy d9fe@,tf Auditor-Canary this proposal is approved,that vvo will provide all equipment,rurnl5h alf materials,except as may otherwise be _Bus,ontce-Green noted above,and perform all services necessary for the work above spedoed,and W)fl a cept a$full payment eonst. gmt h terefor cne._cost.rrtgmt-eiue prates Shown above. -.,-RE/AIM.-afJe �,F,vJ.Ope.•QUIl7enn)0 if the Contractor does not sign acceptance or this order,his attention is direcuzd to the rEquirement s of the _Cnetaclor White Spe IRW(ans eS t0 Proceeding with the ordered work end Filing a written o: �PArovil-Wt,Itc tl specined. pr est witnln the tome therein I I f COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FRESNO COUNTY WESTSIDE GROUND WATER PROJECT CHANGE ORDER NO. 2 EL PORVENIR(CSA 30)and CANTUA CREEK(GSA 32) CONTRACT NO, 18-07-C PILOT HOLE TESTING AND PRODUCTION JULY 31, 2019 WELL CONSTRUCTION PAGE 2 OF 2 PART IV: GRANT TIME EXTENSION FOR WELL DESIGN: Grant a time extension of five working days for a delay in the well design process. This time extension if granted in accordance with Section 8-1.07B,"Time Adjustments,"of the project Special Provisions. TOTAL TIME EXTENSION PART IV: FIVE WORKING DAYS TOTAL COST PART IV: $0.00(NO COST) PART V: GRANT TIME EXTENSION FOR SUBMITTAL ISSUES: Grant a time extension of ten working days for delays in the returning of submittals. This time extension if granted in accordance with Section 8-1.076,'Time Adjustments,"of the project Special Provisions. i TOTAL TIME EXTENSION PART V:TEN WORKING DAYS TOTAL COST PART V: $0.00(NO COST) NET COSTS THIS CHANGE ORDER: ($0.00) NO COST NET TIME EXTENSION THIS CCO: 37 WORKING DAYS x�e;j JAS. N AHUMADA, ;ssi3 i Engineer T APPROVAL RECOMMENDED: ZIM INDUSTRIES INC.. --'`� Contractor �J STEVE7WHITE, Constru By: r 1 ,M / STEVEirector Title: �I ! 1 N9t / IQa /L V- Public Works and Planning Accepted Date: f Date: ? _contractor•white we,the above Signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor-Canary this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Bus. -Onice Pink-Green Board-Pin noted above,and perform all services necessary ror the work above specined,and will accept as full payment _ _coast.tagmt-awe therefor the prices shown above, _RE/Arch.•Blue —pert rev.•Goldenrod If the Contractor does not Sigh acceptance of this order,his attention IS directed to the requirements of the _Contractor before soecl)cd, nc ac to rataoding with the ordered work and ItlIf10 a written pretoet within the the therein �ppravel-white F cpeolned�