HomeMy WebLinkAbout2323C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 3
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE DECEMBER 30, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 1 OF 4
CONTRACT NO. 23-23-C
TO: EMMETT VALLEY CONSTRUCTION:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 19 -WORKING DAYS will be added to the contract time. The revised
completion date was December 5, 2024.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT PRICES
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/0 °�
7 State Water Resources Control $ 380.00 $1.00 $380.00 38.00 38.00
Board Notice of Intent
10 PG&E Gas Line Pothole EA 76.00 240.00 18,240.00 42.22 42.22
25 Hot Mix Asphalt(Type A'/" TON 1,739.09 103.00 179,126.27 9.62 9.62
Grading)
29 Tack Coat TON 17.00 2,200.00 37,400.00 85.00 85.00
31 Thermoplastic Traffic Stripe LF 934.00 0.80 747.20 13.65 13.65
(Detail 34A)
TOTAL INCREASE: $235,893.47
Decreased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount ( (°/�
1 Supplemental Work (Payment $ 145,747.40 $1.00 $145,747.40 (97.16) (97.16)
Adjustments for Price Index
Fluctuations)
12 Replace Asphalt Concrete CY 1.15 410.00 471.50 (0.27) (0.27)
Surfacing
13 Cold Plane Asphalt Concrete SY 1,687.00 9.00 15,183.00 (49.66) (49.66)
Pavement
26 Minor Hot Mix Asphalt (For TON 102.83 112.00 11,516.96 (87.14) (87.14)
Dikes and Misc. Areas)
27 Place Minor HMA SY 244.00 23.00 5,612.00 (15.53) (15.53)
Contractor We, the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 3
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE DECEMBER 30, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 2 OF 4
CONTRACT NO. 23-23-C
(Miscellaneous Areas)
32 Thermoplastic Traffic Stripe LF 1,229.00 0.40 491.60 (7.71) (7.71)
(Detail 5)
33 Thermoplastic Traffic Stripe LF 62.00 0.60 37.20 (0.14) (0.14)
(Detail 27B)
34 Thermoplastic Traffic Stripe LF 20.00 1.00 20.00 (5.71) (5.71)
(Detail 21)
35 Thermoplastic Pavement SF 10.00 8.00 80.00 (1.93) (1.93)
Markings
36 Delineator (Class 1 —Type F) EA 5.00 140.00 700.00 (25.00) (25.00)
TOTAL DECREASE: $179,859.66
Eliminated Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount
17 Remove Wrought Iron Fence LF 70.00 $15.00 $1,050.00 (100.00) (100.00)
with Brick Columns
18 Remove Fence (Chain Link, LF 1,150.00 5.00 5,750.00 (100.00) (100.00)
Barbed Wire, Wood Fence)
TOTAL DECREASE: $6,800.00
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
TOTAL COST PART I: $49,233.81 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: PLACE HYDROSEEDING ON CUT-SLOPE BETWEEN STA. 240+00 AND STA. 244+00 -
EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, place
hydroseeding on cut-slope along the northside (approximately 220 square yards), between sta. 240+00 and
244+00. Use materials as per the approved Submittal No. 27— Hydroseed Mix Design. Perform all work
according to Section 21-2.03D, "Hydromulch and Hydroseed," of the Standard Specifications. Payment for this
work will be made at an agreed lumpsum price of$1,320, according to Section 9-1.03, "Payment Scope," of
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 3
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE DECEMBER 30, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 3 OF 4
CONTRACT NO. 23-23-C
the Special Provisions. This agreed price includes compensation for all labor, equipment, traffic control,
incidentals, mark-ups, and profits for performing the above referenced work, no additional compensation will be
made thereafter. This amount will be paid as extra work.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
TOTAL COST PART II: $1,320.00 INCREASE
TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: ADJUST COMPENSATION FOR ADDITIONAL STORM WATER POLLUTION PREVENTION
PLAN (SWPPP) REPORTING - EXTRA WORK
This compensation adjustment was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, adjust
compensation for the additional costs incurred by the contractor for providing the additional SWPPP monitoring
reports and filling change of information (COI) in the State's SMARTS systems for extending the project
duration due to delays caused by PG&E. This compensation adjustment is being made an agreed Iumpsum
price of$1,232 (actual costs incurred), according to Section 9-1.03, "Payment Scope," of the Special
Provisions. This agreed price includes compensation for all labor, incidentals, mark-ups, and profits for
performing the above referenced work, no additional compensation will be made thereafter. This amount will
be paid as extra work.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
TOTAL COST PART III: $1,232.00 INCREASE
TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
PART IV: GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant a time extension of 19-working days to the allotted contract time due to the delays caused by
PG&E for relocating their high-pressure gas distribution line along the northside of the roadway
between sta. 240+00 and 244+00, and additional time required by the contractor to plan and remobilize
to finish the shoulder widening in this area. This time extension is being granted according to Section 8-
1.07B, "Time Adjustments," of the Special Provisions.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 3
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE DECEMBER 30, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 4 OF 4
CONTRACT NO. 23-23-C
TOTAL COST PART IV: $0.00 (NO COST)
TIME EXTENSION PART IV: 19 -WORKING DAYS
NET COST THIS CHANGE ORDER: $51,785.81 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 19 -WORKING DAYS
Jason Ahumada, Resident Engineer
APPROVAL RECOMMENDED:
EMMET VALLEY CONSTRUCTION
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By A(�gw APPROVED BY:
Digitally signed by Steve
Wh
Vice President Steve WhlteD tlee2025.01.08
Title 15:10:53-08'00'
Steven E. White, Director
Accepted Date:
Jan 7, 2025 Public Works and Planning
Date:
Contractor We, the above signed contractor,have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.