HomeMy WebLinkAbout2304C CCO 04.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 4 FEDERAL PROJECT NUMBER: CML-5942(293) FEBRUARY 11, 2025 CONTRACT NO. 23-04-C PAGE 1 OF 2 TO: AVISON CONSTRUCTION, INC.: Make the following change(s) to the plans and specifications or do work not in the plans and specifications for this contract. Because of the proposed change, THREE (3) -WORKING DAYS will be granted to the allotted contract time. PERFORM EXTRA WORK This extra work was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, perform the following extra work: • Remove and replace existing pavement in the shoulder area beyond the easterly limits of Olive Avenue to correct an existing drainage issue. This work also includes removal and replacement of Type E asphalt dike and shoulder backing. • Remove and dispose of two (2) dry wells found within the subgrade of the new drainage ditch located southeast of the intersection. Perform all work according to the applicable sections of the Standard Specifications and the Special Provisions. Payment for this work will be made as extra work at Force Account according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $30,676.97 increase. Three (3) working days will be added to the contract time for the above referenced extra work, in accordance with Section 8-1.07B, "Time Adjustments," of the Project Specifications. _Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors therefore the prices shown above. _Const.Mgmt RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 4 FEDERAL PROJECT NUMBER: CML-5942(293) FEBRUARY 11, 2025 CONTRACT NO. 23-04-C PAGE 2 OF 2 NET COST THIS CHANGE ORDER: $30,676.97 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: THREE (3) -WORKING DAYS James Drews, Resident Engineer APPROVAL RECOMMENDED: AVISON CONSTRUCTION. INC. Contractor Mandeep S. Sekhon, PE Construction Engineer By APPROVED BY: Digitally signed by Steve 2/1 1 White 11/2/I Steve White Date: Title `t 10:46:09-08'00' Steven E. White, Director Accepted Date: Feb 11 2025 Public Works and Planning Date: Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business Office noted above,and perform all services necessary for the work above specified, and will accept as full payment Board of Supervisors _const.Mgmt therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.