HomeMy WebLinkAbout24S04 CCO 01.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER REEDLEY RADIO TOWER AND EQUIPMENT SHELTER CHANGE ORDER NO. 1 17626 E. MANNING AVE., REEDLEY, CA 93654 FEBRUARY 26, 2025 CONTRACT NO. 24-S-04 PAGE 1 OF 2 TO: KATCH GENERAL: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time. PART I: TRANSPORT OWNER FURNISHED GENERATOR TO THE PROJECT SITE— EXTRA WORK This extra work was requested by the project manager. In accordance with Sub-section 2.25, "Changes to the Work," of Section 007200, "General Conditions," of the Project Manual, transport owner furnished generator from the storage facility located at 2909 S. Elm Avenue, Fresno, California, to the project site, 17626 E Manning Avenue, Reedley, California. Refer to the attached Exhibit A for the weight and dimensions. This work includes providing operator(s) and equipment to upload, transport, and off load the generator. Compensation for this work will be made at an agreed lumpsum price of$4,516.74 in accordance with Sub-section 2.25, "Changes to the Work, D2," of Section 007200, "General Conditions," of the Project Manual. This agreed price includes compensation for all labor, equipment, incidental, permits, markups, and profits, no additional compensation will be allowed thereafter for this work. This amount will be paid as extra work. This extra work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART I: $4,516.74 INCREASE TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS PART II: OBTAIN BUILDING PERMIT— EXTRA WORK This compensation adjustment was requested by the contactor. In accordance with Sub-section 2.25, "Changes to the Work," of Section 007200, "General Conditions," of the Project Manual, obtain a building permit for the project. Compensation for this work will be made as the actual cost incurred, in accordance with Sub-section 2.58, "Building Permit and Other Permits," of Section 007200, "General Conditions," of the Project Manual. The total fees resulted in $10,540.52 (see attached Exhibit B), no additional compensation will be allowed thereafter. This amount will be paid as extra work. This compensation adjustment did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART II: $10,540.52 INCREASE TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS _Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors therefore the prices shown above. _Const.Mgmt RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER REEDLEY RADIO TOWER AND EQUIPMENT SHELTER CHANGE ORDER NO. 1 17626 E. MANNING AVE., REEDLEY, CA 93654 FEBRUARY 26, 2025 CONTRACT NO. 24-S-04 PAGE 2 OF 2 NET COST THIS CHANGE ORDER: $15,057.26 INCREASE NET TIME EXTENSIONS THIS CCO: ZERO (0) -WORKING DAYS Keith licked Keith Eckert(Feb 26,2025 08:21 PST) Keith Eckert, Project Manager APPROVAL RECOMMENDED: KATCH GENERAL V � Contractor Mandeep S. Sekhon, PE Construction Engineer 7'"00v Clwmy By Tom cliacon(Feb 26,2025 11:27 PST) APPROVED BY: Digitally signed by Steve Whit General Manager Steve WhlteD tee2025.02.26 Title 15:15:19-08,00, Steven E. White, Director Accepted Date: Feb 26, 2025 Public Works and Planning Date: Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors therefore the prices shown above. _Const.Mgmt RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. CCO 01 - Exhibit A Diesel r='roduct dine BLUE S T*R 150 kwe/150 We Power Systems Inc. DCP7310 Control Panel Standard Features - Digital Metering - Engine Parameters - Generator Protection Functions O MITAL CONTROL PANEL - Engine Protection •- CAN Bus(J1939)ECU Communications 000 � - Windows-Based Software 0 � - Multilingual Capability GGc BLUE Sr4-R cox - Remote Communications to DSE2548 Remote Annunciator "°' Q Power Systems Inc. O Ocnearo•(Stzna! (h1a.:uz - 8 Programmable Contact Inputs =•D :I •_ � M14N30';yl &ea.a'LED O 5 waic, - 10 Contact Outputs O O • O /1 O Ora 3be LEO - RS485 Communicator Interface a�na+ aux. ear,„�:• rnnr - cLILus Listed,CE Approved s:a�Pc; ace - Event Recording - _.+ •: sr.,.e-1•== ,..,.._..;:,;.,E:...n ar.d.,,����, Aa•m du;e L Larp Tell suits - IP 65 rating(with suppEed gasket)offers increased resistance to vrater ingress """d e-1ntl11.°Ca`0' - NFPA 110 Level 1 Compatible Weights / Dimensions / Sound Data 23.66 L x W x H Weight Ibs �966 s. z O 5in �§ 13.02 LeVel �$4-X-G6-X-$�-iR §l�y(3 APPROX. BREAKER 4144 LOCATION Level-8 174 x 669v-ii•-82 iFi 1.96 1.96 13.15 Please allow 6-12 inches for height of exhaust stack. 70 LITER DEF TAN"STI.-I 2_342-�}- 19 GALLONS AREA 8 X 8 2r.1 Y--••+- 8.30• 35.40 No Load Full Load TDI OPU 79 dBA 82 dBA 1�• (75.00) Level 1 75 dBA 78 dBA ' 5076 Level 2 71 dBA 74 dBA Level 3 67 dBA 69 dBA O O 10.00 10.0o r �6000 0-0 ^ / \ \ \ } 7 ])S/ \ ! ® ! \ ) {/§)in / § ).§. � ,!q!m @ \ }lE\[\ § - Z\\ § !2k§ CL CL (2z �\m.z !\ §\ (\ E2 // .r!\ }� )§ < §§ \uw »k e-- � R lop. ai 0< [§�§ <u< L (/ )Q ƒ§ / \\ &_ <m / ca k[ § )� Ln Ln \\ \ \} \ 4- Lr °� J . - . / O= . 7\ Ln eo ^ ° 2 f§5 eo 00 - « 2/2 O O Ln . ° $ zk(k °z Lri \ \\\ O O \\ . ' § §k \ / )§ \\ \ �22/�Lri G S /\± f/ k j< <vi£=?o< ilL gR>fz £»$@§ }0 c<a c — `A\ a< t=>� 0cna 9 CCO 01 - Exhibit B PCO #003 Katch General Project:2435-Reedley Radio Tower and Equipment Shelter 929 L Street 17626 E Manning Ave Fresno,California 93721 Reedley,California 93654 Phone:+15592926653 Prime Contract Potential Change Order #003: Permit Costs TO: County of Fresno Public Works FROM: Katch General County of Fresno Public Works 2220 Tulare 929 L.St St Fresno,California 93721 Fresno,California 93721 PCO NUMBER/REVISION: 003/0 CONTRACT: 1-Contract Agreement REQUEST RECEIVED FROM: CREATED BY: Jason Cortez(Katch General) STATUS: Approved CREATED DATE: 1/17/2025 REFERENCE: Permits PRIME CONTRACT #002-Permit Costs CHANGE ORDER: FIELD CHANGE: No LOCATION: ACCOUNTING METHOD: Amount Based SCHEDULE IMPACT: PAID IN FULL: No EXECUTED: No SIGNED CHANGE ORDER RECEIVED DATE: TOTAL AMOUNT: $10,540.52 POTENTIAL CHANGE ORDER TITLE:Permit Costs CHANGE REASON:Client Request POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows) Permit Costs This change order is for the costs associated with the grading and building permits for this project.Reference#23-0980 ATTACHMENTS: Permitlnvoice.pdf # I Budget Code Description Amount 1 01-0100.O Permits.Other Permit Costs $10,540.52 Grand Total: $10,540.52 Joseph Harrell(County of Fresno Public County of Fresno Public Works Katch General Works) 2220 Tulare St County of Fresno Public Works 2220 Tulare 929 L.St St Fresno,California 93721 Fresno,California 93721 Fresno,California 93721 SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE Katch General Page 1 of 1 Printed On:2/25/2025 11:53 AM PST