HomeMy WebLinkAbout2304C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 3
FEDERAL PROJECT NUMBER: CML-5942(293) DECEMBER 31, 2024
CONTRACT NO. 23-04-C PAGE 1 OF 3
TO: AVISON CONSTRUCTION, INC.:
Make the following change(s)to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the proposed change(s), TWO (2) -WORKING DAYS will be granted to the allotted
contract time.
PART I: INCREASE/ DECREASE ITEMS AT UNIT PRICES:
This change was proposed by the engineer.
Item quantities in the bid book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total Total
No. Description Unit Quantity a Price Amount
28 Hot Mix Asphalt (Type A 1/" TON 57.02 $110.00 $6,272.20 0.84 0.84
Grading)
30 Place Hot Mix Asphalt Dike LF 342.00 10.00 3,420.00 20.48 20.48
(Type E)
TOTAL INCREASE: $9,692.20
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount % %
7 State Water Resources Control $ 192.00 $1.00 $192.00 (19.20) (19.20)
Board Notice of Intent Filing Fee
20 Tree Removal EA 3.00 700.00 2,100.00 (20.00) (20.00)
24 3-Sack Concrete Slurry Backfill CY 8.00 250.00 2,000.00 (72.73) (72.73)
31 Place Hot Mix Asphalt Dike LF 243.00 8.00 1,944.00 (92.75) (92.75)
(Type F)
TOTAL DECREASE: $6,236.00
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: $3,456.20 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors ere thfore the aces shown above.
_Const.Mgmt p
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 3
FEDERAL PROJECT NUMBER: CML-5942(293) DECEMBER 31, 2024
CONTRACT NO. 23-04-C PAGE 2 OF 3
PART II: PERFORM EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, perform the
following extra work:
• Remove and dispose of existing concrete irrigation vault and pipes (southwest corner).
• Cut and cap existing concrete irrigation pipes in conflict with signal light conduit installation
(southwest comer).
• Excavate to explore existing sinkhole. Backfill and compact with Class II Aggregate Base fill
(Fowler Avenue, southbound lane, approximate sta. 106+80).
Perform all work according to the applicable sections of the Standard Specifications and the Special
Provisions. Payment for this work will be made as extra work at force account according to Section 9-1.03,
"Payment Scope,"of the Special Provisions. Total compensation for this work resulted in $9,234.86.
Two (2)working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments,"of the Project Specifications.
TOTAL COST PART II: $9,234.86 INCREASE
TOTAL TIME EXTENSION PART II: TWO (2) -WORKING DAYS
_contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors therefore the aces shown above.
_Const.Mgmt p
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 3
FEDERAL PROJECT NUMBER: CML-5942(293) DECEMBER 31, 2024
CONTRACT NO. 23-04-C PAGE 3 OF 3
NET COST THIS CHANGE ORDER: $12,691.06 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
AVISON CONSTRUCTION. INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
1/2/24 Steve White Date:
Date:2025.01.06
Title 16:53:39-08'00'
Steven E. White, Director
Accepted Date:
Jan 2, 2025 Public Works and Planning
Date:
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, if
Auditor controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of supervisors therefore the prices shown above.
_Const.Mgmt
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.