HomeMy WebLinkAbout2328C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREA 44C CHANGE ORDER NO. 1
WATER DISTRIBUTION FACILITY IMPROVEMENTS DECEMBER 31, 2024
CONTRACT NO. 23-28-C PAGE 1 OF 1
TO: WEST VALLEY CONSTRUCTION COMPANY, INC.:
Make the following change(s)to the plans and specifications or do work not in the plans and specifications
for this contract. Because of the proposed change(s), 14 -WORKING DAYS will be granted to the allotted
contract time. The revised date of completion for the First Order of Work was December 17, 2024.
GRANT A TIME EXTENSION
Grant a time extension of 14-working days to the "First Order of Work, Submittals" due to the excessive
time required for vendors to provide submittals for review and confirmation of orders. This time
extension shall apply according to Section 8-1.07B, "Time Adjustments," of the Special Provisions.
NET COST THIS CHANGE ORDER: $0.00 (NO COST)
NET TIME EXTENSION THIS CHANGE ORDER: 14 -WORKING DAYS
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
WEST VALLEY CONSTRUCTION CO., INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
L
By APPROVED BY:
Digitally signed by Steve
Whit
Assistant Vice President Steve WhlteD tee2025.01.06
Title 16:54:30-08'00'
Steven E. White, Director
Accepted Date:
Dec 31, 2024 Public Works and Planning
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors therefore the prices shown above.
_Const.Mgmt
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.