HomeMy WebLinkAbout2326C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 3
CONTRACT NO. 23-26-C FEBUARY 11, 2025
PAGE 1 OF 3
TO: WEST VALLEY CONSTRUCTON COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 10 -WORKING DAYS will be added to the contract timeline.
PART I: GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant a 10-working days'time extension to the allotted contract time for the Second Order of Work due
to the additional field exploratory work and replacement/relocation of the 10 new water meters
(addressed previously in CCO No. 2, Part 1) in the County Service Area (CSA) 10. This time extension
is being granted according to Section 8-1.07B, "Time Adjustments," of the Special Provisions.
TOTAL COST PART I: $0.00 (NO COST)
TOTAL TIME EXTENSION PART I: 10 -WORKING DAYS
PART II: INSTALL ADDITIONAL/ALTERNATIVE ITEMS— EXTRA WORK
These additional/alternative items were requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install
additional/alternative items as extra work at the pertaining CSA as shown below. Perform all work
according to the Standard Specifications, Special Provisions, and/ or manufacturer's recommendation,
as directed by the engineer. Compensation for these items will be made at the agreed unit price shown
below, in accordance with Section 9-1.03, "Payment Scope," of the Special Provisions.
Additional/Alternative Items:
CSA 47
Item Total
No. Description Unit Quantity Unit Price Amount
60B Water Meter Box Lid (1330) EA 2.00 153.15 306.30
Replacement
TOTAL INCREASES: $306.30
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 3
CONTRACT NO. 23-26-C FEBUARY 11, 2025
PAGE 2OF3
TOTAL COST PART II: $306.30 INCREASE
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: INCREASE ITEM AT UNIT BID PRICE
This change was proposed by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, increase Bid
Item No. 60, Water Meter Box Steel Lid Retrofit or New Lid by four(4) units. This bid item was previously
reduced, however, is now being increased per the actual field exploration. Compensation for the increased
quantity will be paid at the unit bid price of$712.00 according to Section 9-1.03, "Payment Scope," of the
Special Provisions.
Increased Item:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/0) %
60 Water Meter Box Steel Lid EA 4.00 $712.00 $2,848.00 133.33 (92.16)
Retrofit or New Lid
TOTAL INCREASES: $2,848.00
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
TOTAL COST PART III: $2,848.00 INCREASE
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
_Contractor We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ARPA WATER METER REPLACEMENTS CHANGE ORDER NO. 3
CONTRACT NO. 23-26-C FEBUARY 11, 2025
PAGE 3OF3
NET COST THIS CHANGE ORDER: $3,154.30 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 10 -WORKING DAYS
,P�6a�.tyS��ucc�uc.�aei
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
West Valley Construction Co., Inc.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
Title Assistant Vice President Steve White 6t30202..053 2O,
Steven E. White, Director
Feb 27 2025 Public Works and Planning
Accepted Date: ,
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.