HomeMy WebLinkAbout2413C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
TRACTION RANCH MONITORING WELL CHANGE ORDER NO. 1
CONTRACT NO. 24-13-C JANUARY 15, 2025
PAGE 1 OF 2
TO: BRADLEY AND SON'S, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract timeline.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES
This payment adjustment was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount °t/o °{�
2 Test Hole Drilling LF 40.00 $45.00 $1,800.00 6.90 6.90
4 Test Hole Reaming LF 11.00 30.00 330.00 3.33 3.03
6 Well Screen 2-Inch, ASTM LF 20.00 30.00 600.00 100.00 100.00
F-480-88A Sch. 40 PVC w/0.030
Slot Size
8 Cement Annular Seal LF 60.00 45.00 2,700.00 60.00 60.00
TOTAL INCREASES: $5,430.00
Decrease Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount t%
5 Blank Well Casing 2-Inch ASTM LF 20.00 $18.00 $360.00 (2.33) (2.33)
F-480-88A Sch. 40 PVC
7 Gravel Envelope and LF 45.00 45.00 2,025.00 (9.38) (9.38)
Intermediate Seals
TOTAL DECREASES: $2,385.00
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
TRACTION RANCH MONITORING WELL CHANGE ORDER NO. 1
CONTRACT NO. 24-13-C JANUARY 15, 2025
PAGE 2OF2
Eliminated Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (ON 01/0)
11 Standby Time HR 1.0 $575.00 $575.00 (100.00) (100.00)
13 Supplemental Work $ 1.0 10,000.00 10,000.00 (100.00) (100.00)
TOTAL DECREASE: $10,575.00
NET COST THIS CHANGE ORDER: A $7,530.00 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
LAB�a�
LaRue Goossen, Resident Engineer
APPROVAL RECOMMENDED:
Bradley and Son's, Inc. �AX
Contractor Mandeep S. Sekhon, PE
Construction Engineer
/OG( rra�fGe�
By Rod Bradley(Jan 16,202 07:55 PST) APPROVED BY:
Digitally signed by Steve
Whit
Steve White atee2025.01.16
Title V p 14 46 41-08'00'
Steven E. White, Director
Accepted Date:
Jan 16 2025 Public Works and Planning
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.