HomeMy WebLinkAbout2301C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JENSEN AVENUE SHOULDER IMPROVEMENTS CHANGE ORDER NO. 1
AND OVERLAY, MADERA AVE TO DICKENSON AVE FEBRUARY 4, 2025
FEDERAL PROJECT NO.: CML-5942(283) PAGE 1 OF 5
CONTRACT NO. 23-01-C
TO: AGEE CONSTRUCTION CORPORATION:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 13 -WORKING DAYS will be added to the contract time.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT PRICES
This adjustment was proposed by the engineer.
Quantities in the Bid Book are estimates only. This part adjusts items to the actual quantities used.
Increased Items:
Item Total
No. Description Unit Quantity Price Amount % Total
33 Hot Mix Asphalt (Type A TON 1,477.46 $93.00 $137,403.78 6.69 6.69
1/" Grading)
35 Place Hot Mix Asphalt LF 55.00 15.00 825.00 9.68 9.68
Type D
37 Tack Coat TON 5.56 1,200.00 6,672.00 19.86 19.86
40 Survey Monument EA 2.00 1,200.00 2,400.00 28.57 28.57
45 Install One Roadside Sign EA 1.00 365.00 365.00 50.00 50.00
-One Post
46 Paint (White) Dike and LF 396.00 6.25 2,475.00 130.26 130.26
Concrete Median Curb
47 Type D Pavement Marker EA 142.00 10.10 1,434.20 23.47 23.47
48 Type H Pavement Marker EA 41.00 10.10 414.10 17.83 17.83
50 Thermoplastic Traffic LF 7.00 1.65 11.55 1.94 1.94
Stripe (Detail 22)
51 Thermoplastic Traffic Stipe LF 846.00 0.70 592.20 4.22 4.22
(Detail 6)
52 Thermoplastic Traffic Stipe LF 1,391.00 1.30 1,808.30 25.20 25.20
(Detail 34)
TOTAL INCREASE: $154,401.13
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount (°�
1 Supplemental Work (Payment $ 101,396.39 $1.00 $101,396.39 (101.40) (101.40)
Adjustments for Price Index
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices Shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JENSEN AVENUE SHOULDER IMPROVEMENTS CHANGE ORDER NO. 1
AND OVERLAY, MADERA AVE TO DICKENSON AVE FEBRUARY 4, 2025
FEDERAL PROJECT NO.: CML-5942(283) PAGE 2 OF 5
CONTRACT NO. 23-01-C
Fluctuations)
30 Remove Existing Asphalt LF 4.00 2.00 8.00 (1.61) (1.61)
Dike
31 Replace Asphalt Concrete CY 128.23 250.00 32,057.50 (18.06) (18.06)
Surfacing
32 Cold Plane Asphalt Concrete SQYD 606.31 3.25 1,970.51 (8.99) (8.99)
Pavement
36 Place Hot Mix Asphalt SQYD 309.69 32.00 9,910.08 (67.62) (67.62)
(Miscellaneous Area)
42 Object Marker(L-1) EA 1.00 130.00 130.00 (33.33) (33.33)
43 Object Marker(Type P) EA 1.00 130.00 130.00 (25.00) (25.00)
44 Install Two Roadside Sign - EA 1.00 465.00 465.00 (5.88) (5.88)
One Post
53 Thermoplastic Traffic Stipe LF 8.00 0.80 6.40 (0.02) (0.02)
(Detail 27B)
54 Thermoplastic Pavement SF 243.00 10.10 2,454.30 (32.19) (32.19)
Markings
55 Stop Limit Line LF 17.00 10.10 171.70 (6.67) (6.67)
TOTAL DECREASE: $148,699.88
Eliminated Items:
Item Total Total
No. Description Unit Quantity Price Amount NO
6 State Water Resource $ 1,000.00 $1.00 $1,000.00 (100.00) (100.00)
Control Board Notice of
Intent
7 Storm Water Annual EA 1.00 1,000.00 1,000.00 (100.00) (100.00)
Report
9 Crop 1 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
within County R/W)
10 Crop 2 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
within County R/W)
11 Crop 7 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
within County R/W)
12 Crop 8 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
within County R/W)
13 Crop 9 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
within County R/W)
14 Crop 10 (Remove Crop LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices Shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JENSEN AVENUE SHOULDER IMPROVEMENTS CHANGE ORDER NO. 1
AND OVERLAY, MADERA AVE TO DICKENSON AVE FEBRUARY 4, 2025
FEDERAL PROJECT NO.: CML-5942(283) PAGE 3 OF 5
CONTRACT NO. 23-01-C
within County R/VV)
15 Crop 11 (Remove Crop LS 1.00 5,500.00 5,500.00 (100.00) (100.00)
within County R/VV)
16 Fence 1 (Remove Crop LS 1.00 2,000.00 2,000.00 (100.00) (100.00)
within County RAN)
17 Fence 3 (Remove Crop LS 1.00 5,500.00 5,500.00 (100.00) (100.00)
within County R/VV)
18 Fence 4 (Remove Crop LS 1.00 1,500.00 1,500.00 (100.00) (100.00)
within County R/VV)
19 Landscape 1 (Remove LS 1.00 7,000.00 7,000.00 (100.00) (100.00)
Row of Trees within County
R/VV)
21 Concrete 2 (Remove LS 1.00 9,000.00 9,000.00 (100.00) (100.00)
Concrete Driveway and
Row of Trees within County
R/VV)
23 Culvert Slurry Concrete Fill CY 15.00 650.00 9,750.00 (100.00) (100.00)
34 Minor Hot Mix Asphalt (For TON 52.00 115.00 5,980.00 (100.00) (100.00)
Misc. Areas)
41 Temporary Fence LF 500.00 16.00 8,000.00 (100.00) (100.00)
TOTAL DECREASE: $98,230.00
TOTAL COST PART I: A $92,528.75 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART Ik ADJUST COMPENSATION PER THE CALIFORNIA STATEWIDE CRUDE OIL PRICE
INDEX FLUCTUATION
This compensation adjustment was requested by the contractor.
Compensate the contractor per the methods established in the Standard Specifications and Special
Provisions Section 9-1.07 for fluctuations greater than or less than five percent in the California
Statewide Crude Oil Index for the month the material was placed, when compared to the index
published for the month of the bid opening. The California Statewide Crude Oil Price Index for the bid
opening month, March 2024 was 433.2. The index was 461.6 in August 2024 and 401.4 in October
2024, which applies to Pay Estimate Nos. 2 through 4 for the quantity of asphalt in the hot mix asphalt
(HMA) and SS-1 H Tack Coat.
The asphalt content in the 3/4-inch HMA mix from Vulcan-Ashlan plant was 4.30 percent. The percent
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JENSEN AVENUE SHOULDER IMPROVEMENTS CHANGE ORDER NO. 1
AND OVERLAY, MADERA AVE TO DICKENSON AVE FEBRUARY 4, 2025
FEDERAL PROJECT NO.: CML-5942(283) PAGE 4 OF 5
CONTRACT NO. 23-01-C
was reduced to 2.92 percent to account for the 25 percent reclaimed asphalt pavement(RAP). The
adjustment applies to 5,255.70 tons of HMA placed in Aug 2024, and 8,320.86 tons placed in October
2024.The asphalt content in the 3/4-inch HMA mix from Vulcan-Madera plant was 4.40 percent. The
percent was reduced to 3.07 percent to account for the 25 percent RAP. The adjustment applies to
1381.92 tons of HMA placed in August 2024. Also, asphaltic emulsion (SS-1 h) was utilized on the
project where the minimum percent asphalt residue for the emulsion placed as tack was 57 percent.
The adjustment applies to a total of 0.88 tons of emulsion placed as a tack coat in August 2024 and
24.86 tons placed in October 2024.
The total compensation adjustment for price index fluctuation resulted in a decrease of$1,396.39. This
amount is being adjusted in Bid Item No. 1, Supplemental Work (Payment Adjustments for Price Index
Fluctuations), with no net cost increase to the contract
TOTAL COST PART II: $0.00 (ADJUSTED IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant a time extension of 13 -working days to the allotted contract time according to Section 8-1.07B, "Time
Adjustments," of the Special Provisions. This time extension is being granted due to the delays that occurred
to the striping operation as a result of the shortage for glass bead supply.
TOTAL COST PART III: $0.00 (NO COST)
TOTAL TIME EXTENSION PART III: 13 -WORKING DAYS
Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
_Business Office and perform all services necessary for the work above specified, and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JENSEN AVENUE SHOULDER IMPROVEMENTS CHANGE ORDER NO. 1
AND OVERLAY, MADERA AVE TO DICKENSON AVE FEBRUARY 4, 2025
FEDERAL PROJECT NO.: CML-5942(283) PAGE 5 OF 5
CONTRACT NO. 23-01-C
NET COST THIS CHANGE ORDER: $92,528.75 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 13 -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
AGEE CONSTRUCTION CORPORATION OJY�-�.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
Chief Estimator Steve Whiteptee2025.02.05
Title 12:14:48-08'00'
Steven E. White, Director
Feb 5 2025 Public Works and Planning
Accepted Date: ,
Date:
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices Shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.