HomeMy WebLinkAbout2304C CCO 05.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 5
FEDERAL PROJECT NUMBER: CML-5942(293) FEBRUARY 21, 2025
CONTRACT NO. 23-04-C PAGE 1 OF 2
TO: AVISON CONSTRUCTION, INC.:
Make the following change(s) to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the proposed change, TWO (2) -WORKING DAYS will be granted to the allotted
contract time.
PERFORM EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, perform the
following extra work:
• Excavate, grade, and compact subgrade to build and place a 2.5' wide x 80' long x .25' thick hot
mix asphalt (HMA) shoulder extension and install 80 feet of(Type E) HMA dike along the northwest
corner of the Fowler& Olive Avenues intersection. Perform shoulder backing behind the dike using
native soil.
Perform all work according to the applicable sections of the Standard Specifications and the Special
Provisions. Payment for this work will be made as extra work at Force Account according to Section 9-1.03,
"Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $9,009.41 increase.
Two (2) working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments," of the Project Specifications.
_Contractor We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above, and perform all services necessary for the work above specified, and will accept as full payment
_Board of Supervisors
_Const.Mgmt therefore the prices shown above.
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 5
FEDERAL PROJECT NUMBER: CML-5942(293) FEBRUARY 21, 2025
CONTRACT NO. 23-04-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: $9,009.41 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
i
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
AVISON CONSTRUCTION, INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
Whil
Title Project Manager
Steve White atee2025.02.24
15:25:25-08'00'
Steven E. White, Director
Feb 21 2025 Public Works and Planning
Accepted Date: ,
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.