HomeMy WebLinkAbout1807C CCO01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FRESNO COUNTY WESTSIDE GROUNDWATER PROJECT CHANGE ORDER NO. 1
EL PORVENIR (CSA 30) &CANTUA CREEK (CSA 32) CONTRACT NO. 18-07-C
PILOT HOLE TESTING AND PRODUCTION WELL CONSTRUCTION JUNE 17, 2019
DRINKING WATER STATE REVOLVING FUND- PAGE 1 OF 2
PROJECT NO. 1000359-005C
TO: ZIM INDUSTRIES, INC.: You are hereby directed to make the herein described changes
from the plans and specifications or do the following described work not included in the plans
and specifications on this contract. By reasons of the proposed changes, 22 Working days will
be granted to the allotted contract time. The revised completion date is September 9, 2019.
PART 1: ELIMINATE BID ITEM#41
Eliminate Bid Item#41 Earthwork and Chemical Treatment in its entirety in accordance with
Section 9-1.06D, "Eliminated items", of the State Standard Specifications. The Contractor
incurred no costs related to this bid item, therefore no compensation or partial compensation will
be made to the Contractor for eliminating this bid item. This bid item is being eliminated in its
entirety at its full bid price, resulting in a decrease of$60,000.
TOTAL COST PART I: $60,000 DECREASE
TOTAL TIME EXTENSION PART 1:ZERO -WORKING DAYS
PART 11: PERFORM EARTHWORK BY MIXING CLASS 2 AGGREGE BASE MATERIAL WITH
NATIVE SOIL—EXTRA WORK
Furnish 270 cubic yards of virgin Class 2 Aggregate Base and mix it with approximately 455
cubic yards of washout soil in the basin to stabilize an approximately 725 cubic yard volume near
the south-west corner of the drainage basin at the Cantua Creek project site. This work
includes, but is not limited to, furnishing and delivering the aggregate base material to the
site, removing eroded material from the storage basin, mixing washout soil with aggregate
base material, placing mixture, compacting and grading mixture, and removing and
reinstalling the existing chain link fence. Perform all work in accordance with applicable
sections/portions of the Plans, project Specifications, and State Standard Specification to the
satisfaction of the Engineer. Submit test results for the Class 2 Aggregate Base to the
Engineer for review and approval prior to furnishing the material.
Compensation for this work will be made as extra work at agreed lump sum price of$57,000,
in accordance with Section 9-1.03 Payment Scope of the Special Provisions. This agreed
lump sum price includes compensation for all labor, materials, tools, equipment, traffic
control, incidentals, overhead costs, delay costs if any, and profits for performing the above
referenced work, no additional compensation will be allowed.
TOTAL COST PART If: $57,000 INCREASE
TOTAL TIME EXTENSION PART Il: 0 WORKING DAYS
PART I: GRANT A TIME EXTENSION
Grant the Contractor a time extension of 22 working days in accordance with Section 8-1.07B,
_Contractor-White We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,If
—.Auditor-Canary this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Boar office-Green noted above,and perform all services necessary for the work above specified,and will accept as full payment
Const.Mgmt Blue P
_Board-pink therefor the rices shown above.
_ -
_RE/Arch.-Blue
_Pro),Dev.-Goldenrod If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
_Contractor before speclficatlons as to proceeding with the ordered work and filing a written protest within the time therein
Approval-White specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FRESNO COUNTY WESTSIDE GROUNDWATER PROJECT CHANGE ORDER NO. 1
EL PORVENIR (CSA 30) & CANTUA CREEK(CSA 32) CONTRACT NO. 18-07-C
PILOT HOLE TESTING AND PRODUCTION WELL CONSTRUCTION JUNE 17, 2019
DRINKING WATER STATE REVOLVING FUND- PAGE 2 OF 2
PROJECT NO. 1000359-005C
"Time Adjustments", of the Special Provisions. This time extension includes five working days for
unsuitable.working conditions due to the rain/wet surface conditions; 14 working days for the
delays occurred obtaining the well permits from County's Environmental Health Department; and
three (3)'working days for the unavailability of water at the project site (due to non-project related
water main incident in the area) essential for the drilling operations.
T
.Time Extension Summary/Reference
Weather Days' March 18-22, 2019 5 Working Days
Well Permits March 25-April 11, 2019 14 Working Days
Water Availability April 29-May 1, 2019 3 Working Days
Total Days 22 Working Days
TOTAL COST PART Ill: $0.00 (NO COST)
TOTAL TIME EXTENSION PART III:22 WORKING DAYS
NET COSTS THIS CHANGE ORDER: A$3,000.00 DECRESE
I- TOTAL TIME EXTENSIONS THIS CCO: 22 WORKING DAYS
SUBMITTED BY:
JASO HUMADA, Resident Engineer
AC ED APPROV OMMENDED-
By:
M INDdgT IES, INC. - STEVET5ff1S, Construction Engineer
Contractor
Title:
(� AUTHORIZED FO AYMENT BY: .
Accepted Date:
STEVEN E. WHITE, Director
Public Wor s ,d Planning
T
Date:
_contractor-White We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,If
_Auditor-Canary this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_sus.office-Green noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board-Pink
_Const.Mgmt-Blue therefor the prices shown above.
_RE/Arch.-Blue
_Proj.Dev.-Goldenrod If the Contractor does not sign acceptance of this order,his attention Is directed to the requirements of the
_Contractor before specifications as to proceeding with the ordered work and filing a written protest within the time therein
Approval-White specified.