HomeMy WebLinkAbout24-S-04 Executed Contract.pdf REEDLEY RADIO TOWER AND
EQUIPMENT SHELTER
17626 E. Manning Ave. , Reedley , CA 93654
Contract # 24-S-04
The County of Fresno
Department of Public Works and Planning
2220 Tulare St., 7t" Floor
Fresno, California 93721
PROJECT MANUAL
Bid Date: Thursday, July 18, 2024, 2:00 p.m.
Budget/Account— 8905 / 7295
4� COU��
ti �c Development Services & Capital Projects Division
j85
O�FRE 6 0 Department of Public Works and Planning
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 01
REEDLEY, CA. SECTION 009115 - 1
ADDENDUM 01
Contract# 24-S-04
Dated: July 1, 2024
The foregoing documents are amended in the respects as herein set forth. This addendum and
the amendments herein shall become part of said documents and of any contract entered into
pursuant to said documents.
PLEASE ACKNOWLEDGE THIS ADDENDUM ON YOUR PROPOSAL. IF YOU HAVE GIVEN
THE CONTRACT DOCUMENTS TO SOMEONE ELSE, PLEASE FORWARD THIS
ADDENDUM.
Jul 1, 2024
9?,oFESS/p Date Signed
o No.C80424
C�V
CALF
Engineer of Record: �PE
Joseph C. Harrell, PE C80424
FRESNO COUNTY
Department of Public Works and Planning
m/a 2220 Tulare Street, Suite 720
Fresno, CA 93721-2106
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 01
REEDLEY, CA. SECTION 009115 - 2
A. SPECIFICATIONS:
a. Section 033000 Cast-In-Place Concrete
i. Paragraph 2.10, B:
a. Delete the following sentence: "Use fly ash, pozzolan, slag
cement, and silica fume as needed to reduce the total
amount of portland cement, which would otherwise be used,
by not less than 40 percent."
ii. Paragraph 2.11, A:
a. Delete the following sentence: "Air Content: 6 percent, plus
or minus 1.5 percent at point of delivery for 3/4-inch nominal
maximum aggregate size."
iii. Paragraph 2.11, B:
a. Delete the following sentence: "Air Content: 6 percent, plus
or minus 1.5 percent at point of delivery for 3/4-inch nominal
maximum aggregate size."
iv. Paragraph 2.11, C:
a. Delete the following sentence: "Air Content: 6 percent, plus
or minus 1.5 percent at point of delivery for 3/4-inch nominal
maximum aggregate size."
b. Delete the following sentence: "Steel-Fiber Reinforcement:
Add to concrete mixture, according to manufacturer's written
instructions, at a rate of 50 lb/cu. yd." and replace with:
"Synthetic Fiber Reinforcement: Add to concrete mixture,
according to manufacturer's written instructions, using both
macro and micro size fibers at a combined rate of 5 Ibs/cu.
yd."
v. Paragraph 2.5, C:
a. Replace this paragraph with the following:
Normal-Weight Aggregates: ASTM C 33, Class 3S coarse
aggregate or better, graded. Provide aggregates from a
single source with documented service record data of at
least 10 years' satisfactory service in similar applications and
service conditions using similar aggregates and cementitious
materials.
1. Maximum Coarse-Aggregate Size: 1 inch nominal.
2. Fine Aggregate: Free of materials with deleterious
reactivity to alkali in cement.
B. GENERAL CLARIFICATIONS:
Refer to Responses to Requests for Clarifications published on the County's Bid page.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 02
REEDLEY, CA. SECTION 007200— 52
ADDENDUM 02
Contract # 24-S-04
Dated: July 15, 2024
The foregoing documents are amended in the respects as herein set forth. This addendum and
the amendments herein shall become part of said documents and of any contract entered into
pursuant to said documents.
PLEASE ACKNOWLEDGE THIS ADDENDUM ON YOUR PROPOSAL. IF YOU HAVE GIVEN
THE CONTRACT DOCUMENTS TO SOMEONE ELSE, PLEASE FORWARD THIS
ADDENDUM.
Jul 15, 2024
Date Signed
9?,oFESS/p�,,
o�No.C80424
C/V
q�t OF CALF
Engineer of Record: 6 e
Joseph C. Harrell, PE C80424
FRESNO COUNTY
Department of Public Works and Planning
m/a 2220 Tulare Street, Suite 720
Fresno, CA 93721-2106
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 02
REEDLEY, CA. SECTION 007200— 52
A. PROJECT MANUAL:
a. Section 0001113 Notice to Bidders
DELETE:
2:00 P.M., (1400 hours and 00 seconds)
Thursday, July 18, 2024
REPLACE with:
2:00 P.M., (1400 hours and 00 seconds)
Thursday, July 25, 2024
ADD:
The apparent lowest bidder shall submit a Cost Distribution of the bid, otherwise
known as a "Schedule of Values," (refer to Section 002113 Instructions to
Bidders 1.16 Post-Bid / Pre-Award Information and Requirements) within eight
(8) days of the Bid Opening.
b. Section 002113 Instructions to Bidders
1.06 SUBMISSION OF PROPOSAL
A. Electronic Bid Submittal
Paragraph 1
DELETE:
The bidder has the option to submit the bid for this Project electronically. The
bidder must either attach an electronic bid bond or provide an original bid bond
(or other form of bid security authorized by Public Contract Code Section
20129(a)), prior to the bid opening.
REPLACE with:
The bidder has the option to submit the bid for this Project electronically at:
https://www.bidexpress.com/businesses/36473/home. The bidder must either
attach an electronic bid bond or provide an original bid bond (or other form of
bid security authorized by Public Contract Code Section 20129(a)), prior to the
bid opening.
c. Section 002113 Instructions to Bidders
ADD:
1.16 POST-BID / PRE-AWARD INFORMATION
Within eight (8) calendar days after bid opening, the apparent low bidder shall
submit the following information to the Engineer:
A. A cost distribution of the bid, with costs shown for major items of work
as defined by either the project specification index, the Uniform
Construction Index (UCI), or other method as appropriate for the project
and approved by the Engineer.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 02
REEDLEY, CA. SECTION 007200— 52
B. The cost distribution shall distinguish between work to be done by the
bidder's own forces and work that will be subcontracted (including those
who are to furnish materials or equipment fabricated to a special
design); all subcontractors shall be named, regardless of the dollar
amount of subcontracted work. Bidders' attention is also directed to
California Public Contract Code Section 4100 et seq regarding
subcontracting.
The County reserves the right to reject any proposed subcontractor, installer,
or supplier who cannot show satisfactory evidence of meeting the qualifications
required by the specification documents. In the event of such rejection, the
apparent low bidder shall, within five working days, submit the name and
qualifications of a replacement subcontractor, installer or supplier satisfactory
to the County. Such replacement submittal shall be in accordance with all
specification requirements.
No adjustment of bid prices shall be made in the event of such replacement.
This information may be used in the evaluation of bids. If the project is
awarded, the cost distribution will be used in determining amounts payable on
progress payments and final payment.
The County may request that bidders other than the apparent low bidder submit
similar cost distribution or qualification information, for the purpose of
evaluating bids.
Upon completion of the bid evaluation process, cost distributions or
qualification information submitted by other than the apparent low bidder will be
returned upon request.
d. Section 007200 General Conditions
2.24 PAYMENT
B. SCHEDULE OF VALUES
DELETE:
Before the first Application for Payment, the Contractor shall submit to the
Resident Engineer a Schedule of Values allocated to the various portions of
the Work, prepared in such form and supported by such data to substantiate its
accuracy as the Resident Engineer may require. This schedule, unless
objected to by the Resident Engineer, shall be used only as a basis for the
Contractor's Applications for Payment.
REPLACE with:
Before the first Application for Payment, the Contractor shall submit to the
Project Manager a Schedule of Values allocated to the various portions of the
Work, prepared in such form and supported by such data to substantiate its
accuracy as the Project Manager may require. This schedule, unless objected
to by the Project Manager, shall be used only as a basis for the Contractor's
Applications for Payment.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 02
REEDLEY, CA. SECTION 007200— 52
e. Section 007200 General Conditions
2.40 INSURANCE
B. MINIMUM SCOPE AND LIMITS OF INSURANCE
Paragraph 1
DELETE:
If a general aggregate limit applies, either the general aggregate limit shall
apply separately to this project/location (ISO CG 25 03 or 25 04) or the general
aggregate limit shall be no less than two million dollars ($2,000,000). The
umbrella or excess policy of ten million dollars ($10,000,000) must contain a
clause stating that it takes effect (drops down) in the event the primary limits
are impaired or exhausted.
REPLACE with:
If a general aggregate limit applies, either the general aggregate limit shall
apply separately to this project/location (ISO CG 25 03 or 25 04) or the general
aggregate limit shall be no less than two million dollars ($2,000,000). The
umbrella or excess policy of eight million dollars ($8,000,000) must contain a
clause stating that it takes effect (drops down) in the event the primary limits
are impaired or exhausted.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 03
REEDLEY, CA. SECTION 009115— 1
ADDENDUM 03
Contract # 24-S-04
Dated: July 18, 2024
The foregoing documents are amended in the respects as herein set forth. This addendum and
the amendments herein shall become part of said documents and of any contract entered into
pursuant to said documents.
PLEASE ACKNOWLEDGE THIS ADDENDUM ON YOUR PROPOSAL. IF YOU HAVE GIVEN
THE CONTRACT DOCUMENTS TO SOMEONE ELSE, PLEASE FORWARD THIS
ADDENDUM.
Jul 18, 2024
QRoFESS/Ory� Date Signed
X\ C• hlq�, �
0 No.C80424
c/v
q� OF CALF
Engineer of Record:
Joseph C. Harrell, PE C80424
FRESNO COUNTY
Department of Public Works and Planning
2220 Tulare Street, Suite 720
Fresno, CA 93721-2106
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 03
REEDLEY, CA. SECTION 009115— 2
A. BID FORMS AND CONTRACT CONDITIONS: No changes
B. SPECIFICATIONS: No changes
C. DRAWINGS:
a. ARCHITECTURAL
1. Al — Site Plan
a. Refer to Enlarged Site Plan — Dimensions were added from
the fence corner to the gate posts.
b. Added the limits of AC to be removed and disposed.
c. Added Note #9 to the General Notes.
2. A2.1 — Equipment Plan
a. Added Radio Tower Antenna drawings and details.
b. Added more information to Equipment List#4 of the
Equipment List Table
3. A5 — Details
a. Revised Chain Link Fence and Gate Detail to show the
addition of Barbed Wire and its Outrigger Arm, 8" dia.
Concrete midway between posts for the Hook Bolt to be
embedded on.
b. STRUCTURAL
1. S1 — Structural Gen Notes
a. Added the design criteria for the Microwave Tower.
b. Added details Pipes below Footing, Pipes Thru Footing and
Trenching near Footings.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 04
REEDLEY, CA. SECTION 009115— 1
ADDENDUM 04
Contract # 24-S-04
Dated: July 22, 2024
The foregoing documents are amended in the respects as herein set forth. This addendum and
the amendments herein shall become part of said documents and of any contract entered into
pursuant to said documents.
PLEASE ACKNOWLEDGE THIS ADDENDUM ON YOUR PROPOSAL. IF YOU HAVE GIVEN
THE CONTRACT DOCUMENTS TO SOMEONE ELSE, PLEASE FORWARD THIS
ADDENDUM.
Jul 22, 2024
QgoFESS/p Date Signed
C•
o�No.C80424
A.
C, V
�q�t OF CALF
Engineer of Record:
Joseph C. Harrell, PE C80424
FRESNO COUNTY
Department of Public Works and Planning
2220 Tulare Street, Suite 720
Fresno, CA 93721-2106
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ADDENDUM 04
REEDLEY, CA. SECTION 009115— 2
A. BID FORMS AND CONTRACT CONDITIONS: No changes
B. SPECIFICATIONS:
a. Section 000110 —Table of Contents
i. Under Division 00 — Procurement Contracting Requirements add the
following section to the Table of Contents:
"00 11 14 - LOCATION MAP"
b. Add Section 001114 Location Map, attached.
c. Section 133613 — Self-Supporting Radio Tower
i. Part 2 — Design, B. Design Requirements:
1. Replace e) Provide lightning protection with: e) Provide a lightning
rod at the top of the tower. Each antenna feeder will also require a
polyphaser lightning arrestor.
2. Add to j): Hangers shall be cushion type with 7 runs of 7/8" coaxial
cable with N-Female Connectors at both ends. Antennas must come
with N-Male Pigtails.
C. DRAWINGS:
a. STRUCTURAL
i. S4 — ROOF FRAMING PLAN, FOUNDATION PLAN
1. Added the Generator Anchorage Detail.
b. ELECTRICAL
i. E03 — ELECTRICAL BUILDING PLAN
1. Added a 2"0 Conduit for Fiber Optic
CONTRACT # 24-S-04
~ J
i
z Q REQ w Q OLLIU)Q Qa Q o 0 QU) ~ z
< NO a00 .11lOH N z � Nw z 3nbHO21nH N Qz �N131M/HOM HON 3nbN13 mo1>INH U) wva
Alb' Y
3AV N131li N Q w LLI
O W V
� 3nb'3dOH N
AIV MAIANBAIN/E dOH N J
3AV M3IAM3n1 A N 3AV M31AN3AIN N a Z O W
lllV M31n213AIN/ 33N N AIV M31AN3AIN/a33N N m
3AV a33N S Q a (? Q W
U _ WILL
W
O
O
W
3LL a � w
3 wo Q
° LL z
w 'z z Q
ROBINWpOD CIR r
N OAK DR
Q¢
J FALLBROOK CIR
w �
Q�
LU�co
AAl�ld a00MSONUI N `-
O zJ
LU
Lu m
w 0
0�w z
w _D U)
Q (IN N3AIN SONIA w
F J N
N M O
> 3AV 1wanN S
w b'HSVS z Z
w
y J O C
Q
Q U o
m ENNIS RD J o
3AV ViSln ORI S
t=
O
ca
O w N N
J Q w
z
z N N
z N N
O w
O
� N N
O U U
N L
Z Z Y
and O`dr O`dl S CDU) Q w
w Ir =
t] U
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SEALS PAGE
REEDLEY, CA. SECTION 000107- 1
ENVIRONMENTAL COMPLIANCE CENTER EDUCATIONAL BUILDING
Contract#24-S-04
Nathan Magsig, Chairman 51h District
Buddy Mendes, Vice Chairman 41h District
Brian Pacheco 1 st District
Sal Quintero 3rd District
Steve Brandau 2nd District
Paul Nerland, County Administrative Officer
Steven White, Director�� f y
Department of Public Works and Planning
W/ hozy
Date Tigned
pRE71'E
i o No.C80424r%
1'/V \r.
Supervising Engineer: OF
FRESNO COUNTY Jose C. Harrell, 80424
Department of Public Works and Planning
m/a 2220 Tulare Street, Suite 720
Fresno, CA 93721-2106
CONTRACT#24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SEALS PAGE
REEDLEY, CA. SECTION 000107 - 2
Q,pFESS/oiv 6-18-24
° cgti/- Date Signed
COD
U
No.M23588
Exp.9-30-25
��9T�FCHAN\GP���P
F of CNO
Plumbing and Mechanical Engineer: /
V AQd
-Michael Cantelmi, #M23588
License Renewal 09/30/2025
Lawrence Engineering Group
4910 E. Clinton Way, Suite 101
Fresno, CA 93727
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SEALS PAGE
REEDLEY, CA. SECTION 000107 - 3
4� �8 ,Zvz
ate Si ned
QROFEss/oH
RFV���
w No. 16581 rn
a
OF CA1.1F���
Electrical Engineer:
Joseph Prevendar, #E16581
License Renewal 03/31/2026
Electrical Power Systems, Inc.
2187 Herndon Suite 102
Clovis CA 93611
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER TABLE OF CONTENTS
REEDLEY, CA. SECTION 000110 - 1
TABLE OF CONTENTS
INDEX TO TECHNICAL SPECIFICATIONS AND BID DOCUMENTS
No. of
Pages
DIVISION 00 — PROCUREMENT CONTRACTING REQUIREMENTS
00 00 10 - SPECIFICATIONS COVER........................................................................ 1
00 01 07 - SEALS PAGE............................................................................................. 3
00 01 10 - TABLE OF CONTENTS.............................................................................. 3
00 11 13 - NOTICE TO BIDDERS ............................................................................... 5
00 21 13 - INSTRUCTIONS TO BIDDERS.................................................................. 7
00 22 13 - BIDDERS' CHECKLIST.............................................................................. 2
00 42 13 - PROPOSAL FORM .................................................................................... 2
00 43 13 - BID SECURITY FORM............................................................................... 1
00 43 36 - SUBCONTRACTOR LIST .......................................................................... 5
00 45 19 - NON-COLLUSION DECLARATION............................................................ 1
00 45 56 - TITLE 13 CARB CERTIFICATION.............................................................. 1
00 52 13 - AGREEMENT............................................................................................. 6
Exhibit A— Self Dealing Transaction Disclosure Form
00 65 36 - GUARANTY ............................................................................................... 1
00 72 00 - GENERAL CONDITIONS...........................................................................66
DIVISION 01 — GENERAL REQUIREMENTS
01 10 00 — SUMMARY................................................................................... 6
01 74 19— CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL....................6
01 77 00 — CLOSEOUT PROCEDURES......................................................................6
DIVISION 02 — NOT USED
DIVISION 03 — CONCRETE
03 20 00 — CONCRETE REINFORCEMENT............................................................... 4
03 30 00 — CAST-IN-PLACE CONCRETE...................................................................21
DIVISION 04— MASONRY
04 22 00 — CONCRETE UNIT MASONRY ..................................................................16
DIVISION 05— METALS
05 40 00 — COLD-FORMED METAL FRAMING... ......................................................12
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER TABLE OF CONTENTS
REEDLEY, CA. SECTION 000110 - 2
DIVISION 06 -WOOD AND PLASTICS
06 16 00 - SHEATHING... .......................................................................................... 4
DIVISION 07 -THERMAL AND MOISTURE PROTECTION
07 19 00 -WATER REPELLENTS... .......................................................................... 6
07 21 00 - THERMAL INSULATION...... .................................................................... 4
07 41 13.16 - STANDING-SEAM METAL ROOF PANELS.........................................13
07 62 00 - SHEET METAL FLASHING AND TRIM .....................................................10
07 72 00 - ROOF ACCESSORIES.............................................................................. 6
07 84 13 - PENETRATION FIRESTOPPING.............................................................. 7
DIVISION 08- DOORS AND WINDOWS
08 11 13 - HOLLOW METAL DOORS AND FRAMES................................................ 8
08 12 13 - HOLLOW METAL FRAMES ...................................................................... 9
08 71 00 - DOOR HARDWARE..................................................................................13
DIVISION 09 - FINISHES
09 29 00 - GYPSUM BOARD... .................................................................................. 6
09 67 23 - RESINOUS (EPDXY) FLOORING... ......................................................... 4
09 91 00 - PAINTING..................................................................................................11
DIVISION 10-12 - NOT USED
DIVISION 13- SPECIAL CONSTRUCTION
13 36 13 - SELF-SUPPORTING RADIO TOWER... ................................................... 3
DIVISON 14-19 - NOT USED
DIVISION 20 - MECHANICAL
20 01 00 - GENERAL MECHANICAL PROVISIONS................................................. 10
DIVISON 21 - NOT USED
DIVISION 22 - PLUMBING
22 04 00 - PLUMBING................................................................................................ 6
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER TABLE OF CONTENTS
REEDLEY, CA. SECTION 000110 - 3
DIVISION 23 — HEATING, VENTILIATING AND AIR CONIDTIONING
23 08 00 — HEATING, VENTILATING & AIR CONDITIONING ................................... 21
DIVISON 24— NOT USED
DIVISION 25— INTEGRATED AUTOMATION
25 09 00 — DIRECT DIGITAL CONTROL SYSTEM..................................................... 9
DIVISION 26 — ELECTRICAL
26 01 00 — GENERAL ELECTRICAL PROVISIONS... ................................................ 3
26 10 00 — BASIC ELECTRICAL REQUIREMENTS ...................................................10
26 11 00 — ELECTRICAL RELATED WORK ............................................................... 4
26 20 00 — BASIC MATERIALS AND METHODS........................................................11
26 21 00 — ELECTRICAL IDENTIFICATION ............................................................... 3
26 30 00 — SERVICE, DISTRIBUTION AND GROUNDING......................................... 9
26 31 00 — DRY TYPE TRANSFORMERS.................................................................. 2
26 43 00 — TRANSIENT VOLTAGE SURGE SUPPRESSION..................................... 2
26 49 50 — HEAVY DUTY SAFETY SWITCHES ......................................................... 1
26 50 50 — EQUIPMENT CONNECTIONS .................................................................. 2
26 51 00 — EMERGENCY GENERATOR AND ATS.................................................... 9
26 96 09 — ELECTRICAL COMMISIONING AND FIELD TESTING............................. 6
TestRecord Sheets ................................................................................................... 17
DIVISION 27— COMMUNICATIONS
27 00 00 — GENERAL COMMUNICATIONS... ............................................................ 2
27 05 36 — CABLE TRAYS FOR COMMUNICATIONS SYSTEMS.............................. 7
27 05 44 — SLEEVES AND SLEEVE SEALS .............................................................. 4
27 11 00 — COMMUNICATIONS EQUIPMENT ROOM FITTINGS ............................. 5
DIVISION 28-30 — NOT USED
DIVISION 31 — EARTHWORK
31 10 00 — SITE CLEARING....................................................................................... 6
31 20 00 — EARTH MOVING.......................................................................................12
DIVISION 32 — EXTERIOR IMPROVEMENTS
32 31 13 — CHAIN LINK FENCES AND GATES... ...................................................... 7
END OF SECTION
CONTRACT # 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER NOTICE TO BIDDERS
REEDLEY, CA. SECTION 0001113- 1
BOARD OF SUPERVISORS COUNTY OF FRESNO STATE OF CALIFORNIA
NOTICE TO BIDDERS
Sealed proposals will be received at:
https://www.bidexpress.com/businesses/36473/home
and at the Fresno County Department of Public Works and Planning, Office of the Design
Engineer, Seventh Floor, Fresno County Plaza Building, 2220 Tulare Street, Fresno, CA
93721 until
2:00 P.M., (1400 hours and 00 seconds)
Thursday, July 18, 2024
at which time the bidding will be closed.
If you have any questions about bid submission, please contact us at
DesignServicesCa-)_fresnocountyca.gov or calling (559) 353-4919 or (559) 600-4543.
Promptly following the closing of the bidding all timely submitted bids will be publicly
opened and viewable via a livestream (the link for which will be posted at
http://www.fresnocountyca.gov/pIanholders) for construction in accordance with the project
specifications therefor, to which special reference is made as follows:
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER
17626 MANNING AVENUE
REEDLEY, CA 93654
Contract No. 24-S-04
The work to be done consists, in general, of providing the design, site preparation, and
construction of a 250-foot above grade microwave tower, its corresponding equipment and
the construction of a 1,011 sq ft. equipment shelter per the plans and specifications. The
project also includes, but is not limited to, the installation of an electrical back-up generator,
automatic transfer switch, communication equipment, and all associated site work,
including fencing. The County of Fresno will supply the back-up generator, but it will be
installed by the Contractor.
This project is subject to the contracting requirements and implementing regulations
as amended in Title 13, Section 2449 General Requirements for In-Use Off-Road
Diesel-Fueled Fleets, of the California Code of Regulations (13 CCR § 2449(i)).
Bidders must submit a valid Certificate of Reported Compliance (CRC) issued by the
California Air Resources Control Board at the time of bidding. Bidders are
responsible for submitting their listed subcontractors' CRCs and any supporting
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER NOTICE TO BIDDERS
REEDLEY, CA. SECTION 0001113- 2
documentation within five (5) calendar days of bid opening. Failure to submit the
required CRCs may render a bid non-responsive.
Bidders may fill out a Request to be Added to Planholders list:
https://www.fresnocountyca.gov/Departments/Public-Works-and-Planning/Construction-
Bidding-Opportunities/Request-to-Be-Added-to-the-Planholders-List-Form
Requesters will then be listed as a planholder for the project on the website and receive
notifications and addenda issued for the project.
Prospective bidders may also select the project on
https://www.bidexpress.com/businesses/36473/home. Those that demonstrate interest in
the project will be added to the planholders list, and receive notifications and addenda
issued for the project.
Electronic copies, in ".pdf" file format, of the official project plans and specifications, bid
books and proposal sheets, as well as cross sections and such additional supplemental
project information as may be provided, are available to view, download, and print at
http://www.fresnocountyca.gov/planholders.
If a bidder is unable to submit a bid via Bid Express, Bid Books, which contain bid proposal
sheets necessary to submit a bid, may be obtained within the Specifications documents
posted on the Fresno County website.
Electronic bids shall be submitted via the Bid Express website. Hardcopy bids shall be
submitted in a sealed envelope addressed to the Department and labeled with the name of
the bidder, contract number, name of the project, and the statement "Do Not Open Until the
Time of Bid Opening."
Bid security in the amount of ten (10) percent of the amount of the bid, and in the form of a
bid bond issued by an admitted surety insurer licensed by the California Department of
Insurance, cash, cashier's check or certified check shall accompany the bid. You must
either attach an electronic bid bond or provide an original bid bond (or other form of bid
security authorized by Public Contract Code section 20129(a)), prior to the bid opening. Bid
security shall be made in favor of the County of Fresno.
Hardcopy bid bonds shall be submitted in a sealed envelope addressed to the Department
and labeled with the name of the bidder, the name of the project and the statement "Do Not
Open Until the Time of Bid Opening — BID BOND"
A Summary of Bids and a list of subcontractors for the apparent low bidder will be posted at
the above listed website, generally within 24 hours of the Bid Opening.
All requests for substitutions (refer to Section 012500, Substitution Procedures) and
questions regarding this project shall be in writing and shall be received by the Department
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER NOTICE TO BIDDERS
REEDLEY, CA. SECTION 0001113- 3
of Public Works and Planning, Design Division, no later than 2:00 P.M. on the tenth (10th)
calendar day prior to bid opening. All substitution requests and questions received after
this deadline will not receive a response unless the Department of Public Works and
Planning elects to issue an addendum to revise the bid opening date. In the event that the
bid opening date is revised, the deadline for questions will be extended to no later than
2:00 P.M. on the tenth (10th) calendar day before the revised bid opening date. Questions
shall be submitted on the "Request for Clarification" form provided on the project website
at:
https://www.fresnocountyca.gov/Departments/Public-Works-and-Planning/Construction-
Bidding-Opportunities/24-S-04-Reedley-Radio-Tower-and-Equipment-Shelter/Request-for-
Clarification-Form
Any changes to, or clarification of, the Contract documents and specifications, including
approved substitutions, shall be in the form of a written addendum issued to planholders of
record. Questions that prompt a change or clarification shall be included in the addendum
with the subsequent answer.
Any oral explanation or interpretations provided with regard to this project are not binding.
No contract will be awarded to a contractor who has not been licensed in accordance with
the provisions of the Contractors State License Law, California Business and Professions
Code, Division 3, Chapter 9, as amended, or whose bid is not on the proposal form
included in the contract document. A valid California Contractor's License, Class B
(General Building Contractor), is required for this project.
Asbestos certification from the Contractors State License Board and registration with the
Division of Occupational Safety and Health is not required to bid this project. [Health and
Safety Code 25914.2]
The Contractor and their subcontractors shall comply with all applicable statutes and
regulations, and all provisions of Sections 2.51 , 2.52 and 2.55 of the General Conditions,
regarding payment of wages, hours of work and all other labor compliance issues.
Pursuant to Section 1773 of the Labor Code, the general prevailing wage rates in the
county, or counties, in which the work is to be done have been determined by the Director
of the California Department of Industrial Relations. These wages are set forth in the
General Prevailing Wage Rates for this project, available at County of Fresno, Department
of Public Works and Planning, 2220 Tulare Street, Sixth Floor, Fresno CA 93721-2104 and
available from the California Department of Industrial Relations' Internet web site at
http://www.dir.ca.gov/DLSR/PWD. Future effective general prevailing wage rates, which
have been predetermined and are on file with the California Department of Industrial
Relations are referenced but not printed in the general prevailing wage rates.
This project is subject to compliance monitoring and enforcement by the Department of
Industrial Relations.
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER NOTICE TO BIDDERS
REEDLEY, CA. SECTION 0001113- 4
No contractor or subcontractor may be listed on a bid proposal for a public works project
unless registered with the Department of Industrial Relations pursuant to Labor Code
section 1725.5 [with limited exceptions from this requirement for bid purposes only under
Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public
works project unless registered with the Department of Industrial Relations pursuant to
Labor Code section 1725.5.
This contract is subject to state contract nondiscrimination and compliance requirements
pursuant to Government Code, Section 12990.
Minimum wage rates for this project, as predetermined by the Secretary of Labor, are set
forth in the Special Provisions. If there is a difference between the minimum wage rates
predetermined by the Secretary of Labor and the Prevailing Wage Rates predetermined by
the Director of the Department of Industrial Relations of the State of California for similar
classifications of labor, the contractor and their subcontractors shall pay not less than the
higher wage rate.
The Board of Supervisors hereby specifies that portions of the work can only be performed
outside the regular working hours as defined in the applicable collective bargaining
agreement filed with the Director of Industrial Relations in accordance with Labor Code
Section 1773.1, and that the overtime requirements for Saturdays, and holidays are hereby
waived for these portions of the work, as more particularly described in the specifications.
However, this exemption shall not negate the overtime provisions specified in Labor Code
Section 1815.
Bids are required for the entire work described herein. Bids will be compared on the basis
of the total lump sum bid.
In addition to the bid bond required by law of all bidders on public works projects, the
successful bidder shall furnish a faithful performance bond, a payment bond and a warranty
bond in accordance with the provisions of Section 2.36 of the General Conditions.
The successful bidder shall furnish a faithful performance bond in the amount of 100
percent of the contract amount and a payment bond in the amount of 100 percent of the
contract amount. Each bond specified in this Notice (bid bond, faithful performance bond
and payment bond) shall meet the requirements of all applicable statutes, including but not
limited to those specified in Public Contract Code section 20129 and Civil Code section
3248.
Each bond specified in this Notice shall be issued by a surety company designated as an
admitted surety insurer in good standing with and authorized to transact business in this
state by the California Department of Insurance, and acceptable to the County of Fresno.
Bidders are cautioned that representations made by surety companies will be verified with
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER NOTICE TO BIDDERS
REEDLEY, CA. SECTION 0001113- 5
the California Department of Insurance. Additionally, the County of Fresno, in its discretion,
when determining the sufficiency of a proposed surety company, may require the surety
company to provide additional information supported by documentation. The County
generally requires such information and documentation whenever the proposed surety
company has either a Best's Key Rating Guide of less than A and a financial size
designation of less than VIII. Provided, however, that the County expressly reserves its
right to require all information and documentation to which the County is legally entitled
from any proposed surety company.
Pursuant to Public Contract Code Section 22300, substitution of securities for any moneys
withheld by the County of Fresno to ensure performance under the contract shall be
permitted.
The Board of Supervisors reserves the right to reject any or all bids.
Board of Supervisors, County of Fresno
Paul Nerland, County Administrative Officer
Bernice E. Seidel, Clerk to the Board
Issue Date: June 18, 2024
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 1
INSTRUCTIONS TO BIDDERS
1.01 EXPLANATION TO BIDDERS
An explanation desired by bidders regarding the meaning or interpretation of the bid
documents must be requested in writing no later than seven (7) days prior to the bid
opening.
Oral explanations given before the award of the contract will not be binding. Any
interpretation made will be in the form of an addendum to the bid documents, said
addendum will only be issued by the County's Director of Public Works and Planning
("Director"). Any addenda or supplemental information will be published on the Fresno
County website at https://www.fresnocountyca.gov/planholders and the planholders of
record will be notified.
1.02 EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS AND SITE
OF WORK
The bidder is required to examine carefully the proposal, plans, specifications, special
provisions, and contract forms for submitting a proposal. It is mutually agreed that the
submission of a proposal shall be considered prima facie evidence that the bidder has made
such examination and is satisfied with the conditions to be encountered in performing the
work and as to the requirements of the plans, specifications, and special provisions of the
contract documents.
1.03 PROPOSAL GUARANTEE
The bidder shall furnish a proposal guarantee, consisting of a bid bond, cash, certified
check, or cashier's check, for ten percent (10%) of the total amount bid, including additives.
If security is provided in the form of a certified check or cashier's check, the County may
make such disposition of same as will accomplish the purpose for which submitted. Checks
deposited by unsuccessful bidders will be returned as soon as practicable after the bid
opening.
1.04 PREPARATION OF PROPOSALS
The bidder shall prepare a proposal on the blank proposal form furnished by the County.
The bidder's proposal shall be executed by the individual, by one or more partners of the
partnership, or by one or more of the officers of the corporation submitting it. If the proposal
is made by an individual, a name and post office address must be shown. If made by a
partnership, the name of each member of the partnership must be shown. If made by a
corporation, the proposal must show the name of the state under which the corporation was
chartered and the name of the president, vice president, secretary and treasurer.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 2
1.05 SUBCONTRACTORS
Every person submitting a bid to perform the work called for in the bid request shall set forth
in this bid:
A. The name and the location of the place of business, and the California contractor's
license number, and the public works contractor registration number issued pursuant
to Section 1725.5 of the Labor Code, of each subcontractor who will perform work or
labor or render service to the general contractor in or about the construction of the
work or improvement in an amount in excess of one-half(1/2) of one percent (1%) of
the general contractor's total bid; and
B. The portion of the work which will be done by each subcontractor.
The attention of bidders is directed to the provisions of Public Contract Code Section 4100
et seq which set forth the consequences and possible penalties which may result from a
failure to comply strictly with the foregoing requirements for listing of subcontractors.
1.06 SUBMISSION OF PROPOSAL
A. Electronic Bid Submittal
The bidder has the option to submit the bid for this Project electronically. The
bidder must either attach an electronic bid bond or provide an original bid bond
(or other form of bid security authorized by Public Contract Code Section
20129(a)), prior to the bid opening.
Bidders submitting online may use one of the accepted electronic sureties
(Tinubu Surety or Surety 2000) to submit their bid bond; or may submit cash,
cashier's check, certified check, or a bidder bond to Design Services at 2220
Tulare St., Seventh Floor, Fresno, CA 93721. Those submitting bid bonds
directly to Design Services must submit their bid bond:
1. Under sealed cover
2. Marked as a bid-bond
3. Identifying the contract number and the bid opening date on the cover
If necessary, please e-mail DesignServices(a�fresnocountyca.gov or call
(559) 600-4241 or (559) 600-4543, so that arrangements may be made to
hand deliver your bid bond.
Each proposal shall be submitted in a sealed envelope labeled to clearly indicate
the contract and contents.
B. Bid Submittal by Personal Delivery or by Mail
The bidder has the option to submit the bid by personal delivery or by mail.
The bidder shall specify, on the blank Proposal form, a lump sum price in
both words and figures for each bid item, including alternates, additives and
supplemental items. If the bid is not submitted electronically, then all words
and figures shall be written on the Proposal form in ink. In the case of a
discrepancy between the prices written in words and those written in figures,
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 3
the written words shall govern. The bidder's proposal shall be signed in ink
by the individual executing the bid on behalf of the bidder.
The required proposal guarantee must accompany the proposal.
When sent by mail, a sealed proposal must be addressed to the Fresno
County Department of Public Works and Planning, Office of the Design
Engineer, Sixth Floor, Fresno County Plaza Building, 2220 Tulare Street,
Fresno, CA 93721. All proposals shall be filed prior to the time and at the
place specified in the NOTICE TO BIDDERS. Proposals received after the
time for opening of the proposals will be returned to the bidder unopened.
1.07 IRREGULAR PROPOSALS
Proposals that do not conform to bid requirements may be rejected as nonresponsive.
Proposals shall be considered irregular and may be rejected for various reasons, including
but not limited to the following:
A. The proposal forms furnished by the County are not used or are altered.
B. There are unauthorized additions, conditional or alternate proposals or irregularities
of any kind which tend to make the proposal incomplete or indefinite.
C. The bidder adds any provision reserving the right to accept or reject an award, or to
enter into a contract pursuant to an award.
D. The bid fails to contain a price for each bid component.
1.08 DISQUALIFICATION OF BIDDERS
Any one or more of the following may be considered to constitute sufficient cause for
disqualification of a bidder and rejection of that bidder's proposal:
A. More than one proposal for the same work from an individual, partnership or
corporation.
B. Evidence of collusion among bidders. Participants in such collusion will receive no
recognition as bidders for any future work of the County until such participant shall
have been reinstated as a qualified bidder.
C. Lack of competency or inadequate machinery, plant or other equipment as
considered necessary to perform this project, as may be revealed by financial
statement if required.
D. Unsatisfactory performance record as shown by past work for the County, judged
from the standpoint of workmanship and progress.
E. Prior commitments or obligations which in the judgment of the County might hinder
or prevent the prompt completion of the work.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 -4
F. Failure to pay, or satisfactorily settle, all bills due for labor or materials which remain
pending under any former contract(s) at the time of submittal of the bid for this
project.
G. Failure to comply with any prequalification requirements of the County.
H. Failure to furnish full amount of Proposal Guarantee with bid or failure to sign bid
bond.
1.09 WITHDRAWAL OR REVISION OF PROPOSALS
A bidder may, without prejudice, withdraw a proposal after it has been deposited, provided
the request for such withdrawal is received in writing before the time set for opening
proposals. The request shall be executed by the bidder or the bidder's duly authorized
representative and shall include the name of the individual authorized to receive the
withdrawn proposal. Said individual shall be required to present photo identification prior to
withdrawing the proposal. The bidder may then submit a revised proposal provided it is
received prior to the time set for opening proposals.
1.10 PUBLIC OPENING OF PROPOSALS
Proposals will be opened and read publicly at the time and place indicated in the Notice to
Bidders. Bidders or their authorized agents are invited to be present.
1.11 BID PROTEST PROCEDURE / RELIEF OF BIDDER
A. BID PROTEST PROCEDURE
Any bid protest must be submitted in writing and delivered by the Bidder by either of
the following means: (1) via e-mail to DesignServices(a-.fresnocountyca.gov; or (2)
via certified mail, return receipt requested to the following address: Design Division,
Department of Public Works and Planning, 2220 Tulare Street, Sixth Floor, Fresno,
CA 93721.
The bid protest must be received no later than 5:00 p.m. of the seventh (7th)
calendar day following the deadline for submittal of the specific bid document(s)
placed at issue by the protest. Any Bidder filing a protest is encouraged to submit
the bid protest via e-mail, because the deadline is based on the Department's receipt
of the bid protest. A bid protest accordingly may be rejected as untimely if it is not
received by the deadline, regardless of the date on which it was postmarked. The
Bidder's compliance with the following additional procedures also is mandatory:
The initial protest document shall contain a complete statement of the grounds for
the protest, including a detailed statement of the factual basis and any supporting
legal authority.
The protest shall identify and address the specific portion of the document(s)forming
the basis for the protest.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 5
The protest shall include the name, address and telephone number of the person
representing the protesting party.
The Department will provide a copy of the initial protest document and any attached
documentation to all other Bidders or proposers who appear to have a reasonable
prospect of receiving an award depending upon the outcome of the protest.
The Board of Supervisors will issue a decision on the protest. If the Board of
Supervisors determines that a protest is frivolous, the party originating the protest
may be determined to be irresponsible and that party may be determined to be
ineligible for future contract awards.
The procedure and time limits set forth herein are mandatory and are the Bidder's
sole and exclusive remedy in the event of a bid protest. Failure by the Bidder to
comply with these procedures shall constitute a waiver of any right to further pursue
the bid protest, including the subsequent filing of a Government Code Claim or legal
proceedings.
B. RELIEF OF BIDDER
A bidder who claims a mistake in their bid must follow the procedures in Public
Contract Code Section 5100 et seq in seeking relief of their bid.
1.12 AWARD OF CONTRACT
The award of the contract, if it is awarded, will be to the lowest responsible bidder whose
proposal complies with all the prescribed requirements. The award, if made, will be within
54 days after the opening of proposals.
If the County finds that it will be unable to award the contract within 54 calendar days after
the opening of proposals, the Director may request any or all bidders to extend all terms of
their proposal(s) to a specified date. It is possible that additional extensions may
subsequently be requested. If a bidder does not elect to extend the terms of their proposal
beyond the 54 calendar days following opening of proposals, or does not respond within 10
days to any request for an extension, that bidder's proposal will be deemed as having
expired 54 calendar days following opening of the proposals, and that bidder's proposal will
not be considered for award of the contract.
The successful bidder will be notified in writing, by letter mailed to the address shown on
their proposal, that their bid has been accepted and that they have has been awarded the
contract.
The right is reserved by the County to reject any or all proposals, to waive technicalities
(such as immaterial bid irregularities), to advertise for new proposals, or to proceed to do
this work otherwise, if in the judgment of the awarding authorities the best interests of the
County will be promoted thereby.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 6
1.13 CANCELLATION OF AWARD
The awarding authority reserves the right to cancel the award of any contract at any time
before the execution of said contract by all parties without any liability against the County.
1.14 CONTRACT BONDS
The bidder to whom the award is made shall, within ten days, enter into a written contract
with the County. The bidder shall forfeit the proposal guarantee in case the bidder does not
follow through with execution of the written contract within ten days after the contract is
awarded.
The successful bidder shall furnish a faithful performance bond in the amount of 100 percent
(100%) of the contract amount and a payment bond in the amount of 100 percent (100%) of
the contract amount, and one-year Warranty Bond in the amount of 10 percent (10%) of the
contract amount. Said bonds shall be submitted in triplicate.
The payment bond shall contain provisions such that if the Contractor or their
subcontractors shall fail to pay (a) amounts due under the Unemployment Insurance Code
with respect to work performed under the contract, or (b) any amounts required to be
deducted, withheld and paid over to the Employment Development Department and to the
Franchise Tax Board from the wages of the employees of the Contractor and subcontractors
pursuant to Section 13020 of the Unemployment Insurance Code with respect to such work
and labor, then the surety will pay these amounts. In case suit is brought upon the payment
bond, the surety will pay a reasonable attorney's fee to be fixed by the court.
The contract form is attached hereto for the Contractor's information only. Execution of the
contract by the successful bidder will not be required until after the bid award is made.
Liability and Workers Compensation Insurance requirements shall be as set forth in the
Agreement.
1.15 BUILDERS RISK INSURANCE
The Contractor shall obtain and maintain in force Builder's Risk Insurance against loss or
damage from all perils. The policy shall cover the entire structure on which the work of this
contract is to be done, up to the full insurable value thereof (except that if the contract is for
remodeling, alteration, repair, or maintenance, then the policy shall cover the value of the
contract therefore), including items of labor and materials connected therewith on the site,
materials in place or to be used as part of the permanent construction including materials
stored and partially paid for by the County as provided in Division 00-General Conditions,
surplus materials, shanties, protective fences, bridges, or temporary structures,
miscellaneous materials and supplies incident to the work , and such scaffolding, stagings,
towers, forms and equipment as are not owned or rented by the Contractor, the cost of
which is included in the cost of the work. EXCLUDED: This insurance does not cover any
tools owned by mechanics, any tools, equipment, scaffolding, staging, towers, and forms
owned or rented by the Contractor, the capital value of which is not included in the cost of
the work, or any structures erected for the Contractor's administration of the project.
All subcontractors shall be insured to the extent of their portion of the work under the
Contractor. The Contractor shall request, and is responsible to confirm with its insurer, that
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER INSTRUCTIONS TO BIDDERS
REEDLEY, CA. SECTION 002113 - 7
the County and all subcontractors are named, both as additional insured and as additional
loss payees, on the Builder's Risk insurance policy. The County, Contractor, and all
subcontractors waive all rights, each against the others, for damages arising from perils
covered by the insurance required under the terms of this article, except such rights as they
may have to the proceeds of the Builder's Risk insurance obtained and maintained by the
Contractor. The Contractor shall file a certificate of such insurance with the County upon
issuance of the policy, and with any subcontractors upon its request.
END OF SECTION
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER BIDDERS CHECKLIST
REEDLEY, CA. SECTION 002213 - 1
BIDDERS' CHECKLIST (BUILDING CONTRACTS)
Because of numerous technical irregularities resulting in rejected proposals for projects, the
following checklist is offered for the bidders' information and use in preparing the proposal.
This checklist is not to be considered as part of the contract documents. Bidders are
cautioned that deleting or not submitting a form supplied in the bid documents (even if the
form does not require signature) may result in an irregular bid.
PROPOSAL/BID SHEET (Section 004213)
Bidder name on each sheet. Price for each item including: each additive, deductive,
supplemental or alternate items. Make no additions such as "plus tax", "plus freight", or
conditions such as "less 2% if paid by 15th". Use ink or typewriter. Acknowledge addenda.
BID SECURITY FORM - Read the Notices and Notes (Section 004313)
Indicate type of bid security provided.
Provide contract license information.
State business name and if business is a:
Corporation - list officers
Partnership - list partners
Joint Venture - list members
If Joint Venture members are corporations or partnerships, list their officers or
partners.
Individual - list Owner's name and firm name style
Signature of Bidder—BID MUST BE SIGNED!
Corporation - by an officer
Partnership - by a partner
Joint Venture - by a member
Individual - by the Owner
If signature is by a Branch Manager, Estimator, Agent, etc., the bid must be
accompanied by a power of attorney authorizing the individual to sign bids, otherwise
the bid may be rejected.
Business Address - Firm's Street Address
Mailing Address - P.O. Box or Street Address
BID SECURITY (PROPOSAL GUARANTEE)
Ten percent (10%) of the total amount bid (to include supplemental or additive items).
Type of Bid Security:
Cash - Not recommended; cash is deposited in a clearing account and is returned to
bidders by County warrant. This process may take several weeks.
Cashier's or Certified Checks - Will be held until the bid is no longer under
consideration. If submitted by a potential awardee, they will be returned when the
contract bonds are submitted and approved.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER BIDDERS CHECKLIST
REEDLEY, CA. SECTION 002213 - 2
Bid Bonds - Must be signed by the bidder and by the attorney-in-fact for the bonding
company. Signature of attorney-in-fact should be notarized and the bond should be
accompanied by bonding company's affidavit authorizing attorney-in-fact to execute
bonds. An unsigned bid bond will be cause for rejection. If the bid is submitted
electronically, then the bidder must either attach an electronic bid bond or provide an
original bid bond (or other form of bid security authorized by Public Contract Code
Section 20129(a)), prior to the bid opening, as more thoroughly specified in the
Instructions to Bidders, Section 1.04.A ("Electronic Bid Submittal").
SUBCONTRACTOR LIST (Section 004336)
One firm for each type of work to be subcontracted. Fill out as completely as possible.
Name and location of place of business, California contractor's license number, public works
contractor registration number issued pursuant to Section 1725.5 of the Labor Code, and
description of work to be performed are required to be listed for each subcontractor in
accordance with Public Contract Code section 4104.
NON-COLLUSION DECLARATION (Section 004519)
Must be completed, signed, and returned with bid.
TITLE 13 CARB CERTIFICATION (Section 004556)
Contractors, if applicable, must submit valid Certificates of Reported Compliance with their
bid. Subcontractor certificates will be due no later than 4:00 PM on the fifth (5t') calendar
day after the bid opening if not submitted with the bid.
GUARANTY OF WORK (Section 006536)
Does not need to be submitted with the bid. (Must be signed and submitted by the
successful bidder together with the executed contract and requisite bonds and insurance
certificates, within ten days after award of the Project.)
OTHER
If the bid forms have been removed from the specifications booklet, staple the pages
together.
Make sure the bid envelope is sealed and shows the project name, bid package and
contract number.
If the bid is mailed, allow sufficient time for postal delivery prior to the bid closing time. Bids
received after the scheduled time will be returned unopened. Be sure the statement "DO
NOT OPEN UNTIL TIME OF BID OPENING" is on the envelope.
END OF SECTION
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER PROPOSAL FORM
REEDLEY, CA. SECTION 004213 - 1
PROPOSAL TO THE BOARD OF SUPERVISORS
COUNTY OF FRESNO
Contract: REEDLEY RADIO TOWER AND EQUIPMENT SHELTER
Contract No.: 24-S-04
Fund / Subclass/ Org /Account/ Program or Memo No.: 1020 / 10000 / 8905 / 7295
Work to be performed:
The work to be done is shown on a set of Plans, Department File No. 11328, entitled:
"Reedley Radio Tower and Equipment Shelter"
Building No.: TBD
Project Address:
17626 Manning Avenue
Reedley, CA 93654
In case of a discrepancy between words and figures, the words shall prevail.
If this proposal shall be accepted and the undersigned shall fail to contract, as aforesaid, and
to give the two bonds in the sums to be determined as aforesaid, each issued by a surety
satisfactory to the Awarding Authority, within ten (10) days after the award of the contract, the
Awarding Authority, at its option, may determine that the bidder has abandoned the contract,
and thereupon this proposal and the acceptance thereof shall be null and void, and the
forfeiture of such security accompanying this proposal shall operate and the same shall be the
property of the County.
The undersigned, as bidder, declares that all addenda issued with respect to this bid have
been received and incorporated into this Proposal. The bidder's signature on this Proposal
also constitutes acknowledgement of all addenda.
The undersigned, as bidder, declares that the only persons, or parties interested in this
proposal as principals are those named herein; that this proposal is made without collusion
with any other person, firm or corporation; that the bidder has carefully examined the annexed
proposed form of contract, and the plans therein referred to; and the bidder proposes and
agrees if this proposal is accepted, that the bidder will contract with the County of Fresno to
provide all necessary machinery, tools, apparatus and other means of construction, and to do
all the work and furnish all the materials specified in the contract in the manner and time
therein prescribed, and according to the requirements of the County as therein set forth, and
that the bidder will take in full payment therefor the following lump sum price, to-wit:
CONTRACT# 24-S-04
General Info
Total:
$2,326,683.00
Number Description
24-S-04 Reedley Radio Tower and Equipment Shelter
Deadline
The work to be done consists, in general, of providing the design, site preparation, and
07/25/2024 02:00 PM PDT construction of a 250-foot above grade microwave tower, its corresponding equipment and
the construction of a 1,011 sqft. equipment shelter per the plans and specifications. The
Vendor project also includes, but is not limited to, the installation of an electrical back-up
Katch Environmental, Inc. generator, automatic transfer switch, communication equipment, and all associated site
dba Katch General work including fencing. The County of Fresno will supply the back-up generator, but it will
be installed by the Contractor.
Submitted
Allows zero unit prices and labor
07/25/2024 01:54 PM PDT
No
Signed by
Allows negative unit prices and labor
Paul Katchadourian
Account Holder Jenn No
Schmid
Opened
07/25/2024 02:07 PM PDT
By
jgeddert@fresnocountyca.gov
Attachment List
County of Fresno - Project Website
RFC form, bid opening details, any Supplemental Information
including RFC responses, Pre-bid Conference information, etc.
Project Manual
Specifications
Plans
Drawings
Addendum 1 (http://www.fresnocountyca.gov/files/sharedassets/county/v/2/public-works-and-planning/design/construction-bidding-opportunities/
24-s-04-reedley-radio-tower-and-equipment-shelter/00-91-15-addendum-01.pdf)
Addendum 1
Addendum 2 (http://www.fresnocountyca.gov/files/sha red assets/county/v/2/public-works-and-planning/design/construction-bidding-opportunities/
24-s-04-reedley-radio-tower-and-eq uipment-shelter/001915-addendum-2.pdf)
Addendum 2
Addendum 3 (http://www.fresnocountyca.gov/files/sharedassets/county/v/1/public-works-and-planning/design/construction-bidding-opportunities/
24-s-04-reedley-radio-tower-and-equipment-shelter/00-91-15-addendum-03.pdf)
Page 1 of 20 07/25/2024
Addendum 3
Addendum 3 Plan Sheets (http://www.fresnocountyca.gov/files/sharedassets/county/v/1/public-works-and-planning/design/construction-bidding-
opportun ities/24-s-04-reedley-rad io-tower-a nd-eq u ipment-shelter/add end u m-3-plan-sheets.pdf)
Addendum 3 Plan Sheets
Addendum 4 (http://www.fresnocountyca.gov/files/sharedassets/county/v/1/public-works-and-planning/design/construction-bidding-opportunities/
24-s-04-reedley-radio-tower-and-equipment-shelter/00-91-15-addendum-04.pdf)
Addendum 4
Addendum 4 Plan Sheets (http://www.fresnocountyca.gov/files/sharedassets/county/v/2/public-works-and-planning/design/construction-bidding-
opportun ities/24-s-04-reedley-rad io-tower-a nd-eq u ipment-shelter/add end u m-4-plan-sheets.pdf)
Addendum 4 Plan Sheets
Proposal Section 004213 - 1-2
Proposal to the County of Fresno
Contract Name: Reedley Radio Tower and Equipment Shelter
Contract No.: 24-S-04
Fund / Subclass / Org / Account / Program or Memo No.: 1020 / 10000 / 8905 / 7295
Work to be performed: The work to be done is shown on a set of Plans, entitled: "Reedley Radio Tower and Equipment Shelter"
Building No.: TBD
Project Address:
17626 Manning Avenue
Reedley, CA 93654
In case of a discrepancy between words and figures, the words shall prevail.
If this proposal shall be accepted and the undersigned shall fail to contract, as aforesaid, and to give the two bonds in the sums
to be determined as aforesaid, each issued by a surety satisfactory to the Awarding Authority, within ten (10) days after the award
of the contract, the Awarding Authority, at its option, may determine that the bidder has abandoned the contract, and thereupon
this proposal and the acceptance thereof shall be null and void, and the forfeiture of such security accompanying this proposal
shall operate and the same shall be the property of the County.
The undersigned, as bidder, declares that all addenda issued with respect to this bid have been received and incorporated into
this Proposal. The bidder's signature on this Proposal also constitutes acknowledgement of all addenda.
The undersigned, as bidder, declares that the only persons, or parties interested in this proposal as principals are those named
herein; that this proposal is made without collusion with any other person, firm or corporation; that the bidder has carefully
examined the annexed proposed form of contract, and the plans therein referred to; and the bidder proposes and agrees if this
proposal is accepted, that the bidder will contract with the County of Fresno to provide all necessary machinery, tools, apparatus
and other means of construction, and to do all the work and furnish all the materials specified in the contract in the manner and
time therein prescribed, and according to the requirements of the County as therein set forth, and that the bidder will take in full
payment therefor the following lump sum price, to-wit:
Page 2 of 20 07/25/2024
Proposal Section 004213 - 2 Bid
$2,326,683.00
Item Item Description Item Price Extension
No.
1 250 ft tall, 3-sided, self-supporting radio tower design and construction as per the $683,999.00 $683,999.00
detailed specifications
2 Equipment shelter construction and tower equipment as specified in the plans $1,642,684.00 $1,642,684.00
and specifications and all associated work including fencing
Total: $2,326,683.00
Proposal Section 004213 - 2 Acknowledgement of Addendum
Type N/A if no addenda were issued. Click "+" to add additional fields.
Addendum No. *
01
Dated
07/01/2024
Type N/A if no addenda were issued. Click "+" to add additional fields. 1
Addendum No. *
02
Dated
07/15/2024
Type N/A if no addenda were issued. Click "+" to add additional fields. 2
Addendum No. *
03
Dated
07/18/2024
Page 3 of 20 07/25/2024
Type N/A if no addenda were issued. Click "+" to add additional fields. 3
Addendum No. *
04
Dated
07/22/2024
Bid Security Form Section 004313 - 1
Accompanying this proposal is security (check one only) in an amount equal to at least ten percent (10%) of the total amount of
the bid:
Bond Percentage
10.00%
Guarantee Method
Paper Bid Bond, Certified
Check, Cashier's Check,
Cash
Paper Bid Bond, Certified Check, Cashier's Check, Cash
Confirmation *
I have provided a Paper Bid Bond for 10.00% of the bid total amount, to the public works office, prior to the solicitation deadline.
If Cash Security, Enter Amount
You must either attach an electronic bid bond here or provide an original bid bond (or other form of bid
security authorized by Public Contract Code Section 20129(a)), prior to the bid opening.
Bid Security Form Section 004313 - 1 (cont.)
Business Name *
Katch Environmental, Inc. dba Katch General
Page 4 of 20 07/25/2024
Note: If bidder or other interested person is a corporation, state legal name of corporation. If bidder is a co-partnership, state true
name of firm.
Type of Business
Corporation - list Officers
Business Owners and Officers Names
Paul Katchadourian - President/Owner
Note: If bidder or other interested person is:
• a corporation, list names of the president, secretary, treasurer and manager thereof
• a partnership, list names of all individual co-partners composing firm.
• an individual, state first and last name in full.
Names of Owners and Key Employees
Paul Katchadourian - President/Owner
Note: List majority owners of your firm. If multiple owners, list all. Also include anyone, including key employees, who are actively
promoting the contract. (SB1439)
Licensed in accordance with an act providing for the registration of Contractors:
Class
B
Contractor License No. * Expires
933096 11/30/2025
DIR Registration Number
1000010211
Page 5 of 20 07/25/2024
Business Address
929 L St, Fresno, CA
Zip Code
93721
Mailing Address
929 L St, Fresno, CA
Zip Code
93721
Business Phone * Fax Number
(559) 292-6653
E-mail Address
estimating@katchgeneral.com
Signature of Bidder
Paul Katchadourian
Dated *
07/25/2024
NOTE: If bidder is a corporation, the legal name of the corporation shall be set forth above together with the signature of the
officer or officers authorized to sign contracts on behalf of the corporation; if bidder is a co-partnership, the true name of the firm
shall be set forth above together with the signature of the partner or partners authorized to sign contracts on behalf of the co-
partnership; and if bidder is an individual, his signature shall be placed above. If signature is by an agent, other than an officer of
a corporation or a member of a partnership, a Power of Attorney must be on file with the Owner prior to opening bids or
submitted with the bid; otherwise, the bid will be disregarded as irregular and unauthorized.
Subcontractors List Section 004336 - 1
SUBCONTRACTORS
The following named subcontractor(s) will perform with labor, or otherwise render services to the general contractor in or about
the construction of the work or improvement in an amount in excess of one-half of one percent of the total bid presented
herewith. Please fill out as completely as possible when submitting your bid. Use subcontractor's business name style as
registered with the License Board. Submission of subcontractor's name, location of business and description of work, California
contractor's license number and public works contractor registration number issued pursuant to Section 1725.5 of the Labor Code,
all are REQUIRED, by Section 4104 of the California Public Contract Code, to be submitted prior to bid opening. (The "location of
Page 6 of 20 07/25/2024
business" must specify the city in which the subcontractor's business is located, and the state if other than California.) All other
requested information shall be submitted, either with the bid or within 24 hours after bid opening.
Please fill out as completely as possible when submitting your bid. Use subcontractor's business name style as registered with
the License Board.
FAILURE TO LIST SUBCONTRACTORS AS DIRECTED MAY RENDER THE BID NON-RESPONSIVE, OR MAY RESULT IN
ASSESSMENT OF A PENALTY AGAINST THE BIDDER IN ACCORDANCE WITH SECTION 4110 OF THE CALIFORNIA
PUBLIC CONTRACT CODE.
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields.
Subcontractor: *
Soto Brother Custom Concrete, Inc.
Business Address *
3527 E. Pico Ave„ Fresno, CA 93726
Class
License No.
1094552
DIR Registration No.
1001091041
Item No. or Description of Work
Rebar & Concrete
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 1
Subcontractor: *
EWI Doors and Millwork
Page 7 of 20 07/25/2024
Business Address *
2555 North Argyle, Fresno, CA 93727
Class
License No.
1919914
DIR Registration No.
1000005826
Item No. or Description of Work
Hollow Metal Doors Doors, Frames and Hardware (Materials Only)
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 2
Subcontractor: *
McCurley and Day Masonry
Business Address *
5740 E. Shields Ave., #104, Fresno, CA 93727
Class
License No.
620562
DIR Registration No.
1000012425
Item No. or Description of Work
Masonry
Page 8 of 20 07/25/2024
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 3
Subcontractor:
D-One
Business Address
961 N. Armstrong Ave., Clovis, CA 93611
Class
License No.
1060276
DIR Registration No.
1000561495
Item No. or Description of Work
Cold-Formed Metal Roofing, Sheathing, Rough Carpentry & Gypsum Board
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 4
Subcontractor: *
Ro's Precise Painting, Inc.
Page 9 of 20 07/25/2024
Business Address *
1816 INDUSTRIAL WAY, Sanger, CA 93657
Class
License No.
1937283
DIR Registration No.
1000000284
Item No. or Description of Work
Water Repellants, Resinous Flooring & Painting
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 5
Subcontractor: *
California Building Products
Business Address *
5712 E. Fountain Way, Fresno, CA 93727
Class
License No.
1084969
DIR Registration No.
1000054846
Item No. or Description of Work
Insulation
Page 10 of 20 07/25/2024
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 6
Subcontractor: *
Four CCCC's Constructors
Business Address *
1560 H Street, Fresno, CA 93721
Class
License No.
908294
DIR Registration No.
1000002824
Item No. or Description of Work
Standing Seam Metal Roof Panels, Sheet Metal Flashing & Trim
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 7
Subcontractor: *
Precision Doors Millwork Co.
Page 11 of 20 07/25/2024
Business Address *
15088 La Palma Dr., Chino, CA 91710
Class
License No.
759197
DIR Registration No.
1000007541
Item No. or Description of Work
Hollow Metal Doors, Frames and Hardware (Installer)
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 8
Subcontractor:
Full Signal
Business Address
46750 Longview Lane West, Coarsegold, CA 93614
Class
License No.
819510
DIR Registration No.
1001076948
Item No. or Description of Work
Self-Supporting Radio Tower
Page 12 of 20 07/25/2024
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 9
Subcontractor:
Modern Air
Business Address
2200 Copper Avenue, Merced, CA 95344
Class
License No.
569680
DIR Registration No.
1000002692
Item No. or Description of Work
Mechanical, HVAC & Direct Digital Control System
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 10
Subcontractor: *
Larger Electric, Inc.
Page 13 of 20 07/25/2024
Business Address *
3034 Avenue 393, Kingsburg, CA 93631
Class
License No.
929677
DIR Registration No.
1001013766
Item No. or Description of Work
Electrical & Communications
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor List - Section 004336 - 2
Optional: Vendor is not required to complete.
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields.
Subcontractor: *
JT2 Inc dba Todd Companies
Business Address *
PO Box 6820, Visalia, CA 93290
Class
License No.
788798
Page 14 of 20 07/25/2024
DIR Registration No.
1000002649
Item No. or Description of Work
Plumbing, Site Clearing & Earthwork
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Subcontractor: To add more subcontractor listings, click the "+" to add additional fields. 1
Subcontractor: *
Fresno Fence Connection
Business Address *
PO Box 458, Sanger, CA 93657
Class
License No.
692620
DIR Registration No.
1000014751
Item No. or Description of Work
Chain Link Fences & Gates
Dollar Amount: OR Percentage of Total Bid:
Email Address:
Page 15 of 20 07/25/2024
Noncollusion Declaration Section 004519 - 1
TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID*
The undersigned declares:
I am the (Choose one of the following options):
Owner
If Corporate Officer please list Title:
of (Business Name): *
Katch Environmental, Inc. dba Katch General
the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization,
or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any
other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with
any bidder or anyone else to put in a sham bid, or refrain from bidding. The bidder has not in any manner, directly or indirectly,
sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix
any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true.
The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or
divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository,
or to any member or agent thereof, and has not paid, and will not pay, any person or entity for that purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability
company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does
execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this
declaration is executed on 2024,
Date: *
07/25/2024
at City, State:
Fresno, CA
Signature:
Paul Katchadourian
Page 16 of 20 07/25/2024
(See Title 23 United States Code Section 112; Calif Public Contract Code Section 7106)
*NOTE: Completing, signing, and returning the Non-Collusion Declaration is a required part of the Proposal. Bidders are cautioned
that making a false certification may subject the certifier to criminal prosecution.
Title 13 CARB Certification Section 004556 - 1
In conformance with Title 13 § 2449(i), bidders will be required to attach copies of valid Certificates of Reported Compliance for
the fleet selected for the contract and their listed subcontractors.
Before May 15th of each year, the prime contractor must collect a new valid Certificate of Reported Compliance for the current
compliance year, as defined in section 2449(n), from all fleets that have an ongoing contract with the prime contractor as of
March 1 of that year. Prime contractors must not write contracts to evade this requirement. Annual renewals must be provided to
the Resident Engineer at least one week prior to the expiration date of the current certificate.
https://ww2.arb.ca.gov/resources/fact-sheets/fact-sheet-contracting-requirements
Choose all that apply:
Bidder's Certificate of Reported Compliance has been attached to the bid.
Bidder does not have a fleet subject to this regulation as outlined in Section 2449(i)(1)-(4).
Listed subcontractors' certificates have been attached or will be submitted within five (5) calendar days of the
bid opening.
F—The following subcontractors do not have a fleet subject to this regulation as outlined in Section 2449(i)(1)-(4):
Page 17 of 20 07/25/2024
FAILURE TO PROVIDE THE CERTIFICATES OF REPORTED COMPLIANCE AS DIRECTED MAY RENDER THE BID NOW
RESPONSIVE.
Guaranty Section 006536 - 1
Optional: Vendor is not required to complete.
CONTRACT NO: 24-S-04
This guaranty shall be executed by the successful bidder in accordance with Section 2.32 of the General Conditions. The bidder
may execute the guaranty on this page at the time of submitting the bid or may, in the alternative, submit it with the insurance
certificates and bonds within ten (10) days after award.
GUARANTY
To the Owner: County of Fresno
The undersigned guarantees the construction and installation of the following work included in this project:
ALL WORK
Should any of the materials or equipment prove defective or should the work as a whole prove defective, due to faulty
workmanship, material furnished or methods of installation, or should the work or any part thereof fail to operate properly as
originally intended and in accordance with each individual Work Order Detailed Scope of Work and specifications, due to any of
the above causes, all within 365 calendar days after the date on which the Work under this contract is accepted by the Owner,
the undersigned agrees to reimburse the Owner, upon demand, for its expenses incurred in restoring said work to the condition
contemplated in said project, including the cost of any such equipment or materials replaced and the cost of removing and
replacing any other work necessary to make such replacement or repairs, or, upon demand by the Owner, to replace any such
material and to repair said work completely without cost to the Owner so that said work will function successfully as originally
contemplated.
The Owner shall have the unqualified option to make any needed replacement or repairs itself or to have such replacements or
repairs done by the undersigned. In the event the Owner elects to have said work performed by the undersigned, the undersigned
agrees that the repairs shall be made and such materials as are necessary shall be furnished and installed within a reasonable
Page 18 of 20 07/25/2024
time after the receipt of demand from the Owner. If the undersigned shall fail or refuse to comply with his or her obligations under
this guaranty, the Owner shall be entitled to all costs and expenses reasonably incurred by reason of said failure or refusal.
Date:
No bid
Name (Printed):
No bid
Signature:
No bid
Title:
No bid
Contractor:
No bid
Additional Documents (use if needed)
Name Omission Terms Submitted
File
Not Required - Extra Space if needed Bid Bond_FC
Not Required - Extra Space if needed Not Required - Extra Space if needed Confirmation_07
12 2024.pdf
Not Required - Extra Space if needed Not Required - Extra Space if needed Non-Collusion
Not Required - Extra Space if needed Declaration.pdf
I am not
enclosing this
Not Required - Extra Space if needed document
Not Required - Extra Space if needed Not Required - Extra Space if needed because the
omission terms
have been met.
3 Required Documents
Required Document List
Page 19 of 20 07/25/2024
Name Omission Terms Submitted
File
CARB Certification of Reported Compliance - CARB cert -
Bidder Does not have a fleet subject to this regulation. Blue Line
Valid CARB Certification of Reported Compliance Generator
- Bidder 1.pdf
I am not
CARB Certification(s) of Reported Compliance - enclosing this
Subcontractors Due by 4pm on the 5th calendar day after bid document
Valid CARB Certification(s) of Reported opening or no listed subcontractors have a fleet because the
Compliance - Subcontractors subject to this regulation. omission terms
have been
met.
2 Required Documents
Page 20 of 20 07/25/2024
REEDLEY RADIO TOWER AND EQUIPME T SHELTER GUARANTY
REEDLEY, CA. SECTION 006536 - 1
CONTRACT NO: 24-S-04
This guaranty shall be executed by the successful bidder in accordance with Section 2.32 of
the General Conditions. The bidder may execute the guaranty on this page at the time of
submitting the bid or may, in the alternative, submit it with the insurance certificates and bonds
within ten (10) days after award.
GUARANTY
To the Owner: County of Fresno
The undersigned guarantees the constructidr and installation of the following work included
in this project:
ALL WORK
Should any of the materials or equipment pro*e defective or should the work as a whole prove
defective, due to faulty workmanship, material furnished or methods of installation, or should
the work or any part thereof fail to operate properly as originally intended and in accordance
with each individual Work Order Detailed Scope of Work and specifications, due to any of the
above causes, all within 365 Calendar Days after the date on which the Work under this
contract is accepted by the Owner, the undersigned agrees to reimburse the Owner, upon
demand, for its expenses incurred in restoring said work to the condition contemplated in said
project, including the cost of any such eq Ipment or materials replaced and the cost of
removing and replacing any other work necessary to make such replacement or repairs, or,
upon demand by the Owner, to replace any such material and to repair said work completely
without cost to the Owner so that said work will function successfully as originally
contemplated.
The Owner shall have the unqualified option to make any needed replacement or repairs itself
or to have such replacements or repairs done by the undersigned. In the event the Owner
elects to have said work performed by the undersigned, the undersigned agrees that the
repairs shall be made and such materials as are necessary shall be furnished and installed
within a reasonable time after the receipt of demand from the Owner. If the undersigned shall
fail or refuse to comply with their obligations L nder this guaranty, the Owner shall be entitled
to all costs and expenses reasonably incurrec by reason of said failure or refusal.
Name (Printed): Paul Katchadourian
Signature:
Title: President
Date: 09/27/2024 Contractor: Katch General
END OF ECTION
CONTRACT#24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 - 1
AGREEMENT
THIS AGREEMENT is made at Fresno, in Fresno County, California, by and between
Katch Environmental, Inc. dba Katch General , hereinafter"Contractor", and the County of
Fresno, hereinafter"Owner".
WITNESSETH, the Contractor and the Owner, for the consideration hereinafter named, agree as
follows:
ARTICLE I. The Contractor agrees to furnish all labor, equipment and materials, including tools,
implements, and appliances required, and to perform all the work in a good and workmanlike
manner, free from any and all liens and claims of mechanics, materialmen, subcontractors,
artisans, machinists, teamsters, and laborers required for:
Reedley Radio Tower and Equipment Shelter
Contract No. 24-S-04
Located at 17626 Manning Avenue, Reedley, California, all in strict compliance with the plans,
drawings, and specifications therefore prepared by the Director of the Fresno County Department
of Public Works and Planning and his authorized representatives, hereinafter called the Project
Manager, and other contract documents relating thereto.
ARTICLE II. The Contractor and the Owner agree that the Advertisement (Notice to Bidders), the
Wage Scale, the Proposal hereto attached, the Instructions to Bidders, the General Conditions of
the contract, the Technical Specifications, the Drawings, and the Addenda and Bulletins thereto,
the Contract Bonds and Certificates of Liability and Workers Compensation Insurance, and the
Contract Change Orders, together with this Agreement form the Contract Documents, and they are
as fully a part of the contract as if hereto attached or herein repeated. The Specifications and
Drawings are intended to cooperate so that any work exhibited in the drawings and not mentioned
in the specifications, or vice versa, is to be executed the same as if both are mentioned in the
specifications and set forth in the drawings, to the true intent and meaning of the said drawings
and specifications when taken together. Provided, however, that no part of said specifications that
is in conflict with any portion of this Agreement, or that is not actually descriptive of the work to be
done thereunder, or of the manner in which the said work is to be executed, shall be considered
as any part of this Agreement, but shall be utterly null and void, and anything that is expressly
stated, delineated or shown in or upon the specifications or Detailed Scope of Work shall govern
and be followed, notwithstanding anything to the contrary in any other source of information or
authority to which reference may be made.
ARTICLE III. The Contractor agrees that the work under the contract shall be completed as
determined by the Owner within One hundred sixty (160) CALENDAR DAYS from the date
shown in the Notice to Proceed. Time of performance shall be deemed as of the essence hereof
and it is agreed that actual damages to the Owner from any delay in completion beyond the date
provided for herein, or any extension thereof until the work is completed or accepted, shall be
all provable damages plus liquidated damages in the amount of Three Thousand and 00/100
DOLLARS($3,000.00) per day;that said liquidated damage was arrived at by a studied estimate
of loss to the Owner in the event of a delay considering the following damage items which are
extremely difficult or impossible to determine: Additional construction expense resulting from
delay of completion including, but not limited to, engineering, inspection, rental and utilities;
provided, however, the Owner may conditionally accept the work and occupy and use the same
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 - 2
if there has been such a degree of completion as shall in its opinion render the same safe, fit
and convenient for the use for which it is intended and in such cases the Contractor and Surety
shall not be charged for liquidated damages for any period subsequent to such conditional
acceptance and occupation by the Owner but Owner may assess actual damages caused by
failure of total completion during such period. The time during which the Contractor is delayed
in said work by the acts or neglects of the Owner or its employees or those under it by contract
or otherwise, or by the acts of God which the Contractor could not have reasonably foreseen
and provided for, or by storms and inclement weather which delays the work, or by any strikes,
boycotts, or like obstructive action by employee or labor organizations, or by any general
lockouts or other defensive action by employers, whether general, or by organizations of
employers, shall be added to the time for completion as aforesaid.
ARTICLE IV. COMPENSATION: The Owner agrees to make payments on account thereof as
provided in the General Conditions in the total amount of Two Million Three Hundred TwentV-
Six Thousand Six Hundred Eighty-Three Dollars and 00/100 ($2,326,683.00I in current funds
for the performance of the contract which sum is computed as follows: TOTAL BID LUMP SUM.
ARTICLE V. The Contractor and the Owner agree that changes in this Agreement or in the work
to be done under this Agreement shall become effective only when written in the form of a
supplemental agreement or change order and approved and signed by the Owner and the
Contractor. It is specifically agreed that the Owner shall have the right to request any alterations,
deviations, reductions, or additions to the contract, plans, and/or specifications and the amount
of the cost thereof shall be added to or deducted from the amount of the contract price aforesaid
by fair and reasonable valuations thereof.
This contract shall be deemed completed when the work is finished in accordance with all
Contract Documents as amended by such changes. No such change or modification shall
release or exonerate any surety upon any guaranty or bond given in connection with this
contract.
ARTICLE VI. In the event of a dispute between the Owner or Project Manager and the
Contractor as to an interpretation of any of the specifications or as to the quality of sufficiency of
material or workmanship, the decision of the Project Manager shall for the time being prevail
and the Contractor, without delaying the job, shall proceed as directed by the Project Manager
without prejudice to a final determination by negotiation, arbitration by mutual consent or
litigation and should the Contractor be finally determined to be either wholly or partially correct,
the Owner shall reimburse him for any added costs he may have incurred by reason of work
done or material supplied beyond the terms of the contract as a result of complying with the
Project Manager's directions as aforesaid. In the event the Contractor shall neglect to prosecute
the work properly or fail to perform any provisions of this contract, the Owner, after three days'
written notice to the Contractor, may, without prejudice to any other remedy it may have, make
good such deficiencies and may deduct the cost thereof from the payment then or thereafter due
to the Contractor, subject to final settlement between the parties as in this paragraph
hereinabove provided.
ARTICLE VII. TERMINATION: If the Contractor should be adjudged a bankrupt, or if he should
make a general assignment for the benefit of his creditors, or if a receiver should be appointed
on account of his insolvency, or if he or any of his subcontractors should persistently violate any
of the provisions of the contract, or if he should persistently or repeatedly refuse or should fail,
except in cases for which extension of time is provided, to supply enough properly skilled
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 - 3
except in cases for which extension of time is provided, to supply enough properly skilled
workmen or proper material, or if he should fail to make prompt payment to subcontractors or
for material or labor or persistently disregard laws, ordinances or the instructions of the Project
Manager, then the Owner may, upon the certificate of the Project Manager, when sufficient
cause exists to justify such action, serve written notice upon the Contractor and his surety of its
intention to terminate the contract, such notice to contain the reasons for such intention to
terminate the contract, and unless within five (5) days after the serving of such notice, such
violations shall cease and satisfactory arrangements for correction thereof be made, the contract
shall, upon the expiration of said five days, cease and terminate.
In the event of any such termination, the Owner shall immediately serve written notice thereof
upon the surety and the Contractor, and the surety shall have the right to take over and perform
the contract, provided, however, that if the surety within ten (10) days after the serving upon it
of notice of termination does not give the Owner written notice of its intention to take over and
perform the contract or does not commence performance thereof within the ten (10) days stated
above from the date of the serving of such notice, the Owner may take over the work and
prosecute the same to completion by contract or by any other method it may deem advisable for
the account and at the expense of the Contractor, and the Contractor and his surety shall be
liable to the Owner for any excess cost occasioned the Owner thereby, and in such event the
Owner may without liability for so doing, take possession of and utilize in completing the work,
such materials, appliances, plant and other property belonging to the Contractor as may be on
the site or the work and necessary therefore. In such case, the Contractor shall not be entitled
to receive any further payment until the work is finished.
If the unpaid balance of the contract price shall exceed the expense of finishing the work,
including compensation for additional managerial and administrative services, such excess shall
be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor
shall pay the difference to the Owner. The expense incurred by the Owner as herein provided,
and damage incurred through the Contractor's default, shall be certified by the Project Manager.
ARTICLE VIII. The Contractor and his subcontractors shall comply with Sections 1770 — 1780
of the California Labor Code and the provisions of Sections 2.52 and 2.55 of the General
Conditions concerning the payment of wages to all workers and mechanics, and the employment
and payment of apprentices by the Contractor or any subcontractor for all work performed under
this Agreement.
ARTICLE IX. The Contractor and his subcontractors shall comply with Sections 1810 to 1815
of the California Labor Code and the provisions of Section 2.51 of the General Conditions,
concerning hours of work and payment of overtime compensation for all work performed under
this Agreement.
The Board of Supervisors hereby specifies that portions of the work can only be performed
outside the regular working h ours as defined in the applicable collective bargaining agreement
filed with the Director of Industrial Relations in accordance with Labor Code Section 1773.1, and
that the overtime requirements for Saturdays, and holidays are hereby waived for these portions
of the work, as more particularly described in the specifications. However, this exemption shall
not negate the overtime provisions specified in Labor Code Section 1815.
ARTICLE X. INDEMNIFICATION: To the fullest extent permitted by law, Contractor agrees to
and shall indemnify, save, hold harmless and at County's request, defend County and its officers,
agents and employees, and the Project Manager and their respective officers, agents and
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 -4
employees, from any and all costs and expenses, attorney fees and court costs, damages,
liabilities, claims and losses occurring or resulting to County, or the Project Manager in
connection with the performance, or failure to perform, by Contractor, its officers, agents or
employees under this Agreement, and from any and all costs and expenses, attorney fees and
court costs, damages, liabilities, claims and losses occurring or resulting to any person, firm or
corporation who may be injured or damaged by the performance, or failure to perform, of
Contractor, its officers, agents or employees under this Agreement. In addition, Contractor
agrees to indemnify County for Federal, State of California and/or local audit exceptions resulting
from non-compliance herein on the part of Contractor.
In any and all claims against the County, the Project Manager, or any of their respective officers,
agents or employees, initiated by any employee of the Contractor, any Subcontractor, anyone
directly or indirectly employed by any of them or anyone for whose acts any of them may be
liable, the indemnification obligation set forth in the immediately preceding paragraph shall not
be limited in any way by any limitation on the amount or type of damages, compensation or
benefits payable by or for the Contractor or any Subcontractor under workmen's compensation
acts, disability benefit acts or other employee benefit acts.
ARTICLE XI. INSURANCE: Without limiting the Owner's right to obtain indemnification from
Contractor or any third parties, Contractor, at its sole expense, in accordance with the provisions
of Section 2.40 of the General Conditions, shall maintain in full force and effect the following
insurance policies throughout the term of this Agreement, excepting only those policies for which
a longer term is specified:
A. Course of Construction (Builder's All Risk) Insurance, with scope and amount of
coverage as specified in Section 2.40 B.5 of the General Conditions.
B. Commercial General Liability Insurance, with scope and amount of coverage as
specified in Section 2.40 B.1 of the General Conditions.
C. Automobile Liability Insurance, with scope and amount of coverage as specified in Section
2.40 B.2 of the General Conditions.
D. Professional Liability Insurance, with scope and amount of coverage as specified in Section
2.40 B.4 of the General Conditions.
E. Worker's Compensation Insurance, with scope and amount of coverage as specified in
Section 2.40 B.3 of the General Conditions.
The Certificate of Insurance shall be issued in triplicate, to the County of Fresno, and all other
participating agencies, whether or not said agencies are named herein, who contribute to the
cost of the work or have jurisdiction over areas in which the work is to be performed and all
officers and employees of said agencies while acting within the course and scope of their duties
and responsibilities.
ARTICLE XII. MISCELLANEOUS PROVISIONS:
1. AUDITS AND INSPECTIONS: The Contractor shall at any time during business hours, and
as often as the Owner may deem necessary, make available to the Owner for examination all of
its records and data with respect to the matters covered by this Agreement. The Contractor shall,
upon request by the Owner, permit the Owner to audit and inspect all of such records and data
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 - 5
necessary to ensure Contractor's compliance with the terms of this Agreement. If this Agreement
exceeds ten thousand dollars ($10,000.00), Contractor shall be subject to the examination and
audit of the Auditor General for a period of three (3) years after final payment under contract
(Government Code Section 8546.7).
2. INDEPENDENT CONTRACTOR: In performance of the work, duties, and obligations
assumed by Contractor under this Agreement, it is mutually understood and agreed that
Contractor, including any and all of Contractor officers, agents, and employees will at all times
be acting and performing as an independent contractor, and shall act in an independent capacity
and not as an officer, agent, servant, employee,joint venture, partner, or associate of the Owner.
Contractor and Owner shall comply with all applicable provisions of law and the rules and
regulations, if any, of governmental authorities having jurisdiction over matters of the subject
thereof. Because of its status as an independent contractor, Contractor shall have absolutely no
right to employment rights and benefits available to Owner's employees. Contractor shall be
solely liable and responsible for providing to, or on behalf of, its employees all legally-required
employee benefits. In addition, Contractor shall be solely responsible and save Owner harmless
from all matters related to payment of Contractor's employees, including compliance with social
security, withholding, and all other regulations governing such matters. It is acknowledged that
during the term of this Agreement, Contractor may be providing services to others unrelated to
the Owner or to this Agreement.
3. DISCLOSURE OF SELF-DEALING TRANSACTIONS: This provision is only applicable if
the Contractor is operating as a corporation (a for-profit or non-profit corporation) or if during the
term of the agreement, the Contractor changes its status to operate as a corporation. Members
of the Contractor's Board of Directors shall disclose any self-dealing transactions that they are
a party to while Contractor is providing goods or performing services under this agreement. A
self-dealing transaction shall mean a transaction to which the Contractor is a party and in which
one or more of its directors has a material financial interest. Members of the Board of Directors
shall disclose any self-dealing transactions that they are a party to by completing and signing a
Self-Dealing Transaction Disclosure Form, attached hereto as Exhibit A and incorporated herein
by reference, and submitting it to the Owner prior to commencing with the self-dealing
transaction or immediately thereafter.
4. EXECUTIVE ORDER N-6-22: Under Executive Order N-6-22 as a contractor, subcontractor,
or grantee, compliance with the economic sanctions imposed in response to Russia's actions in
Ukraine is required, including with respect to, but not limited to, the federal executive orders
identified in the EO and the sanctions identified on the U.S. Department of the Treasury website
(https://ofac.treasury.gov/sanctions-programs-and-cou ntry-information/ukraine-russia-related-
sanctions). Failure to comply may result in the termination of contracts or grants, as applicable.
Specially Designated Nationals and Blocked Persons List (SDN)
(https://ofac.treasurV.gov/specially-designated-nationals-and-blocked-persons-list-sdn-human-
readable-lists).
ARTICLE XIII. The Contractor represents that he has secured the payment of Workers
Compensation in compliance with the provisions of the Labor Code of the State of California and
Paragraphs B.3, C.3 and EA of Article 2.40 of the General Conditions, and that he will continue
so to comply with such statutory and contractual provisions for the duration and entirety of the
performance of the work contemplated herein.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMffNT SHELTER AGREEMENT
REEDLEY, CA. SECTION 005213 - 6
This Contract, 24-S-04,was awarded by th Board of Supervisors on September 241", 2024.
It has been reviewed by the Department o Public Works and Planning and is in proper
order for signature of the Chairman of the oard of Supervisors.
IN WITNESS WHEREOF, they have exec ted this Agreement this �� day of
J-4--C-ender 2024
Katch General COUNTY_ _OF FRESNO
(CONTRACTOR) �~ (OWNER)
46-2662960
(TaxJpayer. ederal I.D. No.) --
B /
t Nathan Magsig, Chairman
Name: Paul Katchado_urian ~� of the Board of Supervisors of the
T _ County of Fresno
Title: President
ATTEST:
Bernice E. Seidel
Clerk of the Board of Supervisors
County of Fresno, State of
California
_ter: n�
Deputy
FOR ACCOUNTING USE ONLY
VARIOUS ORGS.
8905 / 7295
END OF SECTION
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND SELF-DEALING TRANSACTION
EQUIPMENT SHELTER DISCLOSURE FORM
REEDLEY, CA. EXHIBIT A - 1
SELF-DEALING TRANSACTION DISCLOSURE FORM
In order to conduct business with the County of Fresno (hereinafter referred to as
"County"), members of a corporation's board of directors of the Consultant, must
disclose any self-dealing transactions that they are a party to while providing goods,
performing services, or both for the County. A self-dealing transaction is defined
below:
"A self-dealing transaction means a transaction to which the corporation is a party and
in which one or more of its directors has a material financial interest"
The definition above will be utilized for purposes of completing this disclosure form.
INSTRUCTIONS
(1) Enter board member's name, job title (if applicable), and date this disclosure is
being made.
(2) Enter the board member's company/agency name and address.
(3) Describe in detail the nature of the self-dealing transaction that is being
disclosed to the County. At a minimum, include a description of the following:
a. The name of the agency/company with which the corporation has the
transaction; and
b. The nature of the material financial interest in the Corporation's
transaction that the board member has.
(4) Describe in detail why the self-dealing transaction is appropriate based on
applicable provisions of the Corporations Code.
(5) Form must be signed by the board member that is involved in the self-dealing
transaction described in Sections (3) and (4).
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND SELF-DEALING TRANSACTION
EQUIPMENT SHELTER DISCLOSURE FORM
REEDLEY, CA. EXHIBIT A - 2
(1) Company Board Member Information:
Name: Date:
Job
Title:
(2) Company/Agency Name and Address:
(3) Disclosure (Please describe the nature of the self-dealing transaction you are a party
to):
(4) Explain why this self-dealing transaction is consistent with the requirements of
Corporations Code 5233 (a):
5 Authorized Signature
Signature: Date:
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 1
GENERAL CONDITIONS
2.01 IDENTIFICATION OF CONTRACT
A. The Agreement shall be signed by the Contractor and the Owner.
B. The Contract Documents are defined in ARTICLE II of the Agreement.
C. The Contract Documents form the Contract for Construction ("Contract"). This
Contract represents the entire and integrated agreement between the parties
hereto and supersedes all prior negotiations, representations or agreements,
either written or oral. The Contract may be amended or modified only by a
Modification as defined above. The Contract Documents shall not be construed
to create any contractual relationship of any kind between the Engineer of
record of record and the Contractor, but the Engineer of record of record shall
be entitled to performance of the obligations of the Contractor intended for their
benefit and to enforcement thereof. Nothing contained in the Contract
Documents shall create any contractual relationship between the Owner and
any Subcontractor or Sub-subcontractor.
2.02 EXECUTION, CORRELATION, AND INTENT OF CONTRACT DOCUMENTS
A. The Contract Documents are complementary and anything called for by one
shall be supplied as if called for by all, providing it comes clearly within the
scope of the Contract.
B. The intent of the Contract Documents is to include all items necessary for the
proper execution and completion of the Work. Words and abbreviations that
have well-known technical or trade meanings are used in the Contract
Documents in accordance with such recognized meanings.
C. Execution of the Contract by the Contractor is a representation that the
Contractor has visited the site, become familiar with the local conditions under
which the Work is to be performed, and has correlated personal observations
with the requirements of the Contract Documents.
D. All work and material shall be the best of the respective kinds specified or
indicated. Should any workmanship or materials be required that are not
directly or indirectly called for in the Contract Documents, but which
nevertheless are necessary for proper fulfillment of the obvious intent thereof,
said workmanship or materials shall be the same for similar parts that are
detailed, indicated or specified, and the Contractor shall understand the same
to be implied and provide for it in his/her tender as if it were particularly
described or delineated.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 2
2.03 OWNERSHIP AND USE OF DOCUMENTS
All Contract Documents and copies thereof furnished shall remain the property of the
Owner. With the exception of one (1) contract set for each party to the Contract, such
documents are to be returned by Contractor or suitably accounted for to the Owner
upon request at the completion of the Work. Submission or distribution to meet official
regulatory requirements or for other purposes in connection with the Project is not to
be construed as publication in derogation of the Engineer of record's common law
copyright or other reserved rights. The Owner's use of the documents will not increase
the Engineer of record's design liability beyond the Project and the site for which the
design was originally intended.
2.04 DEFINITIONS
The following words, or variations thereof, as used in these documents have meanings
as defined:
A. The Work - The Work comprises the completed construction required of the
Contractor by the Contract Documents, and includes all labor, materials,
equipment and services necessary to produce such construction, and all
materials, other permits and equipment incorporated or to be incorporated in
such construction.
B. The Project—The collective improvements to be constructed by the Contractor
pursuant to the construction of the Sheriff Substation, Vehicle/Evidence
Storage building, parking, and associated site improvements for Fresno
County.
C. Owner - The County of Fresno, State of California, as represented by the
Fresno County Board of Supervisors and so named in the Agreement. The
term Owner additionally includes the Owner's authorized representative (also
known as the Resident Engineer) for this Project.
D. Engineer of record — The Owner and his/her authorized representative, as
defined in Section 2.04C, or a duly California licensed Engineer.
E. Contractor- When used in the General Conditions refers to person(s) or entity
(partnership or corporation) so named in Agreement and when used in the
body of the Specifications, refers to the Contractor for that specific work,
whether it be the General Contractor, Subcontractor, or other Contractor. The
term Contractor means the Contractor or the Contractor's authorized
representative.
F. Subcontractor - Person, persons, entity, co-partnership or corporation having
direct contract with Contractor to perform any of the Work at the site. The term
Subcontractor means a Subcontractor or a Subcontractor's authorized
representative. The term Subcontractor does not include any separate
contractor or any separate contractor's subcontractors.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 3
G. Sub-subcontractor — Person, persons, entity, co-partnership or corporation
having a direct or indirect contract with a Subcontractor to perform any of the
Work at the site (i.e. a second-tier, third-tier or lower-tier Subcontractor). The
term Sub-subcontractor means a Sub-subcontractor or an authorized
representative thereof.
H. Notice to Proceed - A written notice issued by the Owner directing the
Contractor to proceed with construction activities to complete the Project.
I. Technical Specifications — Contains the written requirements for materials,
equipment, systems, standards and workmanship for the Work, and
performance of related services.
J. Days- All days shall be measured in calendar days unless specifically noted
otherwise in these documents or referenced codes.
K. Year- One year shall be measured in terms of 365 calendar days.
2.05 SPECIFICATIONS AND DRAWINGS
A. Precedence —Anything mentioned in the Specifications and not shown on the
Drawings, or shown on the drawings and not mentioned in the specifications,
shall be of like effect as if shown or mentioned in both. Subject to Section 2.02,
in cases of discrepancy concerning dimension, quantity and location, the
Drawings shall take precedence over the Specifications. Explanatory notes on
the Drawings shall take precedence over conflicting drawn indications. Large
scale details shall take precedence over smaller scale details and figured
dimensions shall take precedence over scaled measurement. Where figures
are not shown, scale measurements shall be followed but shall in all cases be
verified by measuring actual conditions of Work already in place. In cases of
discrepancy concerning quality and application of materials and non-technical
requirements over materials, the specifications shall take precedence over
Drawings.
B. Division of Specifications — For convenience of reference and to facilitate the
letting of independent contracts, this specification may be separated into
certain sections; such separation shall not operate to oblige the Owner,
Engineer of record or Professional Consultant to establish the limits of any
contract between the Contractor and Sub-Contractor each of whom shall
depend upon his/her own contract stipulations. The General Conditions apply
with equal force to all work, including extra work.
C. Governing Factors—Dimensions figured on drawings shall be followed in every
case in preference to scale of drawings.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 4
D. Discrepancies — Should the Contractor, at any time, discover a discrepancy in
a drawing or specification, or any variation between dimensions on drawings
and measurements at site, or any lacking of dimensions or other information,
he/she shall report at once to the Resident Engineer requesting clarification
and shall not proceed with the work affected thereby until such clarification has
been made. If the Contractor proceeds with work affected by such
discrepancies, without having received such clarification, he/she does so at
his/her own risk. Any adjustments involving such circumstances made by the
Contractor, prior to approval by the Resident Engineer, shall be at the
Contractor's risk and the settlement of any complications or disputes arising
therefrom shall be at the Contractor's sole expense and Contractor shall
indemnify, hold harmless and defend Owner, Owner's representatives, and
Resident Engineer from any liability or loss with respect to said adjustments.
E. Scope of Drawings — The drawings shall be held to determine the general
character of the Work as well as its details. Parts not detailed shall be
constructed in accordance with best standard practice for work of this class, so
as to afford the requisite strength and logically complete the parts they
compose. Where it is obvious that a drawing illustrates only a part of a given
work or of a number of items, the remainder shall be deemed repetitious and
so construed. The Contractor shall be responsible for all errors made in using
any drawings which have been superseded.
F. Shop Drawings, Product Data and Samples —
1. Shop Drawings are drawings, diagrams, schedules and other data
specially prepared for the Work by the Contractor or any Subcontractor,
manufacturer, supplier or distributor to illustrate some portion of the
Work. Product Data are illustrations, standard schedules, performance
charts, instructions, brochures, diagrams and other information
furnished by the Contractor to illustrate a material, product or system
for some portion of the Work. Samples are physical examples that
illustrate materials, equipment or workmanship, and establish
standards by which the work will be judged.
2. The Contractor shall prepare, review, approve and submit to the
Resident Engineer, with reasonable promptness and in such sequence
as to cause no delay in the Work or in the work of the Owner or any
separate contractor, all Shop Drawings, Product Data and Samples
required by the Contract Documents.
3. By preparing, approving and submitting Shop Drawings, Product Data
and Samples, the Contractor represents that the Contractor has
determined and verified all materials, field measurements and field
construction criteria related thereto, or will do so with reasonable
promptness, and has checked and coordinated the information
contained within such submittals with the requirements of the Work, the
Project, the Work Order and the Contract Documents.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 5
4. The Contractor shall not be relieved of responsibility for any deviation
from the requirements of the Contract Documents by the Engineer of
record's review of Shop Drawings, Product Data or Samples, unless
the Contractor has specifically informed the Resident Engineer in
writing of such deviation at the time of submission and the Engineer of
record has reviewed the specific deviation. The Contractor shall not be
relieved from responsibility for errors or omissions in the Shop
Drawings, Product Data or Samples by the Engineer of record's review
of them.
5. When professional certification of performance criteria of materials,
systems or equipment is required by the Contract Documents, the
Engineer of record shall be entitled to rely upon the accuracy and
completeness of such calculations and certifications. The cost of such
certifications shall be borne by the Contractor. Owner may elect to
have an independent certification performed at its own expense. The
Owner shall have final approving authority for performance-based
items.
6. The Contractor shall direct specific attention, in writing or on
resubmitted Shop drawings, Product Data, or Samples, to revisions
other than those requested by the Engineer of record on previous
submittals.
7. No portion of the Work requiring submission of a Shop Drawing,
Product Data or Sample shall be commenced until the submittal has
been reviewed by the Engineer of record. All such portions of the Work
shall be in accordance with reviewed submittals.
8. Submission of Shop Drawings and Samples to the Resident Engineer
is required for only those items specifically mentioned in the
Specification Sections. If Contractor submits Shop Drawings for items
other than the above, the Resident Engineer will not be obligated to
distribute or review them. Contractor shall be responsible for the
procuring of Shop Drawings for his/her own use as he/she may require
for the progress of the Work.
9. The term "Shop Drawings" as used herein also includes but is not
limited to fabrication, erection, layout and setting drawings,
manufacturer's standard drawings, descriptive literature, catalogs,
brochures, performance and test data, wiring and control diagrams, all
other drawings and descriptive data pertaining to materials, equipment,
piping, duct and conduit systems, and methods of construction as may
be required to show that the materials, equipment or systems and the
positions and layout of each conform to the Contract requirements. As
used herein the term "manufactured" applies to standard units usually
mass-produced, and the term "fabricated" means items specifically
assembled or made out of selected materials to meet individual design
requirements. Shop Drawings shall establish the actual detail of all
manufactured or fabricated items; indicate proper relation to adjoining
work; amplify design details of mechanical and electrical equipment in
proper relation to physical spaces in the structure; and incorporate
minor changes of design or construction to suit actual conditions.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 6
10. Drawings: Following Contractor's review and approval, Contractor shall
submit to the Resident Engineer for approval four (4) minimum to six
(6) maximum prints and/or pdf submission of the same information via
email. (Required delivery methods and quantities of submittals will be
determined at the time of the Pre-Construction Meeting.) The Resident
Engineer will check the submittal to see if it is complete. If complete,
the Resident Engineer will forward the drawings to the Owner and the
Engineer of record. The Engineer of record and Owner will check the
drawings and note Engineer of record and Owner comments and affix
a stamp to the drawing s indicating the status of acceptance, and will
return same to the Resident Engineer, each retaining prints for his/her
records. The Engineer of record or his/her consultants, as applicable,
will review the Shop Drawings; mark the prints with required revisions;
stamp the prints and indicate "No Exceptions Taken", "Make
Corrections Noted", "Revise and Resubmit", "Submit Specified Item", or
"Rejected", and return the prints. The Resident Engineer will return the
prints to the Contractor. The Contractor shall then print and distribute
the appropriate number of copies to his/her job personnel as required.
If a drawing is stamped "Rejected" or "Revise and Resubmit", the
Contractor shall correct and resubmit as outlined above. When
stamped "Make Corrections Noted", or similar instructions, the
Contractor shall correct and resubmit for record only, three (3) prints of
each drawing. Also see Technical Specifications, Division I, General
Requirements.
11. Samples: Following Contractor's review and approval, Contractor shall
submit to the Engineer of record, five (5) minimum samples of all
materials in quantities and sizes as specified herein as requested by
the Engineer of record. Submittals shall be given to the Engineer of
record at a time determined by the Contractor, which allows for any
necessary resubmittal and which will not cause any delay in the Work.
Samples will be forwarded to the Engineer of record. If a sample is
stamped "Rejected" or "Revise and Resubmit", one sample so noted
will be returned to the Contractor. The Contractor shall correct and
resubmit as outlined above. If a sample is stamped "Make Corrections
Noted", one sample so noted will be returned. Corrected samples shall
be resubmitted for approval as per the original submittal. Also see
Technical Specifications and General Requirements.
12. Brochures: Following Contractor's review and approval, Contractor
shall submit to the Engineer of record, five (5) copies of all
manufacturer's catalogs or brochures as required. Brochures will be
forwarded to the Engineer of record for review. If a brochure is stamped
"No Exception Taken", two (2)copies will be returned to the Contractor.
If stamped "Rejected", one marked copy and two (2) unmarked copies
will be returned. Corrected copies shall be resubmitted for approval as
per the original submittal. Also see General Requirements.
13. Manufacturer's Instructions: Where any item or work is required by
Specifications to be furnished, installed or performed in accordance
with a specified product manufacturer's instructions, Contractor shall
procure and distribute the necessary copies of such instructions to all
concerned parties.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 7
G. Materials - All materials, unless otherwise specified, shall be new and of good
quality, proof of which shall be furnished by the Contractor; in case of doubt as
to kind or quality required, samples shall be submitted to the Engineer of record
through the Resident Engineer who will specify the kind and use of the material
appropriate to the location and the function of the item in question. Contractor
shall furnish such item accordingly. Before final payment, all material rejected
by the Engineer of record or Resident Engineer shall be promptly removed
from the premises by the Contractor, whether or not completely installed, and
promptly and properly replaced with correct materials, including any other work
adjoining if disturbed, in accordance with the contract and without expense to
the Owner; the Contractor also shall pay for work of other Contractors as is
affected by such removals and replacements.
2.06 THE ARCHITECT
A. The Owner may delegate all or a portion of its rights and responsibilities to a
California licensed Engineer of record as deemed necessary.
B. The Engineer of record advises the Resident Engineer in all aspects of the
construction phase of the Project. The Engineer of record's functions include
advice and assistance to the Resident Engineer in the correct interpretation
and application of the Contract Documents. The Engineer of record is not
authorized independently to issue Addenda, Clarifications, Field Orders, Work
Authorizations, or Supplemental Work Orders, or in any other way to bind the
Owner in discussions with the Contractor.
C. The Contractor shall deliver all correspondence relating to the proper
execution of the Work to the Resident Engineer. The Resident Engineer
reserves the right to consult with the Engineer of record and Owner prior to
responding to the Contractor's correspondence.
D. When discussions between the Contractor and the Resident Engineer occur
either on the site or elsewhere, but the Engineer of record is not present, the
Resident Engineer reserves the right to consult with the Engineer of record
and Owner prior to issuing his/her final decision or instruction.
E. The Engineer of record shall review or take other appropriate action upon the
Contractor's submittals such as Shop Drawings, Product Data and Samples,
but only for conformance with the design concept of the Work and the
information given in the Contract Documents. Such action shall generally be
taken within ten (10)working days, however under certain circumstances such
as very complex submittals or if large number of submittals are submitted at
one (1)time it may take longer. In this case the Contractor will be notified and
given the opportunity to advise the Engineer of record of priorities. The
Engineer of record's review of a specific item shall not indicate review of an
assembly of which the item is a component.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 8
2.07 THE PROJECT MANAGER
A. The Resident Engineer is the authorized representative of the Owner in all
aspects of administering the construction contract on behalf of the Owner. All
communications from and to the Contractor will be channeled through the
Resident Engineer. However, the Resident Engineer does not have the
authority to bind the Owner in matters affecting adjustments to the time or cost
of the Project as defined in the Agreement for Construction.
B. The Resident Engineer will be the Owner's representative during the
construction and warranty periods, and until final payment to all contractors is
due. The Resident Engineer will advise and consult with the Owner. All
instructions to the Contractor shall be forwarded through the Resident
Engineer. The Resident Engineer will have authority to act on behalf of the
Owner only to the extent provided in the Contract Documents, unless otherwise
modified by written instrument.
C. The Resident Engineer will be on site during construction to monitor the
progress and quality of the Work and to determine in general if the Work is
proceeding in accordance with the Contract Documents. On the basis of on-
site observations and communication with the Contractor, the Resident
Engineer will keep the Owner informed of the progress of the Work, and will
endeavor to guard the Owner against defects and deficiencies in the Work of
the Contractor.
D. The Resident Engineer shall at all times have access to the Work wherever it
is in preparation and progress. The Contractor shall provide facilities for such
access so that the Resident Engineer may perform its functions under the
Contract Documents.
E. Based on the Resident Engineer's observations, and an evaluation of the
Contractor's Application for Payment, the Resident Engineer will determine the
amount owing to the Contractor and will issue to the Owner Certificates for
Payment incorporating such amount.
F. The Resident Engineer will be the initial interpreter of the requirements of the
Contract Documents and the initial judge of the performance hereunder by the
Contractor. The Owner will have final authority of all such matters.
G. The Resident Engineer will render interpretations necessary for the proper
execution or progress of the Work, with reasonable promptness and in
accordance with agreed upon time limits. Either party to the Contract may
make written request to the Resident Engineer for such interpretations.
H. Claims, disputes and other matters in question between the Contractor and the
Resident Engineer relating to the execution or progress of the Work or the
interpretation of the Contract Documents shall be referred to the Owner (or
his/her designee).
I. All interpretations and decisions of the Resident Engineer will be in writing or
in graphic form, and shall be both consistent with the intent of the Contract
Documents and reasonably inferable therefrom.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 9
J. The Resident Engineer will have the authority to reject, or recommend to the
Owner the rejection, of any work that does not conform to the Contract
Documents. Whenever, in the Resident Engineer's opinion, it is considered
necessary or advisable for the implementation of the intent of the Contract
Documents, the Resident Engineer will have authority to require special
inspection or testing of the Work whether or not such work be then fabricated,
installed or completed.
K. The Resident Engineer will receive from the Contractor and review all Shop
Drawings, Product Data and Samples, and forward same to Engineer of record
and Owner for review.
L. Following consultation with the Owner, the Resident Engineer will take
appropriate action on changes, and will have authority to order minor changes
in the Work as provided herein.
M. The Resident Engineer will conduct inspections to determine the date of
Completion, and will receive and forward to the Owner for the Owner's review
written warranties and related documents required by the Contract Documents
and assembled by the Contractor. The Resident Engineer will issue a final
Project Certificate for Payment upon compliance with the requirements for
completion and final payment. The Resident Engineer will monitor the warranty
for a period of365 Calendar Days from and after the date of acceptance of the
Work, unless otherwise specified as a longer term.
N. The duties, responsibilities and limitations of authority of the Resident Engineer
as the Owner's representative during construction, as set forth in the Contract
Documents, will not be modified or extended without written consent of the
Owner, the Contractor and the Resident Engineer, which consent shall not be
unreasonably withheld. Failure of the Contractor to respond within ten (10)
business days to a written request shall constitute consent by the Contractor.
O. In case of the termination of the employment of the Resident Engineer, the
Owner may appoint a successor Resident Engineer, whose status and duties
under the Contract Documents shall be the same as those of the former
Resident Engineer.
2.08 OWNER
A. Information and Services Required of the Owner
1. Unless otherwise provided in the Contract Documents, the Owner shall
secure and pay for necessary approvals, easements, assessments and
charges required for the construction, use or occupancy of permanent
structures or for permanent changes in existing facilities.
2. Information or services under the Owner's control shall be furnished by
the Owner with reasonable promptness to avoid delay in the orderly
progress of the Work.
3. The Owner shall forward all instructions to the Contractor through the
Resident Engineer.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 10
B. Owner's Right to Stop the Work
If the Contractor fails to correct defective work as required by Section 2.42
herein or persistently fails to carry out the Work in accordance with the Contract
Documents, the Owner, by a written order signed personally or by an agent
specifically so empowered by the Owner in writing, may order the Contractor
to stop the Work, or any portion thereof, until the cause for such order has been
eliminated; however, this right of the Owner to stop the Work shall not give rise
to any duty on the part of the Owner to exercise this right for the benefit of any
contractor or any other person or entity, except to the extent required by
Section 2.12.C.
C. Owner's Right to Carry Out the Work
If the Contractor defaults or neglects to carry out the Work in accordance with
the Contract Documents, and fails after written notice from the Owner to correct
such default or neglect with diligence and promptness, the Owner may, after
an additional written notice and without prejudice to any other remedy the
Owner may have, make good such deficiencies. In such case an appropriate
Contract Change Order shall be issued deducting from the payments then or
thereafter due the Contractor the cost of correcting such deficiencies, including
compensation for the additional services of the Engineer of record or other
professionals made necessary by such default, neglect or failure. Such action
by the Owner and the amount charged to the Contractor are both subject to
the prior approval of the Engineer of record. If the payments then or thereafter
due the Contractor are not sufficient to cover such amount, the Contractor shall
pay the difference to the Owner, or Owner may require payment by the surety
on the performance or warranty bonds as appropriate. Such action shall, in no
way, affect the status of either party under contract, nor be held as a basis of
any claim by the Contractor for damages or extension of time.
2.09 CONTRACTOR RESPONSIBILITIES
A. Review of Contract Documents and Field Conditions
1. The Contractor shall carefully study and compare the Contract
Documents and shall at once report to the Resident Engineer any
discrepancy or inconsistency that may be discovered. The Contractor
shall not be liable to the Owner or the Resident Engineer for any
damage resulting from any such inconsistencies or discrepancies in the
Contract Documents unless the Contractor recognized such
inconsistencies or discrepancies and knowingly failed to report it to the
Resident Engineer. The Contractor shall perform no portion of the
Work at any time unless authorized by the Contract Documents or,
where required, approved Shop Drawings, Product Data or Samples
for such portion of the Work.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 11
2. Neither the Owner nor the Resident Engineer or Engineer of record
assume any responsibility for an understanding or representation made
by any of their agents or representation prior to the execution of the
Agreement unless (1) such understanding or representations are
expressly stated in the Agreement, and (2) the Agreement expressly
provides that responsibility therefor is assumed by the Owner.
3. Failure by the Contractor to acquaint himself/herself with all available
information will not relieve him/her from responsibility for estimating
properly the difficulty or cost of successfully performing the Work.
4. The Contractor shall take field measurements and verify field conditions
and shall carefully compare such field measurements and conditions
and other information known to the Contractor with the Contract
Documents before commencing activities. Any inconsistencies or
discrepancies discovered by the Contractor shall be reported to the
Resident Engineer at once.
5. Before submitting any Request for Information (RFI), or other
contractor-initiated request for information, the Contractor shall
determine that the information requested is not clearly provided in the
Contract Documents. RFI's shall be submitted to the Resident
Engineer only from the Contractor, or Owner, and not from any
subcontractor, supplier or other vendor, and shall be on a form
approved by the Resident Engineer. The Contractor shall provide a
revised and updated RFI Priority Schedule on a weekly basis. The RFI
Priority Schedule shall rank RFI's in order of priority and include a brief
statement of reason for priority. Owner initiated RFI's will not be listed
on the Contractor's RFI Priority Schedule. The Owner will provide the
Engineer of record a separate list of Owner initiated RFI's upon request
of the Engineer of record. The Engineer of record will endeavor to
respect the order of priorities as requested by the Contractor or Owner
for the overall benefit of the Project. The RFI process is for information
and clarification only and may not be utilized to obtain approval for
changes in Work Order Price or time. Also see Division 01 - General
Requirements.
B. Supervision Procedures
1. The Contractor shall efficiently supervise and direct the Work, using
therein the Contractor's best skill and diligence for which he/she is
remunerated in the Contract Price. The Contractor shall carefully
inspect the site and study and compare the Contract Documents, as
ignorance of any phase of any of the features or conditions affecting
the Contract will not excuse him/her from carrying out its provisions to
its full intent.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 12
2. The Contractor shall employ a competent superintendent and
necessary assistants who shall be in attendance at the Project site
during the progress of the Work. The superintendent shall represent
the Contractor and all communications given to the superintendent
shall be as binding as if given to the Contractor. Important
communications shall be confirmed in writing. Other communications
shall be so confirmed upon written request in each case. The
Superintendent who begins the Project shall remain on the Project until
the Project is completed, as long as the Contractor employs that
person. The Superintendent shall not be replaced without the approval
of the Owner.
3. The Contractor shall be responsible to the Owner for the acts and
omissions of his/her employees, subcontractors and their agents and
employees, and other persons performing any of the Work under a
contract with the Contractor.
4. The Contractor shall at all times enforce strict discipline and good order
among his/her employees and shall not employ on the Work any unfit
person or anyone not skilled in the task assigned to him/her.
5. The Contractor shall not be relieved from his/her obligations to perform
the Work in accordance with the Contract Documents either by the
activities or duties of the Owner or the Engineer of record in his/her
administration of the Contract, or by inspections, tests or approvals
required or performed by persons other than the Contractor.
6. Contractor shall alert and inform their employees that State law
requires that the identities of inmates/wards/patients/clients be kept
confidential. Revealing the identities of inmates/wards/patients/clients
is punishable by law.
C. Construction Procedures
1. Means and Methods — The Contractor shall be solely responsible for
and control of construction means, methods, techniques, sequences,
coordination and procedures for all the Work of this contract.
Additionally, the Contractor shall be responsible for safety precautions
and programs in connection with the Work.
2. Laws of County and State —The Contractor must comply with all laws,
rules, regulations, provisions and ordinances of the County in which the
Work is being done, and all State laws pertaining to the Work.
3. Safeguards — The Contractor shall provide, in conformity with all local
codes and ordinances and as may be required, such temporary walls,
fences, guard-rails, barricades, lights, danger signs, enclosures, etc.,
and shall maintain such safeguards until all work is completed.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 13
4. Housekeeping — Contractor shall keep the premises free of excess
accumulated debris. Clean up as required and as directed by the
Resident Engineer. At completion of work all debris shall be removed
from the site. Refer to General Requirements for additional
requirements.
5. Labor and Materials — Unless otherwise provided in the Contract
Documents, the Contractor shall provide and pay for all labor,
materials, equipment, tools, construction equipment and machinery,
water, heat, utilities, transportation, and other facilities and services
necessary for the proper execution and completion of the Work,
whether temporary or permanent and whether or not incorporated or to
be incorporated in the Work.
6. The Contractor shall deliver to the Resident Engineer, prior to final
acceptance of the Work as a whole, signed certificates from suppliers
of materials and manufactured items stating that such items conform to
the Contract Documents.
7. The Contractor, immediately upon receipt of the Notice to Proceed (or
where shop drawings, samples, etc., are required, immediately upon
receipt of review thereof), shall place orders for all materials, work
fabrication, and/or equipment to be employed by him/her in connection
with that portion of the contracted Work. The Contractor shall keep all
materials, work fabrications and/or equipment specified and shall
advise the Resident Engineer promptly, in writing, of all orders placed
and of such materials, work fabrications and/or equipment which may
not be available in a timely manner for the purposes of the Contract.
8. Any worker whose work is unsatisfactory to the Owner or the Engineer
of record, or are considered by the Owner or Engineer of record to be
careless, incompetent, unskilled or otherwise unfit shall be dismissed
from work under the Contract upon written request to the Contractor
from the Owner or the Engineer of record.
9. Temporary Facilities — Contractor may connect to existing water and
electricity available on the site provided it is suitable to the Contractor's
requirements. Water and electricity used will be paid by the Owner.
Contractor shall bear all expenses for carrying the water or electricity
to the appropriate locations and to connect or tap into existing lines.
Toilet facilities may be available on a site to the workmen engaged in
the performance of this contract. It shall be the responsibility of the
Contractor to confirm with the Owner the availability of toilet facilities on
the site. The use of such facilities may be revoked in the event of
excess janitorial requirements.
10. Contractor shall not perform any fire hazardous operation adjacent to
combustible materials. Any fire hazardous operation shall have proper
fire extinguisher close by and the adjacent area shall be policed before
stopping work for the day. Contractor shall provide not less than one
OSHA/NFPA Class 6-ABC fire extinguisher for each 9,000 square feet
of Project area or fraction thereof.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 14
11. Contractor shall erect temporary dust separation partitions and floor
mats as necessary to confine dust and debris within area of work.
Contractor shall post signs, erect and maintain barriers and warning
devices for the protection of the general public and Owner personnel.
12. Trenching and Excavation — In accordance with Section 7104 of the
California Public Contract Code, the following provisions shall apply to
any contract involving digging of trenches or other excavations that
extend deeper than four feet below the surface:
a. The Contractor shall promptly, and before the following
conditions are disturbed, notify the Owner, in writing, of any:
i. Material that the contractor believes may be material
that is hazardous waste, as defined in Section 25117 of
the Health and Safety Code that is required to be
removed to a Class I, Class II, or Class III disposal site
in accordance with provisions of existing law.
ii. Subsurface or latent physical conditions at the Project
site differing from those indicated by information about
the site made available to bidders prior to the deadline
for submitting bids.
iii. Unknown physical conditions at the site of any unusual
nature, different materially from those ordinarily
encountered and generally recognized as inherent in
work of the character provided for in the contract.
b. The Owner shall promptly investigate the conditions, and if it
finds that the conditions do materially so differ, or do involve
hazardous waste, and cause a decrease or increase in the
contractor's cost of, or the time required for, performance of any
part of the work, shall issue a Contract Change Order in
accordance with the provisions of Section 2.09 of the General
Conditions.
C. In the event that a dispute arises between the Owner and the
contractor whether the conditions materially differ, or involve
hazardous waste, or cause a decrease or increase in the
contractor's cost of, or time required for, performance of any
part of the work, the contractor shall not be excused from any
scheduled completion date provided for by the contract, but
shall proceed with all work to be performed under the contract.
The contractor shall retain any and all rights provided either by
contract or by law which pertain to the resolution of disputes and
protests between the contracting parties.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 15
2.10 SUBCONTRACTORS
A. Agreements — Agreements between the Contractor, Subcontractors, and
Subcontractors of lower tier shall be subject to the approval of the Owner, but
in no case does such approval relieve the Contractor of any conditions imposed
by the Contract Documents. The Contractor shall only use those
subcontractors that are required to be listed and included in his/her sealed bid
Subcontractor List, section 004336, unless any proposed substitution is first
approved by the Owner pursuant to statute. The Contractor shall not use any
subcontractor who is ineligible to perform work on a Public Works Project
pursuant to section 1777.1 or 1777.7 of the Labor Code. Notwithstanding any
other provision of the Contract Documents, subcontractors may be added,
deleted or substituted only in accordance with the provisions of Public Contract
Code Section 4100 et seq.
B. Relation with Subcontractor — By an appropriate agreement, written where
legally required for enforceability, the Contractor shall bind every
Subcontractor and require therein that every Subcontractor agrees to be bound
by the terms of the Contract Documents to carry out their provisions insofar as
applicable to their work; and the Contractor further agrees to pay to each
Subcontractor promptly upon issuance of Certificate of Payment, his/her or
their due portion. Said agreement shall preserve and protect the rights of the
Owner and the Engineer of record under the Contract Documents with respect
to the work to be performed by the Subcontractor so that the subcontracting
thereof will not prejudice such rights, and shall allow to the Subcontractor,
unless specifically provided otherwise in the Contractor-Subcontractor
Agreement, the benefit of all rights, remedies and redress against the
Contractor that the Contractor, under the Contract Documents, has against the
Owner. Where appropriate, the Contractor shall require each Subcontractor to
enter into similar agreements with their Sub-subcontractors. The Contractor
shall make available to each proposed Subcontractor, prior to the execution of
the Subcontract, copies of the Contract Documents to which the Subcontractor
will be bound by this Paragraph and identify to the Subcontractor any terms
and conditions of the proposed Subcontract which may be at variance with the
Contract Documents. Each Subcontractor shall similarly make copies of
Contract Documents available to their Sub-subcontractors. Nothing contained
herein shall be deemed to create an agency relationship between the Owner
and any Subcontractor or material supplier.
C. Owner's Relation — Neither the acceptance of the name of Subcontractor nor
the suggestion of such name nor any other act of the Owner or Engineer of
record nor anything contained in any Contract Document is to be construed as
creating any contractual relation between the Owner (or Owner's authorized
representatives) and any Subcontractor of any tier nor as creating any
contractual relation between the Engineer of record and any Subcontractor of
any tier.
D. All Subcontractors employed by the Contractor shall be appropriately licensed
in conformity with the laws of the State of California.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 16
E. Jurisdictional disputes between Subcontractors or between Contractor and
Subcontractor shall not be mediated or decided by the Owner, Engineer of
record or the Resident Engineer. The Contractor shall be responsible for the
resolution of all such disputes based upon his/her contractual relationship with
his/her Subcontractors.
2.11 OWNER'S RIGHT TO PERFORM WORK AND TO AWARD SEPARATE
CONTRACTS
A. The Owner reserves the right to perform work related to the Project with the
Owner's own forces, and to award separate contracts in connection with other
portions of the Project or other work on the site under these or similar
Conditions of the Contract. If the Contractor claims that the Owner's action
results in delay, damage or additional cost attributable thereto, the Contractor
shall make such claim as provided elsewhere in the Contract Documents.
B. When separate contracts are awarded for different portions of the Project or
other work on the site, the term Contractor in the Contract Documents in each
case shall mean the Contractor who executes each separate Owner-
Contractor Agreement.
C. The Owner shall provide for coordination of the activities of the Owner's own
forces and of each separate contractor with the Work of the Contractor, who
shall cooperate with them. The Contractor shall participate with other separate
contractors and the Owner in reviewing their construction schedules when
directed to do so. The Contractor shall make any revisions to the construction
schedule deemed necessary after a joint review and mutual agreement. The
construction schedules shall then constitute the schedules to be used by the
Contractor, separate contractors and the Owner until subsequently revised.
D. Unless otherwise provided in the Contract Documents, when the Owner
performs construction or operations related to the Project with the Owner's own
forces, the Owner shall be deemed to be subject to the same obligations and
to have the same rights which apply to the Contractor under the Conditions of
the Contract.
2.12 MUTUAL RESPONSIBILITY
A. The Contractor shall afford the Owner and separate contractors reasonable
opportunity for introduction and storage of their materials and equipment and
performance of their activities and shall connect and coordinate the
Contractor's construction and operations with theirs as required by the Contract
Documents.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 17
B. When any part of the Contractor's Work depends upon proper execution or
results of the work of the Owner or any separate contractor, the Contractor
shall, prior to proceeding with the Work, promptly report to the Resident
Engineer any apparent discrepancies or defects in such other work that render
it unsuitable for such proper execution and results. Failure of the Contractor so
to report shall constitute an acceptance of the Owner's or separate contractor's
work as fit and proper to receive the Work, except as to defects which may
subsequently become apparent in such work by others.
C. If, following the reporting of any discrepancy or defect as required herein
above, the Contractor suffers damage due to disruption or delay caused by the
separate contractor, without fault by the Owner, the Contractor's remedy shall
be limited to seeking recovery from the separate contractor.
D. Any costs caused by defective or ill-timed work shall be borne by the Contractor
responsible therefor.
E. Should the Contractor cause damage to the work or property of the Owner, or
to other work or property on the site,the Contractor shall promptly remedy such
damage as provided herein.
F. Should the Contractor wrongfully delay or cause damage to the work or
property of any separate contractor, the Contractor shall, upon due notice,
promptly attempt to settle with such other contractor by agreement, or
otherwise to resolve the dispute. If such separate contractor sues the Owner
on account of any delay or damage alleged to have been caused by the
Contractor, the Owner shall notify the Contractor who shall defend such
proceedings, and if any judgment or award against the Owner (or Owner's
authorized representatives) arises therefrom, the Contractor shall pay or
satisfy such judgment or award in full and shall reimburse the Owner for all
costs which the Owner has incurred in connection with such matter.
2.13 OWNER'S RIGHT TO CLEAN UP
If a dispute arises between the Contractor and separate contractors as to their
responsibility for cleaning up as required in the Contract Documents, the Owner may
clean up and the contractor responsible shall pay Owner such portions of the cost as
the Resident Engineer shall determine to be just.
2.14 GOVERNING LAW
The Contract shall be governed by the law of the State of California.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 18
2.15 INSPECTION
A. All material and workmanship (if not otherwise designated by the Contract
Documents) shall be subject to inspection, examination, and test by the Owner
and Resident Engineer at any and all times during manufacture and/or
construction and at any and all places where such manufacture and/or
construction are carried on. The Owner and Resident Engineer shall have the
right to reject defective material and workmanship or require its correction.
B. The Contractor shall furnish promptly without additional charge, all reasonable
facilities, labor, and materials necessary for the safe and convenient inspection
and tests that may be required by the Owner and Resident Engineer.
C. Where the Contract Documents, instructions by the Owner, laws, ordinances,
or any public authority having jurisdiction requires work to be inspected, tested
or approved before work proceeds, such work shall not proceed, nor shall it be
concealed prior to inspection.
D. The Contractor shall give the Resident Engineer at least two (2) business days
advance notice of the readiness for any Contract compliance inspection by the
Inspector. The Contractor shall give notice as required by all other inspecting
and testing agencies of jurisdiction for Code and regular compliance
inspection. In all cases, the Contractor shall schedule inspections so as not to
delay the Work.
E. If the Resident Engineer determines that any work requires additional special
inspection beyond that identified in the specifications, the Resident Engineer
will, upon written authorization from the Owner, instruct the Contractor to order
such special inspection, testing or approval, and the Contractor shall give
notice as provided above. If such special inspection or testing reveals a failure
of the Work to comply with the requirements of the Contract Documents, the
Contractor shall bear all costs thereof, including compensation for the Resident
Engineer's additional services, testing or inspections made necessary by such
failure; otherwise the Owner shall bear such costs, and an appropriate Contract
Change Order shall be issued.
F. Should it be considered necessary or advisable by the Resident Engineer at
any time either before acceptance of the entire Work or after acceptance and
within the guaranty period to make an examination of work already completed,
by removing or tearing out same, the Contractor shall on request promptly
furnish all necessary facilities, labor, and material. If such work is found to be
defective in any material respect, due to the fault of the Resident Engineer or
his/her Subcontractors, he/she shall defray all the expenses of such
examination and of satisfactory reconstruction. If, however, such work is found
to meet the requirements of the contract, any compensation deemed
appropriate shall be handled by issuance of a Contract Change Order to the
Contractor and he/she shall, in addition, if completion of the work has been
delayed thereby, be granted a suitable extension of time on account of the
additional work involved.
G. Required certificates of inspection, testing or approval shall be secured by the
Contractor and the Contractor shall promptly deliver them to the Resident
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 19
Engineer for review and evaluation of compliance with the appropriate
specifications and standards.
H. When the work is completed the Contractor shall notify the Resident Engineer
in writing that the work will be ready for final inspection and test on a definite
date which shall be stated in such notice.
2.16 TAXES, PERMITS, FEES, AND INDEMNIFICATION FOR PATENT INFRINGEMENT
CLAIM
A. The Contractor shall pay for and include all Federal, State and local taxes direct
or indirect for the work or portions thereof provided by the Contractor which are
legally enacted at the time the Notice to Proceed is issued, whether or not yet
enacted, and secure and pay all fees and charges for permits and licenses,
unless otherwise specified.
B. Royalty and license fees incidental to the use of any patented material, device
or process shall be paid by the Contractor and in the event of a claim of alleged
infringement of patent copyright, or Trade Secret rights, the Contractor shall
indemnify, save the Owner (and Owner's authorized representatives) free and
harmless, and defend, at the Contractor's own expense, any and all suits that
may be brought in such connection.
C. Unless otherwise provided in the Contract Documents, the Owner shall secure
and pay for the building permit, permanent utility connection fees, and right-of-
way encroachment permit. The Contractor shall secure and pay for temporary
construction utilities, and all other permits and governmental fees, licenses and
inspections necessary for the proper execution and completion of the Work.
D. The Contractor shall give all notices and comply with all laws, ordinances,
rules, regulations and lawful orders of any public authority bearing on the
performance of the Work.
E. It is not the responsibility of the Contractor to make certain that the Contract
Documents are in accordance with applicable laws, statutes, building codes
and regulations. If the Contractor observes that any of the Contract Documents
are at variance therewith in any respect, the Contractor shall promptly notify
the Resident Engineer in writing, and any necessary changes shall be
accomplished by appropriate Modification.
F. If the Contractor performs any work knowing it to be contrary to any laws,
ordinances, rules and regulations, without notice to the Resident Engineer, the
Contractor shall assume full responsibility therefor and shall bear all costs
attributable thereto.
G. Any reference in the Contract Documents to codes, standard specifications or
manufacturer's instructions shall mean the latest printed edition of each in
effect at the Contract date.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 20
2.17 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Within thirty (30) calendar days after receipt of Notice to Proceed, the
Contractor shall submit a Construction Schedule in CPM (Critical Path Method)
form to the Resident Engineer for approval. The Construction Schedule shall
be sufficiently detailed to accurately depict all the work required by the
Contract. CPM Construction Schedule shall reflect shop drawings; submittals
due and return dates, fabrication and delivery times, cost loading, crew mix,
and equipment loading data. The Contractor shall thereafter adhere to the
Construction Schedule, as updated monthly, or as necessary in accordance
with the Contract Documents, including any scope changes or changes in the
work approved by the Owner during the course of construction.
"Slack" or "float" time on the CPM Construction Schedule is not intended, and
shall not be, for the sole benefit of either the Owner or Contractor.
B. Within fourteen (14) calendar days after the pre-construction conference, the
Contractor shall provide a Submittal and Procurement Schedule indicating time
periods for review of Shop Drawings, Data, Samples, and procurement of
material and equipment required for the Work. Contractor shall allow time for
submittal review in accordance with the General Requirements Section —
Construction Progress Documentation. All items that require review by the
Resident Engineer and/or are not readily available from stock and requiring
more than thirty-five (35) days lead-time shall be included in the Submittal and
Procurement Schedule. Items listed in the Submittal and Procurement
Schedule shall also be identified as activities on the CPM Construction
Schedule. Contractor shall identify items requiring coordination with work of
separate contractors. The working day to calendar date correlation shall be
based upon the Contractor's proposed work week with adequate allowance for
legal holidays, days lost due to abnormal weather, and any special
requirements of the Project.
C. The Construction Schedule shall be prepared and maintained by the
Contractor.
D. The Owner, Resident Engineer, Contractor and other Contractor(s) shall jointly
review the progress of the work weekly. Should this review, in the opinion of
the Resident Engineer, indicate that the work is behind the schedule
established by currently reviewed Construction Schedule, the Contractor shall
either (1) provide a plan to the Resident Engineer indicating the steps the
Contractor intends to take in order to recover the time behind schedule and
conform to the reviewed Construction Schedule; or (2) submit a revised
Construction Schedule for completion of the work, remaining within the
contract completion time, to the Resident Engineer for review by the next
weekly meeting. If the Contractor's recovery or revised schedule requires work
to occur during other than normal working hours, the Contractor will be
responsible for any resulting costs incurred by the Owner, including but not
limited to, the costs for construction management, contract administration,
inspection, testing and staffing.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 21
E. The Contractor shall deliver copies of his/her daily job logs to the Resident
Engineer and Owner on a weekly basis or as otherwise agreed to by Owner.
At a minimum, the Contractor's daily job log should include the sub-contractors
working onsite, number of workers and their trade classification, description of
work, visitors, temperature and weather conditions, accidents, delays, and any
other important information pertaining to the Project that day. The Contractor
will schedule and coordinate the Work of all sub-contractors on the Project.
The Contractor will keep the Sub-contractors informed of the Construction
Schedule to enable the Contractor to plan and perform the Work properly.
2.18 RECORDS, DOCUMENTS AND SAMPLES AT THE SITE
A. The Contractor shall maintain all records of required Review Agencies, County
or State inspections and shall promptly notify the Resident Engineer of the
results of any inspection. Copies of all such records shall be provided to the
Owner.
B. The Contractor shall secure and maintain required certificates of inspection,
testing or approval and shall promptly deliver them to the Resident Engineer.
C. The Contractor shall maintain at the Project site, on a daily basis, one (1)
record copy of all Drawings, Specifications, Addenda, Change Orders and
other Modifications, in good order and marked currently to record all changes
made during construction, and reviewed Shop Drawings, Product Data and
Samples. These shall be available to the Resident Engineer and the Owner
and reviewed weekly, and shall be delivered to the Resident Engineer for
forwarding to the Owner upon completion of the Project. The Contractor shall
advise the Resident Engineer on a current basis of all changes in the Work
made during construction. Payment may be withheld from Contractor for failure
to maintain current Record Documents.
2.19 USE OF SITE
A. The Contractor shall confine operations at the site to areas permitted by law,
ordinances, permits and the Contract Documents, and shall not unreasonably
encumber the site with any materials or equipment.
B. The Contractor shall coordinate all of the Contractor's operations with, and
secure approval from, the Resident Engineer before using any portion of the
site. Also see Technical Specifications, Division 01, General Requirements.
2.20 CUTTING AND PATCHING OF WORK
A. The Contractor shall be responsible for all cutting, fitting or patching that may
be required to complete the Work or to make its several parts fit together
properly.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 22
B. The Contractor shall not damage or endanger any portion of the Work or the
work of the Owner or any separate contractors by cutting, patching or otherwise
altering any work, or by excavation. The Contractor shall not cut or otherwise
alter the work of the Owner or any separate contractor except with the written
consent of the Owner and of such separate contractor. The Contractor shall
not unreasonably withhold from the Owner or any separate contractor consent
to cutting or otherwise altering the Work.
C. The Contractor in all cases shall exercise extreme care in any cutting
operations, and perform such operations under adequate supervision by
competent mechanics skilled in the applicable trade. Openings shall be neatly
cut and shall be kept as small as possible to avoid unnecessary damage.
Careless and/or avoidable cutting damage, etc., will not be tolerated, and the
Contractor will be held responsible for such avoidable or willful damage.
D. All replacing, patching and repairing of all materials and surfaces cut or
damaged in the execution of the Work shall be performed by experienced
mechanics of the several trades involved. All work of such nature shall be done
with the applicable materials, in such a manner that all surfaces so replaced,
repaired, or patched, will, upon completion of the Work, match the surrounding
similar surfaces.
2.21 CLEANING UP
A. The Contractor shall at all times keep the premises free from accumulation of
waste materials or rubbish caused by the Contractor's operations. At the
completion of the Work, the Contractor shall remove all the Contractor's waste
materials and rubbish from and about the Project as well as all the Contractor's
tools, construction equipment, machinery and surplus materials.
B. If the Contractor fails to clean up at the completion of the Work, the Owner may
do so, and the cost thereof shall be paid by the Contractor.
2.22 INDEMNIFICATION
A. To the fullest extent permitted by law, Contractor agrees to and shall indemnify,
save, hold harmless and at Owner's request, defend Owner and its officers,
agents and employees, and the Engineer of record and Consultants and their
respective officers, agents and employees, from any and all costs and
expenses, attorney fees and court costs, damages, liabilities, claims and
losses occurring or resulting to Owner, the Engineer of record or Consultants
in connection with the performance, or failure to perform, by Contractor, its
officers, agents or employees under this Agreement, and from any and all costs
and expenses, attorney fees and court costs, damages, liabilities, claims and
losses occurring or resulting to any person, firm or corporation who may be
injured or damaged by the performance, or failure to perform, of Contractor, its
officers, agents or employees under this Agreement. In addition, Contractor
agrees to indemnify Owner for Federal, State of California and/or local audit
exceptions resulting from non-compliance herein on the part of Contractor.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 23
B. In any and all claims against the Owner, the Engineer of record or Consultants,
or any of their respective officers, agents or employees, initiated by any
employee of the Contractor, any Subcontractor, anyone directly or indirectly
employed by any of them or anyone for whose acts any of them may be liable,
the indemnification obligation set forth in the immediately preceding paragraph
shall not be limited in any way by any limitation on the amount or type of
damages, compensation or benefits payable by or for the Contractor or any
Subcontractor under workmen's compensation acts, disability benefit acts or
other employee benefit acts.
2.23 FAIR EMPLOYMENT PRACTICES CLAUSE
Nondiscrimination: In connection with the performance of Work under the contract,
the Contractor agrees (as prescribed in Chapter 6 of Division 3 of Title II of the
Government Code of the State of California, commencing at Section 12900 and by
Labor Code Section 1735) not to discriminate against any employee or applicant for
employment because of race, religious creed, color, national origin, ancestry,
physical disability, mental disability, medical condition, marital status or sex. The
aforesaid provisions shall include, but not be limited to, the following: employment,
upgrading, demotion or transfer, recruitment or recruitment advertising, layoff or
termination, rates of pay or other forms of compensation, and selection for training,
including apprenticeship. The Contractor agrees to post hereafter in conspicuous
places, available for employees and applicants for employment, Notices to be
provided by the County, setting forth the provisions of this discrimination clause. The
Contractor further agrees to insert the foregoing provisions in all subcontracts
hereunder, except subcontracts for standard commercial supplies of raw materials.
2.24 PAYMENT
A. CONTRACT SUM
The Contract Sum is stated in the Owner-Contractor Agreement ("the
Agreement"), Section 005213, and, including authorized adjustments thereto,
is the total amount payable by the Owner to the Contractor for the
performance of the Work under the Contract Documents.
B. SCHEDULE OF VALUES
Before the first Application for Payment, the Contractor shall submit to the
Resident Engineer a Schedule of Values allocated to the various portions of
the Work, prepared in such form and supported by such data to substantiate
its accuracy as the Resident Engineer may require. This schedule, unless
objected to by the Resident Engineer, shall be used only as a basis for the
Contractor's Applications for Payment.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 24
C. APPLICATIONS FOR PAYMENT
The Owner will make progress payments to the Contractor upon completion of
portions of the Work, as covered by the Contract Documents, in accordance
with established Owner procedures. Before submitting an Application for
Payment (Final or Partial) the Contractor shall reach an agreement with the
Resident Engineer(in consultation with the Engineer of record) concerning the
percentage complete of the Work and the dollar value for which the Application
for Payment may be submitted.
1. On or about the twentieth (20th) day of the month in which the work
was performed, the Contractor shall submit to the Resident Engineer
an itemized Application for Payment, notarized if required, supported
by such data substantiating the Contractor's right to payment as the
Owner or the Resident Engineer may require, including appropriate
updates to the Construction Schedule, and reflecting retainage, if any,
as provided elsewhere in the Contract Documents. Payment is
expressly conditioned upon submission by the Contractor of conditional
and unconditional waivers and release of lien rights upon progress
payment as the Owner or the Engineer of record may require. Waiver
and Release forms must be submitted on forms approved by the
Owner. Copies of said forms shall comply with Civil Code Section 8132
through 8138, inclusive.
2. Unless otherwise provided in the Contract Documents, payments may
be made on account of materials or equipment not incorporated in the
Work but delivered and suitably stored at the site and, if approved in
advance by the Owner, payments may similarly be made for materials
or equipment suitably stored at some other location agreed upon in
writing. Payments for materials or equipment stored on or off the site
shall be conditioned upon submission by the Contractor of bills of sale
or such other procedures satisfactory to the Owner to establish the
Owner's title to such materials or equipment or otherwise protect the
Owner's interest, including applicable insurance and transportation to
the site for those materials and equipment stored off the site.
3. The Contractor warrants that title to all work, materials and equipment
covered by an Application for Payment will pass to the Owner either by
incorporation in the construction or upon receipt of payment by the
Contractor, whichever occurs first, free and clear of all liens, stop
notices, claims, security interest or encumbrances, hereinafter referred
to as "liens"; and that no work, materials or equipment covered by an
Application for Payment will have been acquired by the Contractor, or
by any other person performing work at the site or furnishing materials
and equipment for the Project, subject to an agreement under which an
interest therein or an encumbrance thereon is retained by the seller or
otherwise imposed by the Contractor or such other person.
4. On or about the twentieth (20t") day of the month following the month
in which the work was performed, the Owner shall pay to the Contractor
ninety-five percent(95%)of the value of said work in place, as checked
and approved by the Resident Engineer. The balance of five percent
(5%) of the estimate shall be retained by the Owner until the time of
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 25
final acceptance of said work. In lieu of the five percent(5%)retainage,
the Contractor may substitute securities as provided herein below.
a. If the Owner does not pay the Contractor within thirty (30) days
after receipt of an undisputed and properly submitted payment
request for a progress payment, excluding that portion of the
final payment designated by the contract as retention earnings,
then the Owner shall pay interest to the Contractor as provided
by Public Contract Code Section 20104.50. Said interest
penalty is the sole recourse of Contractor and Contractor shall
have no right to stop the Work until payment of the amount
owing has been received, nor shall the contract completion time
be extended, nor shall the Contract Sum be increased in any
way, including by reason of any costs incurred by Contractor,
except to the extent of said interest payment.
b. Pursuant to Public Contract Code Section 7107, in the event of
a dispute between the Owner and Contractor, the Owner may
withhold from the final payment an amount not to exceed one
hundred and fifty percent (150%) of the disputed amount.
Except as so provided, the Owner shall release the retention
withheld within sixty(60)days after the date of completion of the
Work, as "completion" is defined in Public Contract Code
Section 7107. In the event that retention payments are not
made within the time periods required by Public Contract Code
Section 7107, the Owner may be subject to the interest
provisions of Public Contract Code Section 7107.
5. Security Substitutions and Escrow for Moneys Withheld to Insure
Contractor's Performance. Pursuant to Public Contract Code section
22300, the Contractor may deposit in an escrow, equivalent securities
for any moneys withheld to ensure performance and have said moneys
paid directly to Contractor, or, in the alternative, have the Owner deposit
such moneys directly into an escrow. Upon the closing of any such
escrow, Contractor shall pay to each Subcontractor, not later than
twenty (20) days after receipt of the closing payment, the respective
amount of interest earned, net of costs attributed to retention withheld
from each Subcontractor, on the amount of retention withheld to insure
the performance of the Contractor. Any escrow established pursuant
to this article shall be with a state or federally chartered bank, shall be
at the sole expense of the Contractor, and shall be established using
an escrow agreement in substantially the following form:
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 26
(Begin Escrow Agreement)
ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION
This Escrow Agreement is made and entered into by and between the County of Fresno,
(hereinafter called "Owner"),
(hereinafter called "Contractor"); and
a state or federally chartered bank
in California, (hereinafter called "Escrow Agent").
For the consideration hereinafter set forth, the Owner, Contractor, and Escrow Agent agree
as follows:
1. Pursuant to Section 22300 of the Public Contract Code of the State of California,
Contractor has the option to deposit securities with Escrow Agent as a substitute for
retention earnings required to be withheld by Owner pursuant to the Construction
Contract entered into between the Owner and Contractor for
in the amount
of$ and dated (hereinafter referred to
as the "Contract"). Alternatively, on written request of the Contractor, the Owner shall
make payments of the retention earnings directly to the Escrow Agent. When
Contractor deposits the securities as a substitute for Contract earnings, the Escrow
Agent shall notify the Owner within ten (10) days of the deposit. The market value of
the securities at the time of the substitution, as valued by the Owner, shall be at least
equal to the cumulative total cash amount then required to be withheld as retention
under the terms of the contract between Owner and Contractor. If the Owner
determines that the securities are not adequate it will notify Contractor and Escrow
Agent, and Contractor shall deposit additional security as further determined by the
Owner. Securities shall be held in the name of the Owner and shall designate the
Contractor as the beneficial owner.
2. Securities eligible for investment under subdivision (c) of the above-referenced
Section 22300 shall include those listed in Section 16430 of the Government Code,
and shall also include bank or savings and loan certificates of deposit, interest-bearing
demand deposit accounts, and standby letters of credit. Deposit of any other type of
security may be permitted only by mutual agreement of the Contractor and the Owner,
evidenced by an amendment to this agreement executed by all of the parties hereto.
3. Upon the deposit of adequate securities, Owner shall make progress payments to the
Contractor for such funds which otherwise would be withheld from progress payments
pursuant to the Contract provisions.
4. When the Owner, at Contractor's written request, makes payment of retentions earned
directly to the Escrow Agent, the Escrow Agent shall hold them for the benefit of the
Contractor until such time as the escrow created under this contract is terminated. The
Contractor may direct the investment of the payments into securities. All terms and
conditions of this agreement and the rights and responsibilities of the parties shall be
equally applicable and binding when the Owner pays the Escrow Agent directly.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 27
5. Contractor shall be responsible for paying all fees for the expenses incurred by Escrow
Agent in administering the Escrow Account and all expenses of the Owner. The
Owner, Contractor and Escrow Agent shall determine these expenses and payment
terms.
6. The interest earned on the securities or the money market accounts held in escrow
and all interest earned on that interest shall be for the sole account of Contractor and
shall be subject to withdrawal by Contractor at any time and from time to time without
notice to the Owner.
7. Contractor shall have the right to withdraw all or any part of the principal in the Escrow
Account only by written notice to Escrow Agent accompanied by written authorization
from Owner to the Escrow Agent that Owner consents to the withdrawal of the amount
sought to be withdrawn by Contractor.
8. The Owner shall have the right to draw upon the securities or any amount paid directly
to Escrow Agent in the event of default by the Contractor. Upon seven (7)days written
notice to the Escrow Agent from the Owner of the default, the Escrow Agent shall
immediately convert the securities to cash and shall distribute the cash, including any
amounts paid directly to Escrow Agent, as instructed by the Owner. Escrow Agent
shall not be concerned with the validity of any notice of default given by Owner
pursuant to this paragraph, and shall promptly comply with Owner's instructions to pay
over said escrowed assets. Escrow Agent further agrees not to interplead the
escrowed assets in response to conflicting demands and hereby waives any present
or future right of interpleader.
9. Upon receipt of written notification from the Owner certifying that the Contract is final
and complete, and that the Contractor has complied with all requirements and
procedures applicable to the Contract, Escrow Agent shall release to Contractor all
securities and interest on deposit less escrow fees and charges of the Escrow
Account. The escrow shall be closed immediately upon disbursement of all moneys
and securities on deposit and payment of fees and charges.
10. Escrow Agent shall rely on the written notifications from the Owner and Contractor
pursuant to Sections (6), (7), (8) and (9) of this Agreement and the Owner and
Contractor shall hold Escrow Agent harmless from Escrow Agent's release and
disbursement of the securities and interest as set forth above.
11. The venue of any litigation concerning the rights and obligations of the parties to this
agreement shall be the County of Fresno and the parties hereto waive the removal
provisions of Code of Civil Procedure Section 394.
12. The names of the persons who are authorized to give written notice or to receive
written notice on behalf of the Owner and on behalf of Contractor in connection with
the foregoing, and exemplars of their respective signatures are as follows:
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 28
On Behalf of Owner: On behalf of Contractor:
Title — Business Manager Title
Name — Lemuel Asprec Name
Signature Signature
Address: 2220 Tulare St, 6th Floor Address:
Fresno, CA 93721
On behalf of Escrow Agent:
Title
Name
Signature
Address
At the time the Escrow Account is opened, the Owner and Contractor shall deliver to the
Escrow Agent a fully executed counterpart of this Agreement
IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers
on the date first set forth above.
Owner: Contractor:
Title — Steve White, Director Title
Department of Public Works Name
and Planning
Signature Signature
Address —2220 Tulare St, 6th Floor Address
Fresno, CA 93721
Escrow Agent:
Title
Name
Signature
Address
(End Escrow Agreement)
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 29
6. Itemized Breakdown: The Contractor shall submit a financial
breakdown of the work, itemized by crafts or sections as designated by
the Owner. The Contractor's payment shall be based upon the monthly
percentage of completion of these items.
7. Lien Waivers: The Owner may require the Contractor to submit, along
with the progress payment request, notarized lien waivers from each
Subcontractor, materials or equipment supplier. Lien waivers shall
comply with Civil Code Section 8132, et seq., and the aggregate sum
thereof shall reflect all progress payments previously made.
D. CERTIFICATES FOR PAYMENT
1. The Resident Engineer shall, within seven (7) days after the receipt of
the Project Application for Payment, review the Project Application for
Payment and either issue a Project Certificate for Payment to the
Owner for such amounts as the Resident Engineer determines are
properly due, or notify the Contractor in writing of the reasons for
withholding a Certificate provided in Part F of this Section 2.24.
2. The issuance of a Project Certificate for Payment will constitute a
representation by the Resident Engineer to the Owner that, based on
the Resident Engineer's observations at the site as provided herein and
the data comprising the Project Application for Payment, the Work has
progressed to the point indicated and that, to the best of the Resident
Engineer's knowledge, information and belief, the quality and
timeliness of the Work is in accordance with the Contract Documents
(subject to an evaluation of the Work for conformance with the Contract
Documents upon Completion of the Work, to the results of any
subsequent tests required by or performed under the Contract
Documents, to minor deviations from the Contract Documents
correctable prior to completion, and to any specific qualifications stated
in the Certificate); and that based upon all currently available
information, the Contractor is entitled to payment in the amount
certified. However, by issuing a Project Certificate for Payment, the
Resident Engineer shall not thereby be deemed to represent that the
Resident Engineer has made exhaustive or continuous on-site
inspections to check the quality or quantity of the Work, has reviewed
the construction means, methods, techniques, sequences or
procedures, or has made any examination to ascertain how or for what
purpose the Contractor has used the monies previously paid on
account of the Contract Sum.
E. PROGRESS PAYMENTS
1. After the Resident Engineer has issued a Project Certificate for
Payment, the Owner shall make payment in the manner and within the
time provided in the Contract Documents.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 30
2. The Contractor shall promptly pay each Subcontractor upon receipt of
payment from the Owner, out of the amount paid to the Contractor on
account of such Subcontractor's Work, the amount to which
Subcontractor is entitled, reflecting the percentage actually retained, if
any, from payments to the Contract on account of such Subcontractor's
Work. The Contractor shall, by an appropriate agreement with each
Subcontractor, require each Subcontractor to make payments to their
Sub-subcontractors in similar manner.
3. The Resident Engineer may on request of any Subcontractor, at the
Resident Engineer's discretion, furnish to that Subcontractor, if
practicable, information regarding the percentages of completion or the
amounts applied for by the Contractor and the action taken thereon by
the Resident Engineer on account of Work done by such
Subcontractor.
4. Neither the Owner nor the Resident Engineer shall have any obligation
to pay or to see to the payment of any monies to any Subcontractor or
Material Suppliers except as may otherwise be required by law.
5. Neither certification of a progress payment, delivery of a progress
payment, nor partial or entire use or occupancy of the Project by the
Owner, shall constitute an acceptance of any Work not performed in
accordance with the Contract Documents.
F. PAYMENTS WITHHELD
1. The Resident Engineer may decline to certify payment and may
withhold the Certificate in whole or in part to the extent necessary to
reasonably protect the Owner, if, in the Resident Engineer's opinion,
the Resident Engineer is unable to make representations to the Owner
as provided herein above for Certificates for Payment. If the Resident
Engineer is unable to make representations to the Owner and certify
payment in the amount of the Project Application, the Resident
Engineer will notify the Contractor as provided herein. If the Contractor
and the Resident Engineer cannot agree on a revised amount, the
Resident Engineer will promptly issue a Project Certificate for Payment
for the amount for which the Resident Engineer is able to make such
representations to the Owner. The Resident Engineer may also decline
to certify payment or, because of subsequently discovered evidence or
subsequent observations, the Resident Engineer may nullify the whole
or any part of any Project Certificate for Payment previously issued to
such extent as may be necessary, in the Resident Engineer's opinion,
to protect the Owner from loss because of:
a. Defective Work not remedied;
b. Third party claims filed or reasonable evidence indicating
probable filing of such claims, including claims by separate
contractors;
C. Failure of the Contractor to make payments properly to
Subcontractors, or for labor, materials or equipment;
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 31
d. Engineer of record's determination, based upon reasonable
evidence, that the Work cannot be completed for the unpaid
balance of the Contract Sum;
e. Damage to the Owner or another contractor;
f. Engineer of record's determination, based upon reasonable
evidence, that the Work will not be accomplished in compliance
with the Work Order Completion Time;
g. Persistent failure to carry out the Work in accordance with the
Contract Documents;
h. Failure of the Contractor to submit Construction Schedules or
Submittal and Procurement Schedules as required;
i. Failure of the Contractor to maintain record drawings on a
current basis;
j. Failure of the Contractor to submit notarized lien waivers from
each Subcontractor, materials or equipment supplier;
k. Failure of the Contractor to submit certified payroll reports;
I. Stop notice served upon the Owner.
2. A retention in the amount of one-thousand dollars ($1,000) will be
withheld from the Contractor's monthly progress payment for each and
every required document not submitted in a timely manner by the
Contractor or its subcontractors up to a maximum of ten-thousand
dollars ($10,000). For purposes of this Paragraph, the term "required
document" includes, but is not limited to, certified payrolls, labor
compliance documents, Disadvantaged Business Enterprise
documents, and any other information or documents required to be
submitted by the Contractor or any of its subcontractors under the terms
of this Agreement or pursuant to applicable federal, state or local laws
or regulations. The retention provided for in this Paragraph shall be in
addition to any other deduction or retention allowed under this
Agreement, and shall be in addition to any other remedy or
consequence provided by law for untimely submission of any required
document. Such retention shall remain in effect only until such time as
the required documents have been submitted by the Contractor or its
subcontractor(s) and have been determined by the Owner to be both
complete and acceptable as to form.
3. When the grounds as noted above are removed, payment shall be
made for amounts withheld on the basis thereof.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 32
G. COMPLETION AND FINAL PAYMENT
1. Following the Contractor's completion of the Work, the Contractor shall
forward to the Resident Engineer a written notice that the Work is ready
for final inspection and acceptance, and shall also forward to the
Resident Engineer a final Application for Payment. Upon receipt, the
Resident Engineer will promptly make such inspection. When the
Resident Engineer finds the Work acceptable under the Contract
documents and the Contract fully performed, the Resident Engineer will
issue a Project Certificate for Payment which will certify the final
payment due the Contractor. This certification will constitute a
representation that, to the best of the Resident Engineer's knowledge,
information and belief, and on the basis of observations and
inspections, the Work has been completed in accordance with the
Terms and Conditions of the Contract Documents and that the entire
balance found to be due the Contractor, and noted in said Certificate,
is due and payable. The Resident Engineer's certification of said
Project Certificate for Payment will constitute a further representation
that the conditions precedent to the Contractor's being entitled to final
payment as set forth herein below have been fulfilled.
2. Neither the final payment nor the remaining retainage shall become due
until the Contractor submits to the Resident Engineer (1) an affidavit
that all payrolls, bills for materials and equipment, and other
indebtedness connected with the Work for which the Owner or the
Owner's property might in any way be responsible, have been paid or
otherwise satisfied, (2) consent of surety, if any, to final payment, and
(3) other data establishing payment or satisfaction of all such
obligations, such as receipts, releases and waivers of liens arising out
of the Contract, to the extent and in such form as may be designated
by the Owner. If any Subcontractor refuses to furnish a release or
waiver required by the Owner, the Contractor may furnish a bond
satisfactory to the Owner to indemnify the Owner against any such lien.
The bond cannot be from the original surety insurer for the Project or
any affiliate of the original surety. If any such lien remains unsatisfied
after all payments are made, the Contractor shall refund to the Owner
all monies that the latter may be compelled to pay in discharging such
lien.
3. All provisions of this Agreement, including without limitation those
establishing obligations and procedures, shall remain in full force and
effect notwithstanding the making or acceptance of final payment, and
the making of final payment shall not constitute a waiver of any claims
by the Owner.
4. Upon completion and acceptance of all work whatsoever required, and
upon the release of all claims against the Owner as specified, the
Owner shall file a written Notice of Completion with the County
Recorder as to the entire amount of work performed.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 33
5. Final payment will be released within sixty (60) days after the date of
acceptance of the Work as reflected in the Notice of Completion filed
with the County Recorder's Office; provided, that Owner may withhold
from the final payment, in the event of a dispute between Owner and
Contractor, retentions in and amount not exceeding 150 percent of the
disputed amount. At the Contractor's option, the Owner may release
retention upon receipt of an unconditional lien release for the full value
of the Work and any of its Contract Change Orders.
6. All manufacturers'warranties required by the Contract Documents shall
commence on the date of the Notice of Completion for the Work. It
shall be the Contractor's responsibility, through appropriate contractual
arrangements with all subcontractors, materialmen and suppliers, to
ensure compliance with this requirement.
7. The acceptance by the Contractor of the final payment, after the date
of Notice of Completion of the Project, shall be and shall operate as a
release to the Owner of all claims and of all liability to the Contractor,
under the Contract Documents or otherwise, for all things done or
furnished in connection with this Work, excepting only the Contractor's
claims for interest upon final payment, if such final payment be
improperly delayed. No payments, however, final or otherwise, shall
operate to release the Contractor or his/her sureties from any
obligations under the Contract Documents, including but not limited to
the Performance and Payment Bonds.
2.25 CHANGES TO THE WORK
A. The Owner, without invalidating the Contract, may order changes in the Work
within the general scope of the Contract consisting of additions, deletion or
other revisions. All such changes in the Work shall be authorized by a Contract
Change Order, and shall be performed under the applicable conditions of the
Contract Documents.
B. CONTRACT CHANGE ORDER: A Change Order issued to add or delete Work
from the Contract. Only an executed Contract Change Order will effectuate
change in either the Contract Sum and/or the contract time. A Change Order
is a written order to the Contractor dually signed to show both the approval of
the Engineer of record and Authorization of the Owner, issued after execution
of the Contract. A Change Order signed by the Contractor indicates the
Contractor's agreement therewith, including any adjustment in the Contract
Sum or the contract time, and the full and final settlement of all costs (direct,
indirect and overhead) related to the Work authorized by the Change Order.
C. All claims for additional compensation to the Contractor shall be presented in
writing before the expense is incurred and will be adjusted as provided herein.
No work shall be allowed to lag pending such adjustment, but shall be promptly
executed as directed, even if a disputed claim arises. No claim will be
considered after the work in question has been done unless a Contract Change
Order has been issued or a timely written notice of claim has been made by
Contractor.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 34
D. Costs mean an itemized breakdown of all labor (by crafts), materials, sales
taxes, equipment rentals, etc., for each portion of the Work which comprises
the Change Order including any Subcontractor's itemized breakdown, plus not
more than twenty (20) percent to cover all profits and administration.
1. Under no circumstance will the total sum of allowable mark up for
General Conditions, General Requirements, supervision, overhead
(excluding small tools) and profit, exceed a cumulative total of twenty
percent (20%), including markups for all parties involved in a change.
i. Work done by Contractor's own forces, not including bond and
insurance premiums, fifteen percent (15%)
ii. Work done by subcontractors, all tiers, including bond and
insurance premiums, if any, shall not exceed a cumulative total
of fifteen percent (15%)
iii. General Conditions, General Requirements, Supervision,
Overhead and Profit for Contractor on Subcontractor's work,
five percent (5%).
2. The cost or credit to the Owner resulting from a change in the Work
shall be determined in one or more of the following ways:
i. By mutual acceptance of a lump sum properly itemized and
supported by sufficient substantiating data to permit evaluation;
ii. By unit prices state in the Contract Documents or subsequently
agreed upon;
iii. By cost to be determined in a manner agreed upon by the
parties and a mutually acceptable fixed or percentage fee; or
iv. By the method provided under Article 2.26.
E. The amount of credit to be allowed by the Contractor to the Owner, as
confirmed by the Resident Engineer, for any deletion or change that results in
a decrease in the Contract Sum will be the amount of the actual cost. When
both additions and credits covering related Work or substitutions are involved
in any one change, the allowance for overhead and profit shall be figured on
the basis of the net increase, if any, with respect to that change.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 35
2.26 CHANGES TO THE CONTRACT (EXTRA WORK AT FORCE ACCOUNT)
A. If none of the methods set forth in Section 2.25.D, is agreed upon, the
Contractor, provided that a written order signed by the Owner is received, shall
promptly proceed with the Work involved. The cost of such Work shall then be
determined by the Resident Engineer, on the basis of reasonable expenditures
or savings of those performing the Work attributable to the change, including,
in the case of an increase in the Contract Sum, not more than twenty percent
(20%)for all overhead and profit. In such case, and also under Section 2.25.D,
Paragraph 3, the Contractor shall keep and present, in such form as the Owner
or the Resident Engineer may prescribe, an itemized accounting of actual cost
together with appropriate supporting data for inclusion in a Contract Change
Order. Unless otherwise provided in the Contract Documents, cost shall be
limited to the following:
1. Labor Cost is the cost of labor for the workers (including working
foremen) used in the actual and direct performance of the extra work,
whether employed by the Contractor, or Subcontractors and
Specialized Forces of any tier. Labor Cost shall include:
a. Actual Wages paid to the works, plus employer payments to or
on behalf of the workers for health and welfare, pension,
vacation, and training. If required by the Resident Engineer,
certified payrolls shall be submitted with extra work reports as
verification of wages paid to the workers.
b. A Labor Surcharge of 20 percent (35 percent for demolition
work and roofing work) will be added to the Actual Wages as
defined above. The Labor Surcharge shall constitute full
compensation for all payments imposed by State and Federal
laws, including Workers Compensation Insurance, Social
Security, and Unemployment Insurance.
C. Subsistence and Travel Allowance if actually paid to the
workers. Labor Surcharge will not be added to Subsistence and
Travel Allowance.
2. Equipment Cost is the payment made for the equipment actually used
in the performance of the extra work.
a. Equipment valued at three hundred dollars ($300) or less shall
be considered as small tools, and no payment will be made
therefor.
b. Equipment costs will be paid in accordance with the rental rates
listed in the "Cal-Trans Equipment Rental Rates, County of
Fresno, Department of Public Works and Planning," in effect at
the time of bid, available from the Department, Suite 711,
Fresno County Plaza Building, 2220 Tulare Street, Fresno, CA
93721.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 36
C. In the event that any of the equipment to be used is not listed in
the above publication, the rental rate shall be agreed upon in
writing by the Contractor and CM before the extra work is
begun.
3. Materials Cost is the payment made for materials incorporated into the
Work.
a. Materials Cost shall include sales tax, freight, and delivery
charges, less any available discounts whether or not said
discounts are taken.
b. Materials Cost shall be based upon supplier's or manufacturer's
invoice. If invoices or other satisfactory evidence of cost are not
furnished within sixty (60) days of delivery or within fifteen (15)
days after acceptance of the Contract, whichever occurs first,
then the Resident Engineer shall determine the Materials Cost,
in his/her sole discretion, on the basis of available information
and on his/her considered experience.
4. Specialized Services are those services or items of extra work that, by
agreement of the Contractor and the Resident Engineer, cannot be
performed by forces of the Contractor of his/her Subcontractors, and
may be performed by a specialist.
a. Specialized Services may be paid for by invoice if the
established practice of the specialized force industry does not
provide complete itemization of Labor, Equipment and Materials
Costs.
5. Markup for Profit, Home Office and Field Office Overhead, Bond
Premium, insurance, taxes, and supervision will be added to the total
of Labor Cost, Equipment Cost, Materials Cost, and Specialized
Services.
a. Markup will be added only once on any Extra Work at Force
Account, regardless of the number of contractors and
subcontractors involved.
b. It is recognized that individual contractors and subcontractors
have different overhead costs, profit requirements and bond
premium rates. The amount to be added to Extra Work for
markup shall include compensation for profit, overhead and
bond premium without distinguishing among these items.
C. The markup to be added for Extra Work at Force Account on
this Project shall be fifteen percent (15%) plus 1-1/2% for
Performance and Payment Bonds for Contractor only.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 37
6. Records shall be maintained by the Contractor and Subcontractors in
such a manner as to provide a clear distinction between the costs of
Extra Work paid for on a forced account basis and the costs of other
operations. From these records, the Contractor shall furnish the
Resident Engineer a completed extra work report for each day's extra
work to be paid for on a force account basis. Extra work reports shall
itemize the materials used, equipment rental charges, and specialized
services costs, and shall provide names or identifications and
classifications of workmen, the hourly rate of pay, and hours worked.
Extra work reports shall be compiled and submitted to the Resident
Engineer daily for verification and signature. Extra work reports shall
be signed by the Contractor or his/her authorized representative.
7. If the Contractor disputes the Engineer of record's cost determination,
the Contractor may initiate a claim in compliance with the Claims and
Disputes Resolution provisions of these General Conditions.
2.27 SITE CONDITIONS
A. Where investigations have been conducted by the Owner of existing conditions
on a site, including subsurface conditions, such investigations are made for the
purpose of design only and for the information of bidders. The results of such
investigations represent only the statement by the Owner as to the
circumstance and character of materials actually encountered by the Owner
during the investigations. The Owner makes no guarantee or warranty,
express or implied, that the conditions indicated are representative of
conditions existing throughout the site of a Project or any part of it, or that
unanticipated conditions might not occur.
B. All excavation work shall be performed on an "unclassified basis"; that is, such
work shall include the removal of all material encountered including earth or
rock formations, regardless of the type or hardness thereof, or groundwater
conditions in the excavation, the cost of such excavations being included in the
Contract Sum. Unclassified excavation Work includes drilling or blasting
operations.
C. If site conditions are discovered that materially differ from previous information
that the Contractor has received, and that could not have been discovered by
the Contractor through prudent and reasonable investigation prior to
developing the Contract Sum for the Work, the Contractor shall be
compensated for additional costs incurred in working with the unknown site
conditions, but only to the extent that such previously unknown and
undiscoverable site conditions cause the Contractor to incur costs in addition
to the Contract Sum for that portion of the Work. The Contractor must be able
to demonstrate clearly the original Contract Sum for that portion of the Work
(plus any Contract Change Orders applicable to that portion of the Work) and
the additional costs incurred as a direct result of the unknown site conditions.
Only additional costs over and above the amount of the Contract Sum for that
portion of the Work will be compensated upon a recommendation of approval
by the Resident Engineer.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 38
2.28 REQUEST FOR EQUITABLE ADJUSTMENT
A. If the Contractor considers a Request for Equitable Adjustment is justified for
any increase in the contract time, the Contractor shall promptly, upon first
observance of the condition giving rise to the request, provide the Resident
Engineer and Owner written notice of such condition and circumstance. This
notice shall be given by the Contractor before proceeding to execute the Work,
except in emergency endangering life or property, in which case the Contractor
shall proceed in accordance with the Emergency provisions of these General
Conditions. No such request shall be valid unless so made. A Contract Change
Order shall be required to authorize any change in the contract time resulting
from such request for equitable adjustment.
B. If the Contractor requests that additional cost or time is involved because of,
but not limited to, (1) any written interpretation pursuant to Section 2.07.G, (2)
any order by the Owner to stop the Work pursuant to Section 2.08 where the
Contractor was not at fault, or any such order by the Resident Engineer as the
Owner's agent, (3) any written order for a minor change in the Work issued
pursuant to Section 2.29, the Contractor shall make such request for equitable
adjustment as provided in Section 2.28.A.
2.29 MINOR CHANGES IN THE WORK
The Resident Engineer will have authority to order minor changes in the Work not
involving an adjustment in the Contract Sum or extension of the contract time and not
inconsistent with the intent of the Contract Documents. Such changes shall be
enacted by written order issued through the Resident Engineer, and shall be binding
on the Owner and the Contractor. The Contractor shall carry out such written orders
promptly.
2.30 SUCCESSORS AND ASSIGNS
The Owner and the Contractor, respectively, bind themselves, their partners,
successors, assigns and legal representatives to the other party hereto and to the
partners, successors, assigns and legal representatives of such other party with
respect to all covenants, agreements and obligations contained in the Contract
Documents. Neither party to the Contract shall assign the Contract or sublet it as a
whole without the written consent of the other.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 39
2.31 ASSIGNMENT OF MONEYS
The Contractor shall not assign moneys due or to become due him/her under the
contract without the written consent of the Auditor-Controller of Fresno County. Any
assignment of moneys shall be subject to all proper set-offs in favor of the County of
Fresno and to all deductions provided for in the contract and particularly all money
withheld, whether assigned or not, shall be subject to being used by the County of
Fresno for the completion of the work in the event that the Contractor should be in
default therein.
2.32 GUARANTEE OF WORK
A. The Contractor warrants to the Owner that all materials and equipment and the
Work as a whole furnished under this Contract will be new unless otherwise
specified, and that all Work will be of good quality, free from faults and defects
and in conformance with the Contract Documents, for a period of 365 Calendar
Days from the date of acceptance of the Work as specified in the Notice of
Completion, unless a longer period is otherwise specified. All manufacturer's
warranties required by the Contract Documents shall commence on the date
of the filing of the Notice of Completion for the Work (which date necessarily
will follow the performance under separate contracts). It shall be the
Contractor's responsibility, through appropriate contractual arrangements with
all subcontractors, material men and suppliers, to ensure compliance with this
requirement. All Work not conforming to these requirements, including
substitutions not properly reviewed and authorized, may be considered
defective. If required by the Resident Engineer, the Contractor shall furnish
satisfactory evidence as to the kind and quality of materials and equipment.
B. If repairs or changes are required in connection with guaranteed work within
any guaranteed period, which, in the opinion of the Resident Engineer is
rendered necessary as the result of the use of materials, equipment or
workmanship which are inferior, defective, or not in accordance with the
Contract Documents, the Contractor shall, promptly upon receipt of notice from
the Owner, and without expense to the Owner(1) place in satisfactory condition
in every particular all of such guaranteed work, correct all defects therein, and
(2) make good all damage to the building or site, or equipment or contents
thereof, which, in the opinion of the Resident Engineer, is the result of the use
of materials, equipment or workmanship which are inferior, defective, or not in
accordance with the Contract Documents; and (3) make good any work or
materials, or the equipment and contents of said building or site disturbed in
fulfilling any such guarantee.
C. If the Contractor disturbs any work guaranteed under another contract in
fulfilling the requirements of the contract or of any guarantee, embraced in or
required thereby, he/she shall restore such disturbed work to a condition
satisfactory to the Resident Engineer and guarantee such restored work to the
same extent as it was guaranteed under such other contract.
D. The Owner may have the defects corrected if the Contractor, after notice, fails
to proceed promptly to comply with the terms of the guarantee and the
Contractor and his/her surety shall be liable for all costs and expenses incurred
in connection therewith.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -40
E. All special guarantees applicable to definite parts of the work that may be
stipulated in the Contract Documents shall be subject to the terms of this Article
2.32 during the first (1st) year (365 Calendar Days) of the life of such special
guarantee.
2.33 RESPONSIBILITY FOR DAMAGE
A. Neither the Owner, the Engineer of record, nor any officer or employee of the
County, or officer or employee thereof, within the limits of which the work is
being performed, shall be answerable or accountable in any manner, for any
loss or damage that may happen to the work or any part thereof; or for any of
the materials or other things used or employed in performing the work; or for
injury to any person or persons, either workmen or the public, for damage to
property from any cause which might have been prevented by the Contractor,
or his/her workmen, or anyone employed by him/her, against all of which
injuries or damages to persons and property the Contractor having control over
such work must properly guard.
B. The Contractor shall be responsible for any liability imposed by law for any
damage to any person or property resulting from defects or obstructions or
from any cause whatsoever during the progress of the work or at any time
before the issuance of the Notice of Completion.
C. The Contractor shall indemnify and hold harmless the Owner, the Resident
Engineer, the Engineer of record, and all of their respective officers and
employees, from all claims, lawsuits or actions of every kind and nature
whatsoever, brought for, or on account of any injuries or damages received or
sustained by any person or persons, resulting from any act or admission by the
Contractor or his/her servants or agents, in the construction of the work or by
or in consequence of any negligence in guarding the same, in improper
materials used in its construction, or by or on account of any act or omission of
the Contractor or his/her agents in the performance of Contractor's obligations
under the Contract Documents. In addition to any remedy authorized by law,
so much of the money due the Contractor under and by virtue of the contract
as shall be considered necessary by the Owner may be retained by the Owner
until disposition has been made of such claims, lawsuits or actions for damages
as aforesaid.
2.34 WRITTEN NOTICE
Subject to any additional requirements that may be applicable to claims under the
immediately following Article 2.35 RESOLUTION OF CONTRACT CLAIMS AND
DISPUTES, formal service, when required, of written notice shall be deemed to have
been duly served if delivered in person, to the individual or member of the firm or entity
or to an officer of the corporation for whom it was intended, or if sent by registered or
certified mail to the listed address of that entity for the attention of such individual.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -41
2.35 RESOLUTION OF CONTRACT CLAIMS AND DISPUTES
A. A Claim is a demand or assertion sent by registered mail or certified mail with
return receipt requested by one (1) of the parties seeking, as a matter of right,
adjustment or interpretation of Contract terms, payment of money, extension
of time, or a request for equitable adjustment or Contract Change Order which
cannot be resolved per provisions of Section 2.25 - CHANGES TO THE
WORK. Any Claim shall be reduced to writing and filed with the Resident
Engineer, within ten (10) calendar days after the Contractor has notice of the
condition giving rise to the Claim, and final action per Section 2.25-CHANGES
TO THE WORK procedures has taken place or has been declared as such in
writing, by either party. Such ten (10)-day notice of an asserted claim is in
addition to the requirement for prompt notice required per Section 2.25 -
CHANGES TO THE WORK.
B. The Contractor shall not claim or recover any overhead cost administrative or
otherwise, particularly 'Home Office' expenses, 'Extended site overhead', or
any other overhead cost on the basis of any 'Home Office' damages formula,
'Eichleay' formula, 'Total Cost' recovery formula or any other such formula.
C. REQUIREMENTS FOR FILING A CLAIM. Claims shall be submitted to the
Resident Engineer. Claims must be filed within the time specified above, but in
no event shall any claim be considered by the Resident Engineer that is filed
later than the date of final payment of the Project. The claim shall be in writing
and shall be a sum certain if known. If unknown, Contractor shall specify the
basis for establishing the sum certain. Claim shall include a statement of the
reasons for the asserted entitlement, and include the documents necessary to
substantiate the claim. Such documents may include but are not limited to
payroll records, purchase orders, quotations, invoices, estimates,
subcontracts, daily logs, supplier contracts, subcontract billings, bid takeoffs,
equipment rental invoices, ledgers,journals, daily reports,job diaries, and any
documentation related to the requirements of Section 2.25 - CHANGES TO
THE WORK. In the case of a continuing delay, only one (1)claim is necessary.
If adverse weather conditions are the basis for a claim for additional time, such
claim shall be documented by data substantiating that weather conditions were
abnormal for the period of time and could not have been reasonably
anticipated, and that weather conditions had an adverse effect on the critical
activities on the construction schedule. The Contractor shall certify, at the time
of submission of a claim, as follows:
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -42
being the
(MUST BE AN OFFICER) of
(GENERAL CONTRACTOR),
declare under penalty of perjury under the laws of the State of
California, and do personally certify and attest that: I have thoroughly
reviewed the attached claim for additional compensation and/or
extension of time, and know its contents, and said claim is made in
good faith; he supporting data is truthful and accurate; the amount
requested accurately reflects the contract adjustment for which the
Contractor believes the Owner is liable; and, further, that I am familiar
with California Penal Code Section 72 and California Government Code
Section 12560, et seq, pertaining to false claims, and further know and
understand that submission or certification of a false claim may lead to
fines, imprisonment and/or other severe legal consequences.
By:
(Contractor's signature) (Date)
D. Nothing in this Article is intended to extend the time limit or supersede notice
requirements otherwise provided by this contract or by applicable law for the
filing of claims. Any formal claim shall be processed in accordance with the
provisions of Public Contract Code Section 9204 and Section 20104 et. seq.,
each of which establishes a process for resolution of claims, the provisions of
which are consistent with and effectively summarized by the following
1. The Owner (or his/her designee), shall review the facts pertinent to the
claim, obtain additional information deemed necessary for a decision (if
any), review recommendations of the Resident Engineer, coordinate
with the contract administrator(if any)and secure assistance from legal
and other advisors, and render a written decision on the claim within
forty-five (45) days of receipt of the claim. If additional information or
documentation is thereafter required, it shall be requested and provided
pursuant to this subdivision, upon mutual agreement of the Owner (or
his/her designee) and claimant. The Owner's (or his/her designee's)
written response to the claim, as supplemented by any additional
information and/or documentation provided by claimant, shall be
submitted to the claimant within fifteen (15) days after receipt of the
further information and/or documentation or within a period of time no
greater than that taken by the claimant in producing the additional
information, whichever is greater.
a. For claims of over fifty thousand dollars ($50,000) and less
than or equal to three hundred seventy-five thousand
dollars ($375,000), the Owner (or his/her designee), shall
respond in writing to all written claims within 60 days of
receipt of the claim, or may request, in writing, within 30
days of receipt of the claim, any additional documentation
supporting the claim or relating to defenses to the claim the
Owner (or his/her designees) may have against the
claimant.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -43
2. If the claimant disputes the written response of Owner (or his/her
designee), or Owner fails to respond within the time prescribed, the
claimant may so notify the Owner(or his/her designee), in writing, either
within fifteen (15) days of receipt of the Owner (or his/her designee's)
response or within fifteen (15)days of the Owner(or his/her designee's)
failure to respond within the time prescribed, respectively, and demand
an informal conference to meet and confer for settlement of the issues
in dispute. Upon a demand, the Owner (or his/her designee) shall
schedule a meet and confer conference within thirty (30) days for
settlement of the dispute.
3. Within ten (10) business days following conclusion of the meet and
confer conference, any unpaid portion of the claim remaining in dispute
shall be submitted to nonbinding mediation, as that term is defined by
Public Contract Code Section 9204(d)(2)(C).
4. If following the conclusion of the meet and confer conference and
mediation process, the claim or any portion thereof remains in dispute,
the claimant may file a claim pursuant to Chapter 1 (commencing with
Section 900) and Chapter 2 (commencing with Section 910) of Part 3
of Division 3.6 of Title 1 of the Government Code. For purposes of
those provisions, the running of the period of time within which a claim
must be filed shall be tolled from the time the claimant submits his/her
written claim pursuant to subdivision (a) until the time the claim is
denied, including any period of time utilized by the meet and confer
conference and mediation process as described in the immediately
preceding Paragraphs 2 and 3 of this Section D.
5. In the event of any perceived conflict between the summary of the
procedure set forth in this Article and the actual provisions of the Public
Contract Code Section 9204 and Section 20104, et seq., the statutory
provisions shall control; and in the event of any perceived conflict
between the provisions of Section 9204 and Section 20104, et seq., the
provisions of Section 9204 shall control.
E. Procedures for Civil Actions to Resolve Disputed Claims: Non-binding
Mediation: Within sixty(60) days, but no earlier than thirty (30)days, following
the filing of a responsive pleading, the court shall submit the matter to
non-binding mediation unless waived by mutual stipulation by both parties.
The mediation process shall provide for the selection within fifteen (15) days
by both parties of a disinterested third person as mediator, shall be
commenced within thirty (30) days of the submittal, and shall be concluded
within fifteen (15)days from the commencement of the mediation unless a time
requirement is extended upon a good cause shown to the court. If the parties
fail to select a mediator within the 15-day period, any party may petition the
court to appoint the mediator.
Judicial Arbitration: If the matter remains in dispute, the case shall be
submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with
Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure,
notwithstanding Section 1141.11 of the code. The Civil Discovery Act of 1986
(Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of
the Code of Civil Procedure) shall apply to any proceeding brought under this
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -44
subsection consistent with the rules pertaining to judicial arbitration. Arbitrators
shall be experienced in construction law.
Appeals: As provided by statute (specifically Public Contract Code section
20104.4(b)(3) and Code of Civil Procedure section 1141.21), any party
appealing an arbitration award who does not obtain a more favorable judgment
shall, in addition to payment of costs and fees, also pay the attorneys' fees on
appeal of the other party.
F. CLAIMS AND DISPUTES EXEMPT FROM FILING REQUIREMENTS. The
requirements and procedures imposed by this Article do not apply to:
1. Any claims by the Owner; or
2. Any claim for or respecting personal injury or death or reimbursement
or other compensation arising out of or resulting from liability for
personal injury or death; or
3. Any claim or dispute relating to stop payment requests or stop notices;
or
4. Any claim or dispute related to the approval, refusal to approve, or
substitution of Subcontractors, regardless of tier, and suppliers.
G. PAYMENT OF UNDISPUTED PORTION OF CLAIM. Owner shall pay claimant
such portion of a claim that is undisputed except as otherwise provided in the
contract.
H. CONTINUE WORK DURING DISPUTE. In the event of any disputed claim or
other dispute between the Owner and the Contractor, the Contractor will not
stop work but will prosecute the work diligently to completion in his/her manner
directed by the Owner, and the dispute shall be resolved by a court of law after
completion of the Work. However, Contractor must submit all disputes in
accordance with the provisions of this Section 2.35.
I. SUIT IN FRESNO COUNTY ONLY. Any litigation arising out of this Contract
shall be brought in Fresno County and Contractor hereby waives the removal
provisions of California Code of Civil Procedure Section 394.
2.36 PERFORMANCE BOND, LABOR AND MATERIAL PAYMENT BOND AND
WARRANTY BOND
A. The Contractor shall furnish Performance Bond in the amount of one hundred
percent (100%) of the Contract Sum, and Payment Bond in the amount of
one hundred percent (100%) of the Contract Sum and One Year Warranty
Bond in the amount of ten percent (10%) of the Final Contract Sum, which is
the cumulative amount that will have been paid to Contractor for all of the
Work performed under the Contract once the Project has been completed
and the Work has been accepted by the County.]
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -45
B. All bonds required, whether Bid bonds, Performance, Payment, Warranty or
other bonds, shall be issued by an admitted surety insurer authorized by the
California Insurance Commissioner to transact surety insurance in the state.
The same admitted surety insurer must issue the Bid Bond, Performance
Bond, Payment Bond, and Warranty Bond. The payment, performance and
warranty bonds required by these specifications will neither be accepted nor
approved by the Owner unless the bonds are underwritten by an admitted
surety and the requirements of California Code of Civil Procedure section
995.630 are met. The bonds must include a physical mailing address, phone
number, FAX number, and contract person for the admitted surety insurer. The
Owner further reserves the right to satisfy itself as to the acceptability of the
surety and the form of bond. Upon request of the Owner, the bidder must
submit the following documents:
1. The original, or a certified copy, of the unrevoked appointment, power
of attorney, bylaws, or other instrument authorizing the person who
executed the bond to do so.
2. A certified copy of the certificate of authority of the insurer issued by
the California Insurance Commissioner.
3. A certificate from the county clerk that the certificate of authority has
not been surrendered, revoked, canceled, annulled, or suspended, or
in the event that it has, that renewed authority has been granted.
4. A financial statement of the assets and liabilities of the insurer to the
end of the quarter calendar year prior to thirty (30) days next preceding
the date of the execution of the bond, in the form of an officers'
certificate as defined in Corporations Code section 173.
2.37 RIGHTS AND REMEDIES
A. The duties and obligations imposed by the Contract Documents and the rights
and remedies available hereunder shall be in addition to, and not a limitation
of, any duties, obligations, rights and remedies otherwise imposed or available
by law.
B. No action or failure to act by the Owner, or by the Resident Engineer or
Engineer of record, regarding any deficiency, breach or default in performance
by the Contractor under the Contract Documents, shall be deemed or
construed to constitute acquiescence of the Owner in connection therewith or
with regard to any subsequent deficiency, breach or default in performance by
the Contractor; nor shall any such prior act of failure to act by or on behalf of
Owner be deemed or construed as a waiver of any rights in favor of Owner
regarding any such deficiency, breach or default in performance by the
Contractor, regardless of the similarity to the prior incident or circumstance
when no action was taken regarding any alleged deficiency, breach or default
in performance by the Contractor.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -46
2.38 TIME, DELAYS AND LIQUIDATED DAMAGES
A. DEFINITIONS
1. Unless otherwise provided, the contract time is the period of time
allotted in the Contract Documents for completion of the Work,
including authorized adjustments thereto.
2. The Date of Commencement of the Work is the date established in the
Notice to Proceed.
3. The Date of Completion of the Work is the date on which the work is
certified as complete by the Resident Engineer as specified in the
Notice of Completion.
4. The term "day" as used in the Contract Documents shall mean calendar
day unless specifically designated otherwise.
B. PROGRESS AND COMPLETION
1. Time is of the essence regarding all time limits stated in the Contract
Documents. By executing the Agreement, the Contractor confirms that
the contract time is a reasonable period for performing the Work.
2. The Contractor shall begin the Work on the Date of Commencement.
The Contractor shall not knowingly, except by agreement or instruction
of the Owner in writing, prematurely commence operations on the site
or elsewhere prior to the effective date of insurance required herein to
be furnished by the Contractor. The Date of Commencement of the
Work shall not be changed by the effective date of such insurance.
3. The Contractor shall carry the Work forward expeditiously with
adequate forces and shall achieve Completion of the Work within the
contract time.
C. DELAYS AND EXTENSIONS OF TIME
1. Delays in prosecution of parts or classes of the Work that are not
demonstrated to prevent or delay completion of the entire Project or
specific milestones within the contract time are not "unavoidable
delays" for purposes of this section.
2. In all cases, the time authorized for extension of the contract time shall
be no greater than the number of days directly attributable to the event
or circumstances which causes unavoidable delay in the completion of
the Project. Contractor shall be entitled, in the case of unavoidable
delays, to an extension in the contract time, but not to any increase to
the Contract Sum. "Unavoidable delay"for this purpose shall be defined
as follows:
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -47
a. Unavailable Materials. That materials or articles called for in the
Contract Documents are not obtainable within the time required
for timely completion; provided that such materials or articles
were listed by the Contractor in the schedule required by
Section 2.17 - CONTRACTOR'S CONSTRUCTION
SCHEDULE; that the Contractor demonstrates that the
unavailability of the materials is in fact the cause for the delay,
and could not have been avoided by an appropriate adjustment
in the Construction Schedule; and that the unavailability of such
materials is due to circumstances beyond the Contractor's
control. If good cause for delay is demonstrated pursuant to this
subsection, the Owner, at its sole discretion, may grant a time
extension.
b. Force Maleure. That delays in construction have resulted from
circumstances beyond the control of the Contractor and which
the Contractor could not have provided against by the exercise
of reasonable care, prudence, foresight, and diligence.
Unavoidable delays within the meaning of this subparagraph
shall be those caused by acts of God, war, insurrection, civil
disorder, fire, floods, epidemic, or strikes.
C. Unseasonable Weather. An extension of contract time may be
granted due to weather which is unsuitable for the Work
currently in progress, upon the determination of the Owner that
the weather conditions in fact caused the delay in completion of
the Project and that such weather conditions were not, and
could not in the exercise of reasonable diligence, have been
foreseen by the Contractor. Seasonable weather that, in the
exercise of reasonable foresight and diligence, should be
expected in the area at the time of year in question is not cause
for an extension of time.
d. Time Extensions Due to Contract Change Orders or Work
Authorizations. A time extension may be granted due to
additional work that results in a delay in the Project caused by
the approval by the Owner of a Contract Change Order or Work
Authorization. The Contractor shall be entitled to a contract
time extension Change Order only when the extra Work is
demonstrated by the Contractor to have caused a delay in the
Project.
e. Owner Caused Delays. In the event that the Project is delayed
by acts of the Owner not authorized by the Contract Documents
which the Contractor demonstrates will or have caused an
unavoidable delay, the Contractor shall be entitled to a contract
time Change Order to offset the extra time incurred by the
Contractor. The Contractor will not be entitled to adjustments
in the Contract Sum. Extra time shall be limited to that which is
directly identified as critical by the delay.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -48
4. The Contractor specifically agrees that a time extension as provided
herein is its sole remedy for Owner-caused delays, and agrees to make
no claim or demand for additional damages, nor claim an acceleration
of the time for performance.
5. The Contractor shall not be entitled to any contract time extension nor
Contract Sum adjustment for alleged Owner delays if the Owner has
acted within the time limits specified by the Contract Documents.
D. NOTICE OF DELAYS
1. Contractor shall notify the Resident Engineer promptly whenever the
Contractor foresees any event or circumstance that may delay the
prosecution of the Work and in Contractor's opinion may provide
grounds for an extension, and shall in any event notify the Resident
Engineer immediately upon the occurrence of any such delay. The
Contractor shall take immediate steps to prevent, if possible, the
occurrence or continuance of the delay. If this cannot be done, the
Resident Engineer shall determine how long the delay shall continue
and to what extent the prosecution and completion of the Work are
being delayed thereby. Such notification shall specify with detail the
cause asserted by the Contractor to constitute grounds for an
extension. Failure of the Contractor to submit such a notice within ten
(10)days after the initial occurrence of the event-giving rise to the delay
shall constitute a waiver by the Contractor of any request for a time
extension, and no extension shall be granted as a consequence of such
delay.
2. If the Contractor believes that the delay in prosecution in the Work will
result in an unavoidable delay in completion of the entire Project, the
Contractor shall submit evidence to support that belief, together with its
request for a time extension. Such evidence shall include a
demonstration that the delayed portion of the Work will affect the Critical
Path Scheduling of the entire Project. The Contractor shall also submit
a proposed revised Construction Schedule, which accounts for the
delay in completion of the entire Project caused by the delay in
prosecution of part of the Project, and includes a revised Critical Path
demonstrating how the Project will be completed within the proposed
revised contract time.
E. INVESTIGATION; PROCEDURE.
1. Upon receipt of a request for Time extension, the Resident Engineer
shall conduct an investigation of the facts asserted by the Contractor to
constitute grounds for an extension. The results of this investigation
shall be reported by the Resident Engineer to the Contractor and shall
indicate whether he/she will recommend for or against such extension
to the Owner. The performance of this investigation by the Resident
Engineer shall not be construed as direction or recommendation to the
Contractor regarding scheduling of the work. Scheduling this work is
the sole responsibility of the Contractor.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 -49
2. The Resident Engineer may, in his/her sole discretion, defer this
recommendation to allow the accumulation of time extensions due to
Work Authorizations into a periodic or final Contract Change Order
request.
3. Upon receiving the Resident Engineer's recommendation to the Owner
regarding the Contractor's request for a time extension, the Contractor
may either withdraw its application for extension or request that it be
scheduled for action by the Owner. If the Owner disallows the request,
there shall be no allowance made for the time during which the request
was pending, and the Contractor shall remain obligated to complete the
Work in the time specified.
4. If the Owner approves the time extension Contract Change Order, the
new Construction Schedule submitted by the Contractor and approved
by the Owner shall be deemed to amend the original Construction
Schedule approved by the Owner; thereafter, the amended
Construction Schedule shall have the same force and effect as the
originally approved Progress Schedule.
5. The revised Construction Schedule must be submitted within seven (7)
calendar days of the date on which the Owner approves the change.
6. The Contractor agrees that the Owner's determination as to the
existence of grounds for an extension and, the duration of any such
extension, shall be final and binding upon both Owner and Contractor.
F. DISCRETIONARY TIME EXTENSION FOR BEST INTEREST OF OWNER
1. The Owner reserves the right to extend the contract time for completion
of the Work if the Director of Public Works and Planning or designee
determines that such extension is in the best interest of the Owner.
2. In the event that such discretionary extension is made at the request of
the Contractor, the Owner shall have the right to charge to the
Contractor all or any part, as the Board may deem proper, of the actual
cost to the Owner for engineering, inspection, supervision, contract
administration, incidental and other overhead expenses that accrue
during the period of such extension, and to deduct all or any portion of
such amounts from the final payment for the Work.
3. In the event such extension is ordered over the objection of the
Contractor, the Contractor shall be entitled to a Contract Change Order
adjusting the price paid to reflect the actual costs incurred by the
Contractor as a direct and proximate result of the delay, upon his/her
written application therefor, accompanied by such verification of costs
as the Resident Engineer requires. Only additional direct costs
incurred at the site will be reimbursable by Contract Change Order.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 50
G. LIQUIDATED DAMAGES
1. If the Work is not completed by Contractor in the time specified in the
Work Order or within any period of extension authorized pursuant to
this Article, the Contractor acknowledges and admits that the Owner
will suffer damage, and that it is impracticable and infeasible to fix the
amount of actual damages. Therefore, it is agreed by and between the
Contractor and the Owner that the Contractor shall pay to the Owner
as fixed and liquidated damages, and not as a penalty, the sum
specified in Section 005213, Agreement, Article III for each calendar
day of delay until the Work is completed and accepted, and that both
the Contractor and the Contractor's surety shall be liable for the total
amount thereof, and that the Owner may deduct said sums from any
monies due or that may become due to the Contractor.
2. This liquidated damages provision shall apply to all delays of any nature
whatsoever, save and except only unavoidable delays approved by the
Owner pursuant to the provisions of Article 2.38.C.2 hereinabove, or
discretionary time extensions approved by the Board of Supervisors
pursuant to the provisions of Article 2.38.F hereinabove.
H. EXTENSION OF TIME NOT A WAIVER.
1. Any extension of contract time granted pursuant to this Article shall not
constitute a waiver by the Owner, nor a release of the Contractor, from
his/her obligations to perform the Work within the allotted contract time.
2. Granting of a time extension due to one (1) circumstance on one (1)
request therefore shall not constitute a granting by the Owner of an
extension of time for any other circumstance or the same circumstance
occurring at some other time, and shall not be interpreted as a
precedent for any other request for extension.
2.39 PROTECTION OF PERSONS AND PROPERTY
A. SAFETY PRECAUTIONS AND PROGRAMS
The Contractor shall be responsible for initiating, maintaining and supervising
all safety precautions and programs in connection with the Work.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 51
B. SAFETY OF PERSONS AND PROPERTY
The Contractor shall take all reasonable precautions for the safety of, and shall
provide all reasonable protection to prevent damage, injury or loss to:
1. All employees on the Work and all other persons who may be affected
thereby;
2. All the work and all materials and equipment to be incorporated therein,
whether in storage or off the site, and that is under the care, custody or
control of the Contractor or any of the Contractor's Subcontractors or
Sub-subcontractors;
3. Other property at the site or adjacent thereto, including trees, shrubs,
lawns, walks, pavements, roadways, structures and utilities not
designated for removal, relocation or replacement in the course of
construction; and
4. The work of the Owner or other separate contractors.
C. The Contractor shall give all notices and comply with all applicable laws,
ordinances, rules, regulations and lawful orders of any public authority bearing
on the safety of persons or property or their protection from damage, injury or
loss.
D. The Contractor shall erect and maintain, as required by existing conditions and
the progress of the Work, all reasonable safeguards for safety and protection,
including posting danger signs and other warnings against hazards,
promulgating safety regulations and notifying owners and users of adjacent
facilities.
E. When the use or storage of explosives or other hazardous materials or
equipment is necessary for the execution of the Work, the Contractor shall
exercise the utmost care and shall carry on such activities under the
supervision of properly qualified personnel.
F. The Contractor shall promptly remedy all damage or loss to any property
referred to above caused in whole or in part by the Contractor, any
Subcontractor, any Sub-subcontractor, anyone directly or indirectly employed
by any of them, or any one for whose acts any of them may be liable, and for
which the Contractor is responsible under the above noted clauses, except
damage or loss attributable solely to the acts or omissions of the Owner, the
Resident Engineer, or anyone directly or indirectly employed by any of them,
or by anyone for whose acts any of them may be liable, and not attributable in
any degree to the fault or negligence of the Contractor. The foregoing
obligations of the Contractor are in addition to the Contractor's obligations
under the Indemnification provisions provided herein.
G. The Contractor shall designate a responsible member of the Contractor's
organization at the site whose duty shall be the prevention of accidents. This
person shall be the Contractor's superintendent unless otherwise designated
by the Contractor in writing to the Owner and the Resident Engineer.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 52
H. The Contractor shall not load or permit any part of the Work to be loaded in a
manner that could endanger its safety or pose a risk to anyone working at the
Project site.
I. EMERGENCIES
In any emergency affecting the safety of persons or property the Contractor
shall act, at the Contractor's discretion, to prevent threatened damage, injury
or loss. Any additional compensation or extension of time claimed by the
Contractor on account of emergency work shall be determined as provided in
the provisions herein for Changes in the Work.
2.40 INSURANCE
A. CONTRACTOR'S INSURANCE
1. Bidders' attention is directed to the insurance requirements below. It is highly
recommended that Bidders confer with their respective insurance carriers or brokers
to determine in advance of bid submission the availability of the insurance certificates
and endorsements required below. A bidder who is awarded a contract and thereafter
fails to comply strictly with the insurance requirements, will be deemed to be in default
of its obligations.
2. Contractor shall procure and maintain for the duration of the Contract, and for 3 years
thereafter, insurance against claims for injuries to persons or damages to property
which may arise from or in connection with the performance of the work hereunder by
the Contractor, his agents, representatives, employees, or subcontractors. The cost of
such insurance shall be included in the Contractor's bid.
3. No later than ten (10) calendar days following the Award of the Contract, and prior to
execution of the Agreement for Construction by the Owner, the Contractor shall submit
certificates of insurance, signed by an authorized agent of the insurer, attesting to
insurance coverage of the Contractor as required by this Article.
B. MINIMUM SCOPE AND LIMITS OF INSURANCE
Coverage shall be at least as broad as:
1. Commercial General Liability (CGL): Insurance Services Office (ISO) Form CG
00 01 covering CGL on an "occurrence" basis, including products and completed
operations, property damage, bodily injury and personal & advertising injury with
limits no less than one million dollars ($1,000,000) per occurrence and an annual
aggregate of two million dollars ($2,000,000). If a general aggregate limit applies,
either the general aggregate limit shall apply separately to this project/location
(ISO CG 25 03 or 25 04) or the general aggregate limit shall be no less than two
million dollars ($2,000,000). The umbrella or excess policy of ten million dollars
($10,000,000) must contain a clause stating that it takes effect (drops down) in
the event the primary limits are impaired or exhausted.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 53
2. Automobile Liability: Insurance Services Office (ISO) Form CA 0001 covering
Code 1 (any auto), with limits no less than one million dollars ($1,000,000) per
accident for bodily injury and property damage. Coverage should include owned
and non-owned vehicles used in connection with this Agreement and all
applicable endorsements.
3. Workers' Compensation insurance as required by the State of California, with
Statutory Limits, and Employers' Liability insurance with a limit of no less than
one million dollars ($1,000,000) per accident for bodily injury or disease.
4. If Contractor is a licensed professional or employs professional staff, (e.g.,
Engineer of record, Resident Engineer, Surveyor, etc.) in providing services,
Professional Liability with limits no less than $1,000,000 per occurrence or claim,
and $3,000,000 annual aggregate.
5. Builder's Risk (Course of Construction) insurance utilizing an "All Risk" (Special
Perils) coverage form, with limits equal to the completed value of the project and
no coinsurance penalty provisions.
If Contractor maintains broader coverage and/or higher limits than the minimums shown
above, the Owner requires and shall be entitled to the broader coverage and/or the higher
limits maintained by the Contractor. Any available insurance proceeds in excess of the
specified minimum limits of insurance and coverage shall be available to the Owner.
Self-Insured Retentions
Self-insured retentions must be declared to and approved by the Owner. At the option of
the Owner, either: the Contractor shall obtain coverage to reduce or eliminate such self-
insured retentions as respects the Owner, its officers, officials, employees, and volunteers;
or the Contractor shall provide a financial guarantee satisfactory to the Owner
guaranteeing payment of losses and related investigations, claim administration, and
defense expenses. The policy language shall provide, or be endorsed to provide, that the
self-insured retention may be satisfied by either the named insured or Owner.
C. OTHER INSURANCE PROVISIONS
Contractor's insurance policies are to contain, or be endorsed to contain, the following
provisions:
1. The coverage shall contain no special limitations on the scope of protection
afforded to the Owner, its officers, officials, employees or volunteers.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 54
2. The County of Fresno, its officers, officials, employees, and volunteers are to be
named individually and collectively, as additional insureds on the CGL policy with
respect to liability arising out of work or operations performed by or on behalf of
the Contractor including materials, parts, or equipment furnished in connection
with such work or operations and automobiles owned, leased, hired, or borrowed
by or on behalf of the Contractor. The coverage shall contain no special
limitations on the scope of protection afforded to the Owner, its officers, officials,
employees or volunteers.
3. The insurer shall agree to waive all rights of subrogation against the Owner, its
officers, officials, employees and volunteers for losses arising from work
performed by the Contractor for the Owner
4. For any claims related to this project, the Contractor's insurance coverage shall
be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as
respects the Owner, its officers, officials, employees, and volunteers. Any
insurance or self-insurance maintained by the Owner, its officers, officials,
employees, or volunteers shall be excess of the Contractor's insurance and shall
not contribute with it.
5. Any failure to comply with reporting provisions of the policies shall not affect
Coverage provided to the Owner, its officers, officials, employees, agents,
Engineers, Consulting Engineers, or volunteers.
6. The Contractor's insurance shall apply separately to each insured against whom
claim is made or suit is brought, except with respect to the limits of the insurer's
liability.
7. All Contractor's insurance policies for coverage required under this agreement
shall not be cancelled or changed without a minimum of thirty (30) days advance
written notice given to Owner.
8. The insurer shall agree to waive all rights of subrogation against the Owner, its
officers, officials, employees and volunteers for losses arising from work
performed by the Contractor for the Owner.
9. The Builder's Risk (Course of Construction) policy shall be an "All Risk" (Special
Perils) coverage form, with limits equal to the completed value of the project and
no coinsurance penalty provisions. All subcontractors shall be insured to the
extent of their portion of the work under the Contractor. The Contractor shall
request, and is responsible to confirm with its insurer, that the County of Fresno
and all subcontractors are named, both as additional insured and as additional
loss payees, on the Builder's Risk insurance policy. The Contractor and all
subcontractors waive all rights, each against the others, for damages arising from
perils covered by the insurance required under the terms of this article, except
such rights as they may have to the proceeds of the Builder's Risk insurance
obtained and maintained by the Contractor.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 55
D. ACCEPTABILITY OF INSURERS
Contractor shall obtain the policies and coverages specified herein from an admitted
insurer in good standing with and authorized to transact business in this state by the
California Department of Insurance, and having a Best's rating of no less than A FSC
Vill.
E. SUBCONTRACTORS
Contractor shall include all Subcontractors as insured under its policies or shall furnish
separate certificates and endorsements for each Subcontractor.
F. EVIDENCE OF COVERAGE
Within ten (10) days of bid award, Contractor shall furnish the Owner with original
Certificates of Insurance including all required amendatory endorsements (or copies of
the applicable policy language effecting coverage required by this Article 2.40) and a
copy of the Declarations and Endorsement Page of the CGL policy listing all policy
endorsements to Owner. However, failure to obtain the required documents prior to the
work beginning shall not waive the Contractor's obligation to provide them. The Owner
reserves the right to require complete, certified copies of all required insurance policies,
including endorsements, required by these specifications, at any time.
Certificates of Insurance and Endorsements for all policies must be signed by a person
authorized by the insurer to bind coverage on its behalf, indicate the name and address
of the official who will administer this contract, state that such insurance coverages have
been obtained and are in full force and effect, and clearly indicate that coverage shall not
be suspended, voided, canceled by either party, reduced in coverage or in limits except
after thirty (30) days' prior written notice has been given to the Owner.
Commercial General Liability Endorsements must name the County of Fresno, its officers,
agents and employees, individually and collectively, as additional insured, but only insofar
as the operations under this Agreement are concerned; that such coverage for additional
insured shall apply as primary insurance and any other insurance, or self-insurance,
maintained by Owner, its officers, agents and employees, shall be excess only and not
contributing with insurance provided under Contractor's policies herein.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 56
2.41 UNCOVERING WORK
A. This Section shall apply to any Work installed and covered up by the
Contractor that is required by the Building Code or other statutory or
regulatory requirement to undergo inspection or special inspection and/or
testing approval by an appropriate official representing the Owner or other
public authority having jurisdiction to conduct such inspection and/or testing.
Work covered up by the Contractor, Contractor's Subcontractor's or
Suppliers prior to inspection/special inspection and/or testing approval shall
be uncovered and repaired or replaced after inspection approval at the sole
expense of the Contractor. This shall apply to all labor and material needed
to complete both physical and cosmetic repairs, and any additional
inspection costs associated with restoring the Work.
B. This Section also shall apply to any Work installed and covered up by the
Contractor, Contractor's Subcontractor's or Suppliers that is determined by
the Owner or its Resident Engineer, during construction or within the
Warranty period, to be defective, broken or inoperative. Work covered up by
the Contractor, Contractor's Subcontractor's or Suppliers that is found to be
defective, broken or inoperative shall be uncovered and repaired or replaced
at the sole expense of the Contractor. This shall apply to all labor and
material needed to complete both physical and cosmetic repairs, and any
additional inspection costs associated with restoring the Work.
2.42 CORRECTION OF WORK
A. The Contractor shall promptly correct all Work rejected by the Resident
Engineer as defective or as failing to conform to the Contract Documents,
whether or not fabricated, installed or completed. The Contractor shall submit
a plan of action, within twenty-four(24) hours of notification of the rejected work
by the Resident Engineer,for correcting the rejected work. The Contractor shall
bear all costs of correcting such rejected Work, including compensation for the
additional architectural and/or engineering services made necessary thereby.
B. If, within 365 Calendar Days after the date of acceptance of the Work as
specified in the Notice of Completion, or designated portion thereof, or within
365 Calendar Days after acceptance by the Owner of designated equipment,
or within such longer period of time as may be prescribed by the terms of any
applicable special warranty required by the Contract Documents, any of the
Work is found by Owner to be defective or not in accordance with the Contract
Documents, the Contractor shall correct it promptly after receipt of a written
notice from the Owner to do so, unless the Owner has previously given the
Contractor a written acceptance of such condition. This obligation shall survive
both final payment for the Work or designated portion thereof and termination
of the Contract. The Owner shall give such notice promptly after discovery of
the condition.
C. The Contractor shall, at his/her sole expense, remove from the site all portions
of the Work that are defective or nonconforming and which have not been
corrected under Articles 2.32, 2.42.A, and 2.42.13, unless the Owner waives
removal.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 57
D. If the Contractor fails to submit a plan of action, within twenty-four (24) hours
of notification of the rejected work by the Resident Engineer, for correcting the
rejected work, or fails to correct defective or nonconforming Work as provided
herein in Articles 2.32, 2.42.A, and 2.42.13, the Owner may correct it in
accordance with Article 2.08.C.
E. If the Contractor does not take action under the plan to initiate such correction
of such defective or nonconforming Work within ten (10) days of written notice
from the Resident Engineer, the Owner may remove it and may store the
materials or equipment at the expense of the Contractor. If the Contractor does
not pay the cost of such removal and storage within ten (10) days thereafter,
the Owner may, upon ten (10) additional days' written notice, sell such Work
at auction or at private sale and shall account for the proceeds thereof, after
deducting all the costs that should have been borne by the Contractor,
including compensation for the Resident Engineer, Engineer of record, or other
Professional's additional services made necessary thereby. If such proceeds
of sale do not cover all costs that the Contractor should have borne, the
difference shall be charged to the Contractor and an appropriate Supplemental
Work Order shall be issued. If the payments then or thereafter due the
Contractor are not sufficient to cover such amount, the Contractor shall pay the
difference to the Owner.
F. The Contractor shall bear the cost of making good all work of the Owner or
separate contractors destroyed or damaged by such correction or removal.
G. Nothing contained in this Section 2.42 shall be construed to establish a period
of limitation with respect to any other obligation which the Contractor might
have under the Contract Documents, including Section 2.32 hereof. The
establishment of the time periods noted in this Section 2.42, or such longer
period of time as may be prescribed by law or by the terms of any warranty
required by the Contract Documents, relates only to the specific obligation of
the Contractor to correct the defective or nonconforming Work, and has no
relationship to the time within which the Contractor's obligation to comply with
the Contract Documents may be sought to be enforced, nor to the time within
which proceedings may be commenced to establish the Contractor's liability
with respect to the Contractor's obligations other than specifically to correct the
defective or nonconforming Work.
2.43 ACCEPTANCE OF DEFECTIVE OR NONCONFORMING WORK
If the Owner prefers to accept defective or nonconforming Work, the Owner may do
so instead of requiring its removal and correction, in which case a Contract Change
Order will be issued to reflect a reduction in the Contract Sum where appropriate and
equitable. Such adjustment shall be given effect whether or not final payment has
been made. The Resident Engineer shall determine the amount of reduction in the
Contract Sum.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 58
2.44 TERMINATION BY THE OWNER
A. If the Contractor is adjudged bankrupt, or makes a general assignment for the
benefit of creditors, or if a receiver is appointed on account of the Contractor's
insolvency, or stop notices are served upon the Owner, or if the Contractor
persistently or repeatedly refuses or fails, except in cases for which extension
of time is provided, to supply enough properly skilled workers or proper
materials, or fails to make prompt payment to Subcontractors or for materials
or labor, or persistently disregards applicable laws, ordinances, rules,
regulations or orders of any public authority having jurisdiction, or otherwise is
guilty of a substantial violation of a provision of the Contract Documents, and
fails after written notice to commence and continue correction of such default,
neglect or violation with diligence and promptness, the Owner upon
certification by the Resident Engineer that sufficient cause exists to justify such
action, may, after an additional written notice and without prejudice to any other
remedy the Owner may have, terminate the Contract and take possession of
all materials, equipment, tools, construction equipment and machinery thereon
owned by the Contractor and may finish the Work by whatever methods the
Owner may deem expedient. In such case the Contractor shall not be entitled
to receive any further payment until the Work is finished.
B. If the unpaid balance of the Contract Sum exceeds the costs of finishing the
Work, including compensation for the Resident Engineer's and Engineer of
record's additional services made necessary thereby, Contractor will only be
paid for his/her actual unpaid costs from such excess. If such costs exceed
the unpaid balance, the contractor shall pay the difference to the Owner. The
amount to be paid to the Contractor or to the Owner, as the case may be, shall
be certified by the Resident Engineer, upon application, in the manner provided
in Section 2.24 and this obligation for payment shall survive the termination of
the Contract.
2.45 SUBSTITUTION OF MATERIALS
A. When a specific manufacturer,trade name or material is specified, or indicated,
it is to establish a standard of quality and shall not be construed as limiting
competition. The intent of the Contract Documents is to specify high-grade
standard material and equipment, and it is not the intent of these Contract
Documents to exclude or omit the products of any responsible manufacturer, if
such products are equally acceptable in terms of quality, finish, performance,
durability, and serviceability, in the judgment of the Owner and the Engineer of
record, to those specified herein. Wherever an article, or any class of
materials, is specified by the trade name or by the name of any particular
patentee, manufacturer or dealer, it shall be taken as intending to mean and
specify the article of material described or any other equal thereto in quality,
finish, performance, durability, and serviceability, in the judgment of the Owner
and the Engineer of record, for the purpose for which it is or they are intended.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 59
B. If the Contractor desires to use material or equipment other than that specified,
he/she shall submit a request for approval of such substitution, in writing, to
the Resident Engineer by no later than 10 days prior to bid opening.
Substitution requests will not be considered if received after the time stipulated.
C. The Owner does not guarantee that alternative articles, components, materials
or equipment other than the item specified by trade name or other specific
identification, will fit within the design parameters of the Project without
alteration of the Project design by the Contractor.
D. The Owner has the right to reject any proposed alternative material which
requires alteration of the project design which impacts the safety of the public
or the user of a completed facility. If the proposed alternative material requires
alteration of the design of the Project or any aspect thereof and said alterations
are acceptable to the Owner,the Contractor shall be responsible for performing
said alterations at no additional cost to the Owner.
E. Submittals for approval of substitute materials shall contain sufficient detailed
information, descriptive brochures, drawings, samples or other data as is
necessary to provide a detailed side-by-side comparison to the specified
materials. It is the sole responsibility of the Contractor to submit complete
descriptive and technical information so the Resident Engineer can make
proper appraisal. Lack of either proper or sufficient information shall constitute
cause for rejection. Reference to product data will not be acceptable.
F. It is the Contractor's responsibility to confirm and correlate all quantities and
dimensions and coordinate with all trades whose work may be affected by the
requested substitution.
2.46 REFERENCE TO STANDARDS
A. Reference to known standards shall mean and intend the latest edition or
amendment published prior to date of these Specifications, unless specifically
indicated otherwise, and to such portions of it that relate and apply directly to
the material or installation called for on the Project.
B. Where material is specified solely by reference to standard specifications, the
Contractor shall, if requested by the Resident Engineer, submit to the Resident
Engineer for his/her approval, data on all such material proposed to be
incorporated into the Work of the Contractor, listing the name and address of
the vendor, the manufacturer or producer, and the trade or brand names of
such materials.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 60
2.47 SPECIFICATIONS
A. The Specifications are organized into Divisions, Sections, and Trade headings
based on the Construction Specifications Institute's Master format and the
Master format numbering system. This organization shall not control the
Contractor in dividing the Work among Subcontractors or in establishing the
extent of the Work to be performed by any trade. The Contractor shall be
responsible for examining all Sections of the Specifications for inter-related
items of the Work, and for furnishing each item identified or specified.
B. No responsibility will be assumed by the Owner, Engineer of record or the
Resident Engineer for omissions or duplications by the Contractor in the
completion of the Contract due to any alleged discrepancy in the arrangement
of the material in these Specifications, nor shall any such segregation of work
and materials operate to make the Resident Engineer an arbiter in defining the
limits to the agreements between the Contractor and his/her Subcontractors or
suppliers.
C. The misplacement, addition or omission of any letter,word or punctuation mark
shall in no way damage the true spirit, intent or meaning of these
Specifications.
D. The words "shown", "indicated", "noted", "scheduled" or words of that effect
shall be understood to mean that reference is made to Drawings
accompanying these Specifications.
E. Where reference herein is made to colors or finishes "as selected", the
reference is to the Engineer of record with concurrence by the Owner.
2.48 APPROVED APPLICATORS
A. Where specific instructions in these Specifications require that a particular
product and/or materials be installed and/or applied by an "approved
applicator" of the manufacturer, it shall be the Contractor's responsibility to
ensure that any Subcontractors used for such work be approved applicators.
B. Contractor accordingly shall bear any and all costs, and shall reimburse Owner
for any such costs incurred by Owner, resulting from Contractor's failure to
insure the use of an "approved applicator".
2.49 DELIVERY AND STORAGE OF MATERIALS
A. Deliver all manufactured materials in the original packages, containers or
bundles (with the seals intact), bearing the name or identification mark of all
manufacturers.
B. Deliver fabrications in as large assemblies as practicable and where specified
to be shop-primed or shop-finished; they shall be packaged or crated as
required to preserve such priming or finish intact and free from abrasion.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 61
C. Store all materials in such manner as necessary to properly protect same from
damage, as materials or equipment damaged by handling, weather, dirt or from
any other cause will not be acceptable.
D. Store materials so as to cause no obstructions (i.e. stored off all sidewalks and
other walkways, roadways, and underground services). The Contractor shall
be responsible for protecting from damage all material and equipment
furnished under the Contract.
2.50 QUALITY OF WORK
A. Where not more specifically described in any of the various Sections of these
Specifications, the quality of work shall conform to all of the methods and
operations of best standards and accepted practices of the trade or trades
involved, and shall include all items of fabrication, construction, or installation
regularly furnished or required for completion of the work(including any finish),
and for successful operation as intended of the Project and the component
thereof corresponding to that work.
B. All Work shall be executed by mechanics skilled in their respective lines of
work.
C. When completed, all parts shall have been durably and substantially built and
shall present a neat, finished appearance.
2.51 HOURS OF WORK
A. Eight (8) hours of labor shall constitute a legal day's work upon all work done
hereunder, and it is expressly stipulated that no worker employed at any time
by the Contractor, or by a Subcontractor under this Contract, upon the Work,
shall be required or permitted to work thereon more than eight (8) hours in any
one (1) calendar day and forty(40) hours in any one (1) calendar week, except
as provided in Sections 1810-1815 inclusive, of the Labor Code of the State of
California, all the provisions of which are deemed to be incorporated herein as
if set forth in full; and it is further expressly stipulated that for each and every
violation of said last named stipulation, said Contractor shall forfeit, as a
penalty to the Owner, fifty dollars ($50.00) for each worker employed by the
Contractor in the execution of this Contract, for each calendar day during which
said worker is required or permitted to labor more than eight (8) hours in any
one (1) calendar day and forty (40) hours in any one (1) calendar week in
violation of any of said provisions of the Labor Code.
B. Notwithstanding the above stipulations, pursuant to Section 1815 of the Labor
Code, work performed by employees of contractors in excess of eight(8) hours
per day and forty (40) hours during any one (1)week shall be permitted on the
Project upon compensation for all hours worked in excess of eight (8) hours
per day at not less than one and a half(1 1/2) times the basic rate of pay.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 62
2.52 WAGE RATES AND RELATED LABOR COMPLIANCE REQUIREMENTS
A. This Project is subject to compliance monitoring and enforcement by the
Department of Industrial Relations (DIR), including the obligation to submit
certified payroll records directly to the DIR Compliance Monitoring Unit (CMU)
at least monthly using the CMU's eCPR system. Detailed information may be
obtained on the State of California's Department of Industrial Relations
website, www.dir.ca.gov/dlse/cmu/CMU.
The Contractor shall also submit certified payroll records of the Contractor,
Subcontractors and all Sub-subcontractors of any tier to the Inspector of
Record at least monthly.
B. Contractor shall, and shall cause each of its Subcontractors (as defined in
Labor Code section 1722.1) to provide written proof that they are currently
registered with the California Department of Industrial Relations at the time of
bid submittal, and have paid the applicable annual fee and are thereby qualified
to submit a bid and to perform public work pursuant to Labor Code section
1725.5, prior to award of this Contract or any subcontract hereunder. No bid
shall be accepted, nor shall this Contract or any subcontract hereunder, be
entered into without such proof.
C. Pursuant to Section 1770-1780 of the Labor Code of the State of California,
the Director of the Department of Industrial Relations has determined the
general prevailing rates of wages and rates for legal holidays and overtime in
the locality in which this work is to be performed, which under Labor Code
Section 1773.1 are deemed to include employer payments for health and
welfare, pension, vacation, travel time and subsistence pay, and
apprenticeship or other authorized training programs, for each craft or type of
worker or mechanic needed to perform this contract. Said wage rates are
available only at the Fresno County Department of Public Works and Planning,
Design Division, and will be made available to any interested person upon
request. Minimum wage rates for this Project, as predetermined by the
Secretary of Labor, are set forth in the Special Provisions. If there is a
difference between the minimum wage rates predetermined by the Secretary
of Labor and the Prevailing Wage Rates predetermined by the Director of the
Department of Industrial Relations of the State of California for similar
classifications of labor, the contractor and his subcontractors shall pay not less
than the higher wage rate.
D. It shall be mandatory upon the Contractor to whom the Contract is awarded,
and upon any Subcontractor under him/her to pay not less than the said
specified rates to all laborers, workers, and mechanics employed by them in
the execution of the Contract, and to pay all laborers, workers and mechanics
not less often than once weekly. The Contractor to whom the Contract is
awarded shall post a copy of the determination of prevailing wages at the job
site. The Contractor shall require all Subcontractors to comply with Sections
1770-1780 of the Labor Code of the State of California and shall insert into
every subcontract the requirements contained therein.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 63
E. The Contractor shall comply with Labor Code Section 1775. In accordance
with said Section 1775, it is hereby further agreed that the Contractor shall
forfeit to the Owner, as a penalty, fifty dollars ($50.00)for each laborer, worker,
or mechanic employed for each calendar day or portion thereof, who is paid
less than the said stipulated rates for any work done under the Contract, by
him/her or by any Subcontractor under him/her. The difference between said
stipulated rates and the amount paid to each worker for each calendar day or
portion thereof for which each worker was paid less than said stipulated rate
shall be paid to each worker by the Contractor. The Contractor, and each
Subcontractor, shall keep or cause to be kept an accurate record showing the
name, address, social security number, work classification, straight time and
overtime hours worked each day and week, and the actual per diem wages
paid to each journeyman, apprentice, worker or other employee employed by
him/her or her in connection with the public work. The records shall be open
at all reasonable hours to the inspection of the Owner, to its officers and
agents, and to the Division of Labor Law Enforcement of the State Department
of Industrial Relations, its deputies and agents, or as otherwise provided by
applicable law (including but not limited to Labor Code 1776).
F. In case it becomes necessary for the Contractor or any Subcontractor to
employ on the Work under this Contract any person in a trade or occupation
(except executive, supervisory, administrative, clerical or other non-manual
workers as such) for which no minimum wage rate is specified, the Contractor
shall immediately notify the Owner who shall promptly thereafter determine the
prevailing rate for such additional trade or occupation from the time of the initial
employment of the person affected and during the continuance of such
employment.
2.53 APPLICATION OF HIGHEST STANDARDS AND REQUIREMENTS
Whenever two (2) or more standards or requirements appear in these General
Conditions or in any other part of the Contract Documents that form the Contract, the
highest standard or requirement shall be applied and followed in the performance
under this Contract.
2.54 NONDISCRIMINATION IN EMPLOYMENT
Contractor shall comply with all Federal and State Laws prohibiting discrimination in
employment, including the following:
A. California Labor Code Section 1735, which prohibits discrimination in
employment on any basis listed in subdivision (a) of Section 12940 of the
Government Code, as those bases are defined in Sections 12926 and 12926.1
of the Government Code, except as otherwise provided in Section 12940 of
the Government Code, and applies to all employers, employment agencies and
labor organizations.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 64
B. Title VII of the Federal 1964 Civil Rights Act (42 U.S.C. Section
2000e - 2000e- 17)which prohibits employment discrimination on the basis of
race, color, sex, religion, or national origin, and applies to all employers that
employ at least fifteen (15)workers during each working day in each of twenty
(20) or more calendar weeks in the current or preceding year.
C. In addition to these two (2) laws of general application listed in the immediately
preceding paragraphs A and B, there are other Federal and State laws that
prohibit employment discrimination in particular cases.
D. The Owner is an Affirmative Action Employer and expects all of its contractors
and suppliers to familiarize themselves with, and comply with, all applicable
laws relating to employment discrimination.
E. To the extent required by law, the Contractor shall meet all requirements of law
relating to the participation of minority, women, and disabled veteran business
enterprise contracting goals, and shall comply with Public Contract Code
10115 et seq. and all applicable regulations. Contractor further agrees that,
when required, Contractor shall ensure compliance by all Subcontractors and
shall complete all forms required by all agencies exercising jurisdiction over
the Project.
2.55 APPRENTICES
A. Pursuant to Sections 1770-1780 of the Labor Code of the State of California,
the Director of the Department of Industrial Relations has determined the
general prevailing rate of wages in the locality for each craft or type of worker
needed to execute the work. Said wage rates pursuant to Section 1773.2 of
the Labor Code are on file with the Clerk of the Fresno County Board of
Supervisors, and will be made available to any interested person on request.
A copy of this wage scale may also be obtained at the following Web Site:
www.dir.ca.gov/dlsr.
B. Pursuant to Section 1775 of the Labor Code of the State of California, nothing
in this Article shall prevent the employment of properly registered apprentices
upon public works. Every such apprentice shall be paid the standard wage paid
to apprentices under the regulations of the craft or trade at which he/she is
employed, and shall be employed only at the work of the craft or trade to which
he/she is registered.
C. Only apprentices, as defined in Section 3077, who are in training under
apprenticeship standards and written apprentice agreements under Chapter 4
(commencing at Section 3070), Division 3, of the Labor Code, are eligible to
be employed on public works. The employment and training of each apprentice
shall be in accordance with the provisions of the apprenticeship standards and
apprentice agreements under which he/she is training.
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 65
D. Fresno County is committed to increasing the availability of employment and
training opportunities, with particular attention to the plight of those who are
most economically disadvantaged. In an effort to advance that purpose, the
County will require that the Contractor and each subcontractor employed on
this Project shall use their best efforts to ensure that thirty-three percent (33%)
of apprentice hours, as determined by California Labor Code Section 1777.5
for each contractor and subcontractor of any tier on this Project, are performed
by qualified participants in state approved apprenticeship programs who also
are current or former "Welfare-to-Work" participants in the CaIWORKs
program. Provided, that nothing contained in this Paragraph D shall be
interpreted to relieve or in any way diminish the obligation of the Contractor
and each subcontractor to comply fully with all applicable apprenticeship laws
in accordance with the California Labor Code and the California Code of
Regulations; and accordingly such requirements as are contractually imposed
by this Paragraph D shall be in addition to such legally mandated requirements,
and applicable only to the extent fully consistent therewith.
E. Incentives whereby the Contractor or Subcontractor receives partial
reimbursement for the wages paid to apprentices who qualify may be available.
The incentive program is administered by the County of Fresno, Department
of Social Services. For questions regarding the incentive program, contact the
Department of Social Services at (559) 230-4008.
2.56 PROVISIONS REQUIRED BY LAW DEEMED INSERTED
Every provision of law and clause required by law to be inserted in this contract shall
be deemed to be inserted, and this contract shall be read and enforced as though it
were included, and if through mistake or otherwise any provision is not inserted or is
not correctly inserted, upon application of either party the contract shall be amended
to make the insertion or correction.
2.57 DRUG FREE WORKPLACE CERTIFICATION
A. The Contractor shall comply with Government Code Section 8355 in matters
relating to providing a drug-free workplace.
B. The Contractor shall publish a statement notifying employees that unlawful
manufacture, distribution, dispensation, possession, or use of controlled
substance is prohibited and specifying actions to be taken against employees
for violations, as required by Government Code Section 8355(a).
CONTRACT# 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER GENERAL CONDITIONS
REEDLEY, CA. SECTION 007200 - 66
C. The Contractor shall establish a Drug-Free Awareness Program as required
by Government Code 8355(a)(2), to inform employees about all of the
following:
1. The dangers of drug abuse in the workplace,
2. The Contractor's policy for maintaining a drug-free workplace,
3. Any available counseling, rehabilitation and employee assistance
programs,
4. Penalties that may be imposed upon employees for drug abuse
violations.
D. Provide as required by Government Code 8355(c), that everyone who provides
work under the Agreement.
1. Will receive a copy of the company's drug-free policy statement, and
2. Will agree to abide by the terms of the Contractor's statement as a
condition of employment on the contract.
2.58 BUILDING PERMIT AND OTHER PERMITS
The Building permit shall be obtained and paid for by the Owner. All other required
permits are the responsibility of the Contractor to obtain. Fees for all other required
permits shall be reimbursed to the Contractor at actual cost when the County is
presented with a valid receipt.
2.59 CODES AND REGULATIONS
All work, materials and equipment shall be in full compliance with the California
Building Code; California Plumbing Code; California Electrical Code; California
Mechanical Code; California Fire Code; California Energy Code; as those codes may
be amended from time to time; Cal/OSHA Safety Regulations; and all Federal, State
and Local laws, ordinances, regulations and Fresno County Charter provisions in
effect and applicable in the performance of the work.
END OF SECTION
CONTRACT# 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work under separate contracts.
5. Owner-furnished products.
6. Access to site.
7. Work restrictions.
8. Specification and drawing conventions.
9. Miscellaneous provisions.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the
following:
1. Design, site preparation, and construction of a 250-foot tall, 3-sided self-
supporting microwave tower and its corresponding equipment
2. Construction of a 1,011 sqft. equipment shelter per the plans and specifications
and all associated site work including fencing.
3. The project also includes, but is not limited to, the installation of the Owner
supplied electrical back-up generator as well as Contractor supplied and
installed communication equipment as specified in the plans and specifications.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
1.4 PHASED CONSTRUCTION
A. The Work shall be conducted in 4 phases, with each phase substantially complete as
indicated:
1. Phase 1: Submittals
Work in this phase shall commence no later than 14 business days after the pre-
construction conference.
Complete this phase thirty (30) working days from the day the Notice to Proceed
is issued.
The Engineer shall have a maximum of ten (10) working days in which to review
and approve or reject each submittal from the Contractor. In the event that the
Engineer rejects any of the Contractor's initial submittals, the Engineer shall have
a maximum of ten (10) working days in which to review and approve or reject
each re-submittal from the Contractor. The ten (10) working day time period for
the Engineer's review shall commence on the day upon which the Engineer re-
ceives the submittal or re-submittal in question.
In the event that the Engineer's review of a submittal or re-submittal requires in
excess of ten (10)working days, the Engineer shall extend the number of work-
ing days allowed for the completion of the first order of work by one working day
for each working day of delay in the Engineer's completion of the review.
Pay the County of Fresno the sum of Three (3,000) dollars per day each and
every calendar days delay in excess of the number of working days prescribed.
2. Phase 2: Construction of the Equipment Shelter, Tower foundations and all
underground utilities.
Complete this phase eighty (80) working days from the date of the Notice to
Proceed is issued.
The Engineer, in their sole discretion, may issue the Notice to Proceed for
Phase 2 immediately upon delivery to the Contractor of the materials and
equipment necessary to construct the project. Alternatively, the Engineer may
defer issuance of the Notice to Proceed for Phase 2 to the extent the Engineer, in
their sole discretion, deems appropriate.
Begin work on the date shown on the Phase 2 Notice to Proceed. Do not begin
work prior to the date shown on the Phase 2 Notice to Proceed . The date
shown on the Notice to Proceed Phase will be the first working day charged
against the allotted number of working days for the second order of work.
Pay the County of Fresno the sum of Three (3,000) dollars per day each and
every calendar days delay in excess of the number of working days prescribed.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
3. Phase 3: Erection of the Tower and its Accessories
Complete this phase thirty (30) working days from the date of the Notice to
Proceed is issued.
The Engineer, in their sole discretion, may issue the Notice to Proceed for Phase
3 immediately while Phase 2 is still on going. Alternatively, the Engineer may
defer issuance of the Notice to Proceed for Phase 3 to the extent the Engineer, in
their sole discretion, deems appropriate.
Begin work on the date shown on the Notice to Proceed — Phase 3. Do not
begin work prior to the date shown on the Notice to Proceed — Phase 3. The
date shown on the Notice to Proceed —Phase 3 will be the first working day
charged against the allotted number of working days for the second order of
work.
Pay the County of Fresno the sum of Three (3,000) dollars per day each and
every calendar days delay in excess of the number of working days prescribed.
4. Phase 4: Installation of Equipment
Complete this phase thirty (20) working days from the date of the Notice to
Proceed is issued.
The Engineer, in their sole discretion, may issue the Notice to Proceed — Phase 4
immediately while Phase 2 and 3 is still on going. Alternatively, the Engineer
may defer issuance of the Notice to Proceed — Phase 4 to the extent the Engi-
neer, in their sole discretion, deems appropriate.
Begin work on the date shown on the Notice to Proceed — Phase 4. Do not
begin work prior to the date shown on the Notice to Proceed — Phase 4. The
date shown on the Notice to Proceed —Phase 4 will be the first working day
charged against the allotted number of working days for the second order of
work.
Pay the County of Fresno the sum of Three (3,000) dollars per day each and
every calendar days delay in excess of the number of working days prescribed.
B. Before commencing Work of each phase, submit an updated copy of Contractor's
construction schedule showing the sequence, commencement and completion dates,
for all phases of the Work.
1.5 OWNER-FURNISHED PRODUCTS
A. Owner will furnish products indicated. The Contractor scope of work includes receiving,
unloading, handling, storing, protecting, and installing Owner-furnished products and
making building services connections.
B. Owner-Furnished Products:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
1. Back-up Generator
1.6 ACCESS TO SITE
A. General: Contractor shall have full use of Project site for construction operations during
construction period. Contractor's use of Project site is limited only by Owner's right to
perform work or to retain other contractors on portions of Project.
B. General: Contractor shall have limited use of Project site for construction operations as
indicated on Drawings by the Contract limits and as indicated by requirements of this
Section.
C. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not
disturb portions of Project site beyond areas in which the Work is indicated.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of
authorities having jurisdiction.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Owner or others unless permitted under the following conditions and then only after
providing temporary utility services according to requirements indicated:
1. Notify Construction Manager not less than two days in advance of proposed
utility interruptions.
2. Obtain Construction Manager's written permission before proceeding with utility
interruptions.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of
noise and vibration, odors, or other disruption with Owner.
1. Notify Construction Manager not less than two days in advance of proposed
disruptive operations.
2. Obtain Construction Manager's written permission before proceeding with
disruptive operations.
D. Controlled Substances: Use of tobacco products and other controlled substances ] [on
Project site is not permitted.
E. Employee Identification: Provide identification tags for Contractor personnel working on
Project site. Require personnel to use identification tags at all times.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of
language and the intended meaning of certain terms, words, and phrases when used in
particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the
Specifications. The words "shall," "shall be," or "shall comply with," depending on
the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically
stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to
the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings
are described in detail in the Specifications. One or more of the following are used on
Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms
used in the individual Specifications Sections.
2. Keynoting: Materials and products are identified by reference keynotes
referencing Specification Section numbers found in this Project Manual.
1.9 CONSTRUCTION FUNDING SIGNS
A. GENERAL
1. Details of the construction funding sign is in the Supplemental Information.
2. Do not add information to a construction project funding identification sign unless
authorized.
3. Always keep construction project funding signs clean and in good repair.
B. MATERIALS
1. Construction project funding sign posts, foundation, back braces and mounting
shall be constructed to hold signs in a proper and permanent position, and to
resist swaying in the wind. Signs will be supported by two (2) posts of appropriate
size.
2. Sign panels shall be fabricated of 0.081 inch minimum extruded aluminum
panels.
3. The background on construction project funding signs must be Type II
retroreflective sheeting (white) and the text color will be as per detail shown on
plans.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SUMMARY
REEDLEY, CA. SECTION 011000
C. CONSTRUCTION
1. Provide and install the construction project funding signs as shown on the plans
or at the location designated by the Engineer before starting major work activi-
ties.
2. Signs should be maintained throughout the contract performance period. Dam-
aged or stolen signs shall be replaced as soon as possible.
3. Upon completion and acceptance of the work, the signs shall be removed and
become the property of the Contractor.
END OF SECTION 011000
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 - 1
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 042000 "Unit Masonry" for disposal requirements for masonry waste.
2. Section 311000 "Site Clearing" for disposition of waste resulting from site
clearing and removal of above- and below-grade improvements.
1.3 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste
resulting from construction, remodeling, renovation, or repair operations. Construction
waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or
selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale,
recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having
jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in
preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in
another facility.
F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent
incorporation into the Work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 - 2
1.4 PERFORMANCE REQUIREMENTS
A. General: Achieve end-of-Project rates for salvage/recycling of 50 percent by weight of
total non-hazardous solid waste generated by the Work. Practice efficient waste
management in the use of materials in the course of the Work. Use all reasonable
means to divert construction and demolition waste from landfills and incinerators.
Facilitate recycling and salvage of materials.
1. Construction Waste:
a. Masonry and CMU.
b. Lumber.
C. Wood sheet materials.
d. Wood trim.
e. Metals.
f. Roofing.
g. Insulation.
h. Gypsum board.
i. Piping.
j. Electrical conduit.
k. Packaging: Regardless of salvage/recycle goal indicated in "General"
Paragraph above, salvage or recycle 100 percent of the following
uncontaminated packaging materials:
1) Paper.
2) Cardboard.
3) Boxes.
4) Plastic sheet and film.
5) Polystyrene packaging.
6) Wood crates.
7) Plastic pails.
1.5 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 7 days of date established for
commencement of the Work.
1.6 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: Concurrent with each Application for Payment,
submit report. Include the following information:
1. Material category.
2. Generation point of waste.
3. Total quantity of waste in tons .
4. Quantity of waste salvaged, both estimated and actual in tons.
5. Quantity of waste recycled, both estimated and actual in tons.
6. Total quantity of waste recovered (salvaged plus recycled) in tons .
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 - 3
7. Total quantity of waste recovered (salvaged plus recycled) as a percentage of
total waste.
B. Waste Reduction Calculations: Before request for Substantial Completion, submit
calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of
total waste generated by the Work.
C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated
to individuals and organizations. Indicate whether organization is tax exempt.
D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to
individuals and organizations. Indicate whether organization is tax exempt.
E. Recycling and Processing Facility Records: Indicate receipt and acceptance of
recyclable waste by recycling and processing facilities licensed to accept them. Include
manifests, weight tickets, receipts, and invoices.
F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by
landfills and incinerator facilities licensed to accept them. Include manifests, weight
tickets, receipts, and invoices.
1.7 QUALITY ASSURANCE
A. Waste Management Coordinator Qualifications: Experienced firm, with a record of
successful waste management coordination of projects with similar requirements.
B. Refrigerant Recovery Technician Qualifications: Certified by EPA-approved certification
program.
C. Regulatory Requirements: Comply with hauling and disposal regulations of authorities
having jurisdiction.
1.8 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to ASTM E 1609 and
requirements in this Section. Plan shall consist of waste identification, waste reduction
work plan, and cost/revenue analysis. Distinguish between demolition and construction
waste Indicate quantities by weight or volume, but use same units of measure
throughout waste management plan.
B. Waste Identification: Indicate anticipated types and quantities of site-clearing and
construction waste generated by the Work. Include estimated quantities and
assumptions for estimates.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged,
recycled, or disposed of in landfill or incineratorinclude points of waste generation, total
quantity of each type of waste, quantity for each means of recovery, and handling and
transportation procedures.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 -4
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in
this Project, describe methods for preparing salvaged materials before
incorporation into the Work.
2. Salvaged Materials for Sale: For materials that will be sold to individuals and
organizations, include list of their names, addresses, and telephone numbers.
3. Salvaged Materials for Donation: For materials that will be donated to individuals
and organizations, include list of their names, addresses, and telephone
numbers.
4. Recycled Materials: Include list of local receivers and processors and type of
recycled materials each will accept. Include names, addresses, and telephone
numbers.
5. Disposed Materials: Indicate how and where materials will be disposed of.
Include name, address, and telephone number of each landfill and incinerator
facility.
6. Handling and Transportation Procedures: Include method that will be used for
separating recyclable waste including sizes of containers, container labeling, and
designated location where materials separation will be performed.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers,
storage, signage, transportation, and other items as required to implement waste
management plan during the entire duration of the Contract.
1. Comply with operation, termination, and removal requirements in Section 015000
"Temporary Facilities and Controls."
B. Waste Management Coordinator: Engage a waste management coordinator to be
responsible for implementing, monitoring, and reporting status of waste management
work plan. Coordinator shall be present at Project site full time for duration of Project.
C. Training: Train workers, subcontractors, and suppliers on proper waste management
procedures, as appropriate for the Work.
1. Distribute waste management plan to everyone concerned within three days of
submittal return.
2. Distribute waste management plan to entities when they first begin work on-site.
Review plan procedures and locations established for salvage, recycling, and
disposal.
D. Site Access and Temporary Controls: Conduct waste management operations to
ensure minimum interference with roads, streets, walks, walkways, and other adjacent
occupied and used facilities.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 - 5
1. Designate and label specific areas on Project site necessary for separating
materials that are to be salvaged, recycled, reused, donated, and sold.
3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Recycling Receivers and Processors: List below is provided for information only;
available recycling receivers and processors include, but are not limited to, the
following:
C. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives
received for recycling waste materials shall accrue to Contractor.
D. Preparation of Waste: Prepare and maintain recyclable waste materials according to
recycling or reuse facility requirements. Maintain materials free of dirt, adhesives,
solvents, petroleum contamination, and other substances deleterious to the recycling
process.
E. Procedures: Separate recyclable waste from other waste materials, trash, and debris.
Separate recyclable waste by type at Project site to the maximum extent practical
according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste
until removed from Project site. Include list of acceptable and unacceptable
materials at each container and bin.
a. Inspect containers and bins for contamination and remove contaminated
materials if found.
2. Stockpile processed materials on-site without intermixing with other materials.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent
windblown dust.
3. Stockpile materials away from construction area. Do not store within drip line of
remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Owner's property and transport to recycling
receiver or processor.
3.3 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store
in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, require deliveries using pallets to remove pallets
from Project site. For pallets that remain on-site, break down pallets into
component wood pieces and comply with requirements for recycling wood.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONST. WASTE
REEDLEY, CA. SECTION 017419 - 6
4. Crates: Break down crates into component wood pieces and comply with
requirements for recycling wood.
B. Wood Materials:
1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.
2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
a. Comply with requirements in Section 329300 "Plants" for use of clean
sawdust as organic mulch.
C. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a
dry location.
1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile
chipper or hammer mill. Screen out paper after grinding.
a. Comply with requirements in Section 329300 "Plants" for use of clean
ground gypsum board as inorganic soil amendment.
3.4 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused,
remove waste materials from Project site and legally dispose of them in a landfill or
incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be
disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent
surfaces and areas.
B. Burning: Do not burn waste materials.
C. Burning: Burning of waste materials is permitted only at designated areas on Owner's
property, provided required permits are obtained. Provide full-time monitoring for
burning materials until fires are extinguished.
D. Disposal: Remove waste materials and dispose of at designated spoil areas on
Owner's property.
E. Disposal: Remove waste materials from Owner's property and legally dispose of them.
END OF SECTION 017419
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout,
including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 017823 "Operation and Maintenance Data" for operation and
maintenance manual requirements.
1.3 ACTION SUBMITTALS
A. Product Data: For cleaning agents.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Certified List of Incomplete Items: Final submittal at Final Completion.
1.4 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.
B. Certificate of Insurance: For continuing coverage.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 2
1.5 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be
completed and corrected (Contractor's punch list), indicating the value of each item on
the list and reasons why the Work is incomplete.
B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10
days prior to requesting inspection for determining date of Substantial Completion. List
items below that are incomplete at time of request.
1. Certificates of Release: Obtain and submit releases from authorities having
jurisdiction permitting Owner unrestricted use of the Work and access to services
and utilities. Include occupancy permits, operating certificates, and similar
releases.
2. Submit closeout submittals specified in other Division 01 Sections, including
project record documents, operation and maintenance manuals, final completion
construction photographic documentation, damage or settlement surveys,
property surveys, and similar final record information.
3. Submit closeout submittals specified in individual Sections, including specific
warranties, workmanship bonds, maintenance service agreements, final
certifications, and similar documents.
4. Submit test/adjust/balance records.
5. Submit sustainable design submittals not previously submitted.
6. Submit changeover information related to Owner's occupancy, use, operation,
and maintenance.
C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10
days prior to requesting inspection for determining date of Substantial Completion. List
items below that are incomplete at time of request.
1. Advise Owner of pending insurance changeover requirements.
2. Make final changeover of permanent locks and deliver keys to Owner. Advise
Owner's personnel of changeover in security provisions.
3. Complete startup and testing of systems and equipment.
4. Perform preventive maintenance on equipment used prior to Substantial
Completion.
5. Instruct Owner's personnel in operation, adjustment, and maintenance of
products, equipment, and systems.
6. Advise Owner of changeover in heat and other utilities.
7. Participate with Owner in conducting inspection and walkthrough with local
emergency responders.
8. Terminate and remove temporary facilities from Project site, along with mockups,
construction tools, and similar elements.
9. Complete final cleaning requirements, including touchup painting.
10. Touch up and otherwise repair and restore marred exposed finishes to eliminate
visual defects.
D. Inspection: Submit a written request for inspection to determine Substantial Completion
a minimum of 10 days prior to date the work will be completed and ready for final
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 3
inspection and tests. On receipt of request, Resident Engineer will either proceed with
inspection or notify Contractor of unfulfilled requirements. Engineer will prepare the
Certificate of Substantial Completion after inspection or will notify Contractor of items,
either on Contractor's list or additional items identified by Engineer, that must be
completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous
inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for final
completion.
1.6 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting final inspection for determining
final completion, complete the following:
1. Submit a final Application for Payment according to Payment Procedures.
2. Certified List of Incomplete Items: Submit certified copy of Engineer's Substantial
Completion inspection list of items to be completed or corrected (punch list),
endorsed and dated by Engineer. Certified copy of the list shall state that each
item has been completed or otherwise resolved for acceptance.
3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage
complying with insurance requirements.
B. Inspection: Submit a written request for final inspection to determine acceptance a
minimum of 10 days prior to date the work will be completed and ready for final
inspection and tests. On receipt of request, Resident engineer will either proceed with
inspection or notify Contractor of unfulfilled requirements. Engineer will prepare a final
Certificate for Payment after inspection or will notify Contractor of construction that
must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous
inspections as incomplete is completed or corrected.
1.7 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Engineer for designated
portions of the Work where commencement of warranties other than date of
Substantial Completion is indicated, or when delay in submittal of warranties might limit
Owner's rights under warranty.
B. Provide additional copies of each warranty to include in operation and maintenance
manuals.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 4
PART 2 - PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or
fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially
hazardous to health or property or that might damage finished surfaces.
1. Use cleaning products that comply with Green Seal's GS-37, or if GS-37 is not
applicable, use products that comply with the California Code of Regulations
maximum allowable VOC levels.
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to
comply with local laws and ordinances and Federal and local environmental and
antipollution regulations.
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning.
Clean each surface or unit to condition expected in an average commercial building
cleaning and maintenance program. Comply with manufacturer's written instructions.
1. Complete the following cleaning operations before requesting inspection for
certification of Substantial Completion for entire Project or for a designated
portion of Project:
a. Clean Project site, yard, and grounds, in areas disturbed by construction
activities, including landscape development areas, of rubbish, waste
material, litter, and other foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and
other foreign deposits.
C. Rake grounds that are neither planted nor paved to a smooth, even-
textured surface.
d. Remove tools, construction equipment, machinery, and surplus material
from Project site.
e. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free
condition, free of stains, films, and similar foreign substances. Avoid
disturbing natural weathering of exterior surfaces. Restore reflective
surfaces to their original condition.
f. Remove debris and surface dust from limited access spaces, including
roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and
similar spaces.
g. Sweep concrete floors broom clean in unoccupied spaces.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 5
h. Vacuum carpet and similar soft surfaces, removing debris and excess nap;
clean according to manufacturer's recommendations if visible soil or stains
remain.
i. Clean transparent materials, including mirrors and glass in doors and
windows. Remove glazing compounds and other noticeable, vision-
obscuring materials. Polish mirrors and glass, taking care not to scratch
surfaces.
j. Remove labels that are not permanent.
k. Wipe surfaces of mechanical and electrical equipment and similar
equipment. Remove excess lubrication, paint and mortar droppings, and
other foreign substances.
I. Clean plumbing fixtures to a sanitary condition, free of stains, including
stains resulting from water exposure.
M. Replace disposable air filters and clean permanent air filters. Clean
exposed surfaces of diffusers, registers, and grills.
n. Clean ducts, blowers, and coils if units were operated without filters during
construction or that display contamination with particulate matter on
inspection.
1) Clean HVAC system in compliance with NADCA Standard 1992-01.
Provide written report on completion of cleaning.
o. Clean light fixtures, lamps, globes, and reflectors to function with full
efficiency.
p. Leave Project clean and ready for occupancy.
C. Construction Waste Disposal: Comply with waste disposal requirements in
Section 017419 "Construction Waste Management and Disposal."
3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for
determination of Substantial Completion.
B. Repair or remove and replace defective construction. Repairing includes replacing
defective parts, refinishing damaged surfaces, touching up with matching materials,
and properly adjusting operating equipment. Where damaged or worn items cannot be
repaired or restored, provide replacements. Remove and replace operating
components that cannot be repaired. Restore damaged construction and permanent
facilities used during construction to specified condition.
1. Remove and replace chipped, scratched, and broken glass, reflective surfaces,
and other damaged transparent materials.
2. Touch up and otherwise repair and restore marred or exposed finishes and
surfaces. Replace finishes and surfaces that that already show evidence of repair
or restoration.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CLOSEOUT PROCEDURES
REEDLEY, CA. SECTION 017700 - 6
a. Do not paint over "UL" and other required labels and identification,
including mechanical and electrical nameplates. Remove paint applied to
required labels and identification.
3. Replace parts subject to operating conditions during construction that may
impede operation or reduce longevity.
4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and
defective and noisy starters in fluorescent and mercury vapor fixtures to comply
with requirements for new fixtures.
END OF SECTION 017700
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE REINFORCING
REEDLEY, CA. SECTION 032000 - 1
SECTION 032000 - CONCRETE REINFORCING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Steel reinforcement bars.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site .
1. Review the following:
a. Special inspection and testing and inspecting agency procedures for field
quality control.
b. Construction contraction and isolation joints.
C. Steel-reinforcement installation.
1.4 ACTION SUBMITTALS
A. Product Data: For the following:
1. Each type of steel reinforcement.
2. Bar supports.
B. Construction Joint Layout: Indicate proposed construction joints required to build the
structure.
1. Location of construction joints is subject to approval of the Engineer.
1.5 INFORMATIONAL SUBMITTALS
A. Field quality-control reports.
B. Minutes of preinstallation conference.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE REINFORCING
REEDLEY, CA. SECTION 032000 - 2
1.6 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending
and damage.
1. Store reinforcement to avoid contact with earth.
PART 2 - PRODUCTS
2.1 STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A615/A615M, Grade 60 , deformed.
2.2 REINFORCEMENT ACCESSORIES
A. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and
fastening reinforcing bars and welded-wire reinforcement in place.
1. Manufacture bar supports from steel wire, plastic, or precast concrete in
accordance with CRSI's "Manual of Standard Practice," of greater compressive
strength than concrete and as follows:
a. For concrete surfaces exposed to view, where legs of wire bar supports
contact forms, use CRSI Class 1 plastic-protected steel wire, all-plastic bar
supports, or CRSI Class 2 stainless steel bar supports.
B. Steel Tie Wire: ASTM A1064/A1064M, annealed steel, not less than 0.0508 inch in
diameter.
1. Finish: Plain .
2.3 FABRICATING REINFORCEMENT
A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."
PART 3 - EXECUTION
3.1 PREPARATION
A. Protection of In-Place Conditions:
1. Do not cut or puncture vapor retarder.
2. Repair damage and reseal vapor retarder before placing concrete.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials
that reduce bond to concrete.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE REINFORCING
REEDLEY, CA. SECTION 032000 - 3
3.2 INSTALLATION OF STEEL REINFORCEMENT
A. Comply with CRSI's "Manual of Standard Practice" for placing and supporting
reinforcement.
B. Accurately position, support, and secure reinforcement against displacement.
1. Locate and support reinforcement with bar supports to maintain minimum
concrete cover.
2. Do not tack weld crossing reinforcing bars.
C. Preserve clearance between bars of not less than 1 inch, not less than one bar
diameter, or not less than 1-1/3 times size of large aggregate, whichever is greater.
D. Provide concrete coverage in accordance with ACI 318.
E. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
F. Splices: Lap splices as indicated on Drawings.
1. Bars indicated to be continuous, and all vertical bars shall be lapped not less
than 36 bar diameters at splices, or 24 inches, whichever is greater.
2. Stagger splices in accordance with ACI 318.
3.3 JOINTS
A. Construction Joints: Install so strength and appearance of concrete are not impaired, at
locations indicated or as approved by Engineer.
1. Place joints perpendicular to main reinforcement.
2. Continue reinforcement across construction joints unless otherwise indicated.
3. Do not continue reinforcement through sides of strip placements of floors and
slabs.
B. Doweled Joints: Install dowel bars and support assemblies at joints where indicated.
Lubricate or asphalt coat one-half of dowel length, to prevent concrete bonding to one
side of joint.
3.4 INSTALLATION TOLERANCES
A. Comply with ACI 117.
3.5 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a special inspector and qualified testing and
inspecting agency to perform field tests and inspections and prepare test reports.
B. Inspections:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE REINFORCING
REEDLEY, CA. SECTION 032000 - 4
1. Steel-reinforcement placement.
END OF SECTION 032000
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 1
SECTION 033000 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete
materials, mixture design, placement procedures, and finishes.
B. Related Requirements:
1. Section 312000 "Earth Moving" for drainage fill under slabs-on-grade.
2. Section 321313 "Concrete Paving" for concrete pavement and walks.
1.3 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of
the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and
silica fume; materials subject to compliance with requirements.
B. W/C Ratio: The ratio by weight of water to cementitious materials.
1.4 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1. Before submitting design mixtures, review concrete design mixture and examine
procedures for ensuring quality of concrete materials. Require representatives of
each entity directly concerned with cast-in-place concrete to attend, including the
following:
a. Contractor's superintendent.
b. Concrete Subcontractor.
C. Special concrete finish Subcontractor.
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 2
B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when
characteristics of materials, Project conditions, weather, test results, or other
circumstances warrant adjustments.
1. Indicate amounts of mixing water to be withheld for later addition at Project site.
C. Steel Reinforcement Shop Drawings: Placing Drawings that detail fabrication, bending,
and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup
spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical
connections, tie spacing, hoop spacing, and supports for concrete reinforcement.
D. Construction Joint Layout: Indicate proposed construction joints required to construct
the structure.
1. Location of construction joints is subject to approval of the Engineer.
E. Samples: For vapor retarder.
1.6 INFORMATIONAL SUBMITTALS
A. Qualification Data: For manufacturer.
B. Welding certificates.
C. Material Certificates: For each of the following, signed by manufacturers:
1. Cementitious materials.
2. Admixtures.
3. Form materials and form-release agents.
4. Steel reinforcement and accessories.
5. Fiber reinforcement.
6. Curing compounds.
7. Floor and slab treatments.
8. Bonding agents.
9. Adhesives.
10. Vapor retarders.
11. Semirigid joint filler.
12. Joint-filler strips.
13. Repair materials.
D. Floor surface flatness and levelness measurements indicating compliance with
specified tolerances.
E. Field quality-control reports.
F. Minutes of preinstallation conference.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 3
1.7 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs on Project personnel qualified
as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-
certified Concrete Flatwork Technician.
B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed
concrete products and that complies with ASTM C 94/C 94M requirements for
production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed
Concrete Production Facilities."
C. Testing Agency Qualifications: An independent agency, acceptable to authorities
having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing
indicated.
1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing
Technician, Grade 1, according to ACI CP-1 or an equivalent certification
program.
2. Personnel performing laboratory tests shall be ACI-certified Concrete Strength
Testing Technician and Concrete Laboratory Testing Technician, Grade I.
Testing agency laboratory supervisor shall be an ACI-certified Concrete
Laboratory Testing Technician, Grade II.
D. Welding Qualifications: Qualify procedures and personnel according to
AWS D1.4/D 1.4M.
1.8 PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Engage a qualified testing agency to perform
preconstruction testing on concrete mixtures.
1.9 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending
and damage.
1.10 FIELD CONDITIONS
A. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete
work from physical damage or reduced strength that could be caused by frost, freezing
actions, or low temperatures.
1. When average high and low temperature is expected to fall below 40 deg F for
three successive days, maintain delivered concrete mixture temperature within
the temperature range required by ACI 301 .
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 4
2. Do not use frozen materials or materials containing ice or snow. Do not place
concrete on frozen subgrade or on subgrade containing frozen materials.
3. Do not use calcium chloride, salt, or other materials containing antifreeze agents
or chemical accelerators unless otherwise specified and approved in mixture
designs.
B. Hot-Weather Placement: Comply with ACI 301 and as follows:
1. Maintain concrete temperature below 90 deg F at time of placement. Chilled
mixing water or chopped ice may be used to control temperature, provided water
equivalent of ice is calculated to total amount of mixing water. Using liquid
nitrogen to cool concrete is Contractor's option.
2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.
Keep subgrade uniformly moist without standing water, soft spots, or dry areas.
PART 2 - PRODUCTS
2.1 CONCRETE, GENERAL
A. ACI Publications: Comply with the following unless modified by requirements in the
Contract Documents:
1. ACI 301
2. ACI 117
2.2 FORM-FACING MATERIALS
A. Smooth-Formed Finished Concrete: Form-facing panels that provide continuous, true,
and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number
of joints.
1. Plywood, metal, or other approved panel materials.
2. Exterior-grade plywood panels, suitable for concrete forms, complying with
DOC PS 1, and as follows:
a. High-density overlay, Class 1 or better.
b. Medium-density overlay, Class 1 or better; mill-release agent treated and
edge sealed.
C. Structural 1, B-B or better; mill oiled and edge sealed.
d. B-B (Concrete Form), Class 1 or better; mill oiled and edge sealed.
3. Overlaid Finnish birch plywood.
B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved
material. Provide lumber dressed on at least two edges and one side for tight fit.
C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch , minimum.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 5
D. Rustication Strips: Wood, metal, PVC, or rubber strips, kerfed for ease of form removal.
E. Form-Release Agent: Commercially formulated form-release agent that does not bond
with, stain, or adversely affect concrete surfaces and does not impair subsequent
treatments of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
F. Form Ties: Factory-fabricated, removable or snap-off glass-fiber-reinforced plastic or
metal form ties designed to resist lateral pressure of fresh concrete on forms and to
prevent spalling of concrete on removal.
1. Furnish units that leave no corrodible metal closer than 1 inch to the plane of
exposed concrete surface.
2. Furnish ties that, when removed, leave holes no larger than 1 inch in diameter in
concrete surface.
3. Furnish ties with integral water-barrier plates to walls indicated to receive
dampproofing or waterproofing.
2.3 STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.
B. Steel Bar Mats: ASTM A 184/A 184M, fabricated from ASTM A 615, Grade 60
ASTM A 706, deformed bars, assembled with clips.
C. Deformed-Steel Wire: ASTM A 1064/A 1064M.
2.4 REINFORCEMENT ACCESSORIES
A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut true to length
with ends square and free of burrs.
B. Epoxy Repair Coating: Liquid, two-part, epoxy repair coating; compatible with epoxy
coating on reinforcement and complying with ASTM A 775/A 775M.
C. Zinc Repair Material: ASTM A 780/A 780M.
D. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and
fastening reinforcing bars and welded-wire reinforcement in place. Manufacture bar
supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of
Standard Practice," of greater compressive strength than concrete and as follows:
1. For concrete surfaces exposed to view, where legs of wire bar supports contact
forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-
steel bar supports.
2. For epoxy-coated reinforcement, use epoxy-coated or other dielectric-polymer-
coated wire bar supports.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 6
3. For zinc-coated reinforcement, use galvanized wire or dielectric-polymer-coated
wire bar supports.
2.5 CONCRETE MATERIALS
A. Source Limitations: Obtain each type or class of cementitious material of the same
brand from the same manufacturer's plant, obtain aggregate from single source, and
obtain admixtures from single source from single manufacturer.
B. Cementitious Materials:
1. Portland Cement: ASTM C 150/C 150M, Type I.
2. Fly Ash: ASTM C 618, Class F or C
3. Slag Cement: ASTM C 989, Grade 100 or 120.
4. Silica Fume: ASTM C 1240, amorphous silica.
C. Normal-Weight Aggregates: ASTM C 33, Class 3S coarse aggregate or better, graded.
Provide aggregates from a single source with documented service record data of at
least 10 years' satisfactory service in similar applications and service conditions using
similar aggregates and cementitious materials.
1. Maximum Coarse-Aggregate Size: 3/4 inch nominal.
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
D. Air-Entraining Admixture: ASTM C 260
E. Chemical Admixtures: Certified by manufacturer to be compatible with other
admixtures and that do not contribute water-soluble chloride ions exceeding those
permitted in hardened concrete. Do not use calcium chloride or admixtures containing
calcium chloride.
1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
2. Retarding Admixture: ASTM C 494/C 494M, Type B.
3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.
4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.
5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M,
Type G.
6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.
F. Set-Accelerating Corrosion-Inhibiting Admixture: Commercially formulated, anodic
inhibitor or mixed cathodic and anodic inhibitor; capable of forming a protective barrier
and minimizing chloride reactions with steel reinforcement in concrete and complying
with ASTM C 494/C 494M, Type C.
G. Non-Set-Accelerating Corrosion-Inhibiting Admixture: Commercially formulated, non-
set-accelerating, anodic inhibitor or mixed cathodic and anodic inhibitor; capable of
forming a protective barrier and minimizing chloride reactions with steel reinforcement
in concrete.
H. Water: ASTM C 94/C 94M and potable.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 7
2.6 VAPOR RETARDERS
A. Sheet Vapor Retarder: ASTM E 1745, Class A. Include manufacturer's recommended
adhesive or pressure-sensitive tape.
2.7 CURING MATERIALS
A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for
application to fresh concrete.
B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf,
weighing approximately 9 oz./sq. yd. when dry.
C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene
sheet.
D. Water: Potable.
E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1,
Class B, dissipating.
2.8 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic
fiber or ASTM D 1752, cork or self-expanding cork.
B. Bonding Agent: ASTM C 1059, Type II, nonredispersible, acrylic emulsion or styrene
butadiene.
C. Reglets: Fabricate reglets of not less than 0.022-inch thick, galvanized-steel sheet.
Temporarily fill or cover face opening of reglet to prevent intrusion of concrete or
debris.
D. Dovetail Anchor Slots: Hot-dip galvanized-steel sheet, not less than 0.034 inch thick,
with bent tab anchors. Temporarily fill or cover face opening of slots to prevent
intrusion of concrete or debris.
2.9 REPAIR MATERIALS
A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can
be applied in thicknesses from 1/8 inch and that can be feathered at edges to match
adjacent floor elevations.
1. Cement Binder: ASTM C 150/C 150M, portland cement or hydraulic or blended
hydraulic cement as defined in ASTM C 219.
2. Primer: Product of underlayment manufacturer recommended for substrate,
conditions, and application.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 8
3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as
recommended by underlayment manufacturer.
4. Compressive Strength: Not less than 4000 psi at 28 days when tested according
to ASTM C 109/C 109M.
2.10 CONCRETE MIXTURES, GENERAL
A. Prepare design mixtures for each type and strength of concrete, proportioned on the
basis of laboratory trial mixture or field test data, or both, according to ACI 301.
1. Use a qualified independent testing agency for preparing and reporting proposed
mixture designs based on laboratory trial mixtures.
B. Cementitious Materials Use fly ash, pozzolan, slag cement, and silica fume as needed
to reduce the total amount of portland cement, which would otherwise be used, by not
less than 40 percent. Limit percentage, by weight, of cementitious materials other than
portland cement in concrete as follows:
1. Fly Ash: 25 percent.
2. Combined Fly Ash and Pozzolan: 25 percent.
3. Slag Cement: 50 percent.
4. Combined Fly Ash or Pozzolan and Slag Cement: 50 percent portland cement
minimum, with fly ash or pozzolan not exceeding 25 percent.
5. Silica Fume: 10 percent.
6. Combined Fly Ash, Pozzolans, and Silica Fume: 35 percent with fly ash or
pozzolans not exceeding 25 percent and silica fume not exceeding 10 percent.
7. Combined Fly Ash or Pozzolans, Slag Cement, and Silica Fume: 50 percent with
fly ash or pozzolans not exceeding 25 percent and silica fume not exceeding 10
percent.
C. Limit water-soluble, chloride-ion content in hardened concrete to 0.06 percent by
weight of cement.
D. Admixtures: Use admixtures according to manufacturer's written instructions.
1. Use water-reducing or plasticizing admixture in concrete, as required, for
placement and workability.
2. Use water-reducing and -retarding admixture when required by high
temperatures, low humidity, or other adverse placement conditions.
3. Use water-reducing admixture in pumped concrete, concrete for heavy-use
industrial slabs and parking structure slabs, concrete required to be watertight,
and concrete with a w/c ratio below 0.50.
4. Use corrosion-inhibiting admixture in concrete mixtures where indicated.
E. Color Pigment: Add color pigment to concrete mixture according to manufacturer's
written instructions and to result in hardened concrete color consistent with approved
mockup.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 9
2.11 CONCRETE MIXTURES FOR BUILDING ELEMENTS
A. Footings: Normal-weight concrete.
1. Minimum Compressive Strength: 3000 psi at 28 days.
2. Maximum W/C Ratio:0.45.
3. Slump Limit: 4 inches for concrete with verified slump of 2 to 4 inches before
adding high-range water-reducing admixture or plasticizing admixture.
4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch
nominal maximum aggregate size.
B. Foundation Walls: Normal-weight concrete.
1. Minimum Compressive Strength: 3000 psi at 28 days.
2. Maximum W/C Ratio:0.45.
3. Slump Limit: 4 inches for concrete with verified slump of 2 to 4 inches before
adding high-range water-reducing admixture or plasticizing admixtur, plus or
minus 1 inch .
4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch
nominal maximum aggregate size.
C. Slabs-on-Grade: Normal-weight concrete.
1. Minimum Compressive Strength: 3000 psi at 28 days.
2. Maximum W/C Ratio: 0.45.
3. Minimum Cementitious Materials Content: 470 lb/cu. yd.
4. Slump Limit:4 inches.
5. Air Content:6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch
nominal maximum aggregate size.
6. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.
7. Steel-Fiber Reinforcement: Add to concrete mixture, according to manufacturer's
written instructions, at a rate of 50 lb/cu. yd. .
2.12 FABRICATING REINFORCEMENT
A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."
2.13 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to
ASTM C 94 and ASTM C 1116, and furnish batch ticket information.
1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery
time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F,
reduce mixing and delivery time to 60 minutes.
B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete
according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch
machine mixer.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 10
1. For mixer capacity of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes,
but not more than 5 minutes after ingredients are in mixer, before any part of
batch is released.
2. For mixer capacity larger than 1 cu. yd., increase mixing time by 15 seconds for
each additional 1 cu. yd..
3. Provide batch ticket for each batch discharged and used in the Work, indicating
Project identification name and number, date, mixture type, mixture time,
quantity, and amount of water added. Record approximate location of final
deposit in structure.
PART 3 - EXECUTION
3.1 FORMWORK INSTALLATION
A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support
vertical, lateral, static, and dynamic loads, and construction loads that might be
applied, until structure can support such loads.
B. Construct formwork so concrete members and structures are of size, shape, alignment,
elevation, and position indicated, within tolerance limits of ACI 117.
C. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as
follows:
1. Class A, 1/8 inch for smooth-formed finished surfaces.
2. Class B, 1/4 inch, Class C, 1/2 inch, Class D, 1 inch for rough-formed finished
surfaces.
D. Construct forms tight enough to prevent loss of concrete mortar.
E. Construct forms for easy removal without hammering or prying against concrete
surfaces. Provide crush or wrecking plates where stripping may damage cast-concrete
surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1
vertical.
1. Install keyways, reglets, recesses, and the like, for easy removal.
2. Do not use rust-stained steel form-facing material.
F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve
required elevations and slopes in finished concrete surfaces. Provide and secure units
to support screed strips; use strike-off templates or compacting-type screeds.
G. Provide temporary openings for cleanouts and inspection ports where interior area of
formwork is inaccessible. Close openings with panels tightly fitted to forms and
securely braced to prevent loss of concrete mortar. Locate temporary openings in
forms at inconspicuous locations.
H. Chamfer exterior corners and edges of permanently exposed concrete.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 11
I. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and
bulkheads required in the Work. Determine sizes and locations from trades providing
such items.
J. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust,
dirt, and other debris just before placing concrete.
K. Retighten forms and bracing before placing concrete, as required, to prevent mortar
leaks and maintain proper alignment.
L. Coat contact surfaces of forms with form-release agent, according to manufacturer's
written instructions, before placing reinforcement.
3.2 EMBEDDED ITEM INSTALLATION
A. Place and secure anchorage devices and other embedded items required for adjoining
work that is attached to or supported by cast-in-place concrete. Use setting drawings,
templates, diagrams, instructions, and directions furnished with items to be embedded.
1. Install anchor rods, accurately located, to elevations required and complying with
tolerances in Section 7.5 of AISC 303.
2. Install reglets to receive waterproofing and to receive through-wall flashings in
outer face of concrete frame at exterior walls, where flashing is shown at lintels,
shelf angles, and other conditions.
3. Install dovetail anchor slots in concrete structures as indicated.
3.3 REMOVING AND REUSING FORMS
A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work
that does not support weight of concrete may be removed after cumulatively curing at
not less than 50 deg F for 24 hours after placing concrete. Concrete has to be hard
enough to not be damaged by form-removal operations, and curing and protection
operations need to be maintained.
1. Leave formwork for beam soffits, joists, slabs, and other structural elements that
support weight of concrete in place until concrete has achieved at least 70
percent of its 28-day design compressive strength.
2. Remove forms only if shores have been arranged to permit removal of forms
without loosening or disturbing shores.
B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed,
delaminated, or otherwise damaged form-facing material are not acceptable for
exposed surfaces. Apply new form-release agent.
C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close
joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed
concrete surfaces unless approved by Engineer.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 12
3.4 SHORING AND RESHORING INSTALLATION
A. Comply with ACI 318 and ACI 301 for design, installation, and removal of shoring and
reshoring.
1. Do not remove shoring or reshoring until measurement of slab tolerances is
complete.
B. Plan sequence of removal of shores and reshore to avoid damage to concrete. Locate
and provide adequate reshoring to support construction without excessive stress or
deflection.
3.5 VAPOR-RETARDER INSTALLATION
A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to
ASTM E 1643 and manufacturer's written instructions.
1. Lap joints 6 inches and seal with manufacturer's recommended tape.
B. Bituminous Vapor Retarders: Place, protect, and repair bituminous vapor retarder
according to manufacturer's written instructions.
3.6 STEEL REINFORCEMENT INSTALLATION
A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing,
and supporting reinforcement.
1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder
before placing concrete.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials
that reduce bond to concrete.
C. Accurately position, support, and secure reinforcement against displacement. Locate
and support reinforcement with bar supports to maintain minimum concrete cover. Do
not tack weld crossing reinforcing bars.
1. Weld reinforcing bars according to AWS D1.4/D 1.4M, where indicated.
D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
E. Install welded-wire reinforcement in longest practicable lengths on bar supports spaced
to minimize sagging. Lap edges and ends of adjoining sheets at least one mesh
spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either
direction. Lace overlaps with wire.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 13
3.7 JOINTS
A. General: Construct joints true to line with faces perpendicular to surface plane of
concrete.
B. Construction Joints: Install so strength and appearance of concrete are not impaired, at
locations indicated or as approved by Engineer.
1. Place joints perpendicular to main reinforcement. Continue reinforcement across
construction joints unless otherwise indicated. Do not continue reinforcement
through sides of strip placements of floors and slabs.
2. Form keyed joints as indicated. Embed keys at least 1-1/2 inches into concrete.
3. Locate joints for beams, slabs, joists, and girders in the middle third of spans.
Offset joints in girders a minimum distance of twice the beam width from a beam-
girder intersection.
4. Locate horizontal joints in walls and columns at underside of floors, slabs,
beams, and girders and at the top of footings or floor slabs.
5. Use a bonding agent at locations where fresh concrete is placed against
hardened or partially hardened concrete surfaces.
C. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints,
sectioning concrete into areas as indicated. Construct contraction joints for a depth
equal to at least one-fourth of concrete thickness as follows:
1. Grooved Joints: Form contraction joints after initial floating by grooving and
finishing each edge of joint to a radius of 1/8 inch. Repeat grooving of contraction
joints after applying surface finishes. Eliminate groover tool marks on concrete
surfaces.
2. Sawed Joints: Form contraction joints with power saws equipped with
shatterproof abrasive or diamond-rimmed blades. Cut 1/8-inch wide joints into
concrete when cutting action does not tear, abrade, or otherwise damage surface
and before concrete develops random contraction cracks.
D. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at
slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade
beams, and other locations, as indicated.
1. Extend joint-filler strips full width and depth of joint, terminating flush with finished
concrete surface unless otherwise indicated.
2. Terminate full-width joint-filler strips not less than 1/2 inch or more than 1 inch
below finished concrete surface where joint sealants, specified in Section 079200
"Joint Sealants," are indicated.
3. Install joint-filler strips in lengths as long as practicable. Where more than one
length is required, lace or clip sections together.
E. Doweled Joints: Install dowel bars and support assemblies at joints where indicated.
Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one
side of joint.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 14
3.8 CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement, and
embedded items is complete and that required inspections are completed.
B. Do not add water to concrete during delivery, at Project site, or during placement
unless approved by Engineer.
C. Before test sampling and placing concrete, water may be added at Project site, subject
to limitations of ACI 301.
1. Do not add water to concrete after adding high-range water-reducing admixtures
to mixture.
D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that
no new concrete is placed on concrete that has hardened enough to cause seams or
planes of weakness. If a section cannot be placed continuously, provide construction
joints as indicated. Deposit concrete to avoid segregation.
1. Deposit concrete in horizontal layers of depth not to exceed formwork design
pressures and in a manner to avoid inclined construction joints.
2. Consolidate placed concrete with mechanical vibrating equipment according to
ACI 301 .
3. Do not use vibrators to transport concrete inside forms. Insert and withdraw
vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer
and at least 6 inches into preceding layer. Do not insert vibrators into lower
layers of concrete that have begun to lose plasticity. At each insertion, limit
duration of vibration to time necessary to consolidate concrete and complete
embedment of reinforcement and other embedded items without causing mixture
constituents to segregate.
E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within
limits of construction joints, until placement of a panel or section is complete.
1. Consolidate concrete during placement operations, so concrete is thoroughly
worked around reinforcement and other embedded items and into corners.
2. Maintain reinforcement in position on chairs during concrete placement.
3. Screed slab surfaces with a straightedge and strike off to correct elevations.
4. Slope surfaces uniformly to drains where required.
5. Begin initial floating using bull floats or darbies to form a uniform and open-
textured surface plane, before excess bleedwater appears on the surface. Do not
further disturb slab surfaces before starting finishing operations.
3.9 FINISHING FORMED SURFACES
A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with
tie holes and defects repaired and patched. Remove fins and other projections that
exceed specified limits on formed-surface irregularities.
1. Apply to concrete surfaces not exposed to public view.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 15
B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material,
arranged in an orderly and symmetrical manner with a minimum of seams. Repair and
patch tie holes and defects. Remove fins and other projections that exceed specified
limits on formed-surface irregularities.
1. Apply to concrete surfaces exposed to public view.
C. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed
surfaces adjacent to formed surfaces, strike off smooth and finish with a texture
matching adjacent formed surfaces. Continue final surface treatment of formed
surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.
3.10 FINISHING FLOORS AND SLABS
A. General: Comply with ACI 302.1 R recommendations for screeding, restraightening,
and finishing operations for concrete surfaces. Do not wet concrete surfaces.
B. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is
small or inaccessible to power-driven floats. Restraighten, cut down high spots, and fill
low spots. Repeat float passes and restraightening until surface is left with a uniform,
smooth, granular texture.
1. Apply float finish to surfaces to receive trowel finish and to be covered with fluid-
applied or sheet waterproofing, built-up or membrane roofing, or sand-bed
terrazzo
C. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete
by hand or power-driven trowel. Continue troweling passes and restraighten until
surface is free of trowel marks and uniform in texture and appearance. Grind smooth
any surface defects that would telegraph through applied coatings or floor coverings.
1. Apply a trowel finish to surfaces exposed to view or to be covered with resilient
flooring, carpet, ceramic or quarry tile set over a cleavage membrane, paint, or
another thin-film-finish coating system.
2. Finish surfaces to the following tolerances, according to ASTM E 1155 , for a
randomly trafficked floor surface:
a. Specified overall values of flatness, F(F) 25; and of levelness, F(L) 20; with
minimum local values of flatness, F(F) 17; and of levelness, F(L) 15.
D. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and
elsewhere as indicated.
1. Immediately after float finishing, slightly roughen trafficked surface by brooming
with fiber-bristle broom perpendicular to main traffic route. Coordinate required
final finish with Engineer before application.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 16
3.11 MISCELLANEOUS CONCRETE ITEM INSTALLATION
A. Filling In: Fill in holes and openings left in concrete structures after work of other trades
is in place unless otherwise indicated. Mix, place, and cure concrete, as specified, to
blend with in-place construction. Provide other miscellaneous concrete filling indicated
or required to complete the Work.
B. Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is
still green and by steel-troweling surfaces to a hard, dense finish with corners,
intersections, and terminations slightly rounded.
C. Equipment Bases and Foundations:
1. Coordinate sizes and locations of concrete bases with actual equipment
provided.
2. Construct concrete bases 6" high unless otherwise indicated, and extend base
not less than 6 inches in each direction beyond the maximum dimensions of
supported equipment unless otherwise indicated or unless required for seismic
anchor support.
3. Minimum Compressive Strength:4000 psi at 28 days.
4. Install dowel rods to connect concrete base to concrete floor. Unless otherwise
indicated, install dowel rods on 18-inch centers around the full perimeter of
concrete base.
5. For supported equipment, install epoxy-coated anchor bolts that extend through
concrete base and anchor into structural concrete substrate.
6. Prior to pouring concrete, place and secure anchorage devices. Use setting
drawings, templates, diagrams, instructions, and directions furnished with items
to be embedded.
7. Cast anchor-bolt insert into bases. Install anchor bolts to elevations required for
proper attachment to supported equipment.
3.12 CONCRETE PROTECTING AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or
hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for
hot-weather protection during curing.
B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot,
dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and
during finishing operations. Apply according to manufacturer's written instructions after
placing, screeding, and bull floating or darbying concrete, but before float finishing.
C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams,
supported slabs, and other similar surfaces. If forms remain during curing period, moist
cure after loosening forms. If removing forms before end of curing period, continue
curing for remainder of curing period.
D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed
surfaces, including floors and slabs, concrete floor toppings, and other surfaces.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 17
E. Cure concrete according to ACI 308.1, by one or a combination of the following
methods:
1. Moisture Curing: Keep surfaces continuously moist for not less than seven days
with the following materials:
a. Water.
b. Continuous water-fog spray.
C. Absorptive cover, water saturated, and kept continuously wet. Cover
concrete surfaces and edges with 12-inch lap over adjacent absorptive
covers.
2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-
retaining cover for curing concrete, placed in widest practicable width, with sides
and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive.
Cure for not less than seven days. Immediately repair any holes or tears during
curing period, using cover material and waterproof tape.
a. Moisture cure or use moisture-retaining covers to cure concrete surfaces to
receive floor coverings.
b. Moisture cure or use moisture-retaining covers to cure concrete surfaces to
receive penetrating liquid floor treatments.
C. Cure concrete surfaces to receive floor coverings with either a moisture-
retaining cover or a curing compound that the manufacturer certifies does
not interfere with bonding of floor covering used on Project.
3. Curing Compound: Apply uniformly in continuous operation by power spray or
roller according to manufacturer's written instructions. Recoat areas subjected to
heavy rainfall within three hours after initial application. Maintain continuity of
coating and repair damage during curing period.
a. Removal: After curing period has elapsed, remove curing compound
without damaging concrete surfaces by method recommended by curing
compound manufacturer unless manufacturer certifies curing compound
does not interfere with bonding of floor covering used on Project.
4. Curing and Sealing Compound: Apply uniformly to floors and slabs indicated in a
continuous operation by power spray or roller according to manufacturer's written
instructions. Recoat areas subjected to heavy rainfall within three hours after
initial application. Repeat process 24 hours later and apply a second coat.
Maintain continuity of coating and repair damage during curing period.
3.13 JOINT FILLING
A. Prepare, clean, and install joint filler according to manufacturer's written instructions.
1. Defer joint filling until concrete has aged at least one month(s). Do not fill joints
until construction traffic has permanently ceased.
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 18
B. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave
contact faces of joints clean and dry.
C. Install semirigid joint filler full depth in saw-cut joints and at least 2 inches deep in
formed joints. Overfill joint and trim joint filler flush with top of joint after hardening.
3.14 CONCRETE SURFACE REPAIRS
A. Defective Concrete: Repair and patch defective areas when approved by Engineer.
Remove and replace concrete that cannot be repaired and patched to Engineer's
approval.
B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1 part portland cement to
2-1/2 parts fine aggregate passing a No. 16) sieve, using only enough water for
handling and placing.
C. Repairing Formed Surfaces: Surface defects include color and texture irregularities,
cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on
the surface, and stains and other discolorations that cannot be removed by cleaning.
1. Immediately after form removal, cut out honeycombs, rock pockets, and voids
more than 1/2 inch in any dimension to solid concrete. Limit cut depth to 3/4 inch.
Make edges of cuts perpendicular to concrete surface. Clean, dampen with
water, and brush-coat holes and voids with bonding agent. Fill and compact with
patching mortar before bonding agent has dried. Fill form-tie voids with patching
mortar or cone plugs secured in place with bonding agent.
2. Repair defects on surfaces exposed to view by blending white portland cement
and standard portland cement so that, when dry, patching mortar matches
surrounding color. Patch a test area at inconspicuous locations to verify mixture
and color match before proceeding with patching. Compact mortar in place and
strike off slightly higher than surrounding surface.
3. Repair defects on concealed formed surfaces that affect concrete's durability and
structural performance as determined by Engineer.
D. Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for
finish and verify surface tolerances specified for each surface. Correct low and high
areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a
sloped template.
1. Repair finished surfaces containing defects. Surface defects include spalls,
popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch
wide or that penetrate to reinforcement or completely through unreinforced
sections regardless of width, and other objectionable conditions.
2. After concrete has cured at least 14 days, correct high areas by grinding.
3. Correct localized low areas during or immediately after completing surface
finishing operations by cutting out low areas and replacing with patching mortar.
Finish repaired areas to blend into adjacent concrete.
4. Correct other low areas scheduled to receive floor coverings with a repair
underlayment. Prepare, mix, and apply repair underlayment and primer
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 19
according to manufacturer's written instructions to produce a smooth, uniform,
plane, and level surface. Feather edges to match adjacent floor elevations.
5. Correct other low areas scheduled to remain exposed with a repair topping. Cut
out low areas to ensure a minimum repair topping depth of 1/4 inch to match
adjacent floor elevations. Prepare, mix, and apply repair topping and primer
according to manufacturer's written instructions to produce a smooth, uniform,
plane, and level surface.
6. Repair defective areas, except random cracks and single holes 1 inch or less in
diameter, by cutting out and replacing with fresh concrete. Remove defective
areas with clean, square cuts and expose steel reinforcement with at least a 3/4-
inch clearance all around. Dampen concrete surfaces in contact with patching
concrete and apply bonding agent. Mix patching concrete of same materials and
mixture as original concrete, except without coarse aggregate. Place, compact,
and finish to blend with adjacent finished concrete. Cure in same manner as
adjacent concrete.
7. Repair random cracks and single holes 1 inch or less in diameter with patching
mortar. Groove top of cracks and cut out holes to sound concrete and clean off
dust, dirt, and loose particles. Dampen cleaned concrete surfaces and apply
bonding agent. Place patching mortar before bonding agent has dried. Compact
patching mortar and finish to match adjacent concrete. Keep patched area
continuously moist for at least 72 hours.
E. Perform structural repairs of concrete, subject to Engineer's approval, using epoxy
adhesive and patching mortar.
F. Repair materials and installation not specified above may be used, subject to
Engineer's approval.
3.15 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a special inspector and qualified testing and
inspecting agency to perform field tests and inspections and prepare test reports.
B. Testing Agency: Engage a qualified testing and inspecting agency to perform tests and
inspections and to submit reports.
C. Inspections:
1. Steel reinforcement placement.
2. Steel reinforcement welding.
3. Headed bolts and studs.
4. Verification of use of required design mixture.
5. Concrete placement, including conveying and depositing.
6. Curing procedures and maintenance of curing temperature.
7. Verification of concrete strength before removal of shores and forms from beams
and slabs.
D. Concrete Tests: Testing of composite samples of fresh concrete obtained according to
ASTM C 172 shall be performed according to the following requirements:
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 20
1. Testing Frequency: Obtain one composite sample for each day's pour of each
concrete mixture exceeding 5 cu. yd., but less than 25 cu. yd., plus one set for
each additional 50 cu. yd. or fraction thereof.
2. Testing Frequency: Obtain at least one composite sample for each 100 cu. yd. or
fraction thereof of each concrete mixture placed each day.
a. When frequency of testing provides fewer than five compressive-strength
tests for each concrete mixture, testing shall be conducted from at least
five randomly selected batches or from each batch if fewer than five are
used.
3. Slump: ASTM C 143/C 143M; one test at point of placement for each composite
sample, but not less than one test for each day's pour of each concrete mixture.
Perform additional tests when concrete consistency appears to change.
4. Air Content: ASTM C 231/C 231M, pressure method, for normal-weight concrete;
ASTM C 173, volumetric method, for structural lightweight concrete.one test for
each composite sample, but not less than one test for each day's pour of each
concrete mixture.
5. Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air
temperature is 40 deg F and below or 80 deg F and above, and one test for
each composite sample.
6. Unit Weight: ASTM C 567/C 567M, fresh unit weight of structural lightweight
concrete; one test for each composite sample, but not less than one test for each
day's pour of each concrete mixture.
7. Compression Test Specimens: ASTM C 31/C 31M.
a. Cast and laboratory cure two sets of two standard cylinder specimens for
each composite sample.
b. Cast and field cure two sets of two standard cylinder specimens for each
composite sample.
8. Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two laboratory-
cured specimens at 7 days and one set of two specimens at 28 days.
a. Test one set of two field-cured specimens at 7 days and one set of two
specimens at 28 days.
b. A compressive-strength test shall be the average compressive strength
from a set of two specimens obtained from same composite sample and
tested at age indicated.
9. When strength of field-cured cylinders is less than 85 percent of companion
laboratory-cured cylinders, Contractor shall evaluate operations and provide
corrective procedures for protecting and curing in-place concrete.
10. Strength of each concrete mixture will be satisfactory if every average of any
three consecutive compressive-strength tests equals or exceeds specified
compressive strength and no compressive-strength test value falls below
specified compressive strength by more than 500 psi .
11. Test results shall be reported in writing to Engineer, concrete manufacturer, and
Contractor within 48 hours of testing. Reports of compressive-strength tests shall
contain Project identification name and number, date of concrete placement,
name of concrete testing and inspecting agency, location of concrete batch in
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CAST-IN-PLACE CONCRETE
REEDLEY, CA. SECTION 033000 - 21
Work, design compressive strength at 28 days, concrete mixture proportions and
materials, compressive breaking strength, and type of break for both 7- and 28-
day tests.
12. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive
device may be permitted by Engineer but will not be used as sole basis for
approval or rejection of concrete.
13. Additional Tests: Testing and inspecting agency shall make additional tests of
concrete when test results indicate that slump, air entrainment, compressive
strengths, or other requirements have not been met, as directed by Engineer.
Testing and inspecting agency may conduct tests to determine adequacy of
concrete by cored cylinders complying with ASTM C 42/C 42M or by other
methods as directed by Engineer.
14. Additional testing and inspecting, at Contractor's expense, will be performed to
determine compliance of replaced or additional work with specified requirements.
15. Correct deficiencies in the Work that test reports and inspections indicate do not
comply with the Contract Documents.
E. Measure floor and slab flatness and levelness according to ASTM E 1155 within 24
hours of finishing.
3.16 PROTECTION OF LIQUID FLOOR TREATMENTS
A. Protect liquid floor treatment from damage and wear during the remainder of
construction period. Use protective methods and materials, including temporary
covering, recommended in writing by liquid floor treatments installer.
END OF SECTION 033000
CONTRACT # 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 1
SECTION 042200 - CONCRETE UNIT MASONRY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Concrete masonry units.
2. Pre-faced concrete masonry units.
3. Mortar and grout.
4. Steel reinforcing bars.
5. Masonry-joint reinforcement.
6. Embedded flashing.
7. Miscellaneous masonry accessories.
8. Masonry-cell fill.
B. Related Requirements:
1. Section 033000 "Cast-in-Place Concrete" for installing dovetail slots for masonry
anchors.
2. Section 071900 "Water Repellents" for water repellents applied to unit masonry
assemblies.
3. Section 076200 "Sheet Metal Flashing and Trim" for exposed sheet metal
flashing and for furnishing manufactured reglets installed in masonry joints.
1.3 DEFINITIONS
A. CMU(s): Concrete masonry unit(s).
B. Reinforced Masonry: Masonry containing reinforcing steel in grouted cells.
1.4 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 2
B. Shop Drawings: For the following:
1. Masonry Units: Show sizes, profiles, coursing, and locations of special shapes.
2. Reinforcing Steel: Detail bending, lap lengths, and placement of unit masonry
reinforcing bars. Comply with ACI 315. Show elevations of reinforced walls.
3. Fabricated Flashing: Detail corner units, end-dam units, and other special
applications.
1.6 INFORMATIONAL SUBMITTALS
A. Qualification Data: For testing agency.
B. Material Certificates: For each type and size of the following:
1. Masonry units.
a. Include data on material properties, material test reports substantiating
compliance with requirements.
b. For masonry units used in structural masonry, include data and
calculations establishing average net-area compressive strength of units.
2. Integral water repellant used in CMUs.
3. Cementitious materials. Include name of manufacturer, brand name, and type.
4. Mortar admixtures.
5. Preblended, dry mortar mixes. Include description of type and proportions of
ingredients.
6. Grout mixes. Include description of type and proportions of ingredients.
7. Reinforcing bars.
8. Joint reinforcement.
9. Anchors, ties, and metal accessories.
C. Mix Designs: For each type of mortar and grout. Include description of type and
proportions of ingredients.
1. Include test reports for mortar mixes required to comply with property
specification. Test according to ASTM C 109/C 109M for compressive strength,
ASTM C 1506 for water retention, and ASTM C 91/C 91 M for air content.
2. Include test reports, according to ASTM C 1019, for grout mixes required to
comply with compressive strength requirement.
D. Statement of Compressive Strength of Masonry: For each combination of masonry unit
type and mortar type, provide statement of average net-area compressive strength of
masonry units, mortar type, and resulting net-area compressive strength of masonry
determined according to TMS 602/ACI 530.1/ASCE 6.
E. Cold-Weather and Hot-Weather Procedures: Detailed description of methods,
materials, and equipment to be used to comply with requirements.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 3
1.7 QUALITY ASSURANCE
A. Testing Agency Qualifications: Qualified according to ASTM C 1093 for testing
indicated.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Store masonry units on elevated platforms in a dry location. If units are not stored in an
enclosed location, cover tops and sides of stacks with waterproof sheeting, securely
tied. If units become wet, do not install until they are dry.
B. Store cementitious materials on elevated platforms, under cover, and in a dry location.
Do not use cementitious materials that have become damp.
C. Store aggregates where grading and other required characteristics can be maintained
and contamination avoided.
D. Deliver preblended, dry mortar mix in moisture-resistant containers. Store preblended,
dry mortar mix in delivery containers on elevated platforms in a dry location or in
covered weatherproof dispensing silos.
E. Store masonry accessories, including metal items, to prevent corrosion and
accumulation of dirt and oil.
1.9 FIELD CONDITIONS
A. Protection of Masonry: During construction, cover tops of walls, projections, and sills
with waterproof sheeting at end of each day's work. Cover partially completed masonry
when construction is not in progress.
1. Extend cover a minimum of 24 inches down both sides of walls, and hold cover
securely in place.
B. Do not apply uniform floor or roof loads for at least 12 hours and concentrated loads for
at least three days after building masonry walls or columns.
C. Stain Prevention: Prevent grout, mortar, and soil from staining the face of masonry to
be left exposed or painted. Immediately remove grout, mortar, and soil that come in
contact with such masonry.
1. Protect base of walls from rain-splashed mud and from mortar splatter by
spreading coverings on ground and over wall surface.
2. Protect sills, ledges, and projections from mortar droppings.
3. Protect surfaces of window and door frames, as well as similar products with
painted and integral finishes, from mortar droppings.
4. Turn scaffold boards near the wall on edge at the end of each day to prevent rain
from splashing mortar and dirt onto completed masonry.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 -4
D. Cold-Weather Requirements: Do not use frozen materials or materials mixed or coated
with ice or frost. Do not build on frozen substrates. Remove and replace unit masonry
damaged by frost or by freezing conditions. Comply with cold-weather construction
requirements contained in TMS 602/ACI 530.1/ASCE 6.
1. Cold-Weather Cleaning: Use liquid cleaning methods only when air temperature
is 40 deg F and higher and will remain so until masonry has dried, but not less
than seven days after completing cleaning.
E. Hot-Weather Requirements: Comply with hot-weather construction requirements
contained in TMS 602/ACI 530.1/ASCE 6.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations for Masonry Units: Obtain exposed masonry units of a uniform
texture and color, or a uniform blend within the ranges accepted for these
characteristics, from single source from single manufacturer for each product required.
B. Source Limitations for Mortar Materials: Obtain mortar ingredients of a uniform quality,
including color for exposed masonry, from single manufacturer for each cementitious
component and from single source or producer for each aggregate.
2.2 PERFORMANCE REQUIREMENTS
A. Provide structural unit masonry that develops indicated net-area compressive strengths
at 28 days.
1. Determine net-area compressive strength of masonry from average net-area
compressive strengths of masonry units and mortar types (unit-strength method)
according to TMS 602/ACI 530.1/ASCE 6.
2. Determine net-area compressive strength of masonry by testing masonry prisms
according to ASTM C 1314.
2.3 UNIT MASONRY, GENERAL
A. Masonry Standard: Comply with TMS 602/ACI 530.1/ASCE 6 except as modified by
requirements in the Contract Documents.
B. Defective Units: Referenced masonry unit standards may allow a certain percentage of
units to contain chips, cracks, or other defects exceeding limits stated. Do not use units
where such defects are exposed in the completed Work and will be within 20 feet
vertically and horizontally of a walking surface].
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 5
2.4 CONCRETE MASONRY UNITS
A. Shapes: Provide shapes indicated and as follows, with exposed surfaces matching
exposed faces of adjacent units unless otherwise indicated.
1. Provide special shapes for lintels, corners, jambs, sashes, movement joints,
headers, bonding, and other special conditions.
2. Provide square-edged units for outside corners unless otherwise indicated.
B. Integral Water Repellent: Provide units made with integral water repellent for exposed
units and where indicated.
1. Integral Water Repellent: Liquid polymeric, integral water-repellent admixture that
does not reduce flexural bond strength. Units made with integral water repellent,
when tested according to ASTM E 514/E 514M as a wall assembly made with
mortar containing integral water-repellent manufacturer's mortar additive, with
test period extended to 24 hours, shall show no visible water or leaks on the back
of test specimen.
C. CMUs: ASTM C 90.
1. Unit Compressive Strength: Provide units with minimum average net-area
compressive strength of 1900 psi..
2. Density Classification: Normal weight.
3. Size (Width): Manufactured to dimensions 3/8 inch less-than-nominal
dimensions.
2.5 CONCRETE AND MASONRY LINTELS
A. General: Provide one of the following:
B. Masonry Lintels: Prefabricated or built-in-place masonry lintels made from bond beam
CMUs matching adjacent CMUs in color, texture, and density classification, with
reinforcing bars placed as indicated and filled with coarse grout. Cure precast lintels
before handling and installing. Temporarily support built-in-place lintels until cured.
2.6 MORTAR AND GROUT MATERIALS
A. Portland Cement: ASTM C 150/C 150M, Type I or II, except Type III may be used for
cold-weather construction. Provide natural color or white cement as required to
produce mortar color indicated.
1. Alkali content shall not be more than 0.1 percent when tested according to
ASTM C 114.
B. Hydrated Lime: ASTM C 207, Type S.
C. Portland Cement-Lime Mix: Packaged blend of portland cement and hydrated lime
containing no other ingredients.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 6
D. Masonry Cement: ASTM C 91/C 91M.
E. Mortar Cement: ASTM C 1329/C 1329M.
F. Mortar Pigments: Natural and synthetic iron oxides and chromium oxides, compounded
for use in mortar mixes and complying with ASTM C 979/C 979M. Use only pigments
with a record of satisfactory performance in masonry mortar.
G. Aggregate for Mortar: ASTM C 144.
1. For mortar that is exposed to view, use washed aggregate consisting of natural
sand or crushed stone.
2. For joints less than 1/4 inch thick, use aggregate graded with 100 percent
passing the No. 16 sieve.
3. White-Mortar Aggregates: Natural white sand or crushed white stone.
4. Colored-Mortar Aggregates: Natural sand or crushed stone of color necessary to
produce required mortar color.
H. Aggregate for Grout: ASTM C 404.
I. Epoxy Pointing Mortar: ASTM C 395, epoxy-resin-based material formulated for use as
pointing mortar for glazed or pre-faced masonry units (and approved for such use by
manufacturer of units); in color indicated or, if not otherwise indicated, as selected by
Architect from manufacturer's colors.
J. Cold-Weather Admixture: Nonchloride, noncorrosive, accelerating admixture complying
with ASTM C 494/C 494M, Type C, and recommended by manufacturer for use in
masonry mortar of composition indicated.
K. Water-Repellent Admixture: Liquid water-repellent mortar admixture intended for use
with CMUs containing integral water repellent from same manufacturer.
L. Water: Potable.
2.7 REINFORCEMENT
A. Uncoated Steel Reinforcing Bars: ASTM A 615/A 615M or ASTM A 996/A 996M,
Grade 60 .
B. Reinforcing Bar Positioners: Wire units designed to fit into mortar bed joints spanning
masonry unit cells and to hold reinforcing bars in center of cells. Units are formed from
0.148-inch steel wire, hot-dip galvanized after fabrication. Provide units designed for
number of bars indicated.
C. Masonry-Joint Reinforcement, General: Ladder type complying with
ASTM A 951/A 951 M.
1. Interior Walls: Mill galvanized carbon steel.
2. Exterior Walls: Hot-dip galvanized carbon.
3. Wire Size for Side Rods: 0.148-inch diameter.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 7
4. Wire Size for Cross Rods: 0.148-inch diameter.
5. Spacing of Cross Rods: Not more than 16 inches o.c.
6. Provide in lengths of not less than 10 feet with prefabricated corner and tee
units.
2.8 TIES AND ANCHORS
A. General: Ties and anchors shall extend at least 1-1/2 inches into masonry but with at
least a 5/8-inch cover on outside face.
B. Materials: Provide ties and anchors specified in this article that are made from
materials that comply with the following unless otherwise indicated:
1. Mill-Galvanized, Carbon-Steel Wire: ASTM A 82/A 82M, with
ASTM A 641/A 641 M, Class 1 coating.
2. Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A 82/A 82M, with
ASTM A 153/A 153M, Class B-2 coating.
3. Galvanized-Steel Sheet: ASTM A 653/A 653M, Commercial Steel, G60 zinc
coating.
4. Steel Sheet, Galvanized after Fabrication: ASTM A 1008/A 1008M, Commercial
Steel, with ASTM A 153/A 153M, Class B coating.
5. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.
2.9 EMBEDDED FLASHING MATERIALS
A. Metal Flashing: Provide metal flashing complying with Section 076200 "Sheet Metal
Flashing and Trim" and as follows:
1. Fabricate continuous flashings in sections 96 inches long minimum, but not
exceeding 12 feet . Provide splice plates at joints of formed, smooth metal
flashing.
2. Fabricate through-wall metal flashing embedded in masonry from with ribs at 3-
inch intervals along length of flashing to provide an integral mortar bond.
3. Fabricate through-wall flashing with snaplock receiver on exterior face where
indicated to receive counterflashing.
4. Fabricate through-wall flashing with drip edge unless otherwise indicated.
Fabricate by extending flashing 1/2 inch out from wall, with outer edge bent down
30 degrees and hemmed.
5. Fabricate through-wall flashing with sealant stop unless otherwise indicated.
Fabricate by bending metal back on itself 3/4 inch (19 mm) at exterior face of wall
and down into joint 1/4 inch (6 mm) to form a stop for retaining sealant backer
rod.
6. Fabricate metal drip edges and sealant stops for ribbed metal flashing from plain
metal flashing of same metal as ribbed flashing and extending at least 3 inches
into wall with hemmed inner edge to receive ribbed flashing and form a hooked
seam. Form hem on upper surface of metal so that completed seam sheds
water.
7. Solder metal items at corners.
B. Application: Unless otherwise indicated, use the following:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 8
1. Where flashing is indicated to receive counterflashing, use metal flashing.
2. Where flashing is indicated to be turned down at or beyond the wall face, use
metal flashing.
3. Where flashing is partly exposed and is indicated to terminate at the wall face,
use metal flashing with a drip edge unless noted otherwise.
4. Where flashing is fully concealed, use metal flashing.
C. Solder and Sealants for Sheet Metal Flashings: As specified in Section 076200 "Sheet
Metal Flashing and Trim."
D. Adhesives, Primers, and Seam Tapes for Flashings: Flashing manufacturer's standard
products or products recommended by flashing manufacturer for bonding flashing
sheets to each other and to substrates.
2.10 MISCELLANEOUS MASONRY ACCESSORIES
A. Compressible Filler: Premolded filler strips complying with ASTM D 1056, Grade 2A1;
compressible up to 35 percent; of width and thickness indicated; formulated from
neoprene or PVC.
B. Preformed Control-Joint Gaskets: Made from styrene-butadiene-rubber compound,
complying with ASTM D 2000, Designation M2AA-805 or PVC, complying with
ASTM D 2287, Type PVC-65406 and designed to fit standard sash block and to
maintain lateral stability in masonry wall; size and configuration as indicated.
C. Bond-Breaker Strips: Asphalt-saturated felt complying with ASTM D 226/D 226M,
Type I (No. 15 asphalt felt).
2.11 MASONRY-CELL FILL
A. Lightweight-Aggregate Fill: ASTM C 331/C 331M.
2.12 MORTAR AND GROUT MIXES
A. General: Do not use admixtures, including pigments, air-entraining agents,
accelerators, retarders, water-repellent agents, antifreeze compounds, or other
admixtures unless otherwise indicated.
1. Do not use calcium chloride in mortar or grout.
2. Use portland cement-lime or mortar cement mortar unless otherwise indicated.
3. For exterior masonry, use portland cement-lime or mortar cement mortar.
4. For reinforced masonry, use portland cement-lime or [mortar cement] mortar.
5. Add cold-weather admixture (if used) at same rate for all mortar that will be
exposed to view, regardless of weather conditions, to ensure that mortar color is
consistent.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 9
B. Preblended, Dry Mortar Mix: Furnish dry mortar ingredients in form of a preblended
mix. Measure quantities by weight to ensure accurate proportions, and thoroughly
blend ingredients before delivering to Project site.
C. Mortar for Unit Masonry: Comply with ASTM C 270, Proportion Specification. Provide
the following types of mortar for applications stated unless another type is indicated or
needed to provide required compressive strength of masonry.
1. For masonry below grade or in contact with earth, use Type M.
2. For reinforced masonry, use Type S.
a. Cast-stone trim units.
D. Grout for Unit Masonry: Comply with ASTM C 476.
1. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse)
that will comply with TMS 602/ACI 530.1/ASCE 6 for dimensions of grout spaces
and pour height.
2. Proportion grout in accordance with ASTM C 476, Table 1 specified 28-day
compressive strength indicated, but not less than 2000 psi .
3. Provide grout with a slump of 8 to 11 inches as measured according to
ASTM C 143/C 143M.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine conditions, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of the Work.
1. For the record, prepare written report, endorsed by Installer, listing conditions
detrimental to performance of the Work.
2. Verify that foundations are within tolerances specified.
3. Verify that reinforcing dowels are properly placed.
4. Verify that substrates are free of substances that would impair mortar bond.
B. Before installation, examine rough-in and built-in construction for piping systems to
verify actual locations of piping.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION, GENERAL
A. Build chases and recesses to accommodate items specified in this and other Sections.
B. Leave openings for equipment to be installed before completing masonry. After
installing equipment, complete masonry to match construction immediately adjacent to
opening.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 10
C. Use full-size units without cutting if possible. If cutting is required to provide a
continuous pattern or to fit adjoining construction, cut units with motor-driven saws;
provide clean, sharp, unchipped edges. Allow units to dry before laying unless wetting
of units is specified. Install cut units with cut surfaces and, where possible, cut edges
concealed.
3.3 TOLERANCES
A. Dimensions and Locations of Elements:
1. For dimensions in cross section or elevation, do not vary by more than plus 1/2
inch or minus 1/4 inch.
2. For location of elements in plan, do not vary from that indicated by more than
plus or minus 1/2 inch .
B. Lines and Levels:
1. For bed joints and top surfaces of bearing walls, do not vary from level by more
than 1/4 inch in 10 feet , or 1/2-inch maximum.
2. For conspicuous horizontal lines, such as lintels, sills, parapets, and reveals, do
not vary from level by more than 1/8 inch in 10 feet.
3. For vertical lines and surfaces do not vary from plumb by more than 1/4 inch in
10 feet maximum.
4. For conspicuous vertical lines, such as external corners, door jambs, reveals,
and expansion and control joints, do not vary from plumb by more than 1/8 inch
in 10 feet maximum.
5. For lines and surfaces, do not vary from straight by more than 1/4 inch in 10
feetm.
6. For vertical alignment of exposed head joints, do not vary from plumb by more
than 1/4 inch in 10 feet .
7. For faces of adjacent exposed masonry units, do not vary from flush alignment
by more than 1/16 inch .
C. Joints:
1. For bed joints, do not vary from thickness indicated by more than plus or minus
1/8 inch , with a maximum thickness limited to 1/2 inch.
2. For exposed bed joints, do not vary from bed-joint thickness of adjacent courses
by more than 1/8 inch.
3. For head and collar joints, do not vary from thickness indicated by more than plus
3/8 inch or minus 1/4 inch.
4. For exposed head joints, do not vary from thickness indicated by more than plus
or minus 1/8 inch.
3.4 LAYING MASONRY WALLS
A. Lay out walls in advance for accurate spacing of surface bond patterns with uniform
joint thicknesses and for accurate location of openings, movement-type joints, returns,
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 11
and offsets. Avoid using less-than-half-size units, particularly at corners, jambs, and,
where possible, at other locations.
B. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed masonry
in running bond pattern as indicated on Drawings; do not use units with less-than-
nominal 4-inch horizontal face dimensions at corners or jambs.
C. Lay concealed masonry with all units in a wythe in running bond or bonded by lapping
not less than 2 inches . Bond and interlock each course of each wythe at corners. Do
not use units with less-than-nominal 4-inch horizontal face dimensions at corners or
jambs.
D. Stopping and Resuming Work: Stop work by stepping back units in each course from
those in course below; do not tooth. When resuming work, clean masonry surfaces that
are to receive mortar, remove loose masonry units and mortar, and wet brick if required
before laying fresh masonry.
E. Built-in Work: As construction progresses, build in items specified in this and other
Sections. Fill in solidly with masonry around built-in items.
F. Fill space between steel frames and masonry solidly with mortar unless otherwise
indicated.
G. Where built-in items are to be embedded in cores of hollow masonry units, place a
layer of metal lath, wire mesh, or plastic mesh in the joint below, and rod mortar or
grout into core.
H. Fill cores in hollow CMUs with grout 24 inches under bearing plates, beams, lintels,
posts, and similar items unless otherwise indicated.
I. Build nonload-bearing interior partitions full height of story to underside of solid floor or
roof structure above unless otherwise indicated.
1. Install compressible filler in joint between top of partition and underside of
structure above.
2. Fasten partition top anchors to structure above and build into top of partition.
Grout cells of CMUs solidly around plastic tubes of anchors and push tubes down
into grout to provide 1/2-inch clearance between end of anchor rod and end of
tube. Space anchors 48 inches o.c. unless otherwise indicated.
3. Wedge nonload-bearing partitions against structure above with small pieces of
tile, slate, or metal. Fill joint with mortar after dead-load deflection of structure
above approaches final position.
4. At fire-rated partitions, treat joint between top of partition and underside of
structure above to comply with Section 078443 "Joint Firestopping."
3.5 MORTAR BEDDING AND JOINTING
A. Lay hollow CMUs as follows:
1. Bed face shells in mortar and make head joints of depth equal to bed joints.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 12
2. Bed webs in mortar in all courses of piers, columns, and pilasters.
3. Bed webs in mortar in grouted masonry, including starting course on footings.
4. Fully bed entire units, including areas under cells, at starting course on footings
where cells are not grouted.
B. Lay solid CMUs with completely filled bed and head joints; butter ends with sufficient
mortar to fill head joints and shove into place. Do not deeply furrow bed joints or slush
head joints.
C. Set cast-stone trim units in full bed of mortar with full vertical joints. Fill dowel, anchor,
and similar holes.
1. Clean soiled surfaces with fiber brush and soap powder and rinse thoroughly with
clear water.
2. Wet joint surfaces thoroughly before applying mortar.
3. Rake out mortar joints for pointing with sealant.
D. Rake out mortar joints at pre-faced CMUs to a uniform depth of 1/4 inch and point with
epoxy mortar to comply with epoxy-mortar manufacturer's written instructions.
E. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than
joint thickness unless otherwise indicated.
F. Cut joints flush for masonry walls to receive plaster or other direct-applied finishes
(other than paint) unless otherwise indicated.
G. Cut joints flush where indicated to receive waterproofing unless otherwise indicated.
3.6 MASONRY-JOINT REINFORCEMENT
A. General: Install entire length of longitudinal side rods in mortar with a minimum cover of
5/8 inch on exterior side of walls, 1/2 inch elsewhere. Lap reinforcement a minimum of
6 inches .
1. Space reinforcement not more than 16 inches o.c.
2. Space reinforcement not more than 8 inches o.c. in foundation walls and parapet
walls.
3. Provide reinforcement not more than 8 inches above and below wall openings
and extending 12 inches beyond openings in addition to continuous
reinforcement.
B. Interrupt joint reinforcement at control and expansion joints unless otherwise indicated.
C. Provide continuity at wall intersections by using prefabricated T-shaped units.
D. Provide continuity at corners by using prefabricated L-shaped units.
E. Cut and bend reinforcing units as directed by manufacturer for continuity at[ corners,]
returns, offsets, column fireproofing, pipe enclosures, and other special conditions.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 13
3.7 ANCHORING MASONRY TO STRUCTURAL STEEL AND CONCRETE
A. Anchor masonry to structural steel and concrete, where masonry abuts or faces
structural steel or concrete, to comply with the following:
1. Provide an open space not less than 1/2 inch wide between masonry and
structural steel or concrete unless otherwise indicated. Keep open space free of
mortar and other rigid materials.
2. Anchor masonry with anchors embedded in masonry joints and attached to
structure.
3. Space anchors as indicated, but not more than 24 inches o.c. vertically and 36
inches o.c. horizontally.
3.8 CONTROL AND EXPANSION JOINTS
A. General: Install control- and expansion-joint materials in unit masonry as masonry
progresses. Do not allow materials to span control and expansion joints without
provision to allow for in-plane wall or partition movement.
B. Form control joints in concrete masonry using one of the following methods or as
indicated in the plans:
1. Fit bond-breaker strips into hollow contour in ends of CMUs on one side of
control joint. Fill resultant core with grout, and rake out joints in exposed faces for
application of sealant.
2. Install preformed control-joint gaskets designed to fit standard sash block.
3. Install interlocking units designed for control joints. Install bond-breaker strips at
joint. Keep head joints free and clear of mortar, or rake out joint for application of
sealant.
4. Install temporary foam-plastic filler in head joints, and remove filler when unit
masonry is complete for application of sealant.
3.9 LINTELS
A. Provide masonry lintels where shown and where openings of more than 24 inches for
block-size units are shown without structural steel or other supporting lintels.
B. Provide minimum bearing of 8 inches at each jamb unless otherwise indicated.
3.10 FLASHING
A. General: Install embedded flashing at ledges and other obstructions to downward flow
of water in wall where indicated.
B. Install flashing as follows unless otherwise indicated:
1. Prepare masonry surfaces so they are smooth and free from projections that
could puncture flashing. Where flashing is within mortar joint, place through-wall
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 14
flashing on sloping bed of mortar and cover with mortar. Before covering with
mortar, seal penetrations in flashing with adhesive, sealant, or tape as
recommended by flashing manufacturer.
2. At lintels, extend flashing a minimum of 6 inches into masonry at each end. At
heads and sills, extend flashing 6 inches at ends and turn up not less than 2
inches to form end dams.
3. Interlock end joints of ribbed sheet metal flashing by overlapping ribs not less
than 1-1/2 inches or as recommended by flashing manufacturer, and seal lap
with elastomeric sealant complying with requirements in Section 079200 "Joint
Sealants" for application indicated.
4. Install metal drip edges and sealant stops with ribbed sheet metal flashing by
interlocking hemmed edges to form hooked seam. Seal seam with elastomeric
sealant complying with requirements in Section 079200 "Joint Sealants" for
application indicated.
5. Install metal drip edges beneath flexible flashing at exterior face of wall. Stop
flexible flashing 1/2 inch back from outside face of wall, and adhere flexible
flashing to top of metal drip edge.
6. Install metal flashing termination beneath flexible flashing at exterior face of wall.
Stop flexible flashing 1/2 inch back from outside face of wall, and adhere flexible
flashing to top of metal flashing termination.
7. Cut flexible flashing off flush with face of wall after masonry wall construction is
completed.
C. Install single-wythe CMU flashing system in bed joints of CMU walls where indicated to
comply with manufacturer's written instructions. Install CMU cell pans with upturned
edges located below face shells and webs of CMUs above and with weep spouts
aligned with face of wall. Install CMU web covers so that they cover upturned edges of
CMU cell pans at CMU webs and extend from face shell to face shell.
D. Install reglets and nailers for flashing and other related construction where they are
shown to be built into masonry.
3.11 REINFORCED UNIT MASONRY INSTALLATION
A. Temporary Formwork and Shores: Construct formwork and shores as needed to
support reinforced masonry elements during construction.
1. Construct formwork to provide shape, line, and dimensions of completed
masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar
and grout. Brace, tie, and support forms to maintain position and shape during
construction and curing of reinforced masonry.
2. Do not remove forms and shores until reinforced masonry members have
hardened sufficiently to carry their own weight and other loads that may be
placed on them during construction.
B. Placing Reinforcement: Comply with requirements in TMS 602/ACI 530.1/ASCE 6.
C. Grouting: Do not place grout until entire height of masonry to be grouted has attained
enough strength to resist grout pressure.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 15
1. Comply with requirements in TMS 602/ACI 530.1/ASCE 6 for cleanouts and for
grout placement, including minimum grout space and maximum pour height.
2. Limit height of vertical grout pours to not more than 60 inches.
3.12 FIELD QUALITY CONTROL
A. Testing and Inspecting: Owner will engage special inspectors to perform tests and
inspections and prepare reports. Allow inspectors access to scaffolding and work areas
as needed to perform tests and inspections. Retesting of materials that fail to comply
with specified requirements shall be done at Contractor's expense.
B. Inspections: Special inspections according to Level B in TMS 402/ACI 530/ASCE 5.
1. Begin masonry construction only after inspectors have verified proportions of
site-prepared mortar.
2. Place grout only after inspectors have verified compliance of grout spaces and of
grades, sizes, and locations of reinforcement.
3. Place grout only after inspectors have verified proportions of site-prepared grout.
C. Testing Prior to Construction: One set of tests.
D. Testing Frequency: One set of tests for each 5000 sq. ft of wall area or portion thereof.
E. Concrete Masonry Unit Test: For each type of unit provided, according to ASTM C 140
for compressive strength.
F. Mortar Aggregate Ratio Test (Proportion Specification): For each mix provided,
according to ASTM C 780.
G. Mortar Test (Property Specification): For each mix provided, according to ASTM C 780.
Test mortar for mortar air content and compressive strength.
H. Grout Test (Compressive Strength): For each mix provided, according to
ASTM C 1019.
I. Prism Test: For each type of construction provided, according to ASTM C 1314 at 7
days and at 28 days.
3.13 REPAIRING, POINTING, AND CLEANING
A. Remove and replace masonry units that are loose, chipped, broken, stained, or
otherwise damaged or that do not match adjoining units. Install new units to match
adjoining units; install in fresh mortar, pointed to eliminate evidence of replacement.
B. Pointing: During the tooling of joints, enlarge voids and holes, except weep holes, and
completely fill with mortar. Point up joints, including corners, openings, and adjacent
construction, to provide a neat, uniform appearance. Prepare joints for sealant
application, where indicated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CONCRETE UNIT MASONRY
REEDLEY, CA. SECTION 042200 - 16
C. In-Progress Cleaning: Clean unit masonry as work progresses by dry brushing to
remove mortar fins and smears before tooling joints.
D. Final Cleaning: After mortar is thoroughly set and cured, clean exposed masonry as
follows:
1. Remove large mortar particles by hand with wooden paddles and nonmetallic
scrape hoes or chisels.
2. Test cleaning methods on sample wall panel; leave one-half of panel uncleaned
for comparison purposes. Obtain Architect's approval of sample cleaning before
proceeding with cleaning of masonry.
3. Protect adjacent stone and nonmasonry surfaces from contact with cleaner by
covering them with liquid strippable masking agent or polyethylene film and
waterproof masking tape.
4. Wet wall surfaces with water before applying cleaners; remove cleaners promptly
by rinsing surfaces thoroughly with clear water.
5. Clean concrete masonry by applicable cleaning methods indicated in
NCMA TEK 8-4A.
3.14 MASONRY WASTE DISPOSAL
A. Salvageable Materials: Unless otherwise indicated, excess masonry materials are
Contractor's property. At completion of unit masonry work, remove from Project site.
B. Waste Disposal as Fill Material: Dispose of clean masonry waste, including excess or
soil-contaminated sand, waste mortar, and broken masonry units, by crushing and
mixing with fill material as fill is placed.
1. Crush masonry waste to less than 4 inches in each dimension.
2. Mix masonry waste with at least two parts of specified fill material for each part of
masonry waste. Fill material is specified in Section 312000 "Earth Moving."
3. Do not dispose of masonry waste as fill within 18 inches of finished grade.
C. Masonry Waste Recycling: Return broken CMUs not used as fill to manufacturer for
recycling.
D. Excess Masonry Waste: Remove excess clean masonry waste that cannot be used as
fill, as described above or recycled, and other masonry waste, and legally dispose of
off Owner's property.
END OF SECTION 042200
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 1
SECTION 054000 - COLD-FORMED METAL FRAMING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Load-bearing wall framing.
2. Exterior non-load-bearing wall framing.
3. Interior non-load-bearing wall framing.
4. Roof rafter framing.
5. Ceiling joist framing.
6. Soffit framing.
B. Related Requirements:
1. Section 055000 "Metal Fabrications" for miscellaneous steel shapes, masonry shelf
angles, and connections used with cold-formed metal framing.
1.3 ACTION SUBMITTALS
A. Product Data: For the following:
1. Cold-formed steel framing materials.
2. Load-bearing wall framing.
3. Exterior non-load-bearing wall framing.
4. Interior non-load-bearing wall framing.
5. Vertical deflection clips.
6. Single deflection track.
7. Drift clips.
8. Roof-rafter framing.
9. Ceiling joist framing.
10. Soffit framing.
11. Post-installed anchors.
12. Power-actuated anchors.
13. Sill sealer gasket.
14. Sill sealer gasket/termite barrier.
B. Shop Drawings:
1. Include layout, spacings, sizes, thicknesses, and types of cold-formed steel framing;
fabrication; and fastening and anchorage details, including mechanical fasteners.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 2
2. Indicate reinforcing channels, opening framing, supplemental framing, strapping,
bracing, bridging, splices, accessories, connection details, and attachment to
adjoining work.
1.4 INFORMATIONAL SUBMITTALS
A. Qualification Data: For testing agency.
B. Welding certificates.
C. Product Certificates: For each type of code-compliance certification for studs and tracks.
D. Product Test Reports: For each listed product, for tests performed by manufacturer and
witnessed by a qualified testing agency .
1. Steel sheet.
2. Expansion anchors.
3. Power-actuated anchors.
4. Mechanical fasteners.
5. Vertical deflection clips.
6. Horizontal drift deflection clips
7. Miscellaneous structural clips and accessories.
E. Research Reports:
1. For nonstandard cold-formed steel framing post-installed anchors and power-
actuated fasteners, from ICC-ES or other qualified testing agency acceptable to
authorities having jurisdiction.
2. For sill sealer gasket/termite barrier, showing compliance with ICC-ES AC380.
1.5 QUALITY ASSURANCE
A. Testing Agency Qualifications: Qualified according to ASTM E329 for testing indicated.
B. Product Tests: Mill certificates or data from a qualified independent testing agency
indicating steel sheet complies with requirements, including base-metal thickness, yield
strength, tensile strength, total elongation, chemical requirements, and metallic-coating
thickness.
C. Code-Compliance Certification of Studs and Tracks: Provide documentation that framing
members are certified according to the product-certification program of the Certified Steel
Stud Association the Steel Framing Industry Association or the Steel Stud Manufacturers
Association.
D. Welding Qualifications: Qualify procedures and personnel according to the following:
1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."
2. AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel."
E. Comply with AISI S230 "Standard for Cold-Formed Steel Framing - Prescriptive Method
for One and Two Family Dwellings."
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 3
PART 2 - PRODUCTS
2.1 COLD-FORMED STEEL FRAMING MATERIALS
A. Steel Sheet: ASTM A1003/A1003M, Structural Grade, Type H, metallic coated, of grade
and coating designation as follows:
1. Grade: ST33H .
2. Coating: G60 , A60 , AZ50 , or GF30 .
B. Steel Sheet for Vertical Deflection and Drift Clips: ASTM A653/A653M, structural steel,
zinc coated, of grade and coating as follows:
1. Grade: 33 .
2. Coating: G60 .
2.2 LOAD-BEARING WALL FRAMING
A. Steel Studs: Manufacturer's standard C-shaped steel studs, of web depths indicated,
punched, with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: 0.0677 inch .
2. Flange Width: 2 inches .
3. Section Properties: As Indicated on Drawings .
B. Steel Track: Manufacturer's standard U-shaped steel track, of web depths indicated,
unpunched, with straight flanges, and as follows:
1. Minimum Base-Metal Thickness: 0.0428 inch .
2. Flange Width: 1-1/4 inches .
C. Steel Box or Back-to-Back Headers: Manufacturer's standard C-shapes used to form
header beams, of web depths indicated, unpunched, with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: 0.0677 inch .
2. Flange Width: 2 inches .
3. Section Properties: As Indicated on Drawings .
2.3 INTERIOR NON-LOAD-BEARING WALL FRAMING
A. Steel Studs: Manufacturer's standard C-shaped steel studs, of web depths indicated,
punched, with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: As Indicated .
2. Flange Width: 1-5/8 inches .
B. Steel Track: Manufacturer's standard U-shaped steel track, of web depths indicated,
unpunched, with unstiffened flanges, and as follows:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 4
1. Minimum Base-Metal Thickness: As Indicated, minimum matching steel stud
thickness .
2. Flange Width: 1-1/4 inches .
C. Vertical Deflection Clips: Manufacturer's standard bypass clips, capable of
accommodating upward and downward vertical displacement of primary structure through
positive mechanical attachment to stud web.
D. Single Deflection Track: Manufacturer's single, deep-leg, U-shaped steel track;
unpunched, with unstiffened flanges, of web depth to contain studs while allowing free
vertical movement, with flanges designed to support horizontal loads and transfer them to
the primary structure, and as follows:
1. Minimum Base-Metal Thickness: As Indicated .
2. Flange Width: 1 inch plus the design gap for one-story structures .
E. Drift Clips: Manufacturer's standard bypass or head clips, capable of isolating wall stud
from upward and downward vertical displacement and lateral drift of primary structure
through positive mechanical attachment to stud web and structure.
2.4 ROOF-RAFTER FRAMING
A. Steel Rafters: Manufacturer's standard C-shaped steel sections, of web depths indicated,
with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: As Indicated on Drawings .
2. Flange Width: As Indicated on Drawings , minimum.
3. Section Properties: As Indicated on Drawings .
2.5 CEILING JOIST FRAMING
A. Steel Ceiling Joists: Manufacturer's standard C-shaped steel sections, of web depths
indicated, punched with standard holes, with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: As Indicated .
2. Flange Width: 1-5/8 inches , minimum.
2.6 SOFFIT FRAMING
A. Exterior Soffit Frame: Manufacturer's standard C-shaped steel sections, of web depths
indicated, with stiffened flanges, and as follows:
1. Minimum Base-Metal Thickness: As Indicated .
2. Flange Width: 1-5/8 inches , minimum.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 5
2.7 FRAMING ACCESSORIES
A. Fabricate steel-framing accessories from ASTM A1003/A1003M, Structural Grade,
Type H, metallic coated steel sheet, of same grade and coating designation used for
framing members.
B. Provide accessories of manufacturer's standard thickness and configuration, unless
otherwise indicated, as follows:
1. Supplementary framing.
2. Bracing, bridging, and solid blocking.
3. Web stiffeners.
4. Anchor clips.
5. End clips.
6. Foundation clips.
7. Gusset plates.
8. Stud kickers and knee braces.
9. Joist hangers and end closures.
10. Hole-reinforcing plates.
11. Backer plates.
2.8 ANCHORS, CLIPS, AND FASTENERS
A. Steel Shapes and Clips: ASTM A36/A36M, zinc coated by hot-dip process according to
ASTM A123/A123M.
B. Anchor Bolts: ASTM F1554, Grade 36 , threaded carbon-steel hex-headed bolts, carbon-
steel nuts, and flat, hardened-steel washers; zinc coated by hot-dip process according to
ASTM A153/A153M, Class C .
C. Post-Installed Anchors: Fastener systems with bolts of same basic metal as fastened
metal, if visible, unless otherwise indicated; with working capacity greater than or equal to
the design load, according to an evaluation report acceptable to authorities having
jurisdiction, based on ICC-ES AC01 ICC-ES AC193 ICC-ES AC58 or ICC-ES AC308 as
appropriate for the substrate.
1. Uses: Securing cold-formed steel framing to structure.
2. Type: Torque-controlled expansion anchor or adhesive anchor.
3. Material for Interior Locations: Carbon-steel components zinc plated to comply with
ASTM B633 or ASTM F1941, Class Fe/Zn 5, unless otherwise indicated.
4. Material for Exterior or Interior Locations and Where Stainless Steel Is Indicated:
Alloy Group 1 stainless-steel bolts, ASTM F593, and nuts, ASTM F594.
D. Power-Actuated Anchors: Fastener systems with working capacity greater than or equal
to the design load, according to an evaluation report acceptable to authorities having
jurisdiction, based on ICC-ES AC70.
E. Mechanical Fasteners: ASTM C1513, corrosion-resistant-coated, self-drilling, self-
tapping, steel drill screws.
1. Head Type: Low-profile head beneath sheathing; manufacturer's standard
elsewhere.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 6
F. Welding Electrodes: Comply with AWS standards.
2.9 MISCELLANEOUS MATERIALS
A. Galvanizing Repair Paint: ASTM A780/A780M MIL-P-21035B or SSPC-Paint 20.
B. Cement Grout: Portland cement, ASTM C150/C150M, Type I; and clean, natural sand,
ASTM C404. Mix at ratio of 1 part cement to 2-1/2 parts sand, by volume, with minimum
water required for placement and hydration.
C. Nonmetallic, Nonshrink Grout: Factory-packaged, nonmetallic, noncorrosive, nonstaining
grout, complying with ASTM C1107/C1107M, and with a fluid consistency and 30-minute
working time.
D. Shims: Load-bearing, high-density, multimonomer, nonleaching plastic; or cold-formed
steel of same grade and metallic coating as framing members supported by shims.
E. Sill Sealer Gasket: Closed-cell neoprene foam, 1/4 inch thick, selected from
manufacturer's standard widths to match width of bottom track or rim track members as
required.
2.10 FABRICATION
A. Fabricate cold-formed steel framing and accessories plumb, square, and true to line, and
with connections securely fastened, according to referenced AISI's specifications and
standards, manufacturer's written instructions, and requirements in this Section.
1. Fabricate framing assemblies using jigs or templates.
2. Cut framing members by sawing or shearing; do not torch cut.
3. Fasten cold-formed steel framing members by welding, screw fastening, clinch
fastening, pneumatic pin fastening, or riveting as standard with fabricator. Wire tying
of framing members is not permitted.
a. Comply with AWS D1.3/D1.3M requirements and procedures for welding,
appearance and quality of welds, and methods used in correcting welding
work.
b. Locate mechanical fasteners and install according to Shop Drawings, with
screws penetrating joined members by no fewer than three exposed screw
threads.
4. Fasten other materials to cold-formed steel framing by welding, bolting, pneumatic
pin fastening, or screw fastening, according to Shop Drawings.
B. Reinforce, stiffen, and brace framing assemblies to withstand handling, delivery, and
erection stresses. Lift fabricated assemblies by means that prevent damage or permanent
distortion.
C. Tolerances: Fabricate assemblies level, plumb, and true to line to a maximum allowable
variation of 1/8 inch in 10 feet and as follows:
1. Spacing: Space individual framing members no more than plus or minus 1/8 inch
from plan location. Cumulative error shall not exceed minimum fastening
requirements of sheathing or other finishing materials.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 7
2. Squareness: Fabricate each cold-formed steel framing assembly to a maximum out-
of-square tolerance of 1/8 inch.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, conditions, and abutting structural framing for compliance with
requirements for installation tolerances and other conditions affecting performance of the
Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Before sprayed fire-resistive materials are applied, attach continuous angles,
supplementary framing, or tracks to structural members indicated to receive sprayed fire-
resistive materials.
B. After applying sprayed fire-resistive materials, remove only as much of these materials as
needed to complete installation of cold-formed framing without reducing thickness of fire-
resistive materials below that required to obtain fire-resistance ratings indicated. Protect
remaining fire-resistive materials from damage.
C. Install load-bearing shims or grout between the underside of load-bearing wall bottom track
and the top of foundation wall or slab at locations with a gap larger than 1/4 inch to ensure
a uniform bearing surface on supporting concrete or masonry construction.
D. Install sill sealer gasket at the underside of wall bottom track or rim track and at the top of
foundation wall or slab at stud or joist locations.
E. Install sill sealer gasket/termite barrier in accordance with manufacturer's written
instructions at the underside of wall bottom track or rim track and at the top of foundation
wall or slab at stud or joist locations.
3.3 INSTALLATION, GENERAL
A. Cold-formed steel framing may be shop or field fabricated for installation, or it may be field
assembled.
B. Install cold-formed steel framing according to AISI S200, AISI S202, and manufacturer's
written instructions unless more stringent requirements are indicated.
C. Install shop- or field-fabricated, cold-formed framing and securely anchor to supporting
structure.
1. Screw, bolt, or weld wall panels at horizontal and vertical junctures to produce flush,
even, true-to-line joints with maximum variation in plane and true position between
fabricated panels not exceeding 1/16 inch.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 8
D. Install cold-formed steel framing and accessories plumb, square, and true to line, and with
connections securely fastened.
1. Cut framing members by sawing or shearing; do not torch cut.
2. Fasten cold-formed steel framing members by welding, screw fastening, clinch
fastening, or riveting. Wire tying of framing members is not permitted.
a. Comply with AWS D1.3/D1.3M requirements and procedures for welding,
appearance and quality of welds, and methods used in correcting welding
work.
b. Locate mechanical fasteners, install according to Shop Drawings, and comply
with requirements for spacing, edge distances, and screw penetration.
E. Install framing members in one-piece lengths unless splice connections are indicated for
track or tension members.
F. Install temporary bracing and supports to secure framing and support loads equal to those
for which structure was designed. Maintain braces and supports in place, undisturbed, until
entire integrated supporting structure has been completed and permanent connections to
framing are secured.
G. Do not bridge building expansion joints with cold-formed steel framing. Independently
frame both sides of joints.
H. Install insulation, specified in Section 072100 "Thermal Insulation," in framing-assembly
members, such as headers, sills, boxed joists, and multiple studs at openings, that are
inaccessible on completion of framing work.
I. Fasten hole-reinforcing plate over web penetrations that exceed size of manufacturer's
approved or standard punched openings.
3.4 INSTALLATION OF LOAD-BEARING WALL FRAMING
A. Install continuous top and bottom tracks sized to match studs. Align tracks accurately and
securely anchor at corners and ends, and at spacings as follows:
1. Anchor Spacing: As Indicated on Drawings .
B. Squarely seat studs against top and bottom tracks, with gap not exceeding 1/8 inch
between the end of wall-framing member and the web of track.
1. Fasten both flanges of studs to top and bottom tracks.
2. Space studs as follows:
a. Stud Spacing: As indicated on Drawings .
C. Set studs plumb, except as needed for diagonal bracing or required for nonplumb walls or
warped surfaces and similar configurations.
D. Align studs vertically where floor framing interrupts wall-framing continuity. Where studs
cannot be aligned, continuously reinforce track to transfer loads.
E. Align floor and roof framing over studs according to AISI S200, Section C1. Where framing
cannot be aligned, continuously reinforce track to transfer loads.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 9
F. Anchor studs abutting structural columns or walls, including masonry walls, to supporting
structure.
G. Install headers over wall openings wider than stud spacing. Locate headers above
openings. Fabricate headers of compound shapes indicated or required to transfer load to
supporting studs, complete with clip-angle connectors, web stiffeners, or gusset plates.
1. Frame wall openings with not less than a double stud at each jamb of frame. Fasten
jamb members together to uniformly distribute loads.
2. Install tracks and jack studs above and below wall openings. Anchor tracks to jamb
studs with clip angles or by welding, and space jack studs same as full-height wall
studs.
H. Install supplementary framing, blocking, and bracing in stud framing indicated to support
fixtures, equipment, services, casework, heavy trim,furnishings, and similar work requiring
attachment to framing.
1. If type of supplementary support is not indicated, comply with stud manufacturer's
written recommendations and industry standards in each case, considering weight
or load resulting from item supported.
I. Install horizontal bridging in stud system, spaced vertically 48 inches . Fasten at each stud
intersection.
1. Channel Bridging: Cold-rolled steel channel, welded or mechanically fastened to
webs of punched studs with a minimum of two screws into each flange of the clip
angle for framing members up to 6 inches deep.
2. Strap Bridging: Combination of flat, taut, steel sheet straps of width and thickness
indicated and stud-track solid blocking of width and thickness to match studs. Fasten
flat straps to stud flanges, and secure solid blocking to stud webs or flanges.
3. Bar Bridging: Proprietary bridging bars installed according to manufacturer's written
instructions.
J. Install steel sheet diagonal bracing straps to both stud flanges; terminate at and fasten to
reinforced top and bottom tracks. Fasten clip-angle connectors to multiple studs at ends
of bracing and anchor to structure.
K. Install miscellaneous framing and connections, including supplementary framing, web
stiffeners, clip angles, continuous angles, anchors, and fasteners, to provide a complete
and stable wall-framing system.
3.5 INSTALLATION OF INTERIOR NONLOADBEARING WALL FRAMING
A. Install continuous tracks sized to match studs. Align tracks accurately and securely anchor
to supporting structure.
B. Fasten both flanges of studs to top and bottom track unless otherwise indicated. Space
studs as follows:
1. Stud Spacing: As indicated on Drawings .
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 10
C. Set studs plumb, except as needed for diagonal bracing or required for nonplumb walls or
warped surfaces and similar requirements.
D. Isolate non-load-bearing steel framing from building structure to prevent transfer of vertical
loads while providing lateral support.
1. Install single deep-leg deflection tracks and anchor to building structure.
2. Install double deep-leg deflection tracks and anchor outer track to building structure.
3. Connect vertical deflection clips to studs and anchor to building structure.
4. Connect drift clips to cold-formed steel metal framing and anchor to building
structure.
E. Install horizontal bridging in wall studs, spaced vertically in rows indicated on Shop
Drawings but not more than 48 inches apart. Fasten at each stud intersection.
1. Channel Bridging: Cold-rolled steel channel, welded or mechanically fastened to
webs of punched studs.
2. Strap Bridging: Combination of flat, taut, steel sheet straps of width and thickness
indicated and stud-track solid blocking of width and thickness to match studs. Fasten
flat straps to stud flanges and secure solid blocking to stud webs or flanges.
3. Bar Bridging: Proprietary bridging bars installed according to manufacturer's written
instructions.
F. Top Bridging for Single Deflection Track: Install row of horizontal bridging within 12 inches
of single deflection track. Install a combination of bridging and stud or stud-track solid
blocking of width and thickness matching studs, secured to stud webs or flanges.
1. Install solid blocking at 96-inch centers .
G. Install miscellaneous framing and connections, including stud kickers, web stiffeners, clip
angles, continuous angles, anchors, and fasteners, to provide a complete and stable wall-
framing system.
3.6 INSTALLATION OF JOIST FRAMING
A. Install perimeter joist track sized to match joists. Align and securely anchor or fasten track
to supporting structure at corners, ends, and spacings indicated.
B. Install joists bearing on supporting frame, level, straight, and plumb; adjust to final position,
brace, and reinforce. Fasten joists to both flanges of joist track.
1. Install joists over supporting frame with a minimum end bearing of 1-1/2 inches.
2. Reinforce ends and bearing points of joists with web stiffeners, end clips, joist
hangers, steel clip angles, or steel-stud sections.
C. Space joists not more than 2 inches from abutting walls, and as follows:
1. Joist Spacing: As indicated on Drawings .
D. Frame openings with built-up joist headers, consisting of joist and joist track or another
combination of connected joists if indicated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 11
E. Install joist reinforcement at interior supports with single, short length of joist section
located directly over interior support, with lapped joists of equal length to joist
reinforcement.
1. Install web stiffeners to transfer axial loads of walls above.
F. Install bridging at smaller intervals of those indicated on drawings or on Shop Drawings.
Fasten bridging at each joist intersection as follows:
1. Joist-Track Solid Bridging: Joist-track solid blocking of width and thickness indicated,
secured to joist webs.
2. Combination Bridging: Combination of flat, taut, steel sheet straps of width and
thickness indicated and joist-track solid blocking of width and thickness indicated.
Fasten flat straps to bottom flange of joists and secure solid blocking to joist webs.
G. Secure joists to load-bearing interior walls to prevent lateral movement of bottom flange.
H. Install miscellaneous joist framing and connections, including web stiffeners, closure
pieces, clip angles, continuous angles, hold-down angles, anchors, and fasteners, to
provide a complete and stable joist-framing assembly.
3.7 INSTALLATION TOLERANCES
A. Install cold-formed steel framing level, plumb, and true to line to a maximum allowable
tolerance variation of 1/8 inch in 10 feet and as follows:
1. Space individual framing members no more than plus or minus 1/8 inch from plan
location. Cumulative error shall not exceed minimum fastening requirements of
sheathing or other finishing materials.
3.8 REPAIR
A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on fabricated and
installed cold-formed steel framing with galvanized repair paint according to
ASTM A780/A780M and manufacturer's written instructions.
3.9 FIELD QUALITY CONTROL
A. Testing: Owner will engage a qualified independent testing and inspecting agency to
perform field tests and inspections and prepare test reports.
B. Field and shop welds will be subject to testing and inspecting.
C. Testing agency will report test results promptly and in writing to Contractor and Architect.
D. Cold-formed steel framing will be considered defective if it does not pass tests and
inspections.
E. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER COLD-FORMED METAL FRAMING
REEDLEY, CA. SECTION 054000 - 12
3.10 PROTECTION
A. Provide final protection and maintain conditions, in a manner acceptable to manufacturer
and Installer, that ensure that cold-formed steel framing is without damage or deterioration
at time of Substantial Completion.
END OF SECTION 054000
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEATHING
REEDLEY, CA. SECTION 061600 - 1
SECTION 061600 - SHEATHING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Roof sheathing.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of process and factory-fabricated product. Indicate
component materials and dimensions and include construction and application details.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Stack panels flat with spacers beneath and between each bundle to provide air
circulation. Protect sheathing from weather by covering with waterproof sheeting,
securely anchored. Provide for air circulation around stacks and under coverings.
PART 2 - PRODUCTS
2.1 WOOD PANEL PRODUCTS
A. Thickness: As needed to comply with requirements specified, but not less than
thickness indicated.
B. Factory mark panels to indicate compliance with applicable standard.
2.2 ROOF SHEATHING
A. Plywood Sheathing: DOC PS 1 sheathing.
1. Span Rating: Not less than 20/0.
2. Nominal Thickness: Not less than 5/8 inch.
B. Oriented-Strand-Board Sheathing: DOC PS 2
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEATHING
REEDLEY, CA. SECTION 061600 - 2
1. Span Rating: Not less than 20/0.
2. Nominal Thickness: 5/8 inch
2.3 FASTENERS
A. General: Provide fasteners of size and type indicated that comply with requirements
specified in this article for material and manufacture.
B. Nails, Brads, and Staples: ASTM F 1667.
C. Power-Driven Fasteners: Fastener systems with an evaluation report acceptable to
authorities having jurisdiction, based on ICC-ES AC70.
D. Screws for Fastening Wood Structural Panels to Cold-Formed Metal Framing:
ASTM C 954, except with wafer heads and reamer wings, length as recommended by
screw manufacturer for material being fastened.
E. Screws for Fastening Gypsum Sheathing to Cold-Formed Metal Framing: Steel drill
screws, in length recommended by sheathing manufacturer for thickness of sheathing
to be attached.
1. For steel framing less than 0.0329 inch thick, use screws that comply with
ASTM C 1002.
2. For steel framing from 0.033 to 0.112 inch thick, use screws that comply with
ASTM C 954.
F. Screws for Fastening Composite Nail Base Insulated Roof Sheathing to Metal Roof
Deck: Steel drill screws, in type and length recommended by sheathing manufacturer
for thickness of sheathing to be attached, with organic-polymer or other corrosion-
protective coating having a salt-spray resistance of more than 800 hours according to
ASTM B 117. Provide washers or plates if recommended by sheathing manufacturer.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Do not use materials with defects that impair quality of sheathing or pieces that are too
small to use with minimum number of joints or optimum joint arrangement. Arrange
joints so that pieces do not span between fewer than three support members.
B. Cut panels at penetrations, edges, and other obstructions of work; fit tightly against
abutting construction unless otherwise indicated.
C. Securely attach to substrate by fastening as indicated, complying with the following:
1. Table 2304.9.1, "Fastening Schedule," in the ICC's International Building Code.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEATHING
REEDLEY, CA. SECTION 061600 - 3
2. Table R602.3(1), "Fastener Schedule for Structural Members," and
Table R602.3(2), "Alternate Attachments," in the ICC's International Residential
Code for One- and Two-Family Dwellings.
3. ICC-ES evaluation report for fastener.
D. Use common wire nails unless otherwise indicated. Select fasteners of size that will not
fully penetrate members where opposite side will be exposed to view or will receive
finish materials. Make tight connections. Install fasteners without splitting wood.
E. Coordinate parapet and roof sheathing installation with flashing and joint-sealant
installation so these materials are installed in sequence and manner that prevent
exterior moisture from passing through completed assembly.
F. Do not bridge building expansion joints; cut and space edges of panels to match
spacing of structural support elements.
G. Coordinate sheathing installation with installation of materials installed over sheathing
so sheathing is not exposed to precipitation or left exposed at end of the workday when
rain is forecast.
3.2 WOOD STRUCTURAL PANEL INSTALLATION
A. General: Comply with applicable recommendations in APA Form No. E30, "Engineered
Wood Construction Guide," for types of structural-use panels and applications
indicated.
B. Fastening Methods: Fasten panels as indicated below:
1. Wall and Roof Sheathing:
a. Screw to cold-formed metal framing.
b. Space panels 1/8 inch apart at edges and ends.
3.3 GYPSUM SHEATHING INSTALLATION
A. Comply with GA-253 and with manufacturer's written instructions.
1. Fasten gypsum sheathing to cold-formed metal framing with screws.
2. Install panels with a 3/8-inch gap where non-load-bearing construction abuts
structural elements.
3. Install panels with a 1/4-inch gap where they abut masonry or similar materials
that might retain moisture, to prevent wicking.
B. Apply fasteners so heads bear tightly against face of sheathing, but do not cut into
facing.
C. Horizontal Installation: Install sheathing with V-grooved edge down and tongue edge
up. Interlock tongue with groove to bring long edges in contact with edges of adjacent
panels without forcing. Abut ends over centers of studs, and stagger end joints of
adjacent panels not less than one stud spacing. Attach at perimeter and within field of
panel to each stud.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEATHING
REEDLEY, CA. SECTION 061600 - 4
1. Space fasteners approximately 8 inches o.c. and set back a minimum of 3/8 inch
from edges and ends of panels.
D. Vertical Installation: Install vertical edges centered over studs. Abut ends and edges
with those of adjacent panels. Attach at perimeter and within field of panel to each
stud.
1. Space fasteners approximately 8 inches o.c. and set back a minimum of 3/8 inch
from edges and ends of panels.
2. For sheathing under stucco cladding, panels may be initially tacked in place with
screws if overlying self-furring metal lath is screw-attached through sheathing to
studs immediately after sheathing is installed.
E. Seal sheathing joints according to sheathing manufacturer's written instructions.
1. Apply elastomeric sealant to joints and fasteners and trowel flat. Apply sufficient
amount of sealant to completely cover joints and fasteners after troweling. Seal
other penetrations and openings.
2. Apply glass-fiber sheathing tape to glass-mat gypsum sheathing joints and apply
and trowel sealant to embed entire face of tape in sealant. Apply sealant to
exposed fasteners with a trowel so fasteners are completely covered. Seal other
penetrations and openings.
END OF SECTION 061600
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 1
SECTION 071900 -WATER REPELLENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes penetrating water-repellent treatments for the following vertical and
horizontal surfaces:
1. Cast-in-place concrete.
2. Concrete unit masonry.
B. Related Requirements:
1. Section 042000 "Unit Masonry" for integral water-repellent admixture for unit
masonry assemblies.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include manufacturer's printed statement of VOC content.
2. Include manufacturer's standard colors.
3. Include manufacturer's recommended number of coats for each type of substrate
and spreading rate for each separate coat.
4. Include printout of current "MPI Approved Products List" for each product
category specified in Part 2 that specifies water repellents approved by MPI, with
the proposed product highlighted.
B. Samples: For each type of water repellent and substrate indicated, 12 by 12 inches in
size, with specified water-repellent treatment applied to half of each Sample.
1.5 INFORMATIONAL SUBMITTALS
A. Product Certificates: For each type of water repellent.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 2
B. Preconstruction Test Reports: For water-repellent-treated substrates.
C. Field quality-control reports.
D. Sample Warranty: For special warranty.
1.6 QUALITY ASSURANCE
A. Applicator Qualifications: An employer of workers trained and approved by
manufacturer.
B. MPI Standards: Comply with MPI standards indicated and provide water repellents
listed in its "MPI Approved Products List."
1.7 PRECONSTRUCTION TESTING
A. Preconstruction Testing: Engage a qualified testing agency to perform preconstruction
testing of water repellents on field mockups.
1. In addition to verifying performance requirements, use mockups to verify
manufacturer's written instructions for application procedure and optimum rates
of product application to substrates.
2. Propose changes to materials and methods to suit Project.
3. Notify Engineer seven days in advance of the dates and times when mockups
will be tested.
1.8 FIELD CONDITIONS
A. Limitations: Proceed with application only when the following existing and forecasted
weather and substrate conditions permit water repellents to be applied according to
manufacturers' written instructions and warranty requirements:
1. Concrete surfaces and mortar have cured for not less than 28 days.
2. Building has been closed in for not less than 30 days before treating wall
assemblies.
3. Ambient temperature is above 40 deg F and below 100 deg F and will remain so
for 24 hours.
4. Substrate is not frozen and substrate-surface temperature is above 40 deg F and
below 100 deg F.
5. Rain or snow is not predicted within 24 hours.
6. Not less than 24 hour have passed since surfaces were last wet.
7. Windy conditions do not exist that might cause water repellent to be blown onto
vegetation or surfaces not intended to be treated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 3
1.9 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer and Applicator
agree(s) to repair or replace materials that fail to maintain water repellency specified in
"Performance Requirements" Article within specified warranty period.
1. Warranty Period: Five years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Performance: Water repellents shall meet the following performance requirements as
determined by preconstruction testing on manufacturer's standard substrates
representing those indicated for this Project.
B. Water Absorption: Minimum 90 percent reduction of water absorption after 24 hours for
treated compared to untreated specimens when tested according to the following:
1. Concrete Masonry Units: ASTM C 140.
C. Water-Vapor Transmission: Comply with one or both of the following:
1. Maximum 10 percent reduction water-vapor transmission of treated compared to
untreated specimens, according to ASTM E 96/E 96M.
2. Minimum 80 percent water-vapor transmission of treated compared to untreated
specimens, according to ASTM D 1653.
D. Water Penetration and Leakage through Masonry: Minimum [90] <Insert number>
percent reduction in leakage rate of treated compared to untreated specimens,
according to ASTM E 514/E 514M.
E. Durability: Maximum 5 percent loss of water-repellent performance after 2500 hours of
weathering according to ASTM G 154 compared to water-repellent-treated specimens
before weathering.
F. Chloride-Ion Intrusion in Concrete: NCHRP Report 244, Series II tests.
1. Reduction of Water Absorption: 80 percent.
2. Reduction in Chloride Content: 80 percent.
2.2 PENETRATING WATER REPELLENTS
A. Silane, Penetrating Water Repellent: Clear, containing 20 percent or more solids of
alkyltrialkoxysilanes; with alcohol, mineral spirits, water, or other proprietary solvent
carrier; and with 400 g/L or less of VOCs.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 4
B. Siloxane, Penetrating Water Repellent: Clear, containing 10 percent or more solids of
oligomerous alkylalkoxysiloxanes; with alcohol, ethanol, mineral spirits, water, or other
proprietary solvent carrier; and with 400 g/L or less of VOCs.
C. Silane/Siloxane-Blend, Penetrating Water Repellent: Clear, silane and siloxane blend
with 400 g/L or less of VOCs.
D. Proprietary-Blend, Penetrating Water Repellent: Clear, consisting of one or several
different resins (silanes or siloxanes), polymers, stearates, or oils plus other
compounds or products of components; with 400 g/L or less of VOCs.
2.3 FILM-FORMING WATER REPELLENTS
A. Silicone-Resin Sealer, Film-Forming Water Repellent: Clear, polymerized, silicone-
resin water repellent for dense substrates; in a solvent- or waterborne solution
containing not less than 3 and up to 7 percent solids by weight; and with 400 g/L or
less of VOCs.
B. Proprietary-Blend, Film-Forming Water Repellent: Clear, consisting of one or several
different resins, acrylics, polymers, stearates, or oils plus other compounds or products
of components; with 400 g/L or less of VOCs.
C. Acrylic, Film-Forming Water Repellent: Clear, breathing coating of acrylic resin, which
may be enhanced with silane and siloxane resins; in a waterborne, solvent-borne, or
acrylic emulsion solution containing less than 15 percent solids by volume; and with
400 g/L or less of VOCs.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Applicator present, for compliance
with requirements and conditions affecting performance of the Work.
1. Verify that surfaces are clean and dry according to water-repellent
manufacturer's requirements. Check moisture content in representative locations
by method recommended by manufacturer.
2. Verify that there is no efflorescence or other removable residues that would be
trapped beneath the application of water repellent.
3. Verify that required repairs are complete, cured, and dry before applying water
repellent.
B. Test pH level according to water-repellent manufacturer's written instructions to ensure
chemical bond to silica-containing or siliceous minerals.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 5
3.2 PREPARATION
A. New Construction and Repairs: Allow concrete and other cementitious materials to age
before application of water repellent, according to repellent manufacturer's written
instructions.
B. Cleaning: Before application of water repellent, clean substrate of substances that
could impair penetration or performance of product according to water-repellent
manufacturer's written instructions.
1. Concrete Unit Masonry: Remove oil, curing compounds, laitance, and other
substances that inhibit penetration or performance of water repellents according
to ASTM E 1857 .
C. Protect adjoining work, including mortar and sealant bond surfaces, from spillage or
blow-over of water repellent. Cover adjoining and nearby surfaces of aluminum and
glass if there is the possibility of water repellent being deposited on surfaces. Cover
live vegetation.
D. Coordination with Mortar Joints: Do not apply water repellent until pointing mortar for
joints adjacent to surfaces receiving water-repellent treatment has been installed and
cured.
E. Coordination with Sealant Joints: Do not apply water repellent until sealants for joints
adjacent to surfaces receiving water-repellent treatment have been installed and cured.
1. Water-repellent work may precede sealant application only if sealant adhesion
and compatibility have been tested and verified using substrate, water repellent,
and sealant materials identical to those required.
3.3 APPLICATION
A. Manufacturer's Field Service: Engage a factory-authorized service representative to
inspect the substrate before application of water repellent and to instruct Applicator on
the product and application method to be used.
B. Apply coating of water repellent on surfaces to be treated using 15 psi pressure spray
with a fan-type spray nozzle, roller or brush to the point of saturation. Apply coating in
dual passes of uniform, overlapping strokes. Remove excess material; do not allow
material to puddle beyond saturation. Comply with manufacturer's written instructions
for application procedure unless otherwise indicated.
C. Apply a second saturation coating, repeating first application. Comply with
manufacturer's written instructions for limitations on drying time between coats and
after rainstorm wetting of surfaces between coats. Consult manufacturer's technical
representative if written instructions are not applicable to Project conditions.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER WATER REPELLENTS
REEDLEY, CA. SECTION 071900 - 6
3.4 FIELD QUALITY CONTROL
A. Testing of Water-Repellent Material: Owner reserves the right to invoke the following
procedure at any time and as often as Owner deems necessary during the period when
water repellent is being applied:
1. Owner will engage the services of a qualified testing agency to sample water-
repellent material being used. Samples of material delivered to Project site will be
taken, identified, sealed, and certified in presence of Contractor.
2. Testing agency will perform tests for compliance of water-repellent material with
product requirements.
3. Owner may direct Contractor to stop applying water repellents if test results show
material being used does not comply with product requirements. Contractor shall
remove noncomplying material from Project site, pay for testing, and correct
deficiency of surfaces treated with rejected materials, as approved by Engineer. .
B. Coverage Test: In the presence of Engineer, hose down a dry, repellent-treated
surface to verify complete and uniform product application. A change in surface color
will indicate incomplete application.
1. Notify the Engineer seven days in advance of the dates and times when surfaces
will be tested.
2. Reapply water repellent until coverage test indicates complete coverage.
3.5 CLEANING
A. Immediately clean water repellent from adjoining surfaces and surfaces soiled or
damaged by water-repellent application as work progresses. Correct damage to work
of other trades caused by water-repellent application, as approved by Engineer.
B. Comply with manufacturer's written cleaning instructions.
END OF SECTION 071900
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER THERMAL INSULATION
REEDLEY, CA. SECTION 072100 - 1
SECTION 072100 -THERMAL INSULATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Extruded polystyrene foam-plastic board.
2. Molded polystyrene foam-plastic board.
3. Mineral-wool blanket.
B. Related Requirements:
1. Section 042000 "Unit Masonry" for insulation installed in masonry cells.
2. Section 061600 "Sheathing" for foam-plastic board sheathing installed directly
over wood or steel framing.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1.4 INFORMATIONAL SUBMITTALS
A. Product Test Reports: For each product, for tests performed by a qualified testing
agency.
B. Evaluation Reports: For foam-plastic insulation, from ICC-ES.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Protect insulation materials from physical damage and from deterioration due to
moisture, soiling, and other sources. Store inside and in a dry location. Comply with
manufacturer's written instructions for handling, storing, and protecting during
installation.
B. Protect foam-plastic board insulation as follows:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER THERMAL INSULATION
REEDLEY, CA. SECTION 072100 - 2
1. Do not expose to sunlight except to necessary extent for period of installation
and concealment.
2. Protect against ignition at all times. Do not deliver foam-plastic board materials to
Project site until just before installation time.
3. Quickly complete installation and concealment of foam-plastic board insulation in
each area of construction.
PART 2 - PRODUCTS
2.1 POLYISOCYAN U RATE FOAM-PLASTIC BOARD
A. Polyisocyanurate Board, Foil Faced: ASTM C 1289, foil faced, Type I, Class 1 or 2.
1. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an
approved assembly.
2.2 MINERAL-WOOL BLANKETS
A. Mineral-Wool Blanket, Unfaced : ASTM C 665, Type I (blankets without membrane
facing); consisting of fibers; with maximum flame-spread and smoke-developed
indexes of 25 and 50, respectively, per ASTM E 84; passing ASTM E 136 for
combustion characteristics.
B. Mineral-Wool Blanket, Reinforced-Foil Faced : ASTM C 665, Type III (reflective faced),
Class A (faced surface with a flame-spread index of 25 or less per ASTM E 84);
Category 1 (membrane is a vapor barrier), faced with foil scrim, foil-scrim kraft, or foil-
scrim polyethylene.
2.3 INSULATION FASTENERS
A. Adhesively Attached, Spindle-Type Anchors: Plate welded to projecting spindle;
capable of holding insulation of specified thickness securely in position with self-locking
washer in place.
1. Plate: Perforated, galvanized carbon-steel sheet, 0.030 inch thick by 2 inches
square.
2. Spindle: Copper-coated, low-carbon steel; fully annealed; 0.105 inch in diameter;
length to suit depth of insulation.
B. Adhesively Attached, Angle-Shaped, Spindle-Type Anchors: Angle welded to
projecting spindle; capable of holding insulation of specified thickness securely in
position with self-locking washer in place.
1. Angle: Formed from 0.030-inch thick, perforated, galvanized carbon-steel sheet
with each leg 2 inches square.
2. Spindle: Copper-coated, low-carbon steel; fully annealed; 0.105 inch in diameter;
length to suit depth of insulation.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER THERMAL INSULATION
REEDLEY, CA. SECTION 072100 - 3
C. Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch thick
galvanized-steel sheet, with beveled edge for increased stiffness, sized as required to
hold insulation securely in place, but not less than 1-1/2 inches square or in diameter.
1. Protect ends with capped self-locking washers incorporating a spring steel insert
to ensure permanent retention of cap in the following locations:
a. Crawl spaces.
b. Ceiling plenums.
C. Attic spaces.
D. Insulation Standoff: Spacer fabricated from galvanized mild-steel sheet for fitting over
spindle of insulation anchor to maintain air space of 1 inch between face of insulation
and substrate to which anchor is attached.
E. Anchor Adhesive: Product with demonstrated capability to bond insulation anchors
securely to substrates without damaging insulation, fasteners, or substrates.
2.4 ACCESSORIES
A. Insulation for Miscellaneous Voids:
1. Glass-Fiber Insulation: ASTM C 764, Type II, loose fill; with maximum flame-
spread and smoke-developed indexes of 5, per ASTM E 84.
2. Spray Polyurethane Foam Insulation: ASTM C 1029, Type II, closed cell, with
maximum flame-spread and smoke-developed indexes of 75 and 450,
respectively, per ASTM E 84.
B. Adhesive for Bonding Insulation: Product compatible with insulation and air and water
barrier materials, and with demonstrated capability to bond insulation securely to
substrates without damaging insulation and substrates.
C. Asphalt Coating for Cellular-Glass Block Insulation: Cutback asphalt or asphalt
emulsion of type recommended by manufacturer of cellular-glass block insulation.
D. Eave Ventilation Troughs: Preformed, rigid fiberboard or plastic sheets designed and
sized to fit between roof framing members and to provide ventilation between insulated
attic spaces and vented eaves.
PART 3 - EXECUTION
3.1 PREPARATION
A. Clean substrates of substances that are harmful to insulation, including removing
projections capable of puncturing insulation or vapor retarders, or that interfere with
insulation attachment.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER THERMAL INSULATION
REEDLEY, CA. SECTION 072100 - 4
3.2 INSTALLATION, GENERAL
A. Comply with insulation manufacturer's written instructions applicable to products and
applications.
B. Install insulation that is undamaged, dry, and unsoiled and that has not been left
exposed to ice, rain, or snow at any time.
C. Extend insulation to envelop entire area to be insulated. Fit tightly around obstructions
and fill voids with insulation. Remove projections that interfere with placement.
D. Provide sizes to fit applications and selected from manufacturer's standard
thicknesses, widths, and lengths. Apply single layer of insulation units unless multiple
layers are otherwise shown or required to make up total thickness or to achieve R-
value.
3.3 INSTALLATION OF INSULATION IN FRAMED CONSTRUCTION
A. Blanket Insulation: Install in cavities formed by framing members according to the
following requirements:
1. Use insulation widths and lengths that fill the cavities formed by framing
members. If more than one length is required to fill the cavities, provide lengths
that will produce a snug fit between ends.
2. Place insulation in cavities formed by framing members to produce a friction fit
between edges of insulation and adjoining framing members.
3. Maintain 3-inch clearance of insulation around recessed lighting fixtures not rated
for or protected from contact with insulation.
4. For metal-framed wall cavities where cavity heights exceed 96 inches , support
unfaced blankets mechanically and support faced blankets by taping flanges of
insulation to flanges of metal studs.
B. Miscellaneous Voids: Install insulation in miscellaneous voids and cavity spaces where
required to prevent gaps in insulation using the following materials:
1. Glass-Fiber Insulation: Compact to approximately 40 percent of normal maximum
volume equaling a density of approximately 2.5 lb/cu. ft.
2. Spray Polyurethane Insulation: Apply according to manufacturer's written
instructions.
3.4 PROTECTION
A. Protect installed insulation from damage due to harmful weather exposures, physical
abuse, and other causes. Provide temporary coverings or enclosures where insulation
is subject to abuse and cannot be concealed and protected by permanent construction
immediately after installation.
END OF SECTION 072100
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 1
SECTION 074113.16 - STANDING-SEAM METAL ROOF PANELS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes standing-seam metal roof panels.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1. Meet with Owner, Architect, Owner's insurer if applicable, metal panel Installer,
metal panel manufacturer's representative, structural-support Installer, and
installers whose work interfaces with or affects metal panels, including installers
of roof accessories and roof-mounted equipment.
2. Review and finalize construction schedule and verify availability of materials,
Installer's personnel, equipment, and facilities needed to make progress and
avoid delays.
3. Review methods and procedures related to metal panel installation, including
manufacturer's written instructions.
4. Examine support conditions for compliance with requirements, including
alignment between and attachment to structural members.
5. Review structural loading limitations of rafters during and after roofing.
6. Review fleshings, special details, drainage, penetrations, equipment curbs, and
condition of other construction that affect metal panels.
7. Review governing regulations and requirements for insurance, certificates, and
tests and inspections if applicable.
8. Review temporary protection requirements for metal panel systems during and
after installation.
9. Review procedures for repair of metal panels damaged after installation.
10. Document proceedings, including corrective measures and actions required, and
furnish copy of record to each participant.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 2
1. Include construction details, material descriptions, dimensions of individual
components and profiles, and finishes for each type of panel and accessory.
B. Shop Drawings:
1. Include fabrication and installation layouts of metal panels; details of edge
conditions, joints, panel profiles, corners, anchorages, attachment system, trim,
flashings, closures, and accessories; and special details.
2. Accessories: Include details of the flashing, trim, and anchorage systems, at a
scale of not less than 1-1/2 inches per 12 inches.
C. Samples for Initial Selection: For each type of metal panel indicated with factory-
applied color finishes.
1. Include similar Samples of trim and accessories involving color selection.
D. Samples for Verification: For each type of exposed finish required, prepared on
Samples of size indicated below.
1. Metal Panels: 12 inches long by actual panel width. Include clips, fasteners,
closures, and other metal panel accessories.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer.
B. Product Test Reports: For each product, for tests performed by a qualified testing
agency.
C. Field quality-control reports.
D. Sample Warranties: For special warranties.
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: For metal panels to include in maintenance manuals.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: An entity that employs installers and supervisors who are
trained and approved by manufacturer.
B. UL-Certified, Portable Roll-Forming Equipment: UL-certified, portable roll-forming
equipment capable of producing metal panels warranted by manufacturer to be the
same as factory-formed products. Maintain UL certification of portable roll-forming
equipment for duration of work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 3
1.8 DELIVERY, STORAGE, AND HANDLING
A. Deliver components, metal panels, and other manufactured items so as not to be
damaged or deformed. Package metal panels for protection during transportation and
handling.
B. Unload, store, and erect metal panels in a manner to prevent bending, warping,
twisting, and surface damage.
C. Stack metal panels horizontally on platforms or pallets, covered with suitable
weathertight and ventilated covering. Store metal panels to ensure dryness, with
positive slope for drainage of water. Do not store metal panels in contact with other
materials that might cause staining, denting, or other surface damage.
D. Retain strippable protective covering on metal panels during installation.
E. Copper Panels: Wear gloves when handling to prevent fingerprints and soiling of
surface.
1.9 FIELD CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted
weather conditions permit assembly of metal panels to be performed according to
manufacturers' written instructions and warranty requirements.
1.10 COORDINATION
A. Coordinate sizes and locations of roof curbs, equipment supports, and roof
penetrations with actual equipment provided.
B. Coordinate metal panel installation with rain drainage work, flashing, trim, construction
of soffits, and other adjoining work to provide a leakproof, secure, and noncorrosive
installation.
1.11 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair
or replace components of metal panel systems that fail in materials or workmanship
within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Structural failures including rupturing, cracking, or puncturing.
b. Deterioration of metals and other materials beyond normal weathering.
2. Warranty Period: Two years from date of Substantial Completion.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 4
B. Special Warranty on Panel Finishes: Manufacturer's standard form in which
manufacturer agrees to repair finish or replace metal panels that show evidence of
deterioration of factory-applied finishes within specified warranty period.
1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following:
a. Color fading more than 5 Hunter units when tested according to
ASTM D 2244.
b. Chalking in excess of a No. 8 rating when tested according to
ASTM D 4214.
C. Cracking, checking, peeling, or failure of paint to adhere to bare metal.
2. Finish Warranty Period: 20 years from date of Substantial Completion.
C. Special Weathertightness Warranty: Manufacturer's standard form in which
manufacturer agrees to repair or replace standing-seam metal roof panel assemblies
that fail to remain weathertight, including leaks, within specified warranty period.
1. Warranty Period: 20 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Energy Performance: Provide roof panels that are listed on the EPA/DOE's ENERGY
STAR "Roof Product List" for low-slope roof products.
B. Energy Performance: Provide roof panels according to one of the following when
tested according to CRRC-1:
1. Three-year, aged solar reflectance of not less than 0.55 and emissivity of not less
than 0.75.
2. Three-year, aged Solar Reflectance Index of not less than 64 when calculated
according to ASTM E 1980.
C. Structural Performance: Provide metal panel systems capable of withstanding the
effects of the following loads, based on testing according to ASTM E 1592:
1. Wind Loads: As indicated on Drawings.
2. Other Design Loads: As indicated on Drawings.
3. Deflection Limits: For wind loads, no greater than 1/180 of the span.
D. Air Infiltration: Air leakage of not more than 0.06 cfm/sq. ft. when tested according to
ASTM E 1680 or ASTM E 283 at the following test-pressure difference:
1. Test-Pressure Difference: 1.57 Ibf/sq. ft.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 5
E. Water Penetration under Static Pressure: No water penetration when tested according
to ASTM E 1646[ or ASTM E 331] at the following test-pressure difference:
1. Test-Pressure Difference:2.86 Ibf/sq. ft. .
F. Hydrostatic-Head Resistance: No water penetration when tested according to
ASTM E 2140.
G. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply with UL 580
for wind-uplift-resistance class indicated.
1. Uplift Rating: UL 30.
H. FM Global Listing: Provide metal roof panels and component materials that comply
with requirements in FM Global 4471 as part of a panel roofing system and that are
listed in FM Global's "Approval Guide" for Class 1 or noncombustible construction, as
applicable. Identify materials with FM Global markings.
1. Fire/Windstorm Classification: Class 1A 60.
2. Hail Resistance: MH.
I. Thermal Movements: Allow for thermal movements from ambient and surface
temperature changes by preventing buckling, opening of joints, overstressing of
components, failure of joint sealants, failure of connections, and other detrimental
effects. Base calculations on surface temperatures of materials due to both solar heat
gain and nighttime-sky heat loss.
1. Temperature Change (Range): 120 deg F , ambient; 180 deg F
2.2 STANDING-SEAM METAL ROOF PANELS
A. General: Provide factory-formed metal roof panels designed to be installed by lapping
and interconnecting raised side edges of adjacent panels with joint type indicated and
mechanically attaching panels to supports using concealed clips in side laps. Include
clips, cleats, pressure plates, and accessories required for weathertight installation.
1. Steel Panel Systems: Unless more stringent requirements are indicated, comply
with ASTM E 1514.
2. Aluminum Panel Systems: Unless more stringent requirements are indicated,
comply with ASTM E 1637.
B. Vertical-Rib, Snap-Joint, Standing-Seam Metal Roof Panels: Formed with vertical ribs
at panel edges and intermediate stiffening ribs symmetrically spaced between ribs;
designed for sequential installation by mechanically attaching panels to supports using
concealed clips located under one side of panels, engaging opposite edge of adjacent
panels, and snapping panels together.
1. Metallic-Coated Steel Sheet: Zinc-coated (galvanized) steel sheet complying with
ASTM A 653/A 653M, G90 coating designation, or aluminum-zinc alloy-coated
steel sheet complying with ASTM A 792/A 792M, Class AZ50 coating
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 6
designation; structural quality. Prepainted by the coil-coating process to comply
with ASTM A 755/A 755M.
a. Nominal Thickness: 0.022 inch .
b. Exterior Finish: Two-coat fluoropolymer
C. Color: As indicated by manufacturer's designations
2. Clips: One-piece fixed to accommodate thermal movement.
a. Material: 0.028-inch nominal thickness, zinc-coated (galvanized) or
aluminum-zinc alloy-coated steel sheet.
3. Panel Coverage: 12 inches.
4. Panel Height: 1.0 inch
2.3 UNDERLAYMENT MATERIALS
A. Self-Adhering, High-Temperature Underlayment: Provide self-adhering, cold-applied,
sheet underlayment, a minimum of 30 mils thick, consisting of slip-resistant,
polyethylene-film top surface laminated to a layer of butyl or SBS-modified asphalt
adhesive, with release-paper backing. Provide primer when recommended by
underlayment manufacturer.
1. Thermal Stability: Stable after testing at 240 deg F ; ASTM D 1970.
2. Low-Temperature Flexibility: Passes after testing at minus 20 deg F;
ASTM D 1970.
B. Felt Underlayment: ASTM D 226/D 22M, Type II (No. 30), asphalt-saturated organic
felts.
C. Slip Sheet: Manufacturer's recommended slip sheet, of type required for application.
2.4 MISCELLANEOUS MATERIALS
A. Miscellaneous Metal Subframing and Furring: ASTM C 645; cold-formed, metallic-
coated steel sheet, ASTM A 653/A 653M, G90 coating designation or
ASTM A 792/A 792M, Class AZ50 ) coating designation unless otherwise indicated.
Provide manufacturer's standard sections as required for support and alignment of
metal panel system.
B. Panel Accessories: Provide components required for a complete, weathertight panel
system including trim, copings, fasciae, mullions, sills, corner units, clips, flashings,
sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of
metal panels unless otherwise indicated.
1. Closures: Provide closures at eaves and ridges, fabricated of same metal as
metal panels.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 7
2. Backing Plates: Provide metal backing plates at panel end splices, fabricated
from material recommended by manufacturer.
3. Closure Strips: Closed-cell, expanded, cellular, rubber or crosslinked, polyolefin-
foam or closed-cell laminated polyethylene; minimum 1-inch-thick, flexible
closure strips; cut or premolded to match metal panel profile. Provide closure
strips where indicated or necessary to ensure weathertight construction.
C. Flashing and Trim: Provide flashing and trim formed from same material as metal
panels as required to seal against weather and to provide finished appearance.
Locations include, but are not limited to, eaves, rakes, corners, bases, framed
openings, ridges, fasciae, and fillers. Finish flashing and trim with same finish system
as adjacent metal panels.
D. Gutters: Formed from same material as roof panels, complete with end pieces, outlet
tubes, and other special pieces as required. Fabricate in minimum 96-inch- long
sections, of size and metal thickness according to SMACNA's "Architectural Sheet
Metal Manual." Furnish gutter supports spaced a maximum of 36 inches o.c.,
fabricated from same metal as gutters. Provide wire ball strainers of compatible metal
at outlets. Finish gutters to match metal roof panels.
E. Downspouts: Formed from same material as roof panels. Fabricate in 10-foot long
sections, complete with formed elbows and offsets, of size and metal thickness
according to SMACNA's "Architectural Sheet Metal Manual." Finish downspouts to
match gutters.
F. Roof Curbs: Fabricated from same material as roof panels, 0.048-inch nominal
thickness; with bottom of skirt profiled to match roof panel profiles and with welded top
box and integral full-length cricket. Fabricate curb subframing of 0.060-inch- nominal
thickness, angle-, C-, or Z-shaped steel sheet. Fabricate curb and subframing to
withstand indicated loads of size and height indicated. Finish roof curbs to match metal
roof panels.
1. Insulate roof curb with 1-inch- thick, rigid insulation.
G. Panel Fasteners: Self-tapping screws designed to withstand design loads.
H. Panel Sealants: Provide sealant type recommended by manufacturer that are
compatible with panel materials, are nonstaining, and do not damage panel finish.
1. Sealant Tape: Pressure-sensitive, 100 percent solids, gray polyisobutylene
compound sealant tape with release-paper backing. Provide permanently elastic,
nonsag, nontoxic, nonstaining tape 1/2 inch wide and 1/8 inch thick.
2. Joint Sealant: ASTM C 920; elastomeric polyurethane or silicone sealant; of type,
grade, class, and use classifications required to seal joints in metal panels and
remain weathertight; and as recommended in writing by metal panel
manufacturer.
3. Butyl-Rubber-Based, Solvent-Release Sealant: ASTM C 1311.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 8
2.5 FABRICATION
A. General: Fabricate and finish metal panels and accessories at the factory, by
manufacturer's standard procedures and processes, as necessary to fulfill indicated
performance requirements demonstrated by laboratory testing. Comply with indicated
profiles and with dimensional and structural requirements.
B. On-Site Fabrication: Subject to compliance with requirements of this Section, metal
panels may be fabricated on-site using UL-certified, portable roll-forming equipment if
panels are of same profile and warranted by manufacturer to be equal to factory-
formed panels. Fabricate according to equipment manufacturer's written instructions
and to comply with details shown.
C. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full
length of panel.
D. Fabricate metal panel joints with factory-installed captive gaskets or separator strips
that provide a weathertight seal and prevent metal-to-metal contact, and that minimize
noise from movements.
E. Sheet Metal Flashing and Trim: Fabricate flashing and trim to comply with
manufacturer's recommendations and recommendations in SMACNA's "Architectural
Sheet Metal Manual" that apply to design, dimensions, metal, and other characteristics
of item indicated.
1. Form exposed sheet metal accessories that are without excessive oil canning,
buckling, and tool marks and that are true to line and levels indicated, with
exposed edges folded back to form hems.
2. Seams for Aluminum: Fabricate nonmoving seams with flat-lock seams. Form
seams and seal with epoxy seam sealer. Rivet joints for additional strength.
3. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories
with flat-lock seams. Tin edges to be seamed, form seams, and solder.
4. Sealed Joints: Form nonexpansion, but movable, joints in metal to accommodate
sealant and to comply with SMACNA standards.
5. Conceal fasteners and expansion provisions where possible. Exposed fasteners
are not allowed on faces of accessories exposed to view.
6. Fabricate cleats and attachment devices from same material as accessory being
anchored or from compatible, noncorrosive metal recommended in writing by
metal panel manufacturer.
a. Size: As recommended by SMACNA's "Architectural Sheet Metal Manual"
or metal panel manufacturer for application, but not less than thickness of
metal being secured.
2.6 FINISHES
A. Protect mechanical and painted finishes on exposed surfaces from damage by
applying a strippable, temporary protective covering before shipping.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 9
B. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces
are acceptable if they are within one-half of the range of approved Samples. Noticeable
variations in same piece are unacceptable. Variations in appearance of other
components are acceptable if they are within the range of approved Samples and are
assembled or installed to minimize contrast.
C. Steel Panels and Accessories:
1. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less
than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply
coating to exposed metal surfaces to comply with coating and resin
manufacturers' written instructions.
2. Concealed Finish: Apply pretreatment and manufacturer's standard white or light-
colored acrylic or polyester backer finish consisting of prime coat and wash coat
with a minimum total dry film thickness of 0.5 mil.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances, metal panel supports, and other conditions
affecting performance of the Work.
1. Examine primary and secondary roof framing to verify that rafters, purlins,
angles, channels, and other structural panel support members and anchorages
have been installed within alignment tolerances required by metal roof panel
manufacturer.
2. Examine solid roof sheathing to verify that sheathing joints are supported by
framing or blocking and that installation is within flatness tolerances required by
metal roof panel manufacturer.
a. Verify that air- or water-resistive barriers have been installed over
sheathing or backing substrate to prevent air infiltration or water
penetration.
B. Examine roughing-in for components and systems penetrating metal panels to verify
actual locations of penetrations relative to seam locations of metal panels before
installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Miscellaneous Supports: Install subframing, furring, and other miscellaneous panel
support members and anchorages according to ASTM C 754 and metal panel
manufacturer's written recommendations.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 10
3.3 UNDERLAYMENT INSTALLATION
A. Felt Underlayment: Apply at locations indicated on Drawings, in shingle fashion to shed
water, and with lapped joints of not less than 2 inches.
1. Apply over the entire roof surface.
2. Apply on roof not covered by self-adhering sheet underlayment. Lap over edges
of self-adhering sheet underlayment not less than 3 inches, in shingle fashion to
shed water.
B. Flashings: Install fleshings to cover underlayment to comply with requirements
specified in Section 076200 "Sheet Metal Flashing and Trim."
3.4 METAL PANEL INSTALLATION
A. General: Install metal panels according to manufacturer's written instructions in
orientation, sizes, and locations indicated. Install panels perpendicular to supports
unless otherwise indicated. Anchor metal panels and other components of the Work
securely in place, with provisions for thermal and structural movement.
1. Shim or otherwise plumb substrates receiving metal panels.
2. Flash and seal metal panels at perimeter of all openings. Fasten with self-tapping
screws. Do not begin installation until air- or water-resistive barriers and flashings
that will be concealed by metal panels are installed.
3. Install screw fasteners in predrilled holes.
4. Locate and space fastenings in uniform vertical and horizontal alignment.
5. Install flashing and trim as metal panel work proceeds.
6. Locate panel splices over, but not attached to, structural supports. Stagger panel
splices and end laps to avoid a four-panel lap splice condition.
7. Align bottoms of metal panels and fasten with blind rivets, bolts, or self-tapping
screws. Fasten flashings and trim around openings and similar elements with
self-tapping screws.
8. Provide weathertight escutcheons for pipe- and conduit-penetrating panels.
B. Fasteners:
1. Steel Panels: Use stainless-steel fasteners for surfaces exposed to the exterior;
use galvanized-steel fasteners for surfaces exposed to the interior.
2. Aluminum Panels: Use aluminum or stainless-steel fasteners for surfaces
exposed to the exterior; use aluminum or galvanized-steel fasteners for surfaces
exposed to the interior.
3. Copper Panels: Use copper, stainless-steel, or hardware-bronze fasteners.
4. Stainless-Steel Panels: Use stainless-steel fasteners.
C. Anchor Clips: Anchor metal roof panels and other components of the Work securely in
place, using manufacturer's approved fasteners according to manufacturers' written
instructions.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 11
D. Metal Protection: Where dissimilar metals contact each other or corrosive substrates,
protect against galvanic action as recommended in writing by metal panel
manufacturer.
E. Standing-Seam Metal Roof Panel Installation: Fasten metal roof panels to supports
with concealed clips at each standing-seam joint at location, spacing, and with
fasteners recommended in writing by manufacturer.
1. Install clips to supports with self-tapping fasteners.
2. Install pressure plates at locations indicated in manufacturer's written installation
instructions.
3. Snap Joint: Nest standing seams and fasten together by interlocking and
completely engaging factory-applied sealant.
4. Seamed Joint: Crimp standing seams with manufacturer-approved, motorized
seamer tool so clip, metal roof panel, and factory-applied sealant are completely
engaged.
5. Watertight Installation:
a. Apply a continuous ribbon of sealant or tape to seal joints of metal panels,
using sealant or tape as recommend in writing by manufacturer as needed
to make panels watertight.
b. Provide sealant or tape between panels and protruding equipment, vents,
and accessories.
C. At panel splices, nest panels with minimum 6-inch (152-mm) end lap,
sealed with sealant and fastened together by interlocking clamping plates.
F. Clipless Metal Panel Installation: Fasten metal panels to supports with screw fasteners
at each lapped joint at location and spacing recommended by manufacturer.
G. Accessory Installation: Install accessories with positive anchorage to building and
weathertight mounting, and provide for thermal expansion. Coordinate installation with
flashings and other components.
1. Install components required for a complete metal panel system including trim,
copings, corners, seam covers, flashings, sealants, gaskets, fillers, closure strips,
and similar items. Provide types indicated by metal roof panel manufacturers; or,
if not indicated, types recommended by metal roof panel manufacturer.
H. Flashing and Trim: Comply with performance requirements, manufacturer's written
installation instructions, and SMACNA's "Architectural Sheet Metal Manual." Provide
concealed fasteners where possible, and set units true to line and level as indicated.
Install work with laps, joints, and seams that will be permanently watertight and
weather resistant.
1. Install exposed flashing and trim that is without buckling and tool marks, and that
is true to line and levels indicated, with exposed edges folded back to form hems.
Install sheet metal flashing and trim to fit substrates and achieve waterproof and
weather-resistant performance.
2. Expansion Provisions: Provide for thermal expansion of exposed flashing and
trim. Space movement joints at a maximum of 10 feet with no joints allowed
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 12
within 24 inches of corner or intersection. Where lapped expansion provisions
cannot be used or would not be sufficiently weather resistant and waterproof,
form expansion joints of intermeshing hooked flanges, not less than 1 inch deep,
filled with mastic sealant (concealed within joints).
I. Gutters: Join sections with riveted and soldered or lapped and sealed joints. Attach
gutters to eave with gutter hangers spaced not more than 36 inches o.c. using
manufacturer's standard fasteners. Provide end closures and seal watertight with
sealant. Provide for thermal expansion.
J. Downspouts: Join sections with telescoping joints. Provide fasteners designed to hold
downspouts securely 1 inch away from walls; locate fasteners at top and bottom and
at approximately 60 inches o.c. in between.
1. Provide elbows at base of downspouts to direct water away from building.
2. Connect downspouts to underground drainage system indicated.
K. Roof Curbs: Install flashing around bases where they meet metal roof panels.
L. Pipe Flashing: Form flashing around pipe penetration and metal roof panels. Fasten
and seal to metal roof panels as recommended by manufacturer.
3.5 ERECTION TOLERANCES
A. Installation Tolerances: Shim and align metal panel units within installed tolerance of
1/4 inch in 20 feet on slope and location lines as indicated and within 1/8-inch offset of
adjoining faces and of alignment of matching profiles.
3.6 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to
test and inspect metal roof panel installation, including accessories. Report results in
writing.
B. Remove and replace applications of metal roof panels where tests and inspections
indicate that they do not comply with specified requirements.
C. Additional tests and inspections, at Contractor's expense, are performed to determine
compliance of replaced or additional work with specified requirements.
D. Prepare test and inspection reports.
3.7 CLEANING AND PROTECTION
A. Remove temporary protective coverings and strippable films, if any, as metal panels
are installed, unless otherwise indicated in manufacturer's written installation
instructions. On completion of metal panel installation, clean finished surfaces as
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER STANDING-STEAM METAL ROOF
REEDLEY, CA. PANELS
SECTION 074113.16 - 13
recommended by metal panel manufacturer. Maintain in a clean condition during
construction.
B. Replace metal panels that have been damaged or have deteriorated beyond
successful repair by finish touchup or similar minor repair procedures.
END OF SECTION 074113.16
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 1
SECTION 076200 - SHEET METAL FLASHING AND TRIM
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following sheet metal flashing and trim:
1. Formed roof drainage system.
2. Formed low-slope roof flashing and trim where not part of Section 07 41 13.
3. Formed wall flashing and trim (typical at perimeter of all wall openings).
4. Self-adhering flexible membrane used in conjunction with sheet metal flashing
where not part of Section 07 13 13 or 07 41 31.
B. Related Sections include the following:
1. Division 7 Section "Metal Roof Panels" for metal roofing and flashing, trim and
accessories, and Self-Adhering Sheet Waterproofing" for flexible flashing at wall
openings.
2. Division 22 Section "Plumbing" for roof drains & pipe fittings that attach to sheet
metal gutters.
1.2 PERFORMANCE REQUIREMENTS
A. General: Install sheet metal flashing and trim to withstand wind loads, structural
movement, thermally induced movement, and exposure to weather without failing,
rattling, leaking, and fastener disengagement.
B. Thermal Movements: Provide sheet metal flashing and trim that allow for thermal
movements resulting from the following maximum change (range) in ambient and
surface temperatures by preventing buckling, opening of joints, hole elongation,
overstressing of components, failure of joint sealants, failure of connections, and other
detrimental effects. Provide clips that resist rotation and avoid shear stress as a result of
sheet metal and trim thermal movements. Base engineering calculation on surface
temperatures of materials due to both solar heat gain and nighttime-sky heat loss.
1. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
C. Water Infiltration: Provide sheet metal flashing and trim that do not allow water
infiltration to building interior.
1.3 SUBMITTALS
A. Shop Drawings: Show layouts of sheet metal flashing and trim, including plans and
elevations. Distinguish between shop- and field-assembled work. Include the following:
1. Identify material, thickness, weight, and finish for each item and location in Project.
2. Details for forming sheet metal flashing and trim, including profiles, shapes, seams,
and dimensions.
3. Details for fastening, joining, supporting, and anchoring sheet metal flashing and
trim, including fasteners, clips, cleats, and attachments to adjoining work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 2
1.4 QUALITY ASSURANCE
A. Sheet Metal Flashing and Trim Standard: Comply with SMACNA's "Architectural Sheet
Metal Manual." Conform to dimensions and profiles shown unless more stringent
requirements are indicated.
B. Standard commercial items may be used for flashing, trim, reglets, and similar purposes
provided such items meet or exceed the quality standards specified.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Deliver sheet metal flashing materials and fabrications undamaged. Protect sheet metal
flashing and trim materials and fabrications during transportation and handling.
B. Unload, store, and install sheet metal flashing materials and fabrications in a manner to
prevent bending, warping, twisting, and surface damage.
C. Stack materials on platforms or pallets, covered with suitable weathertight and ventilated
covering. Do not store sheet metal flashing and trim materials in contact with other
materials that might cause staining, denting, or other surface damage.
1.6 COORDINATION
A. Coordinate installation of sheet metal flashing and trim with interfacing and adjoining
construction to provide a leakproof, secure, and noncorrosive installation.
PART 2 - PRODUCTS
2.1 SHEET METALS
A. Zinc-Coated (Galvanized) Steel Sheet: ASTM A 653/A 653M, G90 coating designation;
structural quality, mill phosphatized for field painting.
B. Lead Sheet: ASTM B 749, Type L51121, copper-bearing lead sheet.
2.2 MISCELLANEOUS MATERIALS
A. General: Provide materials and types of fasteners, solder, welding rods, protective
coatings, separators, sealants, and other miscellaneous items as required for complete
sheet metal flashing and trim installation.
B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets
and bolts, and other suitable fasteners designed to withstand design loads, suitable for
galvanized steel, galvanized or cadmium plated.
1. Nails for Stainless Steel Sheet: Series 300 stainless steel, 0.109 inch minimum
and not less than 7/8 inch long, barbed with large head.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 3
2. Fasteners for Flashing and Trim: Blind fasteners or self-drilling screws, gasketed,
with hex washer head.
3. Blind Fasteners: Rivets High-strength aluminum, stainless-steel or as
recommended for the particular use.
4. Washers: As required, neoprene faced where water-tight condition is required.
5. Bolts and Nuts: FF-B-578 C, FF-B-588C.
C. Solder for Lead: ASTM B 32, Grade Sn50, 50 percent tin and 50 percent lead.
D. Solder for Zinc: ASTM B 32, 60 percent lead and 40 percent tin with low antimony, as
recommended by manufacturer.
E. Burning Rod for Lead: Same composition as lead sheet.
F. Sealing Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound
sealing tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic,
nonstaining tape, suitable for high temperature conditions.
G. Elastomeric Sealant: ASTM C 920, elastomeric polyurethane polymer sealant; of type,
grade, class, and use classifications required to seal joints in sheet metal flashing and
trim and remain watertight.
H. Bituminous Coating: Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-
mil dry film thickness per coat. Provide inert-type noncorrosive compound free of
asbestos fibers, sulfur components, and other deleterious impurities.
I. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required for
application.
J. Self-Adhering, Polyethylene-Faced Sheet: ASTM D 1970, 40 mils thick minimum,
consisting of slip-resisting polyethylene-film reinforcing and top surface laminated to
SBS-modified asphalt adhesive, with release-paper backing; cold applied.
1. Available Products:
a. Carlisle Coatings & Waterproofing, Div. of Carlisle Companies Inc.; "CCW
WIP 300HT."
b. Grace, W. R. & Co.; "Ultra."
C. Owens Corning; "WeatherLock."
d. Protecto Wrap Company; "Rainproof 40."
K. Slip Sheet: Building paper, minimum 5 Ib/100 sq. ft., rosin sized.
L. Underlayment Felt: Asphalt saturated organic felt per CBC Standard 32-1, 15 lb.
minimum.
2.3 FABRICATION, GENERAL
A. General: Custom fabricate sheet metal flashing and trim to comply with
recommendations in SMACNA's "Architectural Sheet Metal Manual" that apply to design,
dimensions, metal, and other characteristics of item indicated. Shop fabricate items
where practicable. Obtain field measurements for accurate fit before shop fabrication.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 4
B. Fabricate sheet metal flashing and trim in thickness or weight needed to comply with
performance requirements, but not less than that specified for each application and
metal.
C. Fabricate sheet metal flashing and trim without excessive oil canning, buckling, and tool
marks and true to line and levels indicated, with exposed edges folded back to form
hems.
1. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories with
flat-lock seams. Tin edges to be seamed, form seams, and solder.
D. Sealed Joints: Form nonexpansion but movable joints in metal to accommodate
elastomeric sealant to comply with SMACNA recommendations.
E. Expansion Provisions: Where lapped or bayonet-type expansion provisions in the Work
cannot be used, form expansion joints of intermeshing hooked flanges, not less than 1
inch deep, filled with elastomeric sealant concealed within joints.
F. Conceal fasteners and expansion provisions where possible on exposed-to-view sheet
metal flashing and trim, unless otherwise indicated.
G. Fabricate cleats and attachment devices from same material as accessory being
anchored or from compatible, noncorrosive metal.
1. Thickness: As recommended by SMACNA's "Architectural Sheet Metal Manual"
for application but not less than thickness of metal being secured.
2.4 ROOF DRAINAGE SHEET METAL FABRICATIONS
A. Hanging Gutters: Fabricate from materials as indicated by the drawings (match siding
when exposed) to cross section indicated, complete with end pieces, outlet tubes, and
other special pieces and accessories as required. Fabricate in minimum 96-inch- long
sections. Furnish flat-stock gutter spacers and gutter brackets fabricated from same
metal as gutters, of size recommended by SMACNA but not less than twice the gutter
thickness at a minimum of 36"o.c. or as indicated by the drawings and/or SMACNA.
Fabricate expansion joints, expansion-joint covers, and gutter accessories from same
metal as gutters.
1. Gutter Style: As indicated by drawings.
2. Expansion Joints: Butt type.
3. Accessories: Stainless steel wire ball downspout strainer.
B. Downspouts: Fabricate downspouts complete with mitered elbows. Furnish with metal
hangers, from same material as downspouts, and anchors.
1. Manufactured Hanger Style: 1-35A for rectangular downspouts and 1-35J for round
downspouts.
2. Provide sheet metal terminal head in shapes indicated or as approved by Architect.
3. Coordinate with plumbing contractor for water-tight installation of horizontal and
vertical roof drains in sheet gutters as indicated in drawings.
2.5 LOW-SLOPE ROOF SHEET METAL FABRICATIONS
A. Base Flashing: Fabricate from the following material:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 5
1. Galvanized Steel: 0.0276 inch, 22 gage, thick, unless indicated otherwise by
drawings.
B. Counter lashing: Fabricate from the following material:
1. Galvanized Steel: 0.0217 inch, 24 gage, thick, unless indicated otherwise by
drawings.
C. Flashing Receivers: Fabricate from the following material:
1. Galvanized Steel: 0.0217 inch, 24 gage, thick, unless indicated otherwise by
drawings.
D. Roof-Penetration Flashing: Fabricate from the following material:
1. Lead: 4.0 lb/sq. ft., hard tempered.
E. Openings Flashing in Frame Construction: Fabricate head, sill, jamb, and similar
flashings to extend 4 inches beyond wall openings. Form head and sill flashing with 2-
inch- high end dams. Fabricate from the following material:
1. Galvanized Steel: 0.0217 inch, 24 gage, thick.
F. Roof Edge Flashing (Gravel Stop) and Fascia Caps: Fabricate in minimum 96-inch-
long, but not exceeding 10-foot- long, sections. Furnish with 6-inch-wide joint cover
plates.
1. Joint Style: Butt, with 12-inch- wide concealed backup plate.
a. Stainless Steel: .031 inch, 22 gage, thick, unless indicated otherwise by
drawings.
b. Galvanized Steel: 0.0396 inch, 24 gage thick, unless indicated otherwise by
drawings.
G. Copings/Parapet Caps: Fabricate in minimum 96-inch- long, but not exceeding 10-foot-
long, sections. Fabricate joint plates of same thickness as copings. Furnish with
continuous cleats to support edge of external leg and interior leg. Miter corners, seal,
and solder or weld watertight.
1. Joint Style: Butt, with 12-inch-wide concealed backup plate.
2. Fabricate copings from the following material:
a. Stainless Steel: .031 inch, 22 gage, thick, unless indicated otherwise by
drawings.
b. Galvanized Steel: 0.0396 inch, 24 gage thick, unless indicated otherwise by
drawings.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, to verify actual
locations, dimensions and other conditions affecting performance of work.
1. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and
securely anchored.
2. Verify compliance with requirements for installation tolerances of substrates.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 6
3.2 UNDERLAYMENT INSTALLATION
A. General: Install underlayment as indicated on Drawings.
B. Felt Underlayment: Install felt underlayment with adhesive for temporary anchorage to
minimize use of mechanical fasteners under sheet metal flashing and trim. Apply in
shingle fashion to shed water, with lapped joints of not less than 2 inches.
C. Self-Adhering membrane underlayment: Install similar to underlayment at parapet caps
and all wall and roof openings including door, window, lower opening perimeters and
other wall/roof penetrations to seal substrate from moisture and shed water.
3.3 INSTALLATION, GENERAL
A. General: Anchor sheet metal flashing and trim and other components of the Work
securely in place, with provisions for thermal and structural movement. Use fasteners,
solder, welding rods, protective coatings, separators, sealants, and other miscellaneous
items as required to complete sheet metal flashing and trim system.
1. Form sheet metal accurately and to the dimensions and shapes required, finishing
molded and broken surfaces with true, sharp, and straight lines and angles and,
where intercepting other members, coping to an accurate fit and soldering
securely.
2. Unless otherwise specifically permitted by the Architect, turn exposed edges back
1/2".
3. Torch cutting of sheet metal flashing and trim is not permitted.
B. Install sheet metal flashing and trim to fit substrates and to result in watertight
performance. Verify shapes and dimensions of surfaces to be covered before fabricating
sheet metal.
1. Make lock seam work flat and true to line, sweating full of solder.
2. Make lock seams and lap seams, when soldered, at least 1/2" wide.
3. Where lap seams are not soldered, lap according to pitch, but in no case less than
3".
4. Make flat and lap seams in the direction of flow.
C. Space cleats not more than 12 inches apart. Anchor each cleat with two fasteners.
Bend tabs over fasteners.
D. Install exposed sheet metal flashing and trim without excessive oil canning, buckling, and
tool marks.
E. Install sheet metal flashing and trim true to line and levels indicated. Provide uniform,
neat seams with minimum exposure of solder, welds, and elastomeric sealant.
F. Metal Protection: Where dissimilar metals will contact each other or corrosive
substrates, protect against galvanic action by painting contact surfaces with bituminous
coating or by other permanent separation as recommended by fabricator or
manufacturers of dissimilar metals.
1. Underlayment: Where installing metal flashing directly on cementitious or wood
substrates, install a course of felt underlayment and cover with a slip sheet or
install a course of polyethylene underlayment.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 7
2. Bed flanges in thick coat of asphalt roofing cement where required for waterproof
performance.
G. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim.
Space movement joints at a maximum of 10 feet with no joints allowed within 24 inches
of corner or intersection. Where lapped or bayonet-type expansion provisions cannot be
used or would not be sufficiently watertight, form expansion joints of intermeshing
hooked flanges, not less than 1 inch deep, filled with elastomeric sealant concealed
within joints.
1. Join parts with rivets or sheet metal screws where necessary for strength and
stiffness.
2. Provide suitable watertight expansion joints for runs of more than 40'-0", except
where closer spacing is indicated on the Drawings or required for proper in-
stallation.
H. Fasteners: Use fasteners of sizes that will penetrate substrate not less than 1-1/4 inches
for nails and not less than 3/4 inch for wood screws.
1. Whenever possible, secure metal by means of clips or cleats, without nailing
through the exterior metal.
2. In general, space nails, rivets, and screws not more than 8" apart and, where
exposed to the weather, use lead washers.
3. For nailing into wood, use barbed roofing nails 1-1/4" long by 11 gage.
4. For nailing into concrete, use drilled plugholes and plugs.
5. Galvanized or Prepainted, Metallic-Coated Steel: Use stainless-steel fasteners
unless noted otherwise.
6. Stainless Steel: Use stainless-steel fasteners.
I. Seal joints with elastomeric sealant as required for watertight construction. Install sealant
tape where indicated.
1. Where sealant-filled joints are used, embed hooked flanges of joint members not
less than 1 inch into sealant. Form joints to completely conceal sealant. When
ambient temperature at time of installation is moderate, between 40 and 70 deg F,
set joint members for 50 percent movement either way. Adjust setting
proportionately for installation at higher ambient temperatures. Do not install
sealant-type joints at temperatures below 40 deg F.
2. Prepare joints and apply sealants to comply with requirements in Division 7
Section "Joint Sealants."
J. Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter. Pre-
tin edges of sheets to be soldered to a width of 1-1/2 inches except where pre-tinned
surface would show in finished Work.
1. Perform soldering slowly, with a well heated copper, in order to heat the seams
thoroughly and to completely fill them with solder.
a. Do not use open-flame torches for soldering.
b. Heat surfaces to receive solder and flow solder into joints.
C. Fill joints completely.
d. Completely remove flux and spatter from exposed surfaces.
2. Perform soldering with a heavy soldering copper of blunt design, properly tinned
for use.
a. Pre-tinning is not required for lead.
3. Make exposed soldering on finished surfaces neat, full flowing, and smooth.
4. After soldering, thoroughly wash acid flux with a soda solution.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 8
3.4 ROOF FLASHING INSTALLATION (Where not included as part of Metal Panel Roofing
System)
A. General: Install sheet metal roof flashing and trim to comply with performance
requirements and SMACNA's "Architectural Sheet Metal Manual." Provide concealed
fasteners where possible, set units true to line, and level as indicated. Install work with
laps, joints, and seams that will be permanently watertight.
B. Roof Edge Flashing: Anchor to resist uplift and outward forces according to
recommendations in FMG Loss Prevention Data Sheet 1-49 for specified wind zone and
as indicated.
1. Interlock bottom edge of roof edge flashing with continuous cleats anchored to
substrate at 16-inch centers.
C. Pipe or Post Counterflashing: Install counterflashing umbrella with close-fitting collar
with top edge flared for elastomeric sealant, extending a minimum of 4 inches over base
flashing. Install stainless-steel draw band and tighten.
D. Counterflashing: Coordinate installation of counterflashing with installation of base
flashing. Insert counterflashing in reglets or receivers and fit tightly to base flashing.
Extend counterflashing 4 inches over base flashing. Lap counterflashing joints a
minimum of 4 inches and bed with elastomeric sealant.
1. Secure in a waterproof manner by means of snap-in installation and sealant or
lead wedges and sealant.
E. Roof-Penetration Flashing: Coordinate installation of roof-penetration flashing with
installation of roofing and other items penetrating roof. Install flashing as follows:
1. Turn lead flashing down inside vent piping, being careful not to block vent piping
with flashing.
2. Seal with elastomeric sealant and clamp flashing to pipes penetrating roof except
for lead flashing on vent piping.
3.5 WALL FLASHING INSTALLATION
A. General: Install sheet metal wall flashing to intercept and exclude penetrating moisture
according to SMACNA recommendations and as indicated. Coordinate installation of
wall flashing with installation of wall-opening components such as windows, doors, and
louvers.
B. Openings Flashing in Frame Construction: Install continuous head, sill, jamb, and similar
flashings to extend 4 inches beyond wall openings.
3.6 MISCELLANEOUS PRODUCTS (if not detailed on the drawings)
A. Sheet metal copings:
1. Follow standards shown in SMACNA manual, CHAPTER 3
2. Use 22 gage MIN. galvanized sheet metal, unless otherwise noted on the
drawings.
3. Slope surface toward roof side of wall with a minimum of 1/2":12" slope.
4. Angle and return bottom edges for rigidity.
5. Turn down a minimum of 4" at inside edges, or as otherwise detailed.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 9
6. Turn down outside a minimum of 4", or as otherwise indicated.
B. Pitch pans (if applicable):
1. Where unflashed projections extend through or rest upon the roof surface, and
cannot be flashed with a prefabricated lead boot or SBS-modified bitumen, provide
a primed pitch pan in accordance with SMACNA Manual, Plate 68, Figure E, with
minimum 4" high collar and 6" flange, except where otherwise indicated.
2. Pitch pan shall be spot welded and hot soldered to prevent bitumen loss.
3. Set flange on last layer of SIBS modified bitumen roofing membrane, and nail at 6"
on centers.
4. Cover flange with one layer of SIBS-modified bitumen, extending onto roof 4", 8",
and 12".
5. Fill inside of pan with minimum 1-1/2" of modified elastomeric asphalt mastic over
grout.
C. Cold pipe flashing:
1. Provide 4 lb lead manufactured flashings in accordance with SMACNA , Figure 4-
14b.
2. Integrate flanges within roofing plies.
D. Provide custom hooded flashings at all ganged vertical pipes/penetrations, using curbed
type flashings in accordance with SMACNA Manual, Figure 4-14A.
E. Surface mounted counterflashings:
1. At concrete or masonry walls, provide a two-piece surface-mounted
counterflashing system of galvanized steel (Fry or approved equal).
2. Seal receiver to wall surface with a thermoplastic rubber sealant approved in
advance by the Architect.
3. Fasten the receiver into the wall at 12" on centers; snap in the second piece after
base flashing has been installed.
4. At concrete masonry units, provide a thermoplastic rubber sealant approved in
advance by the Architect.
F. Drains: SMACNA Figure 1-37
1. Provide 4 lb lead drain pan in drains and overflows.
2. Do not cut lead to fit corners.
3. Install roof around the sump area as specified and cut roofing ply assembly flush
with drain assembly at drain opening.
4. Provide asphalt primed lead flashing on top of roofing felts; size the lead flashing to
extend uninterrupted up cants or tapered edge strips, and to terminate just below
deck line.
5. Immediately install and tighten clamping ring into lead only, using caution not to
break lead sheet.
6. Hand nail perimeter 4" on centers with one row of 1" head ringshanked nails.
7. Cover with roofing cap sheet.
8. All edges shall exhibit minimum 1/4" bead of asphalt.
3.7 ERECTION TOLERANCES
A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed
tolerance of 1/4 inch in 20 feet on slope and location lines as indicated and within 1/8-
inch offset of adjoining faces and of alignment of matching profiles.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SHEET METAL FLASHING AND TRIM
REEDLEY, CA. SECTION 076200 - 10
3.8 ROOF FLASHING INSTALLATIONS
A. Copings: Anchor to resist uplift and outward forces according to recommendations in
FMG Loss Prevention Data Sheet 1-49 for specified wind zone and as indicated.
1. Interlock exterior bottom edge of coping with continuous cleats anchored to
substrate at 24-inch centers.
2. interlock interior leg of coping with continuous cleats anchored at 24-inch centers.
3.9 MISCELLANEOUS FLASHING INSTALLATION
A. Overhead-Piping Safety Pans: Suspend pans from pipe and install drain line to
plumbing waste or drain line.
3.10 TESTS
A. Upon request of the Architect, demonstrate by hose or standing water that the flashing
and sheet metal are completely watertight.
3.11 CLEANING AND PROTECTION
A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and
weathering.
B. Clean and neutralize flux materials. Clean off excess solder and sealants.
C. Remove temporary protective coverings and strippable films as sheet metal flashing and
trim are installed. On completion of installation, clean finished surfaces, including
removing unused fasteners, metal filings, pop rivet stems, and pieces of flashing.
Maintain in a clean condition during construction.
D. Replace sheet metal flashing and trim that have been damaged or that have deteriorated
beyond successful repair by finish touchup or similar minor repair procedures.
END OF SECTION 076200
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 1
SECTION 077200 - ROOF ACCESSORIES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Roof curbs.
2. Equipment supports.
3. Gravity ventilators.
4. Preformed flashing sleeves.
B. Related Sections:
1. Section 076200 "Sheet Metal Flashing and Trim" for shop- and field-formed metal
flashing, roof-drainage systems, roof expansion-joint covers, and miscellaneous
sheet metal trim and accessories.
1.3 COORDINATION
A. Coordinate layout and installation of roof accessories with roofing membrane and base
flashing and interfacing and adjoining construction to provide a leakproof, weathertight,
secure, and noncorrosive installation.
B. Coordinate dimensions with rough-in information or Shop Drawings of equipment to be
supported.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of roof accessory.
1. Include construction details, material descriptions, dimensions of individual
components and profiles, and finishes.
B. Shop Drawings: For roof accessories.
1. Include plans, elevations, keyed details, and attachments to other work. Indicate
dimensions, loadings, and special conditions. Distinguish between plant-and field-
assembled work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 2
C. Samples: For each exposed product and for each color and texture specified, prepared
on Samples of size to adequately show color.
D. Delegated-Design Submittal: For roof curbs, equipment supports indicated to comply
with performance requirements and design criteria, including analysis data signed and
sealed by the qualified professional engineer responsible for their preparation.
1. Detail mounting, securing, and flashing of roof-mounted items to roof structure.
Indicate coordinating requirements with roof membrane system.
2. Wind-Restraint Details: Detail fabrication and attachment of wind restraints. Show
anchorage details and indicate quantity, diameter, and depth of penetration of
anchors.
1.5 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Roof plans, drawn to scale, and coordinating penetrations and
roof-mounted items. Show the following:
1. Size and location of roof accessories specified in this Section.
2. Method of attaching roof accessories to roof or building structure.
3. Other roof-mounted items including mechanical and electrical equipment,
ductwork, piping, and conduit.
4. Required clearances.
B. Sample Warranties: For manufacturer's special warranties.
1.6 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For roof accessories to include in operation and
maintenance manuals.
1.7 WARRANTY
A. Special Warranty on Painted Finishes: Manufacturer's standard form in which
manufacturer agrees to repair finishes or replace roof accessories that show evidence
of deterioration of factory-applied finishes within specified warranty period.
1. Fluoropolymer Finish: Deterioration includes, but is not limited to, the following:
a. Color fading more than 5 Hunter units when tested according to
ASTM D 2244.
b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214.
C. Cracking, checking, peeling, or failure of paint to adhere to bare metal.
2. Finish Warranty Period: 20 years from date of Substantial Completion.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 3
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. General Performance: Roof accessories shall withstand exposure to weather and resist
thermally induced movement without failure, rattling, leaking, or fastener disengagement
due to defective manufacture, fabrication, installation, or other defects in construction.
B. Wind-Restraint Performance: As indicated on Drawings.
2.2 ROOF CURBS
A. Roof Curbs: Internally reinforced roof-curb units capable of supporting superimposed live
and dead loads, including equipment loads and other construction indicated on
Drawings, bearing continuously on roof structure, and capable of meeting performance
requirements; with welded or mechanically fastened and sealed corner joints, straight
sides, integral metal cant, stepped integral metal cant raised the thickness of roof
insulationJand integrally formed deck-mounting flange at perimeter bottom.
B. Size: Coordinate dimensions with roughing-in information or Shop Drawings of
equipment to be supported.
C. Material: Zinc-coated (galvanized) steel sheet, 0.052 inch thick.
1. Finish: Baked enamel or powder coat.
2. Color: As selected by Engineer from manufacturer's full range.
D. Construction:
1. Curb Profile: Profile as indicated on Drawings compatible with roofing system.
2. On ribbed or fluted metal roofs, form deck-mounting flange at perimeter bottom to
conform to roof profile.
3. Fabricate curbs to minimum height of 12 inches above roofing surface unless
otherwise indicated.
4. Top Surface: Level top of curb, with roof slope accommodated by sloping deck-
mounting flange.
5. Sloping Roofs: Where roof slope exceeds 1:48, fabricate curb with perimeter curb
height tapered to accommodate roof slope so that top surface of perimeter curb is
level. Equip unit with water diverter or cricket on side that obstructs water flow.
6. Liner: Same material as curb, of manufacturer's standard thickness and finish.
7. Nailer: Factory-installed wood nailer along top flange of curb, continuous around
curb perimeter.
8. Wind Restraint Straps and Base Flange Attachment: Provide wind restraint straps,
welded strap connectors, and base flange attachment to roof structure at perimeter
of curb, of size and spacing required to meet wind uplift requirements.
9. Platform Cap: Where portion of roof curb is not covered by equipment, provide
weathertight platform cap formed from 3/4-inch thick plywood covered with metal
sheet of same type, thickness, and finish as required for curb.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 4
10. Metal Counterflashing: Manufacturer's standard, removable, fabricated of same
metal and finish as curb.
2.3 EQUIPMENT SUPPORTS
A. Equipment Supports: Internally reinforced perimeter metal equipment supports capable
of supporting superimposed live and dead loads between structural supports, including
equipment loads and other construction indicated on Drawings, spanning between
structural supports; capable of meeting performance requirements; with welded or
mechanically fastened and sealed corner joints, integral metal cant, stepped integral
metal cant raised the thickness of roof insulation, and integrally formed structure-
mounting flange at bottom.
B. Size: Coordinate dimensions with roughing-in information or Shop Drawings of
equipment to be supported.
C. Material: Zinc-coated galvanized steel sheet, 0.052 inch thick.
1. Finish: Baked enamel or powder coat.
2. Color: As selected by Engineer from manufacturer's full range
D. Construction:
1. Curb Profile: Profile as indicated on Drawings compatible with roofing system.
2. Insulation: Factory insulated with 1-1/2-inch thick glass-fiber board insulation.
3. Liner: Same material as equipment support, of manufacturer's standard thickness
and finish.
4. Nailer: Factory-installed continuous wood nailers 3-1/2 inches wide on top flange
of equipment supports, continuous around support perimeter.
5. Wind Restraint Straps and Base Flange Attachment: Provide wind restraint straps,
welded strap connectors, and base flange attachment to roof structure at perimeter
of curb of size and spacing required to meet wind uplift requirements.
6. Platform Cap: Where portion of equipment support is not covered by equipment,
provide weathertight platform cap formed from 3/4-inch thick plywood covered with
metal sheet of same type, thickness, and finish as required for curb.
7. Metal Counterflashing: Manufacturer's standard, removable, fabricated of same
metal and finish as equipment support.
8. On ribbed or fluted metal roofs, form deck-mounting flange at perimeter bottom to
conform to roof profile.
9. Fabricate equipment supports to minimum height of 12 inches above roofing
surface unless otherwise indicated.
10. Sloping Roofs: Where roof slope exceeds 1:48, fabricate each support with height
to accommodate roof slope so that tops of supports are level with each other. Equip
supports with water diverters or crickets on sides that obstruct water flow.
2.4 GRAVITY VENTILATORS
A. Low-Profile, Cylindrical-Style Gravity Ventilators: Manufacturer's standard, fabricated as
indicated, with manufacturer's standard welded or sealed mechanical joints.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 5
1. Construction: Integral base flange, vent cylinder, cylinder bird screen, and rain cap
hood.
2. Dimensions: As indicated on Drawings.
3. Configuration:As indicated on Drawings.
4. Bird Screens: Manufacturer's standard mesh with rewireable frame.
5. Insect Screens: Manufacturer's standard mesh with rewireable frame.
6. Vent Cylinder, Base Flange, and Rain-Cap Hood Material:Zinc-coated
(galvanized) steel sheet, of manufacturer's standard thickness.
7. Finish: As selected by Engineer from manufacturer's full range.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, to verify actual
locations, dimensions, and other conditions affecting performance of the Work.
B. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored.
C. Verify dimensions of roof openings for roof accessories.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General: Install roof accessories according to manufacturer's written instructions.
1. Install roof accessories level; plumb; true to line and elevation; and without
warping, jogs in alignment, buckling, or tool marks.
2. Anchor roof accessories securely in place so they are capable of resisting
indicated loads.
3. Use fasteners, separators, sealants, and other miscellaneous items as required to
complete installation of roof accessories and fit them to substrates.
4. Install roof accessories to resist exposure to weather without failing, rattling,
leaking, or loosening of fasteners and seals.
B. Metal Protection: Protect metals against galvanic action by separating dissimilar metals
from contact with each other or with corrosive substrates by painting contact surfaces
with bituminous coating or by other permanent separation as recommended by
manufacturer.
1. Underlayment: Where installing roof accessories directly on cementitious or wood
substrates, install a course of underlayment and cover with manufacturer's
recommended slip sheet.
2. Bed flanges in thick coat of asphalt roofing cement where required by
manufacturers of roof accessories for waterproof performance.
C. Roof Curb Installation: Install each roof curb so top surface is level.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ROOF ACCESSORIES
REEDLEY, CA. SECTION 077200 - 6
D. Equipment Support Installation: Install equipment supports so top surfaces are level with
each other.
E. Gravity Ventilator Installation: Verify that gravity ventilators operate properly and have
unrestricted airflow. Clean, lubricate, and adjust operating mechanisms.
F. Pipe Support Installation: Comply with MSS SP-58 and MSS SP-89. Install supports and
attachments as required to properly support piping. Arrange for grouping of parallel runs
of horizontal piping, and support together.
1. Pipes of Various Sizes: Space supports for smallest pipe size or install
intermediate supports for smaller diameter pipes as specified for individual pipe
hangers.
G. Seal joints with elastomeric or butyl sealant as required by roof accessory manufacturer.
3.3 REPAIR AND CLEANING
A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and
repair galvanizing according to ASTM A 780/A 780M.
B. Touch up factory-primed surfaces with compatible primer ready for field painting
according to Section 099113 "Exterior Painting."
C. Clean exposed surfaces according to manufacturer's written instructions.
D. Clean off excess sealants.
E. Replace roof accessories that have been damaged or that cannot be successfully
repaired by finish touchup or similar minor repair procedures.
END OF SECTION 077200
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 1
SECTION 078413 - PENETRATION FIRESTOPPING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Penetrations in fire-resistance-rated walls.
2. Penetrations in horizontal assemblies.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Product Schedule: For each penetration firestopping system. Include location,
illustration of firestopping system, and design designation of qualified testing and
inspecting agency.
1. Engineering Judgments: Where Project conditions require modification to a
qualified testing and inspecting agency's illustration for a particular penetration
firestopping system, submit illustration, with modifications marked, approved by
penetration firestopping system manufacturer's fire-protection engineer as an
engineering judgment or equivalent fire-resistance-rated assembly. Obtain
approval of authorities having jurisdiction prior to submittal.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer.
B. Product Test Reports: For each penetration firestopping system, for tests performed by
a qualified testing agency.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 2
1.6 CLOSEOUT SUBMITTALS
A. Installer Certificates: From Installer indicating that penetration firestopping systems
have been installed in compliance with requirements and manufacturer's written
instructions.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: A firm that has been approved by FM Global according to
FM Global 4991, "Approval of Firestop Contractors," or been evaluated by UL and
found to comply with its "Qualified Firestop Contractor Program Requirements."
1.8 PROJECT CONDITIONS
A. Environmental Limitations: Do not install penetration firestopping system when ambient
or substrate temperatures are outside limits permitted by penetration firestopping
system manufacturers or when substrates are wet because of rain, frost, condensation,
or other causes.
B. Install and cure penetration firestopping materials per manufacturer's written
instructions using natural means of ventilations or, where this is inadequate, forced-air
circulation.
1.9 COORDINATION
A. Coordinate construction of openings and penetrating items to ensure that penetration
firestopping systems can be installed according to specified firestopping system
design.
B. Coordinate sizing of sleeves, openings, core-drilled holes, or cut openings to
accommodate penetration firestopping systems.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Fire-Test-Response Characteristics:
1. Perform penetration firestopping system tests by a qualified testing agency
acceptable to authorities having jurisdiction.
2. Test per testing standards referenced in "Penetration Firestopping Systems"
Article. Provide rated systems complying with the following requirements:
a. Penetration firestopping systems shall bear classification marking of a
qualified testing agency.
1) UL in its "Fire Resistance Directory."
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 3
2) Intertek Group in its "Directory of Listed Building Products."
3) FM Global in its "Building Materials Approval Guide."
2.2 PENETRATION FIRESTOPPING SYSTEMS
A. Penetration Firestopping Systems: Systems that resist spread of fire, passage of
smoke and other gases, and maintain original fire-resistance rating of construction
penetrated. Penetration firestopping systems shall be compatible with one another,
with the substrates forming openings, and with penetrating items if any.
B. Penetrations in Fire-Resistance-Rated Walls: Penetration firestopping systems with
ratings determined per ASTM E 814 or UL 1479, based on testing at a positive
pressure differential of 0.01-inch wg.
1. F-Rating: Not less than the fire-resistance rating of constructions penetrated.
C. Penetrations in Horizontal Assemblies: Penetration firestopping systems with ratings
determined per ASTM E 814 or UL 1479, based on testing at a positive pressure
differential of 0.01-inch wg.
1. F-Rating: At least one hour, but not less than the fire-resistance rating of
constructions penetrated.
2. T-Rating: At least one hour, but not less than the fire-resistance rating of
constructions penetrated except for floor penetrations within the cavity of a wall.
3. W-Rating: Provide penetration firestopping systems showing no evidence of
water leakage when tested according to UL 1479.
D. Exposed Penetration Firestopping Systems: Flame-spread and smoke-developed
indexes of less than 25 and 450, respectively, per ASTM E 84.
E. Accessories: Provide components for each penetration firestopping system that are
needed to install fill materials and to maintain ratings required. Use only those
components specified by penetration firestopping system manufacturer and approved
by qualified testing and inspecting agency for conditions indicated.
1. Permanent forming/damming/backing materials.
2. Substrate primers.
3. Collars.
4. Steel sleeves.
2.3 FILL MATERIALS
A. Cast-in-Place Firestop Devices: Factory-assembled devices for use in cast-in-place
concrete floors and consisting of an outer sleeve lined with an intumescent strip, a
flange attached to one end of the sleeve for fastening to concrete formwork, and a
neoprene gasket.
B. Latex Sealants: Single-component latex formulations that do not re-emulsify after cure
during exposure to moisture.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 4
C. Firestop Devices: Factory-assembled collars formed from galvanized steel and lined
with intumescent material sized to fit specific diameter of penetrant.
D. Intumescent Composite Sheets: Rigid panels consisting of aluminum-foil-faced
intumescent elastomeric sheet bonded to galvanized-steel sheet.
E. Intumescent Putties: Nonhardening, water-resistant, intumescent putties containing no
solvents or inorganic fibers.
F. Intumescent Wrap Strips: Single-component intumescent elastomeric sheets with
aluminum foil on one side.
G. Mortars: Prepackaged dry mixes consisting of a blend of inorganic binders, hydraulic
cement, fillers and lightweight aggregate formulated for mixing with water at Project
site to form a nonshrinking, homogeneous mortar.
H. Pillows/Bags: Reusable heat-expanding pillows/bags consisting of glass-fiber cloth
cases filled with a combination of mineral-fiber, water-insoluble expansion agents, and
fire-retardant additives. Where exposed, cover openings with steel-reinforcing wire
mesh to protect pillows/bags from being easily removed.
I. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed,
expand and cure in place to produce a flexible, nonshrinking foam.
J. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric
sealants.
2.4 MIXING
A. Penetration Firestopping Materials: For those products requiring mixing before
application, comply with penetration firestopping system manufacturer's written
instructions for accurate proportioning of materials, water (if required), type of mixing
equipment, selection of mixer speeds, mixing containers, mixing time, and other items
or procedures needed to produce products of uniform quality with optimum
performance characteristics for application indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with
requirements for opening configurations, penetrating items, substrates, and other
conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 5
3.2 PREPARATION
A. Surface Cleaning: Before installing penetration firestopping systems, clean out
openings immediately to comply with manufacturer's written instructions and with the
following requirements:
1. Remove from surfaces of opening substrates and from penetrating items foreign
materials that could interfere with adhesion of penetration firestopping materials.
2. Clean opening substrates and penetrating items to produce clean, sound
surfaces capable of developing optimum bond with penetration firestopping
materials. Remove loose particles remaining from cleaning operation.
3. Remove laitance and form-release agents from concrete.
B. Prime substrates where recommended in writing by manufacturer using that
manufacturer's recommended products and methods. Confine primers to areas of
bond; do not allow spillage and migration onto exposed surfaces.
3.3 INSTALLATION
A. General: Install penetration firestopping systems to comply with manufacturer's written
installation instructions and published drawings for products and applications.
B. Install forming materials and other accessories of types required to support fill
materials during their application and in the position needed to produce cross-sectional
shapes and depths required to achieve fire ratings.
1. After installing fill materials and allowing them to fully cure, remove combustible
forming materials and other accessories not forming permanent components of
firestopping.
C. Install fill materials by proven techniques to produce the following results:
1. Fill voids and cavities formed by openings, forming materials, accessories and
penetrating items to achieve required fire-resistance ratings.
2. Apply materials so they contact and adhere to substrates formed by openings
and penetrating items.
3. For fill materials that will remain exposed after completing the Work, finish to
produce smooth, uniform surfaces that are flush with adjoining finishes.
3.4 IDENTIFICATION
A. Wall Identification: Permanently label walls containing penetration firestopping systems
with the words "FIRE AND/OR SMOKE BARRIER - PROTECT ALL OPENINGS,"
using lettering not less than 3 inches high and with minimum 0.375-inch strokes.
1. Locate in accessible concealed floor, floor-ceiling, or attic space at 15 feet from
end of wall and at intervals not exceeding 30 feet.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 6
B. Penetration Identification: Identify each penetration firestopping system with legible
metal or plastic labels. Attach labels permanently to surfaces adjacent to and within 6
inches of penetration firestopping system edge so labels are visible to anyone seeking
to remove penetrating items or firestopping systems. Use mechanical fasteners or self-
adhering-type labels with adhesives capable of permanently bonding labels to surfaces
on which labels are placed. Include the following information on labels:
1. The words "Warning - Penetration Firestopping - Do Not Disturb. Notify Building
Management of Any Damage."
2. Contractor's name, address, and phone number.
3. Designation of applicable testing and inspecting agency.
4. Date of installation.
5. Manufacturer's name.
6. Installer's name.
3.5 FIELD QUALITY CONTROL
A. Owner will engage a qualified testing agency to perform tests and inspections
according to ASTM E 2174.
B. Where deficiencies are found or penetration firestopping system is damaged or
removed because of testing, repair or replace penetration firestopping system to
comply with requirements.
C. Proceed with enclosing penetration firestopping systems with other construction only
after inspection reports are issued and installations comply with requirements.
3.6 CLEANING AND PROTECTION
A. Clean off excess fill materials adjacent to openings as the Work progresses by
methods and with cleaning materials that are approved in writing by penetration
firestopping system manufacturers and that do not damage materials in which
openings occur.
B. Provide final protection and maintain conditions during and after installation that ensure
that penetration firestopping systems are without damage or deterioration at time of
Substantial Completion. If, despite such protection, damage or deterioration occurs,
immediately cut out and remove damaged or deteriorated penetration firestopping
material and install new materials to produce systems complying with specified
requirements.
3.7 PENETRATION FIRESTOPPING SYSTEM SCHEDULE
A. Where UL-classified systems are indicated, they refer to system numbers in UL's "Fire
Resistance Directory" under product Category XHEZ.
B. Where Intertek Group-listed systems are indicated, they refer to design numbers in
Intertek Group's "Directory of Listed Building Products" under"Firestop Systems."
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PENETRATION FIRESTOPPING
REEDLEY, CA. SECTION 078413 - 7
C. Where FM Global-approved systems are indicated, they refer to design numbers listed
in FM Global's "Building Materials Approval Guide" under "Wall and Floor Penetration
Fire Stops."
END OF SECTION 078413
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 1
SECTION 081113 - HOLLOW METAL DOORS, WINDOWS AND FRAMES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Standard hollow metal doors and frames for doors and windows.
B. Related Sections
1. Division 1 Section "Submittal Procedures" for shop drawing, product data and
sample submittals.
2. Division 8 Section "Door Hardware" for door hardware for hollow metal doors
and/or frames.
1.2 DEFINITIONS
A. Minimum Thickness: Minimum thickness of base metal without coatings.
B. Standard Hollow Metal Work: Hollow metal work fabricated according to
ANSI/SDI A250.8.
1.3 SUBMITTALS
A. Product Data: For each type of product indicated within 30 days of issuance or Notice to
Proceed. Include construction details, material descriptions, core descriptions, and
finishes.
1. Materials list of items proposed to be provided under this Section.
2. Manufacturer's specifications and other data needed to prove compliance with the
specified requirements.
3. Manufacturer's recommended installation procedures which, when approved by the
Engineer, will become the basis for accepting or rejecting actual installation
procedures used on the Work.
B. Shop Drawings: Include the following:
1. Elevations of each door design.
2. Details of doors, including vertical and horizontal edge details and metal
thicknesses.
3. Frame details for each frame type, including dimensioned profiles and metal
thicknesses.
3. Locations of reinforcement and preparations for hardware.
4. Details of each different wall opening condition.
5. Details of anchorages.
6. Details of accessories.
C. Other Action Submittals:
1. Schedule: Provide a schedule of hollow metal work prepared by or under the
supervision of supplier, using same reference numbers for details and openings as
those on Drawings. Coordinate with door hardware schedule.
D. Coordination with other trades:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 2
1. Submittals shall flag areas of coordination with other trades or where materials that
interface with materials specified herein are necessary. Indicate coordination of
glazing frames and stops with glazing requirements; indicate coordination with
finish hardware.
1.4 QUALITY ASSURANCE
A. Source Limitations: Obtain hollow metal work from single source from single
manufacturer.
B. Fire-Rated Door Assemblies: Assemblies complying with CBC Section 715.4 and
NFPA 80 that are listed and labeled by a qualified testing agency, for fire-protection
ratings indicated, based on testing according to UL 10B or UL 10C. Label all such doors
and frames accordingly.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Deliver hollow metal work palletized, wrapped, or crated to provide protection during
transit and Project-site storage. Do not use nonvented plastic.
B. Deliver welded frames with two removable spreader bars across bottom of frames, tack
welded to jambs and mullions.
C. Store hollow metal work under cover at Project site. Place in stacks of five units
maximum in a vertical position with heads up, spaced by blocking, on minimum 4-inch-
high wood blocking. Do not store in a manner that traps excess humidity.
1. Provide minimum 1/4-inch space between each stacked door to permit air
circulation.
1.6 PROJECT CONDITIONS
A. Field Measurements: Verify actual dimensions of openings by field measurements
before fabrication.
1.7 COORDINATION
A. Coordinate installation of anchorages for hollow metal frames. Furnish setting drawings,
templates, and directions for installing anchorages, including sleeves, concrete inserts,
anchor bolts, and items with integral anchors. Deliver such items to Project site in time
for installation.
PART 2 - PRODUCTS
2.2 MATERIALS
A. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B;
suitable for exposed applications.
A. Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, Commercial Steel (CS), Type B; free
of scale, pitting, or surface defects; pickled and oiled.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 3
B. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B;
with minimum G60 or A60 metallic coating.
C. Frame Anchors: ASTM A 591/A 591 M, Commercial Steel (CS), 40Z coating designation;
mill phosphatized, 18 gage minimum.
1. For anchors built into exterior walls, steel sheet complying with
ASTM A 1008/A 1008M or ASTM A 1011/A 1011M, hot-dip galvanized according
to ASTM A 153/A 153M, Class B.
D. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 153/A 153M.
E. Mineral-Fiber Insulation: ASTM C 665, Type I (blankets without membrane facing);
consisting of fibers manufactured from slag or rock wool with 6- to 12-Ib/cu. ft. density;
with maximum flame-spread and smoke-development indexes of 25 and 50,
respectively; passing ASTM E 136 for combustion characteristics.
F. Bituminous Coating: Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-
mil dry film thickness per coat. Provide inert-type noncorrosive compound free of
asbestos fibers, sulfur components, and other deleterious impurities.
G. Shop Applied Primer For Ferrous Metals: Manufacturer or fabricator's standard, fast-
curing, lead free, "universal" primer; selected for good resistance to normal atmospheric
corrosion, for compatibility with finish paint systems indicated. Provide shop primer paint
material that is compatible with finish paint systems indicated and is in compliance with
the current EPA rules and regulations at the time and place of application.
2.3 STANDARD HOLLOW METAL DOORS
A. General: Provide doors of design indicated, not less than thickness indicated; fabricated
with smooth surfaces, without visible joints or seams on exposed faces unless otherwise
indicated. Comply with ANSI/SDI A250.8.
1. Design: Flush panel.
2. Core Construction: Manufacturer's standard kraft-paper honeycomb, polystyrene,
polyurethane, polyisocyanurate, mineral-board, or vertical steel-stiffener core.
a. Fire Door Core: As required to provide fire-protection ratings indicated.
3. Vertical Edges for Single-Acting Doors: Beveled edge.
a. Beveled Edge: 1/8 inch in 2 inches.
4. Top and Bottom Edges: Closed with flush 0.042-inch- thick, end closures or
channels of same material as face sheets.
5. Tolerances: Comply with SDI 117, "Manufacturing Tolerances for Standard Steel
Doors and Frames."
B. Exterior Doors: Face sheets fabricated from metallic-coated steel sheet. Provide doors
complying with requirements indicated below by referencing ANSI/SDI A250.8 for level
and model and ANSI/SDI A250.4 for physical performance level:
1. Level 4 and Physical Performance Level A (Maximum Duty), Model 2 (Seamless).
14 gage faces.
2. Exterior doors to be galvanized complying with ASTM A 525 (A60). Wipe coat
galvanizing is not permitted.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 4
C. Interior Doors: Face sheets fabricated from cold-rolled steel sheet. Provide doors
complying with requirements indicated below by referencing ANSI/SDI A250.8 for level
and model and ANSI/SDI A250.4 for physical performance level:
1. Level 3 and Physical Performance Level A (Extra Heavy Duty), Model 2
(Seamless). 16 gage faces.
D. Hardware Reinforcement: Fabricate according to ANSI/SDI A250.6 with reinforcing
plates from same material as door face sheets.
E. Fabricate concealed stiffeners and hardware reinforcement from either cold- or hot-rolled
steel sheet.
2.4 STANDARD HOLLOW METAL FRAMES
A. General: Comply with ANSI/SDI A250.8 and with details indicated for type and profile.
B. Exterior Frames: Fabricated from metallic-coated steel sheet.
6. Fabricate frames with mitered corners.
7. Fabricate frames as face welded unless otherwise indicated.
8. Frames for Level 4 Steel Doors: 0.067-inch (14 gage) thick steel sheet.
C. Interior Frames: Fabricated from cold-rolled steel sheet.
1. Fabricate frames with mitered corners.
2. Fabricate frames as face welded unless otherwise indicated.
3. Frames for level 3 steel doors 0.053 inch (16 gage) thick sheet steel.
D. Hardware Reinforcement: Fabricate according to ANSI/SDI A250.6 with reinforcement
plates from same material as frames.
2.5 FRAME ANCHORS
A. Jamb Anchors:
1. Stud-Wall Type: Designed to engage stud, welded to back of frames; not less than
0.042 inch thick.
2. Post installed Expansion Type for In-Place Concrete or Masonry: Minimum 3/8-
inch-diameter bolts with expansion shields or inserts. Provide pipe spacer from
frame to wall, with throat reinforcement plate, welded to frame at each anchor
location.
B. Floor Anchors: Formed from same material as frames, not less than 0.042 inch thick,
and as follows:
1. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive fasteners.
2. Separate Topping Concrete Slabs: Adjustable-type anchors with extension clips,
allowing not less than 2-inchneight adjustment. Terminate bottom of frames at
finish floor surface.
2.6 STOPS AND MOLDINGS
B. Fixed Frame Moldings: Formed integral with hollow metal frames, a minimum of 5/8 inch
high unless otherwise indicated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 5
2.8 FABRICATION
A. Fabricate hollow metal work to be rigid and free of defects, warp, or buckle. Accurately
form metal to required sizes and profiles, with minimum radius for thickness of metal.
Where practical, fit and assemble units in manufacturer's plant. To ensure proper
assembly at Project site, clearly identify work that cannot be permanently factory
assembled before shipment.
B. Tolerances: Fabricate hollow metal work to tolerances indicated in SDI 117.
C. Hollow Metal Doors:
1. Exterior Doors: Provide weep-hole openings in bottom of exterior doors to permit
moisture to escape. Seal joints in top edges of doors against water penetration.
D. Hollow Metal Frames: Where frames are fabricated in sections due to shipping or
handling limitations, provide alignment plates or angles at each joint, fabricated of same
thickness metal as frames.
1. Welded Frames: Weld flush all joints continuously; grind, fill, dress, and make
smooth, flush, and invisible.
2. Side Light Frames: Provide closed tubular members with no visible face seams or
joints, fabricated from same material as door frame. Fasten members at crossings
and to jambs by butt welding.
3. Grout Guards: Weld guards to frame at back of hardware mortises in frames to be
grouted.
9. Floor Anchors: Weld anchors to bottom of jambs and mullions with at least four
spot welds per anchor.
10. Jamb Anchors: Provide number and spacing of anchors as follows:
a. Stud-Wall Type: Locate anchors not more than 18 inches from top and
bottom of frame. Space anchors not more than 32 inches o.c. and as
follows:
1) Three anchors per jamb up to 60 inches high.
2) Four anchors per jamb from 60 to 90 inches high.
3) Five anchors per jamb from 90 to 96 inches high.
4) Five anchors per jamb plus 1 additional anchor per jamb for each 24
inches or fraction thereof above 96 inches high.
5) Two anchors per head for frames above 42 inches wide and mounted
in metal-stud partitions.
b. Anchor Fasteners: #8 x '/2" zinc coated self tapping hex washer head
screws, provide two per strap.
11. Door Silencers: Except on gasketed doors, drill stops to receive door silencers as
follows. Keep holes clear during construction.
a. Single-Door Frames: Drill stop in strike jamb to receive three door silences.
b. Double-Door Frames: Drill stop in head jamb to receive two door silencers.
C. Do not provide holes or silencers at openings receiving weatherstripping.
E. Fabricate concealed stiffeners, edge channels, and hardware reinforcement from either
cold- or hot-rolled steel sheet.
F. Hardware Preparation: Factory prepare hollow metal work to receive templated mortised
hardware; include cutouts, reinforcement, mortising, drilling, and tapping according to the
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 6
Door Hardware Schedule and templates furnished as specified in Division 8 Section
"Door Hardware."
1. Locate hardware as indicated, or if not indicated, according to ANSI/SDI A250.8.
2. Reinforce doors and frames to receive nontemplated, mortised and surface-
mounted door hardware.
3. Comply with applicable requirements in ANSI/SDI A250.6 and
ANSI/DHI A115 Series specifications for preparation of hollow metal work for
hardware.
G. Stops and Moldings: Provide stops and moldings around glazed lites where indicated.
Form corners of stops and moldings with butted or mitered hairline joints.
1. Single Glazed Lites: Provide fixed stops and moldings welded on secure side of
hollow metal work.
2. Multiple Glazed Lites: Provide fixed and removable stops and moldings so that
each glazed lite is capable of being removed independently.
3. Provide fixed frame molding on outside of exterior and on secure side of interior
doors and frames.
4. Provide loose stops and moldings on inside of hollow metal work.
5. Coordinate rabbet width between fixed and removable stops with type of glazing
and type of installation indicated.
2.9 ACCESSORIES
A, Mullions and Transom Bars: Join to adjacent members by welding or rigid mechanical
anchors.
2.10 STEEL FINISHES
A. Prime Finish: Apply manufacturer's standard primer immediately after cleaning and
pretreating.
1. Shop Primer: Manufacturer's standard, fast-curing, lead- and chromate-free primer
complying with ANSI/SDI A250.10 acceptance criteria; recommended by primer
manufacturer for substrate; compatible with substrate and field-applied coatings
despite prolonged exposure.
2. Clean, treat, and paint (primer) exposed surfaces of steel door and frame units,
including galvanized surfaces.
3. Clean steel surfaces of mill scale, rust, oil, grease dirt, and other foreign materials
before the application of paint.
4. Apply shop primer evenly to provide uniformly finished surfaces ready for finish
painting.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of the
Work.
B. Examine roughing-in for embedded and built-in anchors to verify actual locations before
frame installation.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 7
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
D. Remove welded-in shipping spreaders installed at factory. Restore exposed finish by
grinding, filling, and dressing, as required to make repaired area smooth, flush, and
invisible on exposed faces.
E. Prior to installation, adjust and securely brace welded hollow metal frames for
squareness, alignment, twist, and plumbness to the following tolerances:
1. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90
degrees from jamb perpendicular to frame head.
2. Alignment: Plus or minus 1/16 inch, measured at jambs on a horizontal line
parallel to plane of wall.
3. Twist: Plus or minus 1/16 inch, measured at opposite face corners of jambs on
parallel lines, and perpendicular to plane of wall.
4. Plumbness: Plus or minus 1/16 inch, measured at jambs on a perpendicular line
from head to floor.
F. Drill and tap doors and frames to receive non-templated, mortised, and surface-mounted
door hardware.
3.3 INSTALLATION
A. General: Install hollow metal work plumb, rigid, properly aligned, and securely fastened
in place; comply with Drawings and manufacturer's written instructions.
B. Hollow Metal Frames: Install hollow metal frames of size and profile indicated. Comply
with ANSI/SDI A250.11.
1. Set frames accurately in position, plumbed, aligned, and braced securely until
permanent anchors are set. After wall construction is complete, remove temporary
braces, leaving surfaces smooth and undamaged.
a. Where frames are fabricated in sections because of shipping or handling
limitations, field splice at approved locations by welding face joint
continuously; grind, fill, dress, and make splice smooth, flush, and invisible
on exposed faces.
b. Install frames with removable glazing stops located on secure side of
opening.
C. Remove temporary braces necessary for installation only after frames have
been properly set and secured.
d. Check plumbness, squareness, and twist of frames as walls are constructed.
Shim as necessary to comply with installation tolerances.
2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to
floor, and secure with postinstalled expansion anchors.
3. Metal-Stud Partitions: Solidly pack mineral-fiber insulation behind frames.
4. Masonry Walls: Coordinate installation of frames to allow for solidly filling space
between frames and masonry with grout. Anchor type shall not obstruct filling the
frame with grout.
5. When detailed for installation in prepared openings in concrete construction
(dimpled frames), provide sealant between frame and concrete in accordance with
provisions of"Joint Sealers" Section of these Specifications.
6. Windows shall have strap anchors within 12" of each corner and at 24"
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL DOORS, WINDOWS
REEDLEY, CA. AND FRAMES
SECTION 081113 - 8
o.c. max. Fasten to framing with 8 d nails.
7. Installation Tolerances: Adjust hollow metal door frames for squareness,
alignment, twist, and plumb to the following tolerances:
a. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90
degrees from jamb perpendicular to frame head.
b. Alignment: Plus or minus 1/16 inch, measured at jambs on a horizontal line
parallel to plane of wall.
C. Twist: Plus or minus 1/16 inch, measured at opposite face corners of jambs
on parallel lines, and perpendicular to plane of wall.
d. Plumbness: Plus or minus 1/16 inch, measured at jambs at floor.
C. Hollow Metal Doors: Fit hollow metal doors accurately in frames, within specified below.
Shim as necessary. Comply with SDI-100.
1. Non-Fire-Rated Standard Steel Doors:
a. Jambs and Head: 1/8 inch plus or minus 1/16 inch.
b. Between Edges of Pairs of Doors: 1/8 inch plus or minus 1/16 inch.
C. Between Bottom of Door and Top of Threshold: Maximum 3/8 inch.
d. Between Bottom of Door and Top of Finish Floor (No Threshold): Maximum
3/4 inch.
2. Fire Rated Doors: Install doors with clearances according to NFPA 80.
D. Glazing: Comply with installation requirements in Division 8 Section "Glazing" and with
hollow metal manufacturer's written instructions.
1. Secure stops with countersunk flat-or oval-head machine screws spaced uniformly
not more than 9 inches o.c. and not more than 2 inches o.c. from each corner.
3.4 ADJUSTING AND CLEANING
A. Final Adjustments: Check and readjust operating hardware items immediately before
final inspection. Leave work in complete and proper operating condition. Remove and
replace defective work, including hollow metal work that is warped, bowed, or otherwise
unacceptable.
B. Remove grout and other bonding material from hollow metal work immediately after
installation.
C. Prime-Coat Touchup: Immediately after erection, sand smooth all rusted or damaged
areas of prime coat and apply touchup of compatible air-drying, rust-inhibitive primer.
D. Metallic-Coated Surfaces: Clean abraded areas and repair with galvanizing repair paint
according to manufacturer's written instructions.
END OF SECTION 081113
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 1
SECTION 081213 - HOLLOW METAL FRAMES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section includes hollow-metal frames.
B. Related Requirements:
1. Section 081113 "Hollow Metal Doors and Frames" for hollow-metal door and
frame assemblies.
1.3 DEFINITIONS
A. Minimum Thickness: Minimum thickness of base metal without coatings according to
NAAMM-HMMA 803 or SDI A250.8.
1.4 COORDINATION
A. Coordinate anchorage installation for hollow-metal frames. Furnish setting drawings,
templates, and directions for installing anchorages, including sleeves, concrete inserts,
anchor bolts, and items with integral anchors. Deliver such items to Project site in time
for installation.
1.5 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.6 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Shop Drawings: Include the following:
1. Frame details for each frame type, including dimensioned profiles and metal
thicknesses.
2. Locations of reinforcement and preparations for hardware.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 2
3. Details of each different wall opening condition.
4. Details of anchorages, joints, field splices, and connections.
C. Samples for Initial Selection: For units with factory-applied color finishes.
D. Samples for Verification: Prepare Samples to demonstrate compliance with
requirements for quality of materials and construction. Show profile, corner joint, floor
and wall anchors, and silencers. Include separate section showing fixed hollow-metal
panels and glazing if applicable.
E. Schedule: Provide a schedule of hollow-metal work prepared by or under the
supervision of supplier, using same reference numbers for details and openings as
those on Drawings. Coordinate with final Door Hardware Schedule.
1.7 INFORMATIONAL SUBMITTALS
A. Product Test Reports: For each type of frame assembly, for tests performed by a
qualified testing agency.
B. Oversize Construction Certification: For assemblies required to be fire rated and
exceeding limitations of labeled assemblies.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Deliver hollow-metal work palletized, packaged, or crated to provide protection during
transit and Project-site storage. Do not use nonvented plastic.
1. Provide additional protection to prevent damage to factory-finished units.
B. Deliver welded frames with two removable spreader bars across bottom of frames, tack
welded to jambs and mullions.
C. Store hollow-metal work vertically under cover at Project site with head up. Place on
minimum 4-inch- high wood blocking. Provide minimum 1/4-inch space between each
unit to permit air circulation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain hollow-metal work from single source from single
manufacturer.
2.2 REGULATORY REQUIREMENTS
A. Fire-Rated Assemblies: Complying with NFPA 80 and listed and labeled by a qualified
testing agency acceptable to authorities having jurisdiction for fire-protection
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 3
ratings and temperature-rise limits indicated, based on testing at positive pressure
according to NFPA 252 or UL 10C.
1. Smoke- and Draft-Control Assemblies: Provide an assembly with gaskets listed
and labeled for smoke and draft control by a qualified testing agency acceptable
to authorities having jurisdiction, based on testing according to UL 1784 and
installed in compliance with NFPA 105.
B. Fire-Rated, Borrowed-Lite Assemblies: Complying with NFPA 80 and listed and labeled
by a testing and inspecting agency acceptable to authorities having jurisdiction for fire-
protection ratings indicated, based on testing according to NFPA 257 or UL 9.
2.3 INTERIOR FRAMES
A. Construct interior frames to comply with the standards indicated for materials,
fabrication, hardware locations, hardware reinforcement, tolerances, and clearances,
and as specified.
B. Heavy-Duty Frames: SDI A250.8, Level 2. At locations indicated in the Door and
Frame Schedule.
1. Physical Performance: Level B according to SDI A250.4.
2. Materials: Metallic-coated steel sheet, minimum thickness of 0.053 inch
3. Construction: Knocked down [Face welded] [Full profile welded].
4. Exposed Finish: [Prime] [Factory].
C. Hollow-Metal Frames: NAAMM-HMMA 860. At locations indicated in the Door and
Frame Schedule.
1. Physical Performance: Level A according to SDI A250.4.
2. Materials: Metallic-coated steel sheet, minimum thickness of 0.042 inch.
3. Construction: Knocked down.
4. Exposed Finish: Prime.
2.4 EXTERIOR HOLLOW-METAL FRAMES
A. Construct exterior frames to comply with the standards indicated for materials,
fabrication, hardware locations, hardware reinforcement, tolerances, and clearances,
and as specified.
B. Heavy-Duty Frames: SDI A250.8, Level 2. At locations indicated in the Door and
Frame Schedule.
1. Physical Performance: Level B according to SDI A250.4.
2. Materials: Metallic-coated steel sheet, minimum thickness of 0.053 inch , with
minimum A40 coating.
3. Construction: Knocked down.
4. Exposed Finish:Factory.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 4
C. Hollow-Metal Frames: NAAMM-HMMA 860. At locations indicated in the Door and
Frame Schedule.
1. Physical Performance: Level A according to SDI A250.4.
2. Materials: Metallic-coated steel sheet, minimum thickness of 0.053 inch, with
minimum G60A60 coating.
3. Construction: Knocked down.
4. Exposed Finish: Prime.
2.5 FRAME ANCHORS
A. Jamb Anchors:
1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame
size, not less than 0.042 inch thick, with corrugated or perforated straps not less
than 2 inches wide by 10 inches long; or wire anchors not less than 0.177 inch
thick.
2. Stud-Wall Type: Designed to engage stud, welded to back of frames; not less
than 0.042 inch thick.
3. Compression Type for Drywall Slip-on Frames: Adjustable compression anchors.
4. Postinstalled Expansion Type for In-Place Concrete or Masonry: Minimum 3/8-
inch- diameter bolts with expansion shields or inserts. Provide pipe spacer from
frame to wall, with throat reinforcement plate, welded to frame at each anchor
location.
B. Floor Anchors: Formed from same material as frames, minimum thickness of 0.042
inch , and as follows:
1. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive
fasteners.
2. Separate Topping Concrete Slabs: Adjustable-type anchors with extension clips,
allowing not less than 2-inch height adjustment. Terminate bottom of frames at
finish floor surface.
2.6 MATERIALS
A. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B;
suitable for exposed applications.
B. Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, Commercial Steel (CS), Type B; free
of scale, pitting, or surface defects; pickled and oiled.
C. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B.
D. Frame Anchors: ASTM A 879/A 879M, Commercial Steel (CS), 04Z (12G) coating
designation; mill phosphatized.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 5
1. For anchors built into exterior walls, steel sheet complying with
ASTM A 1008/A 1008M or ASTM A 1011/A 1011M, hot-dip galvanized according
to ASTM A 153/A 153M, Class B.
E. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 153/A 153M.
F. Power-Actuated Fasteners in Concrete: Fastener system of type suitable for
application indicated, fabricated from corrosion-resistant materials, with clips or other
accessory devices for attaching hollow-metal frames of type indicated.
G. Grout: ASTM C 476, except with a maximum slump of 4 inches, as measured
according to ASTM C 143/C 143M.
H. Mineral-Fiber Insulation: ASTM C 665, Type I (blankets without membrane facing);
consisting of fibers manufactured from slag or rock wool with 6- to 12-Ib/cu. ft. density;
with maximum flame-spread and smoke-developed indexes of 25 and 50, respectively;
passing ASTM E 136 for combustion characteristics.
I. Glazing: Comply with requirements in Section 088000 "Glazing."
J. Bituminous Coating: Cold-applied asphalt mastic, compounded for 15-mil dry film
thickness per coat. Provide inert-type noncorrosive compound free of asbestos fibers,
sulfur components, and other deleterious impurities.
2.7 FABRICATION
A. Fabricate hollow-metal work to be rigid and free of defects, warp, or buckle. Accurately
form metal to required sizes and profiles, with minimum radius for metal thickness.
Where practical, fit and assemble units in manufacturer's plant. To ensure proper
assembly at Project site, clearly identify work that cannot be permanently factory
assembled before shipment.
B. Hollow-Metal Frames: Where frames are fabricated in sections due to shipping or
handling limitations, provide alignment plates or angles at each joint, fabricated of
same thickness metal as frames.
1. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed
fasteners unless otherwise indicated.
2. Grout Guards: Weld guards to frame at back of hardware mortises in frames to
be grouted.
3. Floor Anchors: Weld anchors to bottoms of jambs with at least four spot welds
per anchor; however, for slip-on drywall frames, provide anchor clips or
countersunk holes at bottoms of jambs.
4. Jamb Anchors: Provide number and spacing of anchors as follows:
a. Masonry Type: Locate anchors not more than 16 inches from top and
bottom of frame. Space anchors not more than 32 inches o.c., to match
coursing, and as follows:
1) Two anchors per jamb up to 60 inches high.
2) Three anchors per jamb from 60 to 90 inches high.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 6
b. Stud-Wall Type: Locate anchors not more than 18 inches from top and
bottom of frame. Space anchors not more than 32 inches o.c. and as
follows:
1) Three anchors per jamb up to 60 inches high.
2) Four anchors per jamb from 60 to 90 inches high.
C. Compression Type: Not less than two anchors in each frame.
d. Postinstalled Expansion Type: Locate anchors not more than 6 inches from
top and bottom of frame. Space anchors not more than 26 inches o.c.
5. Head Anchors: Two anchors per head for frames more than 42 inches wide and
mounted in metal-stud partitions.
6. Door Silencers: Except on weather-stripped frames, drill stops to receive door
silencers as follows. Keep holes clear during construction.
a. Single-Door Frames: Drill stop in strike jamb to receive three door
silencers.
b. Double-Door Frames: Drill stop in head jamb to receive two door silencers.
7. Terminated Stops: Terminate stops 6 inches above finish floor with a 45-degree
angle cut, and close open end of stop with steel sheet closure. Cover opening in
extension of frame with welded-steel filler plate, with welds ground smooth and
flush with frame.
C. Hardware Preparation: Factory prepare hollow-metal work to receive templated
mortised hardware; include cutouts, reinforcement, mortising, drilling, and tapping
according to SDI A250.6, the Door Hardware Schedule, and templates.
1. Reinforce frames to receive nontemplated, mortised, and surface-mounted
hardware.
2. Comply with applicable requirements in SDI A250.6 and BHMA Al56.115 for
preparation of hollow-metal work for hardware.
2.8 STEEL FINISHES
A. Prime Finish: Clean, pretreat, and apply manufacturer's standard primer.
1. Shop Primer: Manufacturer's standard, fast-curing, lead- and chromate-free
primer complying with SDI A250.10; recommended by primer manufacturer for
substrate; compatible with substrate and field-applied coatings despite prolonged
exposure.
B. Factory Finish: Clean, pretreat, and apply manufacturer's standard two-coat, baked-on
finish consisting of prime coat and thermosetting topcoat, complying with SDI A250.3.
1. Color and Gloss: As selected by Engineer from manufacturer's full range.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 7
2.9 ACCESSORIES
A. Mullions and Transom Bars: Join to adjacent members by welding or rigid mechanical
anchors.
B. Grout Guards: Formed from same material as frames, not less than 0.016 inch thick.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of
the Work.
B. Examine roughing-in for embedded and built-in anchors to verify actual locations
before frame installation.
C. Prepare written report, endorsed by Installer, listing conditions detrimental to
performance of the Work.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Remove welded-in shipping spreaders installed at factory. Restore exposed finish by
grinding, filling, and dressing, as required to make repaired area smooth, flush, and
invisible on exposed faces.
B. Drill and tap frames to receive nontemplated, mortised, and surface-mounted
hardware.
3.3 INSTALLATION
A. General: Install hollow-metal work plumb, rigid, properly aligned, and securely fastened
in place. Comply with Drawings and manufacturer's written instructions.
B. Hollow-Metal Frames: Install hollow-metal frames for doors, transoms, sidelites,
borrowed lites, and other openings, of size and profile indicated. Comply with
SDI A250.11 or NAAMM-HMMA 840 as required by standards specified.
1. Set frames accurately in position; plumbed, aligned, and braced securely until
permanent anchors are set. After wall construction is complete, remove
temporary braces, leaving surfaces smooth and undamaged.
a. At fire-rated openings, install frames according to NFPA 80.
b. Where frames are fabricated in sections because of shipping or handling
limitations, field splice at approved locations by welding face joint
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 8
continuously; grind, fill, dress, and make splice smooth, flush, and invisible
on exposed faces.
C. Install frames with removable stops located on secure side of opening.
d. Install door silencers in frames before grouting.
e. Remove temporary braces necessary for installation only after frames have
been properly set and secured.
f. Check plumb, square, and twist of frames as walls are constructed. Shim
as necessary to comply with installation tolerances.
g. Field apply bituminous coating to backs of frames that will be filled with
grout containing antifreezing agents.
2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to
floor, and secure with postinstalled expansion anchors.
a. Floor anchors may be set with power-actuated fasteners instead of
postinstalled expansion anchors if so indicated and approved on Shop
Drawings.
3. Metal-Stud Partitions: Solidly pack mineral-fiber insulation inside frames.
4. Masonry Walls: Coordinate installation of frames to allow for solidly filling space
between frames and masonry with grout.
5. In-Place Concrete or Masonry Construction: Secure frames in place with
postinstalled expansion anchors. Countersink anchors, and fill and make smooth,
flush, and invisible on exposed faces.
6. In-Place Metal or Wood-Stud Partitions: Secure slip-on drywall frames in place
according to manufacturer's written instructions.
7. Installation Tolerances: Adjust hollow-metal door frames for squareness,
alignment, twist, and plumb to the following tolerances:
a. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90
degrees from jamb perpendicular to frame head.
b. Alignment: Plus or minus 1/16 inch , measured at jambs on a horizontal
line parallel to plane of wall.
C. Twist: Plus or minus 1/16 inch , measured at opposite face corners of
jambs on parallel lines, and perpendicular to plane of wall.
d. Plumbness: Plus or minus 1/16 inch, measured at jambs at floor.
3.4 ADJUSTING AND CLEANING
A. Final Adjustments: Remove and replace defective work, including hollow-metal work
that is warped, bowed, or otherwise unacceptable.
B. Remove grout and other bonding material from hollow-metal work immediately after
installation.
C. Prime-Coat Touchup: Immediately after erection, sand smooth rusted or damaged
areas of prime coat and apply touchup of compatible air-drying, rust-inhibitive primer.
D. Metallic-Coated Surface Touchup: Clean abraded areas and repair with galvanizing
repair paint according to manufacturer's written instructions.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HOLLOW METAL FRAMES
REEDLEY, CA. SECTION 081213 - 9
E. Factory-Finish Touchup: Clean abraded areas and repair with same material used for
factory finish according to manufacturer's written instructions.
F. Touchup Painting: Cleaning and touchup painting of abraded areas of paint are
specified in painting Sections.
END OF SECTION 081213
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 1
SECTION 087100 - DOOR HARDWARE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes door hardware for the following:
1. Swinging doors.
2. Other doors to the extent indicated.
B. Door hardware includes, but is not necessarily limited to, the following:
1. Mechanical door hardware.
2. Cylinders specified for doors in other sections.
C. Related Sections:
1. Division 08 Section "Hollow Metal Doors and Frames".
D. Codes and References: Comply with the version year adopted by the Authority Having
Jurisdiction.
1. ANSI A117.1 -Accessible and Usable Buildings and Facilities.
2. ICC/IBC - International Building Code.
3. NFPA 70 - National Electrical Code.
4. NFPA 80 - Fire Doors and Windows.
5. NFPA 101 - Life Safety Code.
6. NFPA 105 - Installation of Smoke Door Assemblies.
7. State Building Codes, Local Amendments.
E. Standards: All hardware specified herein shall comply with the following industry
standards:
1. ANSI/BHMA Certified Product Standards -A156 Series
2. UL10C — Positive Pressure Fire Tests of Door Assemblies
1.3 SUBMITTALS
A. Product Data: Manufacturer's product data sheets including installation details, material
descriptions, dimensions of individual components and profiles, operational descriptions
and finishes.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 2
B. Door Hardware Schedule: Prepared by or under the supervision of supplier, detailing
fabrication and assembly of door hardware, as well as procedures and diagrams.
Coordinate the final Door Hardware Schedule with doors, frames, and related work to
ensure proper size, thickness, hand, function, and finish of door hardware.
1. Format: Comply with scheduling sequence and vertical format in DHI's "Sequence
and Format for the Hardware Schedule."
2. Organization: Organize the Door Hardware Schedule into door hardware sets
indicating complete designations of every item required for each door or opening.
Organize door hardware sets in same order as in the Door Hardware Sets at the end
of Part 3. Submittals that do not follow the same format and order as the Door
Hardware Sets will be rejected and subject to resubmission.
3. Content: Include the following information:
a. Type, style, function, size, label, hand, and finish of each door hardware item.
b. Manufacturer of each item.
C. Fastenings and other pertinent information.
d. Location of door hardware set, cross-referenced to Drawings, both on floor
plans and in door and frame schedule.
e. Explanation of abbreviations, symbols, and codes contained in schedule.
f. Mounting locations for door hardware.
g. Door and frame sizes and materials.
h. Warranty information for each product.
4. Submittal Sequence: Submit the final Door Hardware Schedule at earliest possible
date, particularly where approval of the Door Hardware Schedule must precede
fabrication of other work that is critical in the Project construction schedule. Include
Product Data, Samples, Shop Drawings of other work affected by door hardware,
and other information essential to the coordinated review of the Door Hardware
Schedule.
C. Keying Schedule: After a keying meeting with the owner has taken place prepare a
separate keying schedule detailing final instructions. Submit the keying schedule in
electronic format. Include keying system explanation, door numbers, key set symbols,
hardware set numbers and special instructions. Owner must approve submitted keying
schedule prior to the ordering of permanent cylinders/cores.
D. Informational Submittals:
1. Product Test Reports: Indicating compliance with cycle testing requirements, based
on evaluation of comprehensive tests performed by manufacturer and witnessed by
a qualified independent testing agency.
E. Operating and Maintenance Manuals: Provide manufacturers operating and maintenance
manuals for each item comprising the complete door hardware installation in quantity as
required in Division 01, Closeout Procedures.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 3
1.4 QUALITY ASSURANCE
A. Manufacturers Qualifications: Engage qualified manufacturers with a minimum 5 years of
documented experience in producing hardware and equipment similar to that indicated for
this Project and that have a proven record of successful in-service performance.
B. Installer Qualifications: A minimum 3 years documented experience installing both
standard and electrified door hardware similar in material, design, and extent to that
indicated for this Project and whose work has resulted in construction with a record of
successful in-service performance.
C. Door Hardware Supplier Qualifications: Experienced commercial door hardware
distributors with a minimum 5 years documented experience supplying both mechanical
and electromechanical hardware installations comparable in material, design, and extent
to that indicated for this Project. Supplier recognized as a factory direct distributor by the
manufacturers of the primary materials with a warehousing facility in Project's vicinity.
Supplier to have on staff a certified Engineerural Hardware Consultant (AHC) available
during the course of the Work to consult with Contractor, Engineer, and Owner concerning
both standard and electromechanical door hardware and keying.
D. Each unit to bear third party permanent label demonstrating compliance with the
referenced standards.
E. Pre-Submittal Conference: Conduct coordination conference in compliance with
requirements in Division 01 Section "Project Meetings"with attendance by representatives
of Supplier(s), Installer(s), and Contractor(s)to review proper methods and the procedures
for receiving, handling, and installing door hardware.
1. Prior to installation of door hardware, conduct a project specific training meeting to
instruct the installing contractors' personnel on the proper installation and
adjustment of their respective products. Product training to be attended by installers
of door hardware(including electromechanical hardware)for aluminum, hollow metal
and wood doors. Training will include the use of installation manuals, hardware
schedules, templates and physical product samples as required.
2. Review sequence of operation narratives for each unique access controlled opening.
3. Review and finalize construction schedule and verify availability of materials.
4. Review the required inspecting, testing, commissioning, and demonstration
procedures
F. At completion of installation, provide written documentation that components were applied
to manufacturer's instructions and recommendations and according to approved schedule.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Inventory door hardware on receipt and provide secure lock-up and shelving for door
hardware delivered to Project site. Do not store electronic access control hardware,
software or accessories at Project site without prior authorization.
B. Tag each item or package separately with identification related to the final Door Hardware
Schedule, and include basic installation instructions with each item or package.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 -4
C. Deliver, as applicable, permanent keys, cylinders, cores, access control credentials,
software and related accessories directly to Owner via registered mail or overnight
package service. Instructions for delivery to the Owner shall be established at the "Keying
Conference".
1.6 COORDINATION
A. Templates: Obtain and distribute to the parties involved templates for doors, frames, and
other work specified to be factory prepared for installing standard and electrified hardware.
Check Shop Drawings of other work to confirm that adequate provisions are made for
locating and installing hardware to comply with indicated requirements.
B. Door and Frame Preparation: Doors and corresponding frames are to be prepared,
reinforced and pre-wired (if applicable)to receive the installation of the specified electrified,
monitoring, signaling and access control system hardware without additional in-field
modifications.
1.7 WARRANTY
A. General Warranty: Reference Division 01, General Requirements. Special warranties
specified in this Article shall not deprive Owner of other rights Owner may have under
other provisions of the Contract Documents and shall be in addition to, and run concurrent
with, other warranties made by Contractor under requirements of the Contract Documents.
B. Warranty Period: Written warranty, executed by manufacturer(s), agreeing to repair or
replace components of standard and electrified door hardware that fails in materials or
workmanship within specified warranty period after final acceptance by the Owner.
Failures include, but are not limited to, the following:
1. Structural failures including excessive deflection, cracking, or breakage.
2. Faulty operation of the hardware.
3. Deterioration of metals, metal finishes, and other materials beyond normal
weathering.
4. Electrical component defects and failures within the systems operation.
C. Standard Warranty Period: One year from date of Substantial Completion, unless
otherwise indicated.
D. Special Warranty Periods:
1. Five years for standard duty cylindrical (bored) locks and latches.
2. Five years for exit hardware.
3. Twenty five years for manual overhead door closer bodies.
1.8 MAINTENANCE SERVICE
A. Maintenance Tools and Instructions: Furnish a complete set of specialized tools and
maintenance instructions as needed for Owner's continued adjustment, maintenance, and
removal and replacement of door hardware.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 5
PART 2 - PRODUCTS
2.1 SCHEDULED DOOR HARDWARE
A. General: Provide door hardware for each door to comply with requirements in Door
Hardware Sets and each referenced section that products are to be supplied under.
B. Designations: Requirements for quantity, item, size, finish or color, grade, function, and
other distinctive qualities of each type of door hardware are indicated in the Door Hardware
Sets at the end of Part 3. Products are identified by using door hardware designations, as
follows:
1. Named Manufacturer's Products: Product designation and manufacturer are listed
for each door hardware type required for the purpose of establishing requirements.
Manufacturers' names are abbreviated in the Door Hardware Schedule.
C. Substitutions: Requests for substitution and product approval for inclusive mechanical and
electromechanical door hardware in compliance with the specifications must be submitted
in writing and in accordance with the procedures and time frames outlined in Division 01,
Substitution Procedures. Approval of requests is at the discretion of the engineer, owner,
and their designated consultants.
2.2 HANGING DEVICES
A. Hinges: ANSI/BHMA A156.1 certified butt hinges with number of hinge knuckles and other
options as specified in the Door Hardware Sets.
1. Quantity: Provide the following hinge quantity:
a. Two Hinges: For doors with heights up to 60 inches.
b. Three Hinges: For doors with heights 61 to 90 inches.
2. Hinge Size: Provide the following, unless otherwise indicated, with hinge widths
sized for door thickness and clearances required:
a. Widths up to 3'0": 4-1/2" standard or heavy weight as specified.
b. Sizes from 3'1" to 4'0": 5" standard or heavy weight as specified.
3. Hinge Weight and Base Material: Unless otherwise indicated, provide the following:
a. Exterior Doors: Heavy weight, non-ferrous, ball bearing or oil impregnated
bearing hinges unless Hardware Sets indicate standard weight.
b. Interior Doors: Standard weight, steel, ball bearing or oil impregnated bearing
hinges unless Hardware Sets indicate heavy weight.
4. Hinge Options: Comply with the following:
a. Non-removable Pins: Provide set screw in hinge barrel that, when tightened
into a groove in hinge pin, prevents removal of pin while door is closed; for
the all out-swinging lockable doors.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 6
2.3 DOOR OPERATING TRIM
A. Door Push Plates and Pulls: ANSI/BHMA A156.6 certified door pushes and pulls of type
and design specified in the Hardware Sets. Coordinate and provide proper width and
height as required where conflicting hardware dictates.
1. Push/Pull Plates: Minimum .050 inch thick, size as indicated in hardware sets, with
beveled edges, secured with exposed screws unless otherwise indicated.
2. Door Pull and Push Bar Design: Size, shape, and material as indicated in the
hardware sets. Minimum clearance of 2 1/2-inches from face of door unless
otherwise indicated.
3. Offset Pull Design: Size, shape, and material as indicated in the hardware sets.
Minimum clearance of 2 1/2-inches from face of door and offset of 90 degrees unless
otherwise indicated.
4. Fasteners: Provide manufacturer's designated fastener type as indicated in
Hardware Sets.
2.4 CYLINDERS AND KEYING
A. General: Cylinder manufacturer to have minimum (10) years experience designing
secured master key systems and have on record a published security keying system
policy.
B. Source Limitations: Obtain each type of keyed cylinder and keys from the same source
manufacturer as locksets and exit devices, unless otherwise indicated.
C. Cylinders: Original manufacturer cylinders complying with the following:
1. Mortise Type: Threaded cylinders with rings and cams to suit hardware application.
2. Rim Type: Cylinders with back plate, flat-type vertical or horizontal tailpiece, and
raised trim ring.
3. Bored-Lock Type: Cylinders with tailpieces to suit locks.
4. Mortise and rim cylinder collars to be solid and recessed to allow the cylinder face
to be flush and be free spinning with matching finishes.
5. Keyway: Match Facility Standard.
D. Keying System: Each type of lock and cylinders to be factory keyed.
1. Conduct specified "Keying Conference" to define and document keying system
instructions and requirements.
2. Furnish factory cut, nickel-silver large bow permanently inscribed with a visual key
control number as directed by Owner.
3. Existing System: Field verify and key locks to match Owner's existing system.
E. Key Quantity: Provide the following minimum number of keys:
1. Change Keys per Cylinder: Two (2)
2. Master Keys (per Master Key Level/Group): Five (5).
3. Construction Keys (where required): Ten (10).
F. Construction Keying: Provide construction master keyed cylinders.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 7
2.5 MECHANICAL LOCKS AND LATCHING DEVICES
A. Cylindrical Locksets, Grade 2 (Standard Duty): ANSI/BHMA A156.2, Series 4000, Grade
2 certified.
l. Locks are to be non-handed and fully field reversible.
B. Narrow Stile Interconnected Locksets:
1. Interconnected locksets designed with a mortise case which contains both a
latchbolt and deadbolt and allows simultaneous retraction of both the latchbolt and
deadbolt with a single motion turning of the lever handle.
2. Locksets to be non-handed and available with a 1 1/8" or 1 1/2" standard backset.
3. Latchbolt and deadbolt shall be fabricated of wrought brass and bronze with a
minimum 3/4" latchbolt throw and 1" deadbolt throw.
2.6 AUXILIARY LOCKS
A. Cylindrical Deadlocks: ANSI/BHMA A156.36, Grade 1, cylindrical type deadlocks to fit
standard ANSI 161 preparation and 1 3/8" to 1 3/4" thickness doors. Provide tapered
collars to resist vandalism and 1" throw solid steel bolt with hardened steel roller pins.
Deadlocks to be products of the same source manufacturer and keyway as other locksets.
2.7 LOCK AND LATCH STRIKES
A. Strikes: Provide manufacturer's standard strike with strike box for each latch or lock bolt,
with curved lip extended to protect frame, finished to match door hardware set, unless
otherwise indicated, and as follows:
1. Flat-Lip Strikes: For locks with three-piece antifriction latchbolts, as recommended
by manufacturer.
2. Extra-Long-Lip Strikes: For locks used on frames with applied wood casing trim.
3. Aluminum-Frame Strike Box: Provide manufacturer's special strike box fabricated
for aluminum framing.
4. Double-lipped strikes: For locks at double acting doors. Furnish with retractable stop
for rescue hardware applications.
B. Standards: Comply with the following:
1. Strikes for Mortise Locks and Latches: BHMA A156.13.
2. Strikes for Bored Locks and Latches: BHMA A156.2.
3. Strikes for Auxiliary Deadlocks: BHMA Al56.36.
4. Dustproof Strikes: BHMA Al56.16.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 8
2.8 CONVENTIONAL EXIT DEVICES
A. General Requirements: All exit devices specified herein shall meet or exceed the following
criteria:
l. At doors not requiring a fire rating, provide devices complying with NFPA 101 and
listed and labeled for "Panic Hardware" according to UL305. Provide proper
fasteners as required by manufacturer including sex nuts and bolts at openings
specified in the Hardware Sets.
2. Where exit devices are required on fire rated doors, provide devices complying with
NFPA 80 and with UL labeling indicating "Fire Exit Hardware". Provide devices with
the proper fasteners for installation as tested and listed by UL. Consult
manufacturer's catalog and template book for specific requirements.
3. Except on fire rated doors, provide exit devices with hex key dogging device to hold
the pushbar and latch in a retracted position. Provide optional keyed cylinder
dogging on devices where specified in Hardware Sets.
4. Devices must fit flat against the door face with no gap that permits unauthorized
dogging of the push bar. The addition of filler strips is required in any case where
the door light extends behind the device as in a full glass configuration.
5. Lever Operating Trim: Where exit devices require lever trim, furnish manufacturer's
heavy duty escutcheon trim with threaded studs for thru-bolts.
a. Lock Trim Design:As indicated in Hardware Sets, provide finishes and designs
to match that of the specified locksets.
b. Where function of exit device requires a cylinder, provide a cylinder (Rim or
Mortise) as specified in Hardware Sets.
6. Vertical Rod Exit Devices: Where surface or concealed vertical rod exit devices are
used at interior openings, provide as less bottom rod (LBR) unless otherwise
indicated. Provide dust proof strikes where thermal pins are required to project into
the floor.
7. Narrow Stile Applications: At doors constructed with narrow stiles, or as specified in
Hardware Sets, provide devices designed for maximum 2" wide stiles.
8. Dummy Push Bar: Nonfunctioning push bar matching functional push bar.
9. Rail Sizing: Provide exit device rails factory sized for proper door width application.
10. Through Bolt Installation: For exit devices and trim as indicated in Door Hardware
Sets.
B. Conventional Push Rail Exit Devices (Heavy Duty): ANSI/BHMA A156.3, Grade 1 certified
panic and fire exit hardware devices furnished in the functions specified in the Hardware
Sets. Exit device latch to be stainless steel, pullman type, with deadlock feature.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 9
2.9 DOOR CLOSERS
A. All door closers specified herein shall meet or exceed the following criteria:
l. General: Door closers to be from one manufacturer, matching in design and style,
with the same type door preparations and templates regardless of application or
spring size. Closers to be non-handed with full sized covers including installation and
adjusting information on inside of cover.
2. Standards: Closers to comply with UL-10C for Positive Pressure Fire Test and be
U.L. listed for use of fire rated doors.
3. Cycle Testing: Provide closers which have surpassed 15 million cycles in a test
witnessed and verified by UL.
4. Size of Units: Comply with manufacturer's written recommendations for sizing of
door closers depending on size of door, exposure to weather, and anticipated
frequency of use. Where closers are indicated for doors required to be accessible to
the physically handicapped, provide units complying with ANSI ICC/A117.1.
5. Closer Arms: Provide heavy duty, forged steel closer arms unless otherwise
indicated in Hardware Sets.
6. Closers shall not be installed on exterior or corridor side of doors; where possible
install closers on door for optimum aesthetics.
7. Closer Accessories: Provide door closer accessories including custom templates,
special mounting brackets, spacers and drop plates as required for proper
installation. Provide through-bolt and security type fasteners as specified in the
hardware sets.
B. Door Closers, Surface Mounted (Heavy Duty): ANSI/BHMA A156.4, Grade 1 surface
mounted, heavy duty door closers with complete spring power adjustment, sizes 1 thru 6;
and fully operational adjustable according to door size, frequency of use, and opening
force. Closers to be rack and pinion type, one piece cast iron or aluminum alloy body
construction, with adjustable backcheck and separate non-critical valves for closing sweep
and latch speed control. Provide non-handed units standard.
2.10 DOOR STOPS AND HOLDERS
A. General: Door stops and holders to be of type and design as specified below or in the
Hardware Sets.
B. Door Stops and Bumpers: ANSI/BHMA A156.16, Grade 1 certified door stops and wall
bumpers. Provide wall bumpers, either convex or concave types with anchorage as
indicated, unless floor or other types of door stops are specified in Hardware Sets. Do not
mount floor stops where they will impede traffic. Where floor or wall bumpers are not
appropriate, provide overhead type stops and holders.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 10
2.11 ENGINEERURAL SEALS
A. General: Thresholds, weatherstripping, and gasket seals to be of type and design as
specified below or in the Hardware Sets. Provide continuous weatherstrip gasketing on
exterior doors and provide smoke, light, or sound gasketing on interior doors where
indicated. At exterior applications provide non-corrosive fasteners and elsewhere where
indicated.
B. Smoke Labeled Gasketing: Assemblies complying with NFPA 105 that are listed and
labeled by a testing and inspecting agency acceptable to authorities having jurisdiction,
for smoke control ratings indicated, based on testing according to UL 1784.
1. Provide smoke labeled perimeter gasketing at all smoke labeled openings.
C. Fire Labeled Gasketing: Assemblies complying with NFPA 80 that are listed and labeled
by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire
ratings indicated, based on testing according to UL-10C.
1. Provide intumescent seals as indicated to meet UL10C Standard for Positive
Pressure Fire Tests of Door Assemblies, and NPFA 252, Standard Methods of Fire
Tests of Door Assemblies.
D. Sound-Rated Gasketing:Assemblies that are listed and labeled by a testing and inspecting
agency, for sound ratings indicated.
E. Replaceable Seal Strips: Provide only those units where resilient or flexible seal strips are
easily replaceable and readily available from stocks maintained by manufacturer.
2.12 FABRICATION
A. Fasteners: Provide door hardware manufactured to comply with published templates
generally prepared for machine, wood, and sheet metal screws. Provide screws according
to manufacturers recognized installation standards for application intended.
2.13 FINISHES
A. Standard: Designations used in the Hardware Sets and elsewhere indicate hardware
finishes complying with ANSI/BHMA A156.18, including coordination with traditional U.S.
finishes indicated by certain manufacturers for their products.
B. Provide quality of finish, including thickness of plating or coating (if any), composition,
hardness, and other qualities complying with manufacturer's standards, but in no case less
than specified by referenced standards for the applicable units of hardware
C. Protect mechanical finishes on exposed surfaces from damage by applying a strippable,
temporary protective covering before shipping.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 11
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine scheduled openings, with Installer present, for compliance with requirements for
installation tolerances, labeled fire door assembly construction, wall and floor construction,
and other conditions affecting performance.
B. Notify engineer of any discrepancies or conflicts between the door schedule, door types,
drawings and scheduled hardware. Proceed only after such discrepancies or conflicts
have been resolved in writing.
3.2 PREPARATION
A. Hollow Metal Doors and Frames: Comply with ANSI/DHI A115 series.
B. Wood Doors: Comply with ANSI/DHI A115-W series.
3.3 INSTALLATION
A. Install each item of mechanical and electromechanical hardware and access control
equipment to comply with manufacturer's written instructions and according to
specifications.
1. Installers are to be trained and certified by the manufacturer on the proper
installation and adjustment of fire, life safety, and security products including:
hanging devices; locking devices; closing devices; and seals.
B. Mounting Heights: Mount door hardware units at heights indicated in following applicable
publications, unless specifically indicated or required to comply with governing regulations:
1. Where indicated to comply with accessibility requirements, comply with ANSI A117.1
"Accessibility Guidelines for Buildings and Facilities."
2. Provide blocking in drywall partitions where wall stops or other wall mounted
hardware is located.
C. Retrofitting: Install door hardware to comply with manufacturer's published templates and
written instructions. Where cutting and fitting are required to install door hardware onto or
into surfaces that are later to be painted or finished in another way, coordinate removal,
storage, and reinstallation of surface protective trim units with finishing work specified in
Division 9 Sections. Do not install surface-mounted items until finishes have been
completed on substrates involved.
D. Thresholds: Set thresholds for exterior and acoustical doors in full bed of sealant
complying with requirements specified in Division 7 Section "Joint Sealants."
E. Storage: Provide a secure lock up for hardware delivered to the project but not yet
installed. Control the handling and installation of hardware items so that the completion of
the work will not be delayed by hardware losses before and after installation.
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 12
3.4 FIELD QUALITY CONTROL
A. Field Inspection (Punch Report): Reference Division 01 Section "Closeout Procedures"for
project punch and reporting requirements including compliance with approved submittals
and verification door hardware is properly installed, operating and adjusted.
3.5 ADJUSTING
A. Initial Adjustment: Adjust and check each operating item of door hardware and each door
to ensure proper operation or function of every unit. Replace units that cannot be adjusted
to operate as intended. Adjust door control devices to compensate for final operation of
heating and ventilating equipment and to comply with referenced accessibility
requirements.
3.6 CLEANING AND PROTECTION
A. Protect all hardware stored on construction site in a covered and dry place. Protect
exposed hardware installed on doors during the construction phase. Install any and all
hardware at the latest possible time frame.
B. Clean adjacent surfaces soiled by door hardware installation.
C. Clean operating items as necessary to restore proper finish. Provide final protection and
maintain conditions that ensure door hardware is without damage or deterioration at time
of owner occupancy.
3.7 DEMONSTRATION
A. Instruct Owner's maintenance personnel to adjust, operate, and maintain mechanical and
electromechanical door hardware.
3.8 DOOR HARDWARE SETS
A. The hardware sets represent the design intent and direction of the owner and engineer.
They are a guideline only and should not be considered a detailed hardware schedule.
Discrepancies, conflicting hardware and missing items should be brought to the attention
of the engineer with corrections made prior to the bidding process. Omitted items not
included in a hardware set should be scheduled with the appropriate additional hardware
required for proper application and functionality.
1. Quantities listed are for each pair of doors, or for each single door.
2. The supplier is responsible for handing and sizing all products.
3. Where multiple options for a piece of hardware are given in a single line item, the
supplier shall provide the appropriate selection for the material and application.
B. HARDWARE SETS
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER DOOR HARDWARE
REEDLEY, CA. SECTION 087100 - 13
D1
3 Stainless tamperproof steel ball bearing hinges
1 Heavy Duty Mortise Lockset— Lever handles and Dead Bolt
1 Puck Lock and accessories (if applicable)
1 Door Closer
1 Threshold
1 Rain Guard
1 Sweep
1 Gasket/Weather Stripping
1 Door Stop (if applicable)
D2,D3
3 Hinges
1 Heavy Duty Mortise Lockset -Lever handles and Dead Bolt
1 Door Closer
1 Kickplate
1 Threshold
1 Gasket
1 Door Stop (of applicable)
END OF SECTION 087100
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 1
SECTION 092900 - GYPSUM BOARD
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes the following:
1. Interior gypsum board for walls and ceilings.
B. Related Sections include the following:
1. Division 05 Section "Cold-Formed Metal Framing" for metal framing and backing.
2. Division 07 Section "Thermal Insulation" for insulation and vapor retarders installed
in assemblies that incorporate gypsum board.
3. Division 09 painting Sections for primers applied to gypsum board surfaces.
1.02 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Samples: For the following products:
1. Trim Accessories: Full-size Sample in 12-inch long lengths for each trim
accessory indicated.
2. Textured Finishes: 24 inch square size for each textured finish indicated and on
same backing indicated for Work.
1.03 QUALITY ASSURANCE
A. Fire-Resistance-Rated Assemblies: For fire-resistance-rated assemblies, provide
materials and construction identical to those tested in assembly indicated according to
ASTM E 119 by an independent testing agency.
1.04 STORAGE AND HANDLING
A. Store materials inside under cover and keep them dry and protected against damage
from weather, condensation, direct sunlight, construction traffic, and other causes. Stack
panels flat to prevent sagging.
1.05 PROJECT CONDITIONS
A. Environmental Limitations: Comply with ASTM C 840 requirements or gypsum board
manufacturer's written recommendations, whichever are more stringent.
B. Do not install interior products until installation areas are enclosed and environmental
conditions are acceptable.
C. Do not install panels that are wet, those that are moisture damaged, and those that are
mold damaged.
1. Indications that panels are wet or moisture damaged include, but are not limited to,
discoloration, sagging, or irregular shape.
2. Indications that panels are mold damaged include, but are not limited to, fuzzy or
splotchy surface contamination and discoloration.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 2
PART 2 - PRODUCTS
2.01 PANELS, GENERAL
A. Size: Provide in maximum lengths and widths available that will minimize joints in each
area and that correspond with support system indicated.
2.02 INTERIOR GYPSUM BOARD
A. General: Complying with ASTM C 36/C 36M or ASTM C 1396/C 1396M, as applicable
to type of gypsum board indicated and whichever is more stringent.
B. Regular Type (Type "X" Fire Rated):
1. Thickness: 5/8 inch.
2. Long Edges: Tapered and featured (rounded or beveled) for prefilling.
C. Ceiling Type: Manufactured to have more sag resistance than regular-type gypsum
board. Use Type C (Fire Rated where required for fire assemblies):
1. Thickness: 5/8 inch.
2. Long Edges: Tapered.
D. Other types and thicknesses specifically indicated or otherwise required to achieve fire-
rated and sound rated wall and ceiling assemblies.
2.03 TRIM ACCESSORIES
A. Interior Trim: ASTM C 1047.
1. Material: Galvanized or aluminum-coated steel sheet or rolled zinc.
2. Shapes:
a. Cornerbead.
b. Bullnose bead.
C. LC-Bead: J-shaped; exposed long flange receives joint compound.
d. L-Bead: L-shaped; exposed long flange receives joint compound.
e. U-Bead: J-shaped; exposed short flange does not receive joint compound.
f. Expansion (control)joint.
g. Curved-Edge Cornerbead: With notched or flexible flanges.
2.04 JOINT TREATMENT MATERIALS
A. General: Comply with ASTM C 475/C 475M.
B. Joint Tape:
1. Interior Gypsum Wallboard: Reinforced Paper.
C. Joint Compound for Interior Gypsum Wallboard: For each coat use formulation that is
compatible with other compounds applied on previous or for successive coats.
1. Prefilling: At open joints, rounded or beveled panel edges, and damaged surface
areas, use setting-type taping compound.
2. Embedding and First Coat: For embedding tape and first coat on joints, fasteners,
and trim flanges, use drying-type, all-purpose compound.
3. Fill Coat: For second coat, use drying-type, all-purpose compound.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 3
4. Finish Coat: For third coat, use setting-type, sandable-type sandable topping
compound.
5. Skim Coat: When a level 5 finish is required, for the final coat use setting-type,
sandable topping compound.
2.05 AUXILIARY MATERIALS
A. General: Provide auxiliary materials that comply with referenced installation standards
and manufacturer's written recommendations.
B. Laminating Adhesive: Adhesive or joint compound recommended for directly adhering
gypsum panels to continuous substrate.
1. Use adhesives that have a VOC content of 50 g/L or less when calculated
according to 40 CFR 59, Subpart D (EPA Method 24).
C. Gypsum Board Adhesive:
1. DAP Professional Drywall Construction Adhesive.
2. Liquid Nails Drywall Adhesive.
D. Steel Drill Screws: ASTM C 1002, unless otherwise indicated.
E. Acoustical Sealant: As specified in Division 07 Section "Joint Sealants."
F. Thermal Insulation: As specified in Division 07 Section "Thermal Insulation."
G. Vapor Retarder: As specified in Division 07 Section "Thermal Insulation."
2.06 TEXTURE FINISHES
A. Finish: As recommended by textured finish manufacturer.
1. Texture Finish: Water-based, job- mixed, drying-type texture finish for spray
application.
2. Texture: Medium orange peel, smooth sand, light orange peel or match existing
adjacent finish.
3. Engineer to approve samples prior to application.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Examine areas and substrates, with Installer present, and including welded hollow-metal
frames and framing, for compliance with requirements and other conditions affecting
performance. Verify that all blocking, backing, strapping and framed openings as
required for attachment of accessories, equipment, fixtures and cabinetry has been
properly installed.
B. Examine panels before installation. Reject panels that are wet, moisture damaged, and
mold damaged.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 4
3.02 APPLYING AND FINISHING PANELS, GENERAL
A. Comply with ASTM C 840.
B. Install ceiling panels across framing to minimize the number of abutting end joints and to
avoid abutting end joints in central area of each ceiling. Stagger abutting end joints of
adjacent panels not less than one framing member.
C. Install panels with face side out. Butt panels together for a light contact at edges and
ends with not more than 1/16 inch of open space between panels. Do not force into
place.
D. Locate edge and end joints over supports, except in ceiling applications where
intermediate supports or gypsum board back-blocking is provided behind end joints. Do
not place tapered edges against cut edges or ends. Stagger vertical joints on opposite
sides of partitions. Do not make joints other than control joints at corners of framed
openings.
E. Form control and expansion joints with space between edges of adjoining gypsum
panels.
F. Cover both faces of support framing full height with gypsum panels in concealed spaces
(above ceilings, etc.), except in chases braced internally. Fully encapsulate interior side
of insulated walls with gypsum board panels.
1. Unless concealed application is indicated or required for sound, fire, air, or smoke
ratings, coverage may be accomplished with scraps of not less than 8 sq. ft. in
area.
2. Fit gypsum panels around ducts, pipes, and conduits.
3. Where partitions intersect structural members projecting below underside of
floor/roof slabs and decks, cut gypsum panels to fit profile formed by structural
members; allow 1/4- to 3/8-inch-wide joints to install sealant.
4. At fire-resistive wall and ceiling assemblies, install gypsum board panels cut tight
to and around rafters, joints, blocking, beams and similar projections to provide full
membrane protection to roof or floor deck above and/or to rated membrane applied
to underside of roof/floor framing to achieve the fire protection required by
referenced CBC UL or W-H assemblies and as indicated in drawings. Seal voids
with fire resistant sealant.
G. Isolate perimeter of gypsum board applied to non-load-bearing partitions at structural
abutments, except floors. Provide 1/4- to 1/2-inch- wide spaces at these locations, and
trim edges with edge trim where edges of panels are exposed. Seal joints between
edges and abutting structural surfaces with acoustical sealant.
H. Attachment to Steel Framing: Attach panels so leading edge or end of each panel is
attached to open (unsupported) edges of stud flanges first.
I. Wood Framing: Install gypsum panels over wood or metal framing, with floating internal
corner construction. Do not attach gypsum panels across the flat grain of wide-
dimension lumber, including floor joists and headers. Float gypsum panels over these
members, or provide control joints to counteract wood shrinkage.
J. STC-Rated Assemblies: Seal construction at perimeters, behind control joints, and at
openings and penetrations with a continuous bead of acoustical sealant. Install
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 5
acoustical sealant at both faces of partitions at perimeters and through penetrations.
Comply with ASTM C 919 and with manufacturer's written recommendations for locating
edge trim and closing off sound-flanking paths around or through assemblies, including
sealing partitions above acoustical ceilings.
3.03 APPLYING INTERIOR GYPSUM BOARD
A. Install interior gypsum board in the following locations:
1. Regular Type: Vertical surfaces, unless otherwise indicated.
2. Ceiling Type: Ceiling surfaces.
B. Single-Layer Application:
1. On ceilings, apply gypsum panels before wall/partition board application to greatest
extent possible and at right angles to framing, unless otherwise indicated.
2. On partitions/walls, apply gypsum panels vertically (parallel to framing), unless
otherwise indicated or required by fire-resistance-rated assembly, and minimize
end joints.
a. Stagger abutting end joints not less than one framing member in alternate
courses of panels.
3. Fastening Methods: Apply gypsum panels to supports with steel drill screws.
3.04 INSTALLING TRIM ACCESSORIES
A. General: For trim with back flanges intended for fasteners, attach to framing with same
fasteners used for panels. Otherwise, attach trim according to manufacturer's written
instructions.
B. Control Joints: Install control joints according to ASTM C 84 in specific locations
approved by Engineer for visual effect and as indicated on the drawings.
C. Interior Trim: Install in the following locations:
1. Cornerbead: Use at outside corners.
2. LC-Bead: Use at exposed panel edges.
3. L-Bead: Use at exposed panel edges. Leave 1/4" space for caulk where abutting
dissimilar materials.
3.05 FINISHING GYPSUM BOARD
A. General: Treat gypsum board joints, interior angles, edge trim, control joints,
penetrations, fastener heads, surface defects, and elsewhere as required to prepare
gypsum board surfaces for decoration. Promptly remove residual joint compound from
adjacent surfaces.
B. Prefill open joints and damaged surface areas.
C. Apply joint tape over gypsum board joints, except those with trim having flanges not
intended for tape.
D. Gypsum Board Finish Levels: Finish panels to levels indicated below and according to
ASTM C 840:
1. Level 1: Ceiling plenum areas, concealed areas, and where indicated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GYPSUM BOARD
REEDLEY, CA. SECTION 092900 - 6
2. Level 2: Panels that are substrate for acoustical tile and vinyl covered tackboard.
3. Level 3: Where indicated on the drawings.
4. Level4: At panel surfaces that will be exposed to view, unless otherwise
indicated.
a. Primer and its application to surfaces are specified in other Division 09
Sections.
5. Level 5: Where wall coverings are specified or where indicated for a very
smooth/level finish.
a. Primer and its application to surfaces are specified in other Division 09
Sections.
3.06 APPLYING TEXTURE FINISHES
A. Surface Preparation and Primer: Prepare and apply primer to gypsum panels and other
surfaces receiving texture finishes. Apply primer to surfaces that are clean, dry, and
smooth.
B. Texture Finish Application: Mix and apply finish using powered spray equipment, to
produce a uniform texture free of starved spots or other evidence of thin application or of
application patterns.
C. Prevent texture finishes from coming into contact with surfaces not indicated to receive
texture finish by covering them with masking agents, polyethylene film, or other means.
If, despite these precautions, texture finishes contact these surfaces, immediately
remove droppings and overspray to prevent damage according to texture-finish
manufacturer's written recommendations.
3.07 PROTECTION
A. Protect installed products from damage from weather, condensation, direct sunlight,
construction, and other causes during remainder of the construction period.
B. Remove and replace panels that are wet, moisture damaged, and mold damaged.
1. Indications that panels are wet or moisture damaged include, but are not limited to,
discoloration, sagging, or irregular shape.
2. Indications that panels are mold damaged include, but are not limited to, fuzzy or
splotchy surface contamination and discoloration.
END OF SECTION 09290
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER RESINOUS FLOORING
REEDLEY, CA. SECTION 096723 - 1
SECTION 096723 — RESINOUS FLOORING
PART 1 -GENERAL
1.1 SUMMARY
A. This Section includes:
1. High-performance resinous flooring systems.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Installer Certificates for Qualification: Signed by manufacturer stating that installers
comply with specified requirements.
C. Material Certificates: For each resinous flooring component, from manufacturer.
D. Maintenance Data: For maintenance manuals.
E. Samples: Submit two 6" X 6" samples of each resinous flooring system applied to a
rigid backing. Provide sample which is a true representation of proposed field applied
finish. Provide sample color and texture for approval from Owner in writing or
approved by General Contractor prior to installation.
F. Product Schedule: For resinous flooring.
1.3 QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is trained and
approved for installation of flooring systems required for this Project.
1. Engage an installer who is approved in writing by resinous flooring manufacturer
as qualified to apply resinous flooring systems indicated.
2. Installer Letter of Qualification: Installer to provide letter stating that they have
been in business for at least 5 years and listing 5 projects in the last 2 years of
similar scope. For each project provide: project name, location, date of
installation, contact information, size of project, and manufacturer of materials
with system information.
B. Source Limitations: Obtain primary resinous flooring materials, including primers,
resins, hardening agents, grouting coats, and topcoats, from single source from single
manufacturer. Provide secondary materials, including patching and fill material, joint
sealant, and repair materials, of type and from source recommended by manufacturer
of primary materials.
C. Pre-installation Conference: Conduct conference at Project site before work and
mockups begin.
D. Mockups: Apply mockups to verify selections made under sample submittals and to
demonstrate aesthetic effects and set quality standards for materials and execution.
Do not cover up mockup area.
1. Apply full-thickness mockups on 16 square foot floor area selected by Architect.
2. Finish surfaces for verification of products, color, texture, and sheen.
3. Simulate finished lighting conditions for Architect's review of mockups.
4. Approved mockups may become part of the completed Work if undisturbed at
time of Substantial Completion.
5. Mockup shall demonstrate desired slip resistance for review and approval by
Owner's representative in writing.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER RESINOUS FLOORING
REEDLEY, CA. SECTION 096723 - 2
1.4 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials in original packages and containers, with seals unbroken, bearing
manufacturer's labels indicating brand name and directions for storage and mixing with
other components.
1. Maintain containers in clean condition, free of foreign materials and residue.
2. Remove rags and waste from storage areas daily.
1.5 PROJECT CONDITIONS
A. Environmental Limitations: Comply with resinous flooring manufacturer's written
instructions for substrate temperature, ambient temperature, moisture, ventilation, and
other conditions affecting resinous flooring application.
B. Lighting: Provide permanent lighting or, if permanent lighting is not in place, simulate
permanent lighting conditions during resinous flooring application.
C. Close spaces to traffic during resinous flooring application and for not less than 24
hours after application unless manufacturer recommends a longer period.
PART2 - PRODUCTS
2.1 MATERIALS
A. VOC Content of Resinous Flooring: Provide resinous flooring systems, for use inside
the weatherproofing system, that comply with the following limits for VOC content when
calculated according to 40 CFR 59, Subpart D (EPA Method 24)].
1. Resinous Flooring: 100 g/L.
2.2 HIGH-PERFORMANCE RESINOUS FLOORING
A. Resinous Flooring: Abrasion-, impact- and chemical-resistant, high-performance,
resin-based, monolithic floor surfacing and cove base system designed to produce a
seamless floor
B. System Characteristics:
1. Color and Pattern: As indicated from manufacturers
2. Slip Resistance: Provide slip resistant finish.
PART 3 - EXECUTION
3.1 PREPARATION
A. Inspection: Prior to commencing Work, thoroughly examine all underlying and
adjoining work, surfaces and conditions upon which Work is in any way dependent for
perfect results. Report all conditions which affect Work. No "waiver of responsibility" for
incomplete, inadequate or defective underlaying and adjoining work, surfaces and
conditions will be considered, unless notice of such unsatisfactory conditions has been
filed and agreed to in writing before Work begins. Commencement of Work constitutes
acceptance of surfaces.
B. Surface Preparation: Remove all surface contamination, loose or weakly adherent
particles, laitance, grease, oil, curing compounds, paint, dust and debris by blast track
method or approved mechanical means (acid etch not allowed). If surface is
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER RESINOUS FLOORING
REEDLEY, CA. SECTION 096723 - 3
questionable try a test patch. Create a minimum surface profile for the system
specified in accordance with the methods described in ICRI No. 03732 to achieve
profile numbers as follows:
C.
1. Thin film, to 10 mils CSP-1 to CSP-3
2. Thin and medium films, 10 to 40 mils CSP-3 to CSP-5
3. Self-leveling mortars, to 3/16" CSP-4 to CSP-6
4. Mortars and laminates, to 1/4" or more CSP-5 to CSP-10
D. Verify that concrete substrates are dry and moisture-vapor emissions are within
acceptable levels according to manufacturer's written instructions.
1. Moisture Testing: Perform tests indicated below.
a. Calcium Chloride Test: Perform anhydrous calcium chloride test per
ASTM F 1869. Proceed with installation only after substrates have
maximum moisture-vapor-emission rate of 3 lb of water/1000 sq. ft. in 24
hours. Perform tests so that each test area does not exceed 1000 sq. ft.
and perform 3 tests for the first 1000 sq. ft. and one additional test for
every additional 1000 sq ft.
b. In-Situ Probe Test: Perform relative-humidity test using in-situ probes per
ASTM F 2170. Proceed with installation only after substrates have a
maximum 75 percent relative-humidity-level measurement.
3.2 ENVIRONMENTAL CONDITIONS
A. All applicators and all other personnel in the area of the RF installation shall take all
required and necessary safety precautions. All manufacturers' installation instructions
shall be implicitly instructions shall be implicitly followed.
B. Repair damaged and deteriorated concrete according to resinous flooring
manufacturer's written instructions.
C. Alkalinity and Adhesion Testing: Verify that concrete substrates have pH within
acceptable range. Perform tests recommended by manufacturer. Proceed with
application only after substrates pass testing.
D. Resinous Materials: Mix components and prepare materials according to resinous
flooring manufacturer's written instructions.
E. Use patching and fill material to fill holes and depressions in substrates according to
manufacturer's written instructions.
F. Treat control joints and other nonmoving substrate cracks to prevent cracks from
reflecting through resinous flooring according to manufacturer's written instructions.
3.3 APPLICATIONS
A. Install resinous floor over properly prepared concrete surface in strict accordance with
the manufacturer's directions.
1. Install the primer and/or base coats over thoroughly cleaned and prepared
concrete.
2. Install topcoat over flooring after excess aggregate has been removed.
3. Maintain a slab temperature of 60°F to 80°F for 24 hours minimum before
applying floor topping, or as instructed by manufacturer.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER RESINOUS FLOORING
REEDLEY, CA. SECTION 096723 -4
B. Apply components of resinous flooring system according to manufacturer's written
instructions to produce a uniform, monolithic wearing surface of thickness indicated.
1. Coordinate application of components to provide optimum adhesion of resinous
flooring system to substrate, and optimum intercoat adhesion.
2. Cure resinous flooring components according to manufacturer's written
instructions. Prevent contamination during application and curing processes.
3. At substrate expansion and isolation joints, comply with resinous flooring
manufacturer's written instructions.
C. Sealant: Saw cut resinous floor topping at expansion joints in concrete slab. Fill
sawcuts with sealant prior to final seal coat application. Follow manufacturer's written
recommendations.
D. Apply primer over prepared substrate at manufacturer's recommended spreading rate.
E. Slip Resistant Finish: Provide grit for slip resistance.
F. Apply topcoats in number indicated for flooring system and at spreading rates
recommended in writing by manufacturer.
3.4 COMPLETED WORK
A. Cleaning: Upon completion of the Work, clean up and remove from the premises
surplus materials, tools, appliances, empty cans, cartons and rubbish resulting from
the Work. Clean off all spattering and drippings, and all resulting stains.
B. Protection: Protect Work in accordance with manufacturer's directions from damage
and wear during the remainder of the construction period. Use protective methods and
materials, including temporary covering, recommended in writing by resinous flooring
manufacturer.
C. Contractor shall insure that coating is protected from any traffic until it is fully cured to
the satisfaction of the coating manufacturer.
END OF SECTION 096723
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 1
SECTION 099100— PAINTING
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes surface preparation and field painting of exposed exterior and
interior items and surfaces, as indicated on the drawings and schedules, and as
specified herein.
1. Surface preparation, priming, and finish coats specified in this Section are in
addition to shop priming and surface treatment specified in other Sections.
2. Paint and finish exposed surfaces using the combination of materials listed on
Painting Schedule in part 3 of this Section, as specified herein, and as needed for
a complete and proper installation.
B. Paint exposed surfaces, except where these Specifications indicate that the surface or
material is not to be painted or is to remain natural. If an item or a surface is not
specifically mentioned, paint the item or surface the same as similar adjacent materials
or surfaces. If a color of finish is not indicated, Engineer will select from standard colors
and finishes available.
1. Painting includes field painting of exposed bare and covered pipes and ducts
(including color coding), hangers, exposed steel and iron supports, and surfaces of
mechanical and electrical equipment that do not have a factory-applied final finish
except when specifically noted otherwise.
2. Priming or priming and finishing of certain surfaces may be specified to be factory-
performed or installer-performed under pertinent other Sections. Said provisions
DO NOT negate the primers required to be applied on-site where finishing is a part
of this Section.
C. Provide labor, materials, equipment, and services needed in areas of alteration work and
new construction to clean and prepare the surfaces, and to paint including, but not
necessarily limited to:
1. Interiors requiring painting of surfaces including gyp. board walls/ceilings, wood
casework, trim, window panels/frames/sash, doors/frames and other similar items in
the areas of work.
2. Exterior:
a. Trim, window panels/frames/sash, doors/frames and other similar items in
the area of work.
D. Do not paint prefinished items, concealed surfaces, finished metal surfaces, operating
parts, and required labels.
1. Prefinished items include (but not necessarily limited to) the following factory-
finished components:
a. Finished mechanical and electrical equipment.
b. Light fixtures.
2. Concealed surfaces include walls or ceilings in the following generally inaccessible
spaces:
a. Furred areas.
b. Ceiling plenums.
C. Utility tunnels.
d. Pipe spaces.
e. Duct shafts.
3. Finished metal surfaces include (but not necessarily limited to) the following:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 2
a. Anodized aluminum.
b. Stainless steel.
C. Chromium plate.
d. Copper and copper alloys.
e. Bronze and brass.
4. Operating parts include moving parts of operating equipment and the following:
a. Valve and damper operators.
b. Linkages.
C. Sensing devices.
d. Motor and fan shafts.
5. Labels: Do not paint over UL, FMG, or other code-required labels or equipment
name, identification, performance rating, or nomenclature plates.
6. Sandblasted concrete: Do not paint unless so scheduled.
E. Related Sections include the following:
1. Division I Section "Product Requirements".
2. Division 8 Section "Hollow Meta Doors and Window Frames" for factory priming
steel doors and frames.
3. Division 9 Section "Gypsum Board" for surface preparation of gypsum board.
F. The Finish Schedules and descriptive notes indicated on the drawings, indicates
the location of interior room surfaces to be painted or finished. The Schedule indications
are general and do not necessarily define the detail requirements. Include all detailed
refinements and further instructions as may be given for the required complete finishing
of all spaces and rooms. Interior Elevations, building Sections and Details, Room Finish
Schedules and Color Schedules are all to be used in concert to determine requirements
of this Section.
1.2 REFERENCES
A. Green Seal Standard GS-11, Paints, First Edition, May 1993.
B. Green Seal Standard GC-03, Anti Corrosive Paints, Second Edition, January 1997.
C. SCAQMD —South Coast Air Quality Management District
1. SCAQMD-1113— Rule 1113, Engineerural Coatings
D. SJVAPCD — San Joaquin Valley Air Pollution Control District
1. SJVAPCD Regulations — Local Regulations
E. SSPC — Steel Structures Painting Council.
1.3 DEFINITIONS
A. General: "Paint," as used herein, means coating systems materials including primers,
emulsions, epoxy, enamels, stains, sealers, fillers, and other applied materials whether
used as prime, intermediate, or finish coats. Standard coating terms defined in
ASTM D 16 apply to this Section.
1. Flat refers to a lusterless or matte finish with a gloss range below 15 when
measured at an 85-degree meter.
2. Eggshell refers to low-sheen finish with a gloss range between 20 and 35 when
measured at a 60-degree meter.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 3
3. Semigloss refers to medium-sheen finish with a gloss range between 35 and 70
when measured at a 60-degree meter.
4. Full gloss refers to high-sheen finish with a gloss range more than 70 when
measured at a 60-degree meter.
1.4 SUBMITTALS
A. Product Data: Within 25 calendar days after the Contractor has received the Owner's
Notice to proceed, submit, for each paint system indicated, (include block fillers and
primers) the following:
1. Material List: An inclusive list of required coating materials. Indicate each material
and cross-reference specific coating, finish system, and application. Identify each
material by manufacturer's catalog number and general classification. Submit only
those products applicable to the project scope for work indicated in the drawings.
2. Manufacturer's Information: Manufacturer's technical information, including label
analysis and instructions for handling, storing, and applying each coating material.
Data proving compliance with the specified requirements and regulations shall be
submitted for inclusion with warranty and certification information to be retained by
the Owner.
B. Samples
1. Following the selection of colors and glosses by the Engineer, submit Samples for
the Engineer's review. If selection of colors/glosses has been scheduled, commence
immediately with the sample submittal.
a. Provide five Samples of each color and each gloss for each material on which
the finish is specified to be applied. Submittals will be reviewed for color and
texture/finish only. Provide a listing of material and application for each coat
of each finish sample.
b. Except as otherwise directed by the Engineer, make Samples approximately
8" x 10" in size on materials simulating actual finished conditions.
C. If so directed by the Engineer, submit Samples during progress of the Work in
the form of actual application of the approved materials on actual surfaces to
be painted. Provide full-coat finish samples on at least 100 sq. ft. of surface
as directed, until required sheen, color and texture is obtained; simulate
finished lighting conditions for review of in-place work.
2. Revise and resubmit each Sample as requested until the required gloss, color, and
texture is achieved. Such Samples, when approved, will become standards of color
and finish for accepting or rejecting the work of this Section.
3. Do not commence finish painting until approved Samples are on file at the job site.
C. Qualification Data: For Applicator.
1.6 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced
in the necessary crafts and who are completely familiar with the specified requirements
and the methods needed for proper performance of the work of this Section.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 4
B. Paint coordination:
1. Provide finish coats which are compatible with the prime coats actually used. Provide
priming, undercoating, coating and finishing products produced by a single
manufacturer source. Use only thinners approved by the paint manufacturers, and
use only within recommended limits. Insofar as practicable, use undercoat, finish
coat, and thinner material as parts of a unified system of paint finish.
2. Review other Sections of these Specifications as required, verifying the prime coats
to be used and assuring compatibility of the total coating system for the various
substrata.
3. Upon request, furnish information on the characteristics of the specific finish materials
to assure that compatible prime coats are used.
4. Provide barrier coats over noncompatible primers, or remove the primer and reprime
as required.
5. Notify the Engineer in writing of anticipated problems in using the specified coating
systems over prime-coatings supplied under other Sections.
C. Intent of the drawings is to have a completed product. Where work of the Contract disturbs
existing finishes such that repair is required, said repair work is to be accomplished to
logical architectural stopping points.
D. Protect finished work from damage by other trades, workers and processes until work is
turned over to the Owner. Provide temporary protective barriers and coverings when
necessary.
E. Protect other work/surfaces from damage, drips or overspray by using appropriate shields,
tarps, masks, etc. Clean any errant paint from adjacent materials as required and in
accordance with appropriate cleaning methods for both the paint and for the materials
being cleaned.
F. Regulatory Requirements:
1. Comply with applicable codes and regulations of governmental agencies
having jurisdiction including those having jurisdiction over airborne emissions and
industrial waste disposal. Where those requirements conflict with this Specification,
comply with the more stringent provisions.
2. Regulatory changes may affect the formulation, availability, or use of specified
coatings. Confirm availability of coatings to be used prior to job going out to bid and
before start of painting project.
3. Comply with the current applicable regulations of the California Air Resources Board
(CARB) and the Environmental Protection Agency (EPA).
4. Conform to SJVAPCD Regulations for maximum VOC limits.
G. Quality verification requirements: These specifications call for a per-coat dry film
thickness. The Contractor shall have available upon 48 hours notice a spectrographic
measuring device (or other appropriate device) able to measure total thickness should
there be a question as to the number of coats or compliance with the overall film
thickness requirements.
H. Source Limitations: Obtain primers for each coating system from the same manufacturer
as the finish coats.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 5
1.7 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials to Project site in manufacturer's original, unopened packages and
containers bearing manufacturer's name and label and the following information:
1. Product name or title of material.
2. Product description (generic classification or binder type).
3. Manufacturer's stock number and date of manufacture.
4. Contents by volume, for pigment and vehicle constituents.
5. Thinning instructions.
6. Application instructions.
7. Color name and number.
8. VOC content.
B. Store materials not in use in tightly covered containers in a well-ventilated area at a
minimum ambient temperature of 45 deg F. Maintain storage containers in a clean
condition, free of foreign materials and residue.
1. Protect from freezing. Keep storage area neat and orderly. Remove oily rags and
waste daily.
1.8 PROJECT CONDITIONS
A. IF APPLICABLE: Do not apply solvent-thinned paints when the temperature of surfaces
to be painted and the surrounding air temperatures are below 45' F, unless otherwise
permitted by the manufacturer's printed instructions.
B. Apply waterborne paints only when temperatures of surfaces to be painted and
surrounding air are between 50 and 90 deg F, unless otherwise permitted by the
manufacturer's printed instructions.
Do not apply paint in snow, rain, fog, or mist; or when relative humidity exceeds 85
percent; or at temperatures less than 5 deg F above the dew point; or to damp or wet
surfaces, unless otherwise permitted by the manufacturer's printed instructions.
1. Painting may continue during inclement weather only if surfaces and areas to be
painted are enclosed and heated (or cooled) within temperature limits specified by
manufacturer during application and drying periods.
2. Applications may also continue during inclement weather only within the
temperature and humidity limits specified by the paint manufacturer as being
suitable for use during application and drying periods.
D. Avoid painting surfaces when exposed to direct sunlight.
1.9 EXTRA MATERIALS
A. Furnish extra paint materials from the same production run as the materials applied and
in the quantities described below. Package with protective covering for storage and
identify with labels describing contents and location where used. Deliver extra materials
to Owner.
1. Quantity: Furnish Owner with an additional 4 percent, but not less than 1 gal. or 1
case, as appropriate, of each material and color and gloss applied.
PART 2 — PRODUCTS
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 6
2.2 PAINT MATERIALS
A. Paints: Provide Ready-Mixed, except field catalyzed coatings. Pigments shall be fully
ground maintaining soft paste consistency, capable of being readily and uniformly
dispersed to complete homogeneous mixture. Paints shall have good flowing and brushing
properties and be capable of drying or curing free of streaks and sags.
B. Acceptable materials: Provide the best professional quality grade of various types of
coatings as regularly manufactured by acceptable paint materials manufacturers that
comply with the current EPA rules and regulations in place where the project is located.
Materials not displaying manufacturer's identification as a standard, best professional line
product, and not complying with the EPA rules and regulations, will not be acceptable. The
quantity of titanium dioxide, the use of clays, aluminum silicate, talc and the purity of acrylic
materials are a few of the criteria which will be used by the Engineer in determining
equivalency of materials.
C. Accessory Materials: Linseed oil, shellac, solvents, and other materials not specified but
required to achieve required finishes shall be of high quality and approved by manufacturer.
D. Proprietary names used to designate colors, materials or finishes are not intended to imply
that products of above-named manufacturers are unacceptable or excluded where
equivalent products are available.
E. Paint Pigments shall be pure, unfading, applicable types suited to the substrates and
services to which they are to be applied.
2.4 APPLICATION EQUIPMENT
A. For application of the approved paint, use only such equipment as is recommended for
application of the particular paint by the manufacturer of the particular paint, and as allowed
by the rules and regulations (i.e. EPA) in place at the project location.
B. Prior to use of application equipment, verify that the proposed equipment is actually
compatible with the material to be applied, and that integrity of the finish will not be
jeopardized by use of the proposed equipment.
2.5 OTHER MATERIALS
A. Provide other materials, not specifically described but required for a complete and proper
installation, as selected by the Contractor subject to the approval of the Engineer.
B. If materials are not listed for items such as patching, provide quality patching materials
specifically developed for the use, applied as per the manufacturer's recommendations.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 7
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Applicator present, for compliance with
requirements for paint application.
1. Proceed with paint application only after unsatisfactory conditions have been
corrected and surfaces receiving paint are thoroughly dry.
2. Start of painting will be construed as Applicator's acceptance of surfaces and
conditions within a particular area.
B. Coordination of Work: Review other Sections in which primers are provided to ensure
compatibility of the total system for various substrates. On request, furnish information
on characteristics of finish materials to ensure use of compatible primers.
1. Notify Engineer about anticipated problems when using the materials specified
over substrates primed by others.
C. Do not paint over dirt, dust, rust scale, grease, moisture, scuffed surfaces, or conditions
otherwise detrimental to formation of a durable paint finish.
D. Beware of a condition known as "critical lighting". This condition causes shadows that
accentuate even the slightest surface variations. A pigmented sealer will provide tooth
for succeeding decorative coating, but "does not" equalize smoothness or surface
texture. Any corrective action to drywall must be done by the drywall contractor prior to
decorating.
E. Follow all applicable procedures and requirements in the Lead Based Paint & Coating
Removal Guidelines furnished by FUSD prior to applying new paint coatings.
3.2 PROTECTION
A. Protect previously installed work and materials which may be affected by Work of this
Section.
1. Protect prefinished surfaces, lawns, shrubbery and adjacent surfaces against paint
and damage.
2. Furnish sufficient drop cloths, shields, and protective equipment to prevent spray
or splatter from fouling surfaces to being painted.
3. Protect surfaces, equipment, and fixtures from damage resulting from use of fixed,
movable and hanging scaffolding, planking, and staging.
3.3 MATERIALS PREPARATION
A.General:
1. Mix and prepare paint materials in strict accordance with the manufacturers'
recommendations.
2. Maintain containers used in storage, mixing, and application of paint in a clean
condition, free from foreign materials and residue.
B. Stirring:
1. Stir materials before application, producing a mixture of uniform density.
2. Stir as required during application. Do not stir surface film into material. If
necessary, remove surface film and strain material before using.
3. Use only thinners approved by paint manufacturer and only within recommended
limits.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 8
C. Tinting: Tint each undercoat a lighter shade to simplify identification of each coat when
multiple coats of same material are applied. Tint undercoats to match the color of the
finish coat, but provide sufficient differences in shade of undercoats to distinguish each
separate coat.
3.4 SURFACE PREPARATION
A. General:
1. Perform preparation and cleaning procedures in strict accordance with the paint
manufacturers' recommendations and instructions and as herein specified, for each
particular substrate condition.
a. Provide barrier coats over incompatible primers or remove and reprime as
required. Notify Engineer in writing of any anticipated problems in using the
specified coating systems with substrates primed by others.
Remove hardware, hardware accessories, machined surfaces, plates, lighting
fixtures, and similar items in place and not to be finish-painted, or provide
surface applied protection prior to surface preparation and painting
operations. Remove, if necessary, for complete painting of items and
adjacent surfaces. Following completion of painting each space or area,
reinstall removed items without damaging treated surfaces by using workmen
who are skilled in the necessary trades.
b. Clean each surface to be painted before applying paint or surface treatments.
Remove oil and grease prior to mechanical cleaning. Schedule cleaning and
painting so that contaminants from cleaning process will not fall onto wet,
newly painted surfaces.
C. Follow all applicable procedures and requirements in the Lead Based Paint&
Coating Removal Guidelines furnished by FUSD prior to and during all
preparation work.
3.5 PAINT APPLICATION
A.General:
1. Apply paint in accordance with manufacturer's directions and in strict compliance
with all current EPA Standards, Rules and Regulations, and other governing
regulations applicable at the time of application. Use applicators and techniques
best suited for the substrate and type of material being applied.
2. Paint colors, surface treatments, and finishes are indicated in "schedules" of the
Contract Documents.
3. Provide finish coats which are compatible with prime paints used.
4. Apply additional coats when undercoats, stains or other conditions show through the
final coat of paint, until the paint film is of uniform finish, color, and appearance. Give
special attention to insure that surfaces, including edges, corners, crevices, welds,
and exposed fasteners receive a dry film thickness equivalent to that of flat surface
areas.
5. Paint surfaces behind moveable equipment and furniture same as similar exposed
surfaces. Paint surfaces behind permanently-fixed equipment or furniture with prime
coat only before final installation of equipment.
3. Finish exterior doors on tops, bottoms and side edges same as exterior faces, unless
indicated otherwise.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 9
4. Touch up shop-applied prime coats which have been damaged, and touchup bare
areas prior to start of finish coats application.
5. Slightly vary the color of succeeding coats.
a. Do not apply additional coats until the completed coat has been inspected and
approved.
b. Only the inspected and approved coats of paint will be considered in
determining the number of coats applied.
6. Sand and dust between coats to remove defects visible to the unaided eye from a
distance of five feet.
B. Schedule Painting: Apply first-coat material to surfaces that have been cleaned,
pre-treated or otherwise prepared for painting as soon as practicable after preparation
and before subsequent surface deterioration.
1. Apply prime coat on material which is required to be painted or finished, and which
has not been prime coated by others. Recoat primed or sealed surfaces where there
is evidence of suction spots or unsealed areas in first coat, to assure a finish coat
with no burn-through or other defects due to insufficient sealing.
2. Allow sufficient drying time between coats, modifying the period as recommended
by the material manufacturer to suit adverse weather conditions.
3. Do not apply successive coatings until dry to where the paint feels firm, does not
deform or feel sticky under moderate pressure of the thumb, and when the
application of another coat of paint does not cause lifting or loss of adhesion of the
undercoat.
C. Minimum Coating Thickness: Apply each coat of materials at not less than manufacturer's
recommended spreading rate, to establish a dry film thickness of not less than 1.2 mils or
as recommended by the coating manufacturer.
D. Brush applications:
1. Brush out and work the brush coats onto the surface in an even film.
2. Completely cover to provide opaque, smooth surface of uniform finish, color,
appearance and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs,
sags, ropiness, and other surface imperfections will not be acceptable.
E. Spray application:
1. Except as specifically otherwise approved by the Engineer, and allowed by
governing regulations, confine spray application to metal framework and similar
surfaces where hand brush work would be inferior.
2. Where spray application is used, apply each coat to provide the hiding equivalent of
brush coats.
3. Do not double back with spray equipment to build up film thickness of two coats in
one pass.
F. For completed work, match the approved Samples as to texture, color, and coverage.
Remove, refinish, or repaint work not in compliance with the specified requirements.
G. Interior: Use "stipple" finish where enamel is specified. Roll and redistribute paint to an
even and fine texture. Leave no evidence of rolling such as laps, irregularity in texture,
skid marks, or other surface imperfections.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 10
H. Miscellaneous surfaces and procedures:
1. Exposed mechanical/electrical items (not pre-finished):
a. Finish electric panels, access doors, conduits, pipes, ducts, grilles, registers,
vents, and items of similar nature to match the adjacent wall and ceiling
surfaces, or as directed.
b. Paint interior surfaces of ducts, where visible through registers or grilles, with
a flat, non-specular black paint.
C. Paint back sides of access panels, and removable or hinged covers to match
exposed surfaces.
d. Paint exposed piping, conduit and fittings, vents and jacks, pipe hangers and
supports, electrical trays, piping shrouds, exposed equipment supports and
frames.
2. Exposed pipe and duct insulation:
a. Apply one coat of latex paint on insulation which has been sized or primed
under other Sections; apply two coats on such surfaces when unprepared.
b. Match color of adjacent surfaces.
C. Remove band before painting, and replace after painting.
3. Hardware:
a. Paint prime coated hardware to match adjacent surfaces;
b. Paint metal portions of head seals, jamb seals, and astragal seals to match
the color of the door frame unless otherwise directed by the Engineer.
4. Wet areas:
b. For oil base paints, use 1% phenolmercuric or 4% tetrachlorophenol.
C. For water emulsion and glue size surfaces, use 4% sodium tetrachlorophnate.
5. Equipment: Unless otherwise noted, paint the following equipment items:
a. Mechanical equipment and exposed roof HVAC Units and platforms.
b. Electrical Panels and switchgear
C. Accessory items
3.6 CLEAN-UP AND FINAL PROTECTION
A. During the progress of work, remove paint splatters from window glass and other surfaces.
Remove splattering paint by proper methods of washing and scraping, using care not to
scratch or otherwise damage finish surfaces.
B. Correct any damage by cleaning, repairing or replacing, and repainting, as acceptable to
the Engineer.
1. Provide "Wet Paint" signs as required to protect newly-painted finishes. Remove
temporary protective wrappings provided by others for the protection of their work
after completion of painting operations.
2. At completion of work of other trades, touch-up and restore all damaged or defaced
painted surfaces.
3. Remove all rubbish, paint cans, and accumulated materials resulting from work in
each space or room. All areas shall be left in a clean, orderly condition.
3.7 PAINT SCHEDULE
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PAINTING
REEDLEY, CA. SECTION 099100 - 11
A.General:
1. Materials required to complete the painting are herein specified and listed by
material number and name for each type of finish and substrate, solely to establish
a standard for kind, quality and function. Unlisted manufacturers of equivalent
products, upon compliance with these specifications and with the requirements of
specification Section"Product Substitutions", may submit their products for approval.
2. Except for specialty items or as otherwise specified, all materials shall be by one
manufacturer.
3.8 PAINTING SYSTEMS SCHEDULE
A.Provide the following paint systems for the various substrates, as indicated. This list complied
with the EPA rules and regulations at last checking. Changes in product compliance after
the date listed above should be brought to the attention of the Engineer.
3.9 PAINTING FINISHES
A. Apply the following finishes to the surfaces specified and/or as scheduled on the finish
and paint schedule on the Drawings. Apply all materials in accord with manufacturer's
instructions on properly prepared surfaces and foundations coats. Manufacturers shall
verify that the paint type specified is the appropriate product for the location and
application depicted on the drawings.
1. If not included in the Drawings, the Engineer will issue a Color Schedule prior to start
of painting to designate the various colors and locations required for work.
2. Apply additional primers, sealers and fillers in addition to the listed finish coats as
required for the substrate and as recommended by the manufacturer.
END OF SECTION 099100
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SELF-SUPPORING RADIO TOWER
REEDLEY, CA. SECTION 133613 - 1
SECTION 133613 — 250' SELF-SUPPORTING RADIO TOWER
1. DESCRIPTION
The Contractor shall furnish and install a 250-foot tall (above grade line) self-supporting tower and
all associated site work including fencing.
The Contractor shall supply all supervision, labor, materials, equipment and services to construct
the tower per the detailed specifications within. Each unit of installation shall be clearly defined
and shall be approved by the Engineer before work begins.
The Contractor is responsible for the work of all sub-contractors. The Contractor shall comply with
all regulations, laws, ordinances, and requirements of all governmental agencies and authorities
that have jurisdiction applicable to the project.
2. DESIGN.
A. Design Standard
The following documents form a part of this specification.
a. Grounding Standards: Motorola R-56 or approved equal is required throughout the project.
b. American Institute of Steel Construction (AISC) Manual of Steel Construction
c. Electronic Industries Assoc. (TIA/EIA-222-G) Standard or latest issue Structural Standards
for Steel Antenna Towers and Antenna Supporting Structures
d. American Welding Society (AWS) D1.1 Structural Welding Code
e. FAA Advisory Circular#AC 70/7460 Obstruction Marking and Lighting
f. National Electric Code (NEC) Tower Lighting Kits (as required) Not required under 200
Feet.
g. American Institute of Steel Construction Specification for Structural Joints using
h. ASTM A325 or A490 Bolts
i. FCC Federal Communications Commission Rules and Regulations — Part 17
j. American Concrete Institute ACI 318 Building Code Requirements for Reinforced Concrete
k. Concrete Reinforcing Steel Institute (CRSI) Manual of Standard Practice
I. American Society of Testing and Materials (ASTM)for:
1. A-36 and A572 Structural Steel
2. A-53 Welded and Seamless Steel Pipe
3. A-123 Zinc (hot-dipped galvanized coatings on products fabricated from rolled,
pressed, and forged steel shapes, plates, bars, and strips)
4. A-153 Zinc Coatings (hot-dip) on Iron and Steel Hardware
5. B-695 Coatings of Zinc mechanically deposited on Iron and Steel (minimum
thickness 0.0026")
6. A-385 Zinc Coating (hot-dip) on assembled Steel Products
7. A-307 Low-Carbon Steel externally and internally threaded standard
fasteners
8. A-325 High Strength Steel Bolts
9. A-500 Steel Tubing
10. A-615 Reinforcing Bars
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SELF-SUPPORING RADIO TOWER
REEDLEY, CA. SECTION 133613 - 2
11. A-706 Reinforcing Bars
12. ASTM C-9 Ready-mixed Concrete
In the event of a conflict between this specification and the codes, standards, and specifications
below, the most stringent requirement shall govern.
B. Design Requirements
The tower structure shall be designed in compliance with the latest version of TIA/EIA-222-G and all
requirements included in the detailed specifications. The tower design shall accommodate the
following:
a) The Radio Tower shall stand 250 foot in height, must be self-supporting with 3-sided truss
configuration.
b) Tower legs must be solid rod, diagonals must be angle or solid rod.
c) Provide a provision for an antenna system.
d) Lighting: Provide a dual lighting for daytime and nighttime operations complying with the
current version of the FAA Advisory Circular AC70/7460.
e) Provide lightning protection.
f) Furnish a climbing ladder, safety climbing cable, fall safety system and fall protection
device designed and constructed to meet all applicable OSHA and ANSI standards.
Provide
g) Tower Grounding including air terminal system, lightning dissipators, down conductor,
grounding ring, grounding rods and radio equipment ground conductor.
h) Provide X2 36" antenna standoffs to be installed at the 250' mark of the tower.
i) Provide X1 Sector Frame Tower Kit to be installed at the 150' mark of the tower.
j) Tower will include a full length 12" ladder rack with coaxial hangers.
k) Provide 24" wide ice bridge from the tower to building penetration.
C. Design calculations and shop drawings
1. Drawings and design calculations shall be approved and sealed by a Professional Engineer
registered in the State of California. Final and complete tower design, drawings and
specifications shall be submitted by the Contractor and accepted by Fresno County building
department and Resident Engineer prior to fabrication and construction.
2. Ensure the correctness and completeness of the drawings, and also the shop fit and field
connections.
3. Tower designer of contractor shall provide foundation design and while soil investigations are
provided for bid purposes, shall provide their own soil analysis and design accordingly signed by
a PE registered in the State of California.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SELF-SUPPORING RADIO TOWER
REEDLEY, CA. SECTION 133613 - 3
3. MEASUREMENT
This item will be measured by the acceptable tower in place of the height specified.
4. TOWER ACCEPTANCE
Notify the Fresno County ISD Radio Engineers after the completion of the installation of tower
and antenna system. The purpose of this notification is to allow testing of the antenna
system by Fresno County ISD Radio Engineers. If a failure is noted, Work with Fresno
County ISD Radio Engineers to resolve and correct any and all problems. System
acceptance will occur after a minimum of 5 consecutive failure free days of operation
following installation.
5. PAYMENT
The work performed and materials furnished in accordance with this Item and measured as
provided under"Measurement" will be paid for at the unit price bid for"250' Self Supporting
Radio Tower". This price is full compensation for designing, furnishing, fabricating and
installing self supporting radio towers and for materials, tools, labor, equipment and
incidentals necessary to complete the work.
END OF SECTION 133613
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 1
SECTION 200100 — GENERAL MECHANICAL PROVISIONS
PART 1 - GENERAL
1.1 GENERAL CONDITIONS
A. The preceding General Conditions shall form a part of this Section with the same
force and effect as though repeated here. The provisions of this Section shall also
apply to the following Divisions 21, 22, 23 and 25 of these Specifications and shall
be considered a part of those Divisions.
1.2 CODES AND REGULATIONS
A. All work and materials shall be in accordance with current rules and regulations of
applicable codes. Nothing in these Drawings or Specifications is to be construed to
permit work not conforming to these codes. Should the Drawings or Specifications
call for material or methods of construction of a higher quality or standard than
required by these codes, the Drawings and Specifications shall govern. Applicable
codes and regulations include, but are not necessarily limited to, the following:
California Building Code CCR Title 24, Part 2
California Electrical Code CCR Title 24, Part 3
California Mechanical Code CCR Title 24, Part 4
California Plumbing Code CCR Title 24, Part 5
California Energy Code CCR Title 24, Part 6
California Fire Code CCR Title 24, Part 9
Local Codes
1.3 DEFINITIONS
A. Provide: The term "provide" as used in these specifications or on the drawings
shall mean furnish and install.
B. Piping: The term "piping" as used in these specifications or on the drawings shall
mean all pipe, fittings, valves, hangers, insulation, etc. as may be required for a
complete and functional system.
C. Ductwork: The terms "duct" or"ductwork" as used in these specifications or on the
drawings shall mean all ducts, fittings,joints, dampers, hangers, insulation, etc. as
may be required for a complete and functional system.
D. Wiring: The term "wiring" as used in these specifications or on the drawings shall
mean all wiring, conduit, boxes, connections, transformers, relays, switches etc. as
may be required for a complete and functional system.
1.4 PERMITS AND FEES
A. The Contractor shall take out all permits and arrange for all tests in connection with
his work as required. All charges are to be included in the work.
1.5 COORDINATION OF WORK
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 2
A. Examination: Before starting work, thoroughly examine existing and newly
completed underlying and adjoining work and conditions on which the installation
of this work depends. Report to the Engineer in writing all conditions which might
adversely affect this work.
B. Layout: Layout of materials, equipment and systems is generally diagrammatic
unless specifically dimensioned. Some work may be shown offset for clarity. The
actual locations of all materials, piping, ductwork, fixtures, equipment, supports,
etc. shall be carefully planned prior to installation of any work in order to avoid all
interference with each other, or with structural, electrical, architectural or other
elements.
C. Verification: If discrepancies are discovered between drawing and specification
requirements, the more stringent requirement shall apply. All conflicts shall be
called to the attention of the Engineer prior to the installation of any work or the
ordering of any equipment. No work shall be prefabricated or installed prior to this
coordination. No costs will be allowed to the Contractor for any prefabrication or
installation performed prior to this coordination. Verify the proper voltage and
phase of all equipment with the electrical plans.
D. Location of Utilities Prior to Trenching or Earthwork: The Contractor shall notify
the Owner a minimum of two business days prior to beginning trenching or
earthwork. Prior to this notification, the Contractor shall have marked all
proposed trenches with paint and shall have contacted a utility locating company
and have had this company mark all found underground utilities with paint. The
Contractor shall then coordinate and arrange for a site visit with the Owner to
review the proposed trenching and/or earthwork areas. Trenching and/or
earthwork shall not begin until the Owner agrees. Repair and/or compensation
for repair of marked utilities is the responsibility of the Contractor. The Owner
retains the right to either self-perform the repair or require the Contractor to
complete the repair, as directed by the Owner. If while performing the work, the
Contractor discovers utilities that have not been marked, the Contractor shall
immediately notify the Owner verbally and in writing.
1.6 GUARANTEE
A. Guarantee shall be in accordance with the General Conditions. The Contractor
shall repair any defects due to faulty materials or workmanship and pay for any
resulting damage to other work which appears within the guarantee period. These
Specifications may extend the period of the guarantee for certain items. Where
such extensions are called for, or where items are normally provided with
guarantee periods in excess of that called for in the General Conditions, the
certificate of guarantee shall be furnished to the Owner through the Engineer.
1.7 QUIETNESS
A. Piping, ductwork and equipment shall be arranged and supported so that vibration
is a minimum and is not transmitted to the structure.
1.8 DAMAGES BY LEAKS
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 3
A. The Contractor shall be responsible for damages caused by leaks in the temporary
or permanent piping systems prior to completion of work and during the period of
the guarantee, and for damages caused by disconnected pipes or fittings, and the
overflow of equipment prior to completion of the work.
1.9 EXAMINATION OF SITE
A. The Contractor shall examine the site, compare it with Plans and Specifications,
and shall have satisfied himself as to the conditions under which the work is to be
performed. No allowance shall subsequently be made in his behalf for any extra
expense to which he may be put due to failure or neglect on his part to make such
an examination.
1.10 COMPATIBILITY WITH EXISTING SYSTEMS
A. Any work which is done as an addition, expansion or remodel of an existing
system shall be compatible with that system.
1.11 MATERIALS AND EQUIPMENT
A. Materials and equipment shall be new unless otherwise noted. Materials and
equipment of a given type shall be by the same manufacturer. Materials and
equipment shall be free of dents, scratches, marks, shipping tags and all defacing
features at time of project acceptance. Materials and equipment shall be covered
or otherwise protected during construction as required to maintain the material and
equipment in new factory condition until project acceptance. All HVAC equipment
and ductwork shall be covered, sealed and protected per CGBSC Section 5.504.3
from delivery on site until final start-up.
1.12 SUBMITTALS
A. Shop Drawings: Within 30 days of contract award, the Contractor shall submit six
copies of shop drawings for all materials, equipment, etc. proposed for use on this
project. Material or equipment shall not be ordered or installed until written review
is processed by the Engineer.
All shop drawings must comply with the following:
1. Shop drawings are required for all material and equipment items and shall
include manufacturer's name and catalog numbers, dimensions, capacities,
performance curves, and all other characteristics and accessories as listed
in the specifications or on the drawings. Descriptive literature shall be
current factory brochures and submittal sheets. Capacities shall be certified
by the factory. FAX submittals are not acceptable.
2. All shop drawings shall be submitted at one time in a neat and orderly
fashion in a suitable binder with title sheet including Project, Engineer and
Contractor, table of contents, and indexed tabs dividing each group of
materials or item of equipment. All items shall be identified by the
specification paragraph number for which they are proposed. All equipment
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 -4
shall also be identified by the mark number as indicated on drawings.
3. All capacities, characteristics, and accessories called for in the
specifications or on the drawings shall be high-lighted, circled or underlined
on the shop drawings. Calculations and other detailed data indicating how
the item was selected shall be included for items that are not scheduled.
Data must be complete enough to permit detailed comparison of every
significant characteristic which is specified, scheduled or detailed.
4. Electronic Submittals: Where allowed by Division 01, electronic submittals
are acceptable providing the following requirements are met. Electronic
submittals which do not comply with these requirements will be rejected.
a. Submittal shall be a single file in PDF format, with bookmarks for
table of contents and each tab, and sub-bookmarks for each item.
b. All text shall be searchable (except text that is part of a graphic).
C. Submittal shall include all items noted in 1 through 3 above, except
a binder is not required.
d. Electronic submittals shall be processed through normal channels.
Do not submit directly to the Engineer unless the Engineer is the
prime consultant for the project.
e. Contractor shall provide Owner and Owner's Representative with
hard copies of the final submittal. Coordinate exact number required
with Owner through Architect/Engineer.
B. Substitutions: Manufacturers and model numbers listed in the specifications or on
the drawings represent the standard of quality and features desired. Proposed
substitutions shall comply with the Owner's General Requirements. Calculations
and other detailed data indicating how the item was selected shall be included. The
Contractor shall assume full responsibility that substituted items or procedures will
meet the specifications and job requirements and shall be responsible for the cost
of redesign and modifications to the work caused by these items. At the Engineer's
request, furnish locations where equipment similar to the substituted equipment is
installed and operating along with the user's phone numbers and contact person.
Satisfactory operation and service history will be considered in the acceptance or
rejection of the proposed substitution.
C. Review: Submittals will be reviewed for general conformance with the design
concept, but this review does not guarantee quantity shown, nor does it supersede
the responsibility of the Contractor to provide all materials, equipment and
installation in accordance with the drawings and specifications. The Contractor
shall agree that shop drawing submittals processed by the Engineer are not
Change Orders; that the purpose of shop drawing submittals by the Contractor is
to demonstrate to the Engineer that the Contractor understands the design
concept, that he demonstrates his understanding by indicating which equipment
and material he intends to furnish and install and by detailing the fabrication and
installation methods he intends to use. The Contractor shall agree that if
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 5
deviations, discrepancies or conflicts between shop drawings and design drawings
and specifications are discovered either prior to or after shop drawing submittals
are processed by the Engineer, the design drawings and specifications shall
control and shall be followed. If a resubmittal is required, submit a complete copy
of the Engineer's review letter requiring such with the resubmittal.
1.13 MANUFACTURER'S RECOMMENDATIONS
A. All material, equipment, devices, etc., shall be installed in accordance with the
recommendations of the manufacturer of the particular item. The Contractor shall
be responsible for all installations contrary to the manufacturer's
recommendations. The Contractor shall make all necessary changes and revisions
to achieve such compliance. Manufacturer's installation instructions shall be
delivered to and maintained at the job site through the construction of the project.
1.14 SCHEDULING OF WORK
A. All work shall be scheduled subject to the review of the Engineer and the Owner.
No work shall interfere with the operation of the existing facilities on or adjacent to
the site. The Contractor shall have at all times, as conditions permit, a sufficient
force of workmen and quantity of materials to install the work contracted for as
rapidly as possible consistent with good work, and shall cause no delay to other
Contractors engaged upon this project or to the Owner. HVAC equipment and
functions, whether existing or new, shall be maintained in operating condition
whenever the facility is occupied, unless otherwise approved by the Owner.
1.15 DEMOLITION
A. Existing equipment, ducts, piping, etc. noted for removal shall be removed and
delivered to the Owner at a location to be determined by the Owner. Those items
determined by the Owner to be of no value shall become the property of the
Contractor and shall be removed from the job site by the Contractor at the
Contractor's expense. Existing piping, ducts, services, etc. requiring capping shall
be capped below floors, behind walls, above ceilings or above roof unless
otherwise noted. Where items are removed, patch the surfaces to match the
existing surfaces.
1.16 HAZARDOUS MATERIAL REMOVAL
A. All hazardous material removal will be by the Owner. Hazardous material is to be
removed before the work is started. If the Contractor discovers hazardous material
which has not been removed, the Contractor shall immediately cease work in that
area and promptly notify the Owner.
1.17 OPENINGS, CUTTING AND PATCHING
A. The locations and dimensions for openings through walls, floors, ceilings,
foundations, footings, etc. required to accomplish the work under this Specification
Division shall be provided under this Division. Except as noted below, the actual
openings and the required cutting and patching shall be provided by other
Divisions. Coring through existing concrete or masonry walls, floors, ceilings,
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 6
foundations, footings, etc., and saw cutting of concrete floors or asphaltic concrete
required to accomplish the work under this Specification Division shall be provided
under this Division. Patching of these surfaces shall be provided by other
Divisions. Cutting or coring shall not impair the strength of the structure. Any
damage resulting from this work shall be repaired at the Contractor's expense to
the satisfaction of the Engineer.
1.18 EXCAVATION AND BACKFILL
A. General: Barrel of pipe shall have uniform support on sand bed. Sand shall be free
from clay or organic material, suitable for the purpose intended and shall be of
such size that 90 percent to 100 percent will pass a No. 4 sieve and not more than
5 percent will pass a No. 200 sieve. Unless otherwise noted, minimum earth cover
above top of pipe or tubing outside building walls shall be 24", not including base
and paving in paved areas.
B. Excavation: Width of trench at top of pipe shall be minimum of 16", plus the outside
diameter of the pipe. Provide all shoring required by site conditions. Where over
excavation occurs, provide compacted sand backfill to pipe bottom. Where
groundwater is encountered, remove to keep excavation dry, using well points and
pumps as required.
C. Backfill:
1. 6" Below, Around, and to 12"Above Pipe: Material shall be sand. Place
carefully around and on top of pipe, taking care not to disturb piping,
consolidate with vibrator.
2. One Foot Above Pipe to Grade: Material shall be sandy or silty loam, free
of lumps, laid in 6" layers, uniformly mixed to proper moisture and
compacted to required density. If backfill is determined to be suitable and
required compaction is demonstrated by laboratory test, water compaction
in 6" layers may be used, subject to review by Engineer.
D. Compaction: Compact to density of 95% within building and under walkways,
driveways, traffic areas, paved areas, etc. and to 90% elsewhere. Demonstrate
proper compaction by testing at top, bottom and one-half of the trench depth.
Perform these tests at three locations per 100' of trench.
1.19 CONTINUITY OF SERVICES
A. Existing services and systems shall be maintained except for short intervals when
connections are made. The Contractor shall be responsible for interruptions of
services and shall repair damage done to any existing service caused by the work.
If utilities not indicated on the drawings are uncovered during excavation, the
Contractor shall notify the Engineer immediately.
1.20 PROTECTIVE COATING FOR UNDERGROUND PIPING
A. All ferrous pipe below grade (except cast iron) shall have a factory applied
protective coating of extruded high density polyethylene, 35 to 70 mils total
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 7
thickness, X-Tru-Coat, Scotchkote. All fittings and areas of damaged coating shall
be covered with two layer double wrap of 10 mil polyvinyl tape to total thickness of
40 mils. John-Mansville. Protective coating shall be extended 6" above surrounding
grade.
1.21 ACCESS DOORS
A. Provide access doors as required where equipment, piping, valves, ductwork, etc.
are not otherwise accessible. Access doors shall match the wall or ceiling finish
and fire rating as indicated on the Architectural drawings. 16-gage steel frame and
14-gage steel door with paintable finish, except in ceramic tile, where door shall be
16-gage stainless steel with satin finish. Continuous hinge. Deliver doors to the
General Contractor for installation. Milcor. Unless otherwise noted, the minimum
sizes shall be as follows:
1 valve up to 1-1/2" 12" x 12"
1 valve up to 3" 16" x 16"
1.22 HOUSEKEEPING PAD
A. Housekeeping pads shall be 6" high concrete, 3000 PSI strength, unless otherwise
noted. Pad shall extend 6" beyond the largest dimensions of the equipment, unless
otherwise noted. The top edge of the pad shall have a 3/4" chamfer. Unless
otherwise noted, the pad shall have#4 reinforcing bars at 12" on center, each way,
located at mid-depth of the pad. If not poured at the same time as the slab with pad
rebar tied to slab rebar, the pad shall be anchored as follows: Drill 5/8" diameter, 3"
deep hole in slab. Install 7" long, #4 rebar with Simpson Set epoxy system. Provide
a minimum of 4 of these anchors per pad, but no more than 4 feet apart in either
direction. Anchor points shall be 12"from the edge of the pad.
1.23 CONCRETE ANCHORS
A. Steel bolt with expansion anchor requiring a drilled hole - powder driven anchors,
adhesive anchors and concrete screws are not acceptable. Re-use of screw
anchor holes shall not be permitted. Minimum concrete embedment shall be 4-1/2
diameters. Minimum spacing shall be 12 diameters center to center and 6
diameters center to edge of concrete. Post-installed anchors in concrete used for
component anchorage shall be pre-qualified for seismic application in accordance
with ACI 355.2 and ICC-ES AC193. Post-installed anchors in masonry used for
component anchorage shall be pre-qualified for seismic applications in accordance
with ICC-ES AC01. Maximum allowable loads for tension and shear shall be as
determined by Calculation in compliance with ACI 318-14, Chapter 17, and the
anchor's ICC or IAPMO evaluation report. Hilti, Powers, Red Head.
1.24 EQUIPMENT ANCHORING AND OTHER SUPPORTS
A. Mechanical systems (equipment, ductwork, piping, conduit, etc.) shall be anchored
in accordance with the CBC. All systems mounted on concrete shall be secured
with a concrete anchor at each mounting point. All air handlers shall be mounted
on spring isolators. Secure base plate as indicated above. Attachment of
equipment, ductwork, piping, conduit, etc. supported on curbs or platforms shall be
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 8
made to the side of curbs and platforms, where possible. Where screws or lag
bolts must be installed through the top of a sheet metal cap, the installation shall
be as follows. Pre-drill pilot hole. Fill pilot hole with polyurethane sealant. Install
screw or lag bolt with a flat washer and an EPDM washer adjacent to the sheet
metal.
1.25 SUPPORTS AND SEISMIC RESTRAINTS
A. Any structural element required to hang or support piping, ducts or equipment
provided under this Division and not shown on other drawings shall be provided
under this Division.
B. Mechanical systems (equipment, ductwork, piping, etc.) shall be provided with
supports and seismic restraints in accordance with the CBC. Submit anchorage
calculations and details stamped and signed by a structural engineer registered in
the State of California. Submit shop drawings showing location, type and detail of
restraints. Submit manufacturer's data for restraints. Restraint system shall be
Mason West, Inc. (OSHPD OPM 0043-13), or other OSHPD preapproved system.
1.26 PAINTING
A. Paint all black iron supports, hangers, anchors, etc. with two coats of rust resisting
primer. Also paint all uninsulated black iron piping exposed to weather with two
coats of rust resisting primer.
1.27 ROOF PENETRATIONS AND PATCHING
A. Whenever any part of the mechanical systems penetrates the roof or exterior wall,
the openings shall be flashed and counter-flashed water tight with minimum 22
gauge galvanized sheet metal. Flashing shall extend not less than eight inches
from the duct, pipe, or supporting member in all directions unless detailed
otherwise. All roof penetrations and patching shall be in accordance with the
recommendations of the National Roofing Contractor's Association and the
Owner's roofing standards.
1.28 SYSTEM IDENTIFICATION
A. Above Grade Piping: Provide markers on piping which is either exposed or
concealed in accessible spaces. For piping systems, other than drain and vent
lines, indicate the fluid conveyed or its abbreviation, either by pre-printed markers
or stenciled marking, and include arrows to show direction of flow. Pre-printed
markers shall be the type that wrap completely around the pipe, requiring no other
means of fastening such as tape, adhesive, etc. Comply with ANSI A13.1 for
colors. Locate markers at ends of lines, near major branches and other
interruptions including equipment in the line, where lines pass through floors, walls
or ceilings or otherwise pass into inaccessible spaces, and at 50' maximum
intervals along exposed portions of lines. Marking of short branches and repetitive
branches for equipment connections is not required.
B. Below Grade Piping: Bury a continuous, pre-printed, bright-colored, metallic ribbon
marker capable of being located with a metal detector with each underground pipe.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 9
Locate directly over buried pipe, 6" to 8" below finished grade.
C. Equipment: All equipment shall be identified with a plastic laminated, engraved
nameplate which bears the unit mark number as indicated on the drawings (e.g.
AC-4) and identifies the area or space served by the equipment. Provide 1/2" high
lettering -white on black background. Nameplates shall be permanently secured to
the exterior of the unit.
D. Valves: Provide stamped brass valve tags with brass hooks or chains on all valves
of each piping system, excluding check valves, valves within equipment, faucets,
stops and shut-off valves at fixtures and other repetitive terminal units. Prepare
and submit a tagged-valve schedule, listing each valve by tag number, location
and piping service.
1.29 CLEANING
A. Progressively and at completion of the job, the Contractor shall thoroughly clean all
of his work, removing all debris, stain and marks resulting from his work. This
includes but is not limited to building surfaces, piping, equipment and ductwork,
inside and out. Surfaces shall be free of dirt, grease, labels, tags, tape, rust, and all
foreign material.
B. At the end of each work day, the Contractor shall cover all open ends of piping and
ductwork with protective plastic.
1.30 OPERATION AND MAINTENANCE INSTRUCTIONS
A. Printed: Three copies of Operation and Maintenance Instructions and Wiring
Diagrams for all equipment and parts list for all faucets, trim, valves, etc. shall be
submitted to the Engineer. All instructions shall be clearly identified by marking
them with the same designation as the equipment item to which they apply (e.g.
AC-3). All Wiring Diagrams shall agree with reviewed Shop Drawings and indicate
the exact field installation. All instructions shall be submitted at the same time and
shall be bound in a suitable binder with tabs dividing each type of equipment (e.g.
Pumps, Fans, Motors, etc.). Each binder shall be labeled indicating "Operating and
Maintenance Instructions, Project Title, Contractor, Date" and shall have a Table of
Contents listing all items included. Electronic O & M's shall comply with the
Electronic submittal requirements in this Section.
B. Verbal: The Contractor shall verbally instruct the Owner's maintenance staff in the
operation and maintenance of all equipment and systems. The controls contractor
shall present that portion of the instructions that apply to the control system. The
Engineer's office shall be notified 48 hours prior to this meeting.
1.31 RECORD DRAWINGS
A. The Contractor shall obtain one set of prints for the project, upon which a record of
all construction changes shall be made. As the work progresses, the Contractor
shall maintain a record of all deviations in the work from that indicated on the
drawings. Final location of all underground work shall be recorded by depth from
finished grade and by offset distance from permanent surface structures, i.e.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL MECHANICAL
REEDLEY, CA. PROVISIONS
SECTION 200100 - 10
building, curbs, walks. In addition, the water, gas, sewer, under floor duct, etc.
within the building shall be recorded by offset distances from building walls. An
electronic copy of the original drawings will be made available to the Contractor.
The Contractor shall transfer the changes, notations, etc. from the marked-up
prints to the electronic copy. The record drawings (marked-up prints, electronic
drawings disc and a hard copy) shall be submitted to the Engineer for review.
1.32 ACCEPTANCE TESTING
A. All acceptance testing as required by California Code of Regulations, Title 24, and
as noted on the Certificate of Compliance form, (where applicable), shall be
performed and documented by an Acceptance Test Technician (ATT). These
documents must be provided to the building inspector during construction and
must be completed through an Acceptance Test Technician Certification Provider
(ATTCP). The Contractor shall submit a copy of the documentation to the Engineer
for review (hardcopy or electronic), prior to submitting to Administrative Authority.
END OF SECTION 20 01 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 1
SECTION 220400 - PLUMBING
PART 1 - GENERAL
1.1 GENERAL PLUMBING PROVISIONS
A. The General Mechanical Provisions, Section 20 01, 00, shall form a part of this
Section with the same force and effect as though repeated here.
1.2 SCOPE:
A. Included: Provide all labor, materials and services necessary for complete, lawful
and operating systems as shown or noted on the drawings or as specified here.
The work includes, but is not necessarily limited to, the following:
1. Sanitary sewer system.
2. Drain system (including condensate drain).
3. All fixtures as shown or noted on the drawings or as specified.
4. Demolition as indicated on drawings. Where demolition is called for,
remove all equipment, piping, braces, housekeeping pads, supports and
related items no longer required.
B. Work Specified Elsewhere:
1. Concrete and reinforcing steel unless specifically called for on the drawings
or specifications.
2. Painting unless specifically called for in the drawings or specifications.
3. Carpentry.
PART 2 - PRODUCTS
2.1 PIPING MATERIALS:
A. Sanitary Sewer:
1. Soil, Waste and Vent Piping (Non-Pressurized):
a. Inside Building and Within Five Feet of Building Walls: Standard
weight coated cast iron pipe and fittings. Plain end, CISPI 301,
ASTM A888, or hub end with rubber gaskets, ASTM A74, ASTM
C564. ABI, Tyler, Charlotte. Couplings shall be heavy-duty shielded
couplings. Type 304 stainless steel, with neoprene gasket, ASTM
C1540. Husky HD 2000, Clamp-All 80, Mission HeavyWeight. MG
Couplings are also acceptable. 2" and smaller exposed to view
shall be galvanized steel, ASTM A53, with coated cast iron
recessed drainage fittings, ANSI B16.12.
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 2
Where required by soil conditions, as determined by the
method described in ASTM A74-09, Appendix X2, below grade
cast iron pipe and fittings shall have 8 mil (minimum)
Polyethylene Encasement (Poly Wrap), Per ANSI/AWWA
C 105/A21.5.
b. Outside Building: Solid wall Schedule 40 PVC,ASTM D1785, D2665,
with solvent weld DWV fittings, ASTM D2665, D3311. Piping with
less than 24" of cover outside building walls shall be cast iron.
2. Cleanouts: Comparable models of Josam, Wade, Mifab or Zurn are
acceptable. Grease plug prior to installation. Floor Cleanouts: Smith 4023
with nickel bronze top in finished areas; Smith 4223 in utility areas. Wall
Cleanouts: Smith 4532 with stainless steel cover and screw. Pipe
Cleanouts: Iron body with threaded brass plug. Site cleanouts more than 5'
outside building may be PVC with PVC plug.
3. Cleanout Box: Precast reinforced concrete. Cast iron lid marked for service.
Christy F8 in foot traffic areas; G5 in roadways. Provide with PVC pipe
extension down to top of pipe.
B. Drain Piping (including Condensate): Hard temper seamless copper, ASTM B88.
Wrought copper fittings, ANSI B16.22. Type L with brazed joints (1100F, min.). 1-
1/2" and smaller above grade may be soldered, 95-5 tin-antimony solder. All
nipples shall be lead-free red brass (85% copper)..
C. Miscellaneous Piping Items:
1. Pipe Support:
a. Pipe Hanger: Steel "J" hanger with side bolt for piping 4" and
smaller; steel clevis hanger for piping 5" and larger. Load and jam
nuts. Size and maximum load per manufacturer's recommendation.
Felt liner for copper piping. Hanger and rod shall have galvanized
finish. B-Line, Anvil, Unistrut.
b. Isolating Shield: Galvanized steel shell and reinforcing ribs. 1/4"
non-conducting hair felt pad. Pipe hanger in accordance with
paragraph above. Increase hanger size per manufacturer's
recommendation. B-Line, Semco, Superstrut.
C. Construction Channel: 12-gage, 1-5/8" x 1-5/8" galvanized steel
channel. Single or multiple section. Self-locking nuts and fittings.
B-Line, Anvil, Unistrut.
2. Flashing: Vent flashing shall be 4 Ib/ft2 lead, 16" sq. flange, length sufficient
to be turned down 2" into vent. Oatey. Flashing for other piping through
roof shall be prefabricated galvanized steel roof jacks with 16" sq. flange.
Provide clamp-on storm collar and seal water tight with mastic. For cold
process built-up roof, material shall be 4 Ib/ft2 lead instead of galvanized
steel. For single-ply roofing, use the roofing manufacturer's recommended
flashing material.
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 3
2.2 PIPING INSULATION MATERIALS:
A. General: All piping insulation materials shall have fire and smoke hazard ratings as
tested under ASTM E-84 and UL 723 not exceeding a flame spread of 25 and
smoke developed of 50.
B. PVC Jacket (for pipe, fittings and valves): Pre-molded polyvinyl chloride (PVC)
jackets, 0.020" thickness. Size to match application. Provide solvent weld adhesive
and PVC vapor barrier pressure sealing tape by same manufacturer. Zeston.
C. Foamed Plastic: Rubber based elastomeric preformed pipe insulation. Thermal
conductivity shall not exceed 0.27 Btu in/hr ft2 OF at a mean temperature of 70°F.
1" thick. Provide adhesive by same manufacturer. Armacell Armaflex.
PART 3 - EXECUTION
3.1 PIPING INSTALLATION:
A. General:
1. Piping Layout: Piping shall be concealed in walls, above the ceilings, or
below grade unless otherwise noted. Exposed piping shall run parallel to
room surfaces; location to be approved by Architect. No structural member
shall be weakened by cutting, notching, boring or otherwise, unless
specifically allowed by structural drawings and/or specifications. Where
such cutting is required, reinforcement shall be provided as specified or
detailed. All piping shall be installed in a manner to ensure unrestricted
flow, eliminate air pockets, prevent any unusual noise, and permit complete
drainage of the system. All piping shall be installed to permit expansion and
contraction without strain on piping or equipment. Vertical lines shall be
installed to allow for building settlement without damage to piping. Pipe
sizes indicated on the drawings are nominal sizes unless otherwise noted.
2. Joints:
a. Threaded: Pipe shall be cut square and reamed to full size.
Threads shall be in accordance with ANSI B2.1. Joint compound or
tape suitable for conveyed fluid shall be applied to male thread only.
Joints shall be made with three threads exposed.
b. Brazed: Filler rod shall be of suitable or the same alloy as pipe.
Brazing filler metal shall have a minimum melting point of 1100F.
Brazing shall be performed by a Certified Brazer as certified by an
organization/institution that uses standards recognized by the
American Welding Society (AWS) and meets the requirements of
the ASME Boiler and Pressure Vessels Code, Section 9.
C. Open Ends: Open ends of piping shall be capped during progress
of work to preclude foreign matter.
d. Electrical Equipment: Piping shall not be run over electrical panels,
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 4
motor control centers or switchboards.
3. Fittings and Valves:
a. Standard Fittings: All joints and changes in direction shall be made
with standard fittings. Close nipples shall not be used.
b. Reducers: Pipe size reduction shall be made with bell reducer
fittings. Bushings shall not be used.
C. Unions: A union shall be installed on the leaving side of each valve,
at all sides of automatic valves, at equipment connections, and
elsewhere as necessary for assembly or disassembly of piping.
4. Pipe Support:
a. General: Hangers shall be placed to support piping without strain
on joints or fittings. Maximum spacing between supports shall be as
specified below. Actual spacing requirements will depend on
structural system. Side beam clamps shall be provided with
retaining straps to secure the clamp to the opposite side of the
beam. Vertical piping shall be supported with riser clamp at 20' on
center(maximum). Support pipe within 12" of all changes in
direction. Support individual pipes with pipe hanger. Copper piping
systems which protrude through a surface for connection to a fixture
stop or other outlet shall be secured with a drop ell, Nibco 707-3-5,
to a Holdrite Model #SB1 bracket; nipple through surface shall be
threaded brass.
(1) Pressure Pipe:
Maximum Spacing*
Pipe Size (Inches) Between Supports (ft.)
Copper Sch. 40 steel
1/2 6 6
3/4 6 8
1 6 8
1-1/4 6 10
1-1/2 6 10
2 10 10
2-1/2 10 10
3 10 10
4 10 10
6 10 10
*Based on straight lengths of pipe with couplings only. Provide
additional supports for equipment, valves or other fittings. Seismic
requirements may reduce maximum spacing.
(2) Gravity Drain Pipe: Piping shall be supported at each length
of pipe or fitting, but in no case at greater spacing than
indicated above for pressure pipe.
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 5
b. Trapeze: Trapeze hangers of construction channel and pipe clamps
may be used. Submit design to Engineer for review.
5. Miscellaneous:
a. Escutcheons: Provide chrome plated metal escutcheons where
piping penetrates walls, ceilings, or floors in finished areas.
b. Pipe Sleeves: All piping passing through concrete shall be provided
with pipe sleeves. Allow 1" annular clearance between sleeve and
pipe for piping 3" and smaller, otherwise 2" annular clearance.
Piping through walls and footings below grade shall be sealed with
Link-Seal.
C. Pipes Passing through Fire Rated Surfaces: Pipes passing through
fire rated walls, floors, ceilings, partitions, etc. shall have the
annular space surrounding the pipe or pipe insulation sealed with
fire rated materials in accordance with the requirements of 2022
CBC Section 714.
d. Dielectric Couplings: Dielectric couplings shall be installed wherever
piping of dissimilar metals are joined, except that bronze valves
may be installed in ferrous piping without dielectric couplings.
B. Sanitary Sewer Piping:
1. General: Where inverts are not indicated, sanitary sewer piping shall be
installed at 1/4" per foot pitch. Piping 4" and larger may be installed at 1/8"
per foot pitch where structural or other limitations prevent installation at a
greater pitch. Bell and spigot piping shall be installed with barrel on sand
bed; excavate hole for bell.
2. Cleanouts: Install cleanouts at ends of lines, at changes of direction greater
than 45 degrees, and at not greater than 100 foot intervals. Locate interior
cleanouts in accessible locations and bring flush to finished surface.
3. Vents: Vents shall terminate not less than 6" above the roof nor less than
12"from any vertical surface nor within 10' of any outside air intake. Install
horizontal vent lines at 1/4" per foot pitch. Offset vents 2' minimum from
gutters, parapets, ridges and roof flashing.
C. Drain Piping (Including Condensate): Install with constant pitch to receptacle, 1/4"
per foot where possible, otherwise 1/8" per foot minimum. Provide TEE with
clean-out plug at all changes of direction. Provide trap at each air handling unit to
prevent air leakage. Only equipment mounted on vibration isolators shall be
connected with flexible connection. Piping not concealed in wall structure, above
ceilings or below floors shall be chrome plated brass, except in equipment rooms,
piping shall be galvanized steel. P&T relief and water heater drain piping shall be
galvanized steel. Provide secondary drain piping where required.
3.2 PIPING INSULATION INSTALLATION:
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER PLUMBING
REEDLEY, CA. SECTION 220400 - 6
A. Condensate Piping Freeze Protection: All condensate piping above grade or other
areas subject to freezing (i.e. ventilated attics, uninsulated exterior soffits, etc.)
shall be insulated, 1" thick insulation. Cover with PVC jacketing where exposed to
view. Apply at least two coats of protective finish where exposed to weather.
3.3 EQUIPMENT INSTALLATION:
A. General: It shall be the responsibility of the equipment installer to insure that no
work done under other specification sections shall in any way block, or otherwise
hinder the equipment. All equipment shall be securely anchored in place.
B. Connections to Equipment: Where size changes are required for connections to
equipment, they shall be made immediately adjacent to the equipment and, if
possible, inside the equipment cabinet.
3.4 TESTS AND ADJUSTMENTS:
A. General: Unless otherwise directed, tests shall be witnessed by a representative of
the Architect. Work to be concealed shall not be enclosed until prescribed tests are
made. Should any work be enclosed before such tests, the Contractor shall, at his
expense, uncover, test and repair all work to original conditions. Leaks and defects
shown by tests shall be repaired and entire work retested. Tests may be made in
sections, however, all connections between sections previously tested and new
section shall be included in the new test.
B. Gravity Systems:
1. Sanitary Sewer: All ends of the sanitary sewer system shall be capped and
lines filled with water to the top of the highest vent, 10' above grade
minimum. This test shall be made before any fixtures are installed. Test
shall be maintained until all joints have been inspected, but no less than 2
hours.
2. Drains (Including Condensate): Similar to Sanitary Sewer.
END OF SECTION 22 04 00
CONTRACT 24-S-01
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 1
SECTION 230800 — HEATING, VENTILATING, AND AIR-CONDITIONING
PART 1 - GENERAL
1.1 GENERAL MECHANICAL PROVISIONS
A. The General Mechanical Provisions, Section 20 01 00, shall form a part of this
Section with the same force and effect as though repeated here.
1.2 SCOPE
A. Included: Provide all labor, materials and services necessary for complete, lawful
and operating systems as shown or noted on the drawings or as specified here.
The work includes, but is not necessarily limited to, the following:
1. Air distribution system.
2. All equipment as shown or noted on the drawings or as specified.
3. Refrigeration system.
4. System energy balance.
5. Coordinate with Section 25 09 00 (Direct Digital Control System)
regarding location and installation of system sensors, valves, actuators,
etc. and to provide simultaneous start-up.
6. Demolition as indicated on drawings. Where demolition is called for,
remove all equipment, piping, ductwork, braces, supports, housekeeping
pads, temperature controls and related items no longer required.
B. Work Specified Elsewhere:
1. Line voltage power wiring to equipment, motor starters in motor control
centers, disconnect switches and installation of all starters are included in
the Electrical Sections, unless otherwise noted.
2. Connection of condensate drains and domestic water to equipment.
3. Access doors.
4. Concrete and reinforcing steel unless specifically called for in the
drawings or specifications.
5. Painting unless specifically called for in the drawings or specifications.
6. Carpentry.
7. Direct Digital Control System.
PART 2 - PRODUCTS
2.1 PIPING MATERIALS
A. Refrigerant Piping: Hard drawn Type ACR copper, dried and capped, ASTM
B280. Wrought copper fittings, silver alloy brazed, 11001F, Silfos.
B. Miscellaneous Piping Items:
1. Pipe Support:
a. Pipe Hanger: Steel "J" hanger with side bolt for piping 4" and
smaller; steel clevis hanger for piping 5" and larger. Load and jam
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 2
nuts. Size and maximum load per manufacturer's
recommendations. Felt liner for copper piping. Hanger and rod
shall have galvanized finish. B-Line, Unistrut.
b. Isolating Shield: Galvanized steel shell and reinforcing ribs. 1/4"
non-conducting hair felt pad. Pipe hanger in accordance with
paragraph above. Increase hanger size per manufacturer's
recommendation. B-Line, Semco.
C. Construction Channel: 12-gage, 1-5/8" x 1-5/8" galvanized steel
channel. Single or multiple section. Self-locking nuts and fittings.
B-Line, Unistrut.
2. Flashing: Flashing for piping through roof shall be prefabricated
galvanized steel roof jacks with 16" square flange around pipe. Provide
clamp-on storm collar and seal water tight with mastic. Maintain dielectric
separation between copper and galvanized materials. For cold process
built-up roof, material shall be 4 Ib/ft2 lead instead of galvanized steel.
2.2 PIPING INSULATION MATERIALS
A. General: All piping insulation materials shall have fire and smoke hazard ratings
as tested under ASTM E-84 and UL 723 not exceeding a flame spread of 25 and
smoke developed of 50.
B. PVC Jacket (for pipe, fittings and valves): Pre-molded polyvinyl chloride (PVC)
jackets, 0.020" thickness. Size to match application. Provide solvent weld
adhesive and PVC vapor barrier pressure sealing tape by same manufacturer.
Zeston.
C. Aluminum Jacketing: Aluminum pipe and fitting jacketing, 0.016" thickness for
straight pipe. 0.024" thickness for fittings. Integral moisture barrier. Stucco-
Embossed finish. Provide pre-fabricated aluminum strapping and seals by same
manufacturer. ITW or RPR.
D. Metal Jacketing Sealant: Childers CP-76, Foster 95-44.
E. Flexible Elastomeric: Closed cell flexible elastomeric preformed pipe insulation.
Thermal conductivity shall not exceed 0.27 Btu-in/hr-ft2°F at a mean temperature
of 70°F. 1/2" thick. Provide #520 adhesive and Armaflex insulation pipe hangers
by same manufacturer. Armacell Armaflex.
2.3 DUCTWORK MATERIALS:
A. General: All ductwork materials shall have fire and smoke hazard ratings as
tested under ASTM E-84 and UL 723 not exceeding a flame spread of 25 and
smoke developed of 50. Shall comply with 2022 CIVIC.
B. Metal Ductwork: Metal ductwork shall be galvanized sheet steel, lock forming
quality, ASTM A-653, with gage and construction to match SMACNA Standard
for pressure required (26 gage minimum).
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 3
C. Duct Sealants: All Joints Exposed to Weather: Sealant shall be water based,
Foster 32-19/32-17, Childers CP-146/148, United Duct Sealer WB or G.E.
"SilPruf' SCS2000 silicone sealant. Joints Not Exposed to Weather (Except
Spiral Wound Exposed to View in Finished Areas): Fiber reinforced. White in
color. Foster 32-17, Childers CP-148, Design Polymerics DP1030, Hardcast
Versa-Grip 181, Hardcast CCWI-181. Spiral Wound Joints Not Exposed to
Weather and Exposed to View in Finished Areas: Non fibrated. Gray in color.
Foster 32-19, Childers CP-146, Design Polymerics DP 1010, or United Duct
Sealer WB.
2.4 AIR TERMINALS AND DUCT FITTINGS:
A. Grilles: (Grilles, Registers, Diffusers and Louvers)
1. Information on Drawings: Refer to Grille Schedule on the drawings for the
list of grilles. Manufacturer's model numbers are listed to complete the
description Titus. Equivalent models of Anemostat or Krueger are
acceptable. Refer to the floor plans for neck size, CFM, air diffusion
pattern and fire damper, if required.
2. Performance: Submit complete performance data (throw, pressure drop,
noise level, etc.) for all grilles proposed, other than those scheduled.
Testing shall be in accordance with ANSI/ASHRAE 70-1991. If, according
to the certified data of the manufacturer of the proposed units, the sizes
indicated on the drawings will not perform satisfactorily, the units shall be
reselected by the Contractor for the proper diffusion, spread, pressure
drop, throw and noise level.
3. Frame and Accessories: Supply, return, and exhaust grilles shall not have
an opposed blade volume control damper unless otherwise noted. All
surface mounted grilles shall have a perimeter gasket and flanged edge.
All grilles shall have frames suitable for mounting in the surfaces
designated by the architectural drawings. Key or screwdriver operated, no
slide bars.
4. Finish: All ceiling and wall grilles and all louvers shall have a paintable
white finish unless otherwise noted. Interior components (everything
behind the face plate) shall be flat black. Floor grilles shall have an
anodized aluminum finish unless otherwise noted.
B. Turning Vanes: Double wall, hollow metal, air foil shape. Spacing in accordance
with manufacturer's recommendations. Aero Dyne HEP.
2.5 DUCTWORK INSULATION MATERIALS:
A. General: All ductwork insulation materials shall have fire and smoke hazard
ratings as tested under ASTM E-84 and UL 723 not exceeding a flame spread of
25 and smoke developed of 50.
B. Acoustic Lining: Glass fiber. Installed thermal resistance at a mean temperature
of 750F shall meet or exceed indicated value. One side coated to prevent fiber
erosion up to 6000 ft/min. Average noise reduction coefficient of 0.80. 1.5 Ib/ft3
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 4
density. 1" thick (R-4.2) where ductwork is within the building thermal insulation
envelope. 2" thick (R-8)where ductwork is outside the building thermal insulation
envelope and/or above the roof. Certainteed, Knauf, Johns-Manville,
Owens-Corning.
C. Bonding Adhesive: Design Polymerics DP2501, Foster 85-60.
2.6 EQUIPMENT
A. General Requirements:
1. Start-up: All equipment shall be started and tested in accordance with the
manufacturer's written instructions. Start-up procedure shall be performed
by a factory trained service technician — not the installing contractor.
Provide the inspector of record with factory start-up literature for each
mechanical equipment item. Demonstrate to inspector that the start-up
procedure has been completed. Start-up sheets shall be completed and
submitted with O&M manuals. Start-up sheets shall be submitted,
certifying that start-up has been completed per manufacturer's written
instructions.
2. Capacity: Capacities shall be in accordance with schedules shown on
drawings. Capacities are to be considered minimum.
3. Dimensions: Equipment must conform to space requirements and
limitations as indicated on drawings and as required for operation and
maintenance. Where Architectural screening is indicated, equipment shall
not extend above or beyond screening. Equipment will not be accepted
that does not readily conform to space conditions. Prepare and submit
layout drawings for all proposed equipment (different than scheduled
units) showing actual job conditions, required clearances for proper
operation, maintenance, etc.
4. Ratings: Electrical equipment shall be in accordance with NEMA
Standards and UL or ETL listed where applicable standards have been
established.
5. Piping: Each item or assembly of items shall be furnished completely
piped for connection to services. Control valves and devices shall be
provided. For equipment mounted on springs, provide flex connections.
Equipment requiring domestic water for non-potable use shall be provided
with backflow preventer acceptable for intended use by local governing
authorities.
6. Electrical:
a. General: Each item or assembly of items shall be furnished
completely wired to individual terminal blocks for connection to
single branch electrical circuit. All electrical accessories required
by equipment shall be furnished. Provide terminal blocks for
controls and interlocks not included in equipment package.
Manual and magnetic starters shall have ambient compensating
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 5
running overcurrent protection in all ungrounded conductors.
Magnetic starters shall be NEMA rated, manual reset, shall have
H-O-A switches and auxiliary contacts. Controllers and other
devices shall be in NEMA 1 or 3R enclosures as applicable.
b. Wiring: Conductors, conduit, and wiring shall be in accordance
with Electrical Specifications. Individual items within assembly
shall be separately protected with dead front, fused disconnect,
fuse block, or circuit breaker for each ungrounded conductor, all
accessible on operating side of equipment. Switches, contacts
and other devices shall be in ungrounded conductors.
C. Motors: Shall be rated, constructed and applied in accordance
with NEMA and ANSI Standards without using service factor.
Single-phase motor shall be of type to suit application.
Three-phase motors shall be NEMA B design on pumps and fans,
NEMA C on reciprocating equipment, sealed ball bearing,
three-phase induction unless otherwise noted. Motors 1 HP and
above shall be NEMA premium efficiency, Class F insulation.
Motors in a fan air stream shall be TEFC or TEAO. Vertical motors
exposed to weather shall be TEFC and shall have rain caps.
Horizontal motors exposed to weather shall be TEFC. Motors for
use with VFD's shall be inverter ready.
d. Starters: Motor starters shall be furnished for all equipment except
where starter is in a motor control center as designated on the
electrical drawings. Deliver starter to Electrical Contractor for
installation and wiring.
e. Control Voltage: Equipment connected to greater than 240 volts
shall be provided with 120 volt control circuit from integral
protected transformer if separate source is not indicated on plans.
240 volt control is acceptable if confined within control panel.
f. Submittals: Included in shop drawings shall be internal wiring
diagrams and manufacturer's recommended external wiring.
7. Fan Selection:
a. Fan Curves: Performance curves shall be submitted for all units of
3000 CFM or greater. Operating point for forward curved fans
shall be from point of maximum efficiency toward increased CFM
limited by horsepower scheduled. Operating point for backward
inclined fans shall be selected near point of maximum efficiency.
Curves shall plot CFM verses static pressure with constant brake
horsepower, RPM and efficiency lines.
b. Static Pressure: Unless otherwise noted, pressure scheduled as
external static pressure (ESP) includes all ductwork and
accessory losses external to the unit housing. Unless otherwise
noted, pressure scheduled as total static pressure includes all
ductwork, filter, coil, cabinet, damper and other accessory losses.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 6
Unless otherwise noted, pressure scheduled as duct static
pressure includes all supply and return ductwork and accessory
losses external to the unit housing and plenum (as applicable).
The allowance for filter losses is 0.3" WC, unless otherwise noted.
Submit itemized static pressure losses for all components.
8. Filters:
a. General: Tested and rated in accordance with ASHRAE Standard
52.2 and Title 24, C.C.R. Furnish and install one complete change
of all filters after air balance is completed and prior to acceptance.
b. Filter Media: 2" media. MERV-13. Clean filter resistance 0.41"
water at 500 fpm. Throw-away frame. Class 2. Camfil AP-Thirteen.
9. Screens: All duct or louver openings to the outside shall be covered with
1/2", 16-gage, galvanized wire mesh screen.
10. Mixing Dampers: Opposed blade, 16 gage. Six inch maximum blade
width, 48" maximum length. Nylon or oil impregnated bronze bearings.
One half inch diameter pin shaft. 16 gage channel frame. One percent
maximum leakage at 4" WC in accordance with AMCA 500 for outside air
dampers. Actuating rod out of air stream. Arrow.
11. Sound Ratings: Shall be in accordance with ASHRAE 36 - 72. Sound
ratings shall not exceed scheduled values.
12. Drives: Unless noted as direct connected, drives shall be V-belt, rated at
150% of motor horsepower. Multiple drive belts shall be matched set.
Drive sheaves shall be dynamically balanced, adjustable, range +/- 10%,
selected at mid range. Adjustable relative movement shall be lockable to
shaft. Belts shall be aligned within 1-1/2 degrees at all times. Open drives
shall be provided with OSHA approved open mesh belt guards. Belt
guards exposed to weather shall be weatherproof enclosure with louvered
face for adequate ventilation. Driving motor shall be mounted on
adjustable rails. T.B. Woods, Browning. Submit RPM range of driven
machine with drive selection.
B. Variable Refrigerant Volume System: Note: All pipe size changes required
due to manufacturer equipment revisions or design layout revisions shall
be provided by the Contractor at no additional cost. Provide Factory Start-
up and Commissioning of VRF Controls.
1. General: Variable capacity, heat pump heat recovery air conditioning
system providing simultaneous cooling and heating. Refer to Paragraph
2.6A for general requirements. The system shall consist of outdoor units,
multiple indoor units, and M-NET DDC (Direct Digital Controls). Each
indoor unit or group of indoor units shall be capable of operating in any
mode independently of other indoor units or groups. System shall be
capable of changing mode (cooling to heating, heating to cooling) with no
interruption to system operation. Each indoor unit or group of indoor units
shall be independently controlled. The sum of connected capacity of all
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 7
indoor air handlers shall range from 50% to 150% of outdoor rated
capacity. The units shall be listed by Electrical Laboratories (ETL) and
bear the ETL label. A full charge of R-410A for the condensing unit only
shall be provided in the condensing unit. The units shall be covered by
the manufacturer's limited warranty for a period of one (1) year from date
of installation. In addition the compressor shall have a manufacturer's
limited warranty for a period of seven (7) years from date of installation.
The mandatory contractor service and install training shall be
performed by the manufacturer. Trane-Mitsubishi.
2. Outdoor Units (ODU):
a. General: The outdoor unit shall be used specifically with CITY
MULTI VRFZ components. The outdoor units shall be equipped
with multiple circuit boards that interface to the M-NET controls
system and shall perform all functions necessary for operation.
Each outdoor unit module shall be completely factory assembled,
piped and wired and run tested at the factory.
(1) All units requiring a factory supplied twinning kits shall be
piped together in the field, without the need for equalizing
line(s). If an alternate manufacturer is selected, any
additional material, cost, and labor to install additional lines
shall be incurred by the contractor.
(2) Outdoor unit shall have a sound rating no higher than 60
dB(A) individually or 64 dB(A) twinned. Units shall have a
sound rating no higher than 50 dB(A) individually or 53
dB(A) twinned while in night mode operation. If an
alternate manufacturer is selected, any additional material,
cost, and labor to meet published sound levels shall be
incurred by the contractor.
(3) Outdoor unit shall be able to connect to up to 50 indoor
units depending upon model.
(4) The outdoor unit shall have an accumulator with refrigerant
level sensors and controls.
(5) The outdoor unit shall have a high pressure safety switch,
over-current protection, crankcase heater and DC bus
protection.
(6) The outdoor unit shall have the ability to operate with a
maximum height difference of 164 feet and have total
refrigerant tubing length of 1804-2625 feet. The greatest
length is not to exceed 541 feet between outdoor unit and
the indoor units without the need for line size changes or
traps.
(7) The outdoor unit shall be capable of operating in heating
mode down to -40F ambient temperature or cooling mode
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 8
down to 230F ambient temperature, without additional low
ambient controls. If an alternate manufacturer is selected,
any additional material, cost, and labor to meet low
ambient operating condition and performance shall be
incurred by the contractor.
(8) The outdoor unit shall be capable of operating in cooling
mode down to -101F with optional manufacturer supplied
low ambient kit.
(9) Manufacturer supplied low ambient kit shall be provided
with predesigned control box rated for outdoor installation
and capable of controlling kit operation automatically in all
outdoor unit operation modes.
(10) Manufacturer supplied low ambient kit shall be listed by
Electrical Laboratories (ETL) and bear the ETL label.
(11) Manufacturer supplied low ambient kit shall be factory
tested in low ambient temperature chamber to ensure
operation. Factory performance testing data shall be
available when requested.
(12) The outdoor unit shall not cease operation in any mode
based solely on outdoor ambient temperature.
(13) The outdoor unit shall have a high efficiency oil separator
plus additional logic controls to ensure adequate oil
volume in the compressor is maintained.
(14) Unit must defrost all circuits simultaneously in order to
resume full heating more quickly. Partial defrost which may
extend "no or reduced heating" periods shall not be
allowed.
b. Unit Cabinet: The casing(s) shall be fabricated of galvanized steel,
bonderized and finished. Units cabinets shall be able to withstand
960 hours per ASTM 13117 criteria for seacoast protected models
(—BS models)
C. Fan:
(1) Each outdoor unit module shall be furnished with one
direct drive, variable speed propeller type fan. The fan
shall be factory set for operation under 0 in. WG external
static pressure, but capable of normal operation under a
maximum of 0.24 in. WG external static pressure via
dipswitch.
(2) All fan motors shall have inherent protection, have
permanently lubricated bearings, and be completely
variable speed.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 9
(3) All fan motors shall be mounted for quiet operation.
(4) All fans shall be provided with a raised guard to prevent
contact with moving parts.
(5) The outdoor unit shall have vertical discharge airflow.
d. Refrigerant: R410A refrigerant shall be required for outdoor unit
systems.
e. Coil:
(1) The outdoor coil shall be of nonferrous construction with
lanced or corrugated plate fins on copper tubing.
(2) The coil fins shall have a factory applied corrosion resistant
blue-fin finish.
(3) The coil shall be protected with an integral metal guard.
(4) Refrigerant flow from the outdoor unit shall be controlled by
means of an inverter driven compressor.
(5) The outdoor coil shall include 4 circuits with two position
valves for each circuit, except for the last stage.
f. Compressor:
(1) Each outdoor unit module shall be equipped with one
inverter driven scroll hermetic compressor. Non inverter-
driven compressors shall not be allowed.
(2) A crankcase heater(s) shall be factory mounted on the
compressor(s).
(3) The outdoor unit compressor shall have an inverter to
modulate capacity. The capacity shall be completely
variable with a turndown of 19%-5% of rated capacity,
depending upon unit size.
(4) The compressor will be equipped with an internal thermal
overload.
(5) The compressor shall be mounted to avoid the
transmission of vibration.
(6) Field-installed oil equalization lines between modules are
not allowed. Prior to bidding, manufacturers requiring
equalization must submit oil line sizing calculations specific
to each system and module placement for this project.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 10
g. Electrical:
(1) The outdoor unit electrical power shall be 208/230 or 460
volts, 3-phase, 60 hertz.
(2) The outdoor unit shall be capable of satisfactory operation
within voltage limits of 187-228 volts (208V/60Hz), 207-
253V (230V/60Hz) or 414-506V (460V/60Hz).
(3) The outdoor unit shall be controlled by integral
microprocessors.
(4) The control circuit between the indoor units, BC Controller
and the outdoor unit shall be 24VDC completed using a 2-
conductor, twisted pair shielded cable to provide total
integration of the system.
3. Indoor Units (IDU-2A,2B):
a. General: The TPEFY shall be a ceiling-concealed ducted indoor
fan coil design that mounts above the ceiling with a 2-position,
field adjustable return and a fixed horizontal discharge supply and
shall have a modulating linear expansion device. The TPEFY shall
be used with the R2-Series outdoor unit and BC Controller, Y-
Series outdoor unit, or S-Series outdoor unit. The TPEFY shall
support individual control using M-NET DDC controllers.
b. Indoor Unit. The indoor unit shall be factory assembled, wired and
run tested. Contained within the unit shall be all factory wiring,
piping, electronic modulating linear expansion device, control
circuit board and fan motor. The unit shall have a self-diagnostic
function, 3-minute time delay mechanism, and an auto restart
function. Indoor unit and refrigerant pipes shall be charged with
dehydrated air before shipment from the factory.
C. Unit Cabinet:
(1) The unit shall be, ceiling-concealed, ducted.
(2) The cabinet panel shall have provisions for a field installed
filtered outside air intake.
d. Fan:
(1) TPEFY models shall feature external static pressure
settings from 0.14 to 0.60 in. WG.
(2) The indoor unit fan shall be an assembly with one or two
Sirocco fan(s) direct driven by a single motor.
(3) The indoor fan shall be statically and dynamically balanced
and run on a motor with permanently lubricated bearings.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 11
(4) The indoor fan shall consist of three (3) speeds, High, Mid,
and Low plus the Auto-Fan function
(5) The indoor unit shall have a ducted air outlet system and
ducted return air system.
e. Filter:
(1) Return air shall be filtered by means of a standard factory
installed return air filter.
(2) Optional return filter box (rear or bottom placement) with
high-efficiency filter shall be available for all TPEFY indoor
units.
f. Coil:
(1) The indoor coil shall be of nonferrous construction with
smooth plate fins on copper tubing.
(2) The tubing shall have inner grooves for high efficiency heat
exchange.
(3) All tube joints shall be brazed with phos-copper or silver
alloy.
(4) The coils shall be pressure tested at the factory.
(5) A condensate pan and drain shall be provided under the
coil.
(6) The condensate shall be gravity drained from the fan coil.
(7) Both refrigerant lines to the TPEFY indoor units shall be
insulated.
g. Electrical:
(1) The unit electrical power shall be 208/230 volts, 1-phase,
60 hertz.
(2) The system shall be capable of satisfactory operation
within voltage limits of 187-228 volts (208V/60Hz) or 207-
253 volts (230V/60Hz).
h. Controls:
(1) This unit shall use controls provided by Mitsubishi Electric
Cooling & Heating to perform functions necessary to
operate the system. Please refer to Part 5 of this guide
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 12
specification for details on controllers and other control
options.
(2) Indoor unit shall compensate for the higher temperature
sensed by the return air sensor compared to the
temperature at level of the occupant when in HEAT mode.
Disabling of compensation shall be possible for individual
units to accommodate instances when compensation is not
required.
(3) Control board shall include contacts for control of external
heat source. External heat may be energized as second
stage with 1.8°F —9.0°F adjustable deadband from set
point.
(4) Indoor unit shall include no less than four (4) digital inputs
capable of being used for customizable control strategies.
(5) Indoor unit shall include no less than three (3) digital
outputs capable of being used for customizable control
strategies.
(6) Manufacturer to provide drain pan level sensor powered by
a 20-year life lithium battery. Sensor shall require no
external power for operation and shall have an audible
indication of low battery condition.
(7) The drain pan sensor shall provide protection against drain
pan overflow by sensing a high condensate level in the
drain pan. Should this occur the control shuts down the
indoor unit before an overflow can occur. A thermistor error
code will be produced should the sensor activate indicating
a fault which must be resolved before the unit re-starts.
4. Indoor Units (IDU-1,A,1B,3A-3F):
a. General: The TPKFY shall be a wall-mounted indoor unit section
and shall have a modulating linear expansion device and a flat
front. The TPKFY shall be used with the R2-Series outdoor unit
and BC Controller, Y-Series outdoor unit, or S-Series outdoor unit.
The TPKFY shall support individual control using M-NET DDC
controllers.
b. Indoor Unit: The indoor unit shall be factory assembled, wired and
run tested. Contained within the unit shall be all factory wiring,
piping, electronic modulating linear expansion device, control
circuit board and fan motor. The unit shall have a self-diagnostic
function, 3-minute time delay mechanism, an auto restart function,
and a test run switch. Indoor unit and refrigerant pipes shall be
charged with dehydrated air before shipment from the factory.
C. Unit Cabinet: All casings, regardless of model size, shall have the
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 13
same white finish. Multi directional drain and refrigerant piping
offering four (4) directions for refrigerant piping and two (2)
directions for draining shall be standard. There shall be a separate
back plate which secures the unit firmly to the wall.
d. Fan:
(1) The indoor fan shall be an assembly with one or two line-
flow fan(s) direct driven by a single motor.
(2) The indoor fan shall be statically and dynamically balanced
to run on a motor with permanently lubricated bearings.
(3) A manual adjustable guide vane shall be provided with the
ability to change the airflow from side to side (left to right).
(4) A motorized air sweep louver shall provide an automatic
change in airflow by directing the air up and down to
provide uniform air distribution.
e. Filter: Return air shall be filtered by means of an easily removable,
washable filter.
f. Coil:
(1) The indoor coil shall be of nonferrous construction with
smooth plate fins on copper tubing.
(2) The tubing shall have inner grooves for high efficiency heat
exchange.
(3) All tube joints shall be brazed with phos-copper or silver
alloy.
(4) The coils shall be pressure tested at the factory.
(5) A condensate pan and drain shall be provided under the
coil.
(6) Both refrigerant lines to the TPKFY indoor units shall be
insulated.
g. Electrical:
(1) The unit electrical power shall be 208/230 volts, 1-phase,
60 hertz.
(2) The system shall be capable of satisfactory operation
within voltage limits of 187-228 volts (208V/60Hz) or 207-
253 volts (230V/60Hz)
h. Controls:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 14
(1) This unit shall use controls provided by Mitsubishi Electric
Cooling & Heating to perform functions necessary to
operate the system. Please refer to Part 4 of this guide
specification for details on controllers and other control
options.
(2) The unit shall be able to control external backup heat.
(3) The unit shall have a factory built in receiver for wireless
remote control
(4) Indoor unit shall compensate for the higher temperature
sensed by the return air sensor compared to the
temperature at level of the occupant when in HEAT mode.
Disabling of compensation shall be possible for individual
units to accommodate instances when compensation is not
required.
(5) Control board shall include contacts for control of external
heat source. External heat may be energized as second
stage with 1.8°F —9.0°F adjustable deadband from set
point.
(6) Indoor unit shall include no less than four (4) digital inputs
capable of being used for customizable control strategies.
(7) Indoor unit shall include no less than three (3) digital
outputs capable of being used for customizable control
strategies.
(8) Manufacturer to provide drain pan level sensor powered by
a 20-year life lithium battery. Sensor shall require no
external power for operation and shall have an audible
indication of low battery condition.
(9) The drain pan sensor shall provide protection against drain
pan overflow by sensing a high condensate level in the
drain pan. Should this occur the control shuts down the
indoor unit before an overflow can occur. A thermistor error
code will be produced should the sensor activate indicating
a fault which must be resolved before the unit re-starts.
C. Exhaust Fans:
1. General: All exhaust fans shall be tested according to AMCA Standard
210 in an AMCA registered laboratory. Fans exposed to weather shall
have ventilated weatherproof housing over motor and drive assembly.
Refer to Paragraph 2.6A for general requirements. All direct drive fans
shall be provided with unit mounted speed controllers, unless otherwise
noted. All motors 1 horsepower and larger shall be the premium efficiency
type.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 15
2. Roof Fan: Spun aluminum, roof mounted, direct driven, downblast
centrifugal exhaust ventilator. Fan shall be of bolted and welded
construction utilizing corrosion resistant fasteners and stainless-steel
fasteners on cap. Spun aluminum structural components shall be
constructed of minimum 16-gauge marine alloy aluminum, bolted to a
rigid aluminum support structure. Aluminum base shall have continuously
welded curb cap corners for maximum leak protection. Discharge baffle
shall have a rolled bead for added strength. An integral conduit chase
shall be provided through the curb cap and into the motor compartment to
facilitate wiring connections. Motor shall be enclosed in a weather-tight
compartment, separated from the exhaust airstream. Unit shall bear an
engraved aluminum nameplate. Wheel shall be centrifugal backward
inclined, constructed of 100% aluminum, including a precision machined
cast aluminum hub. An aerodynamic aluminum inlet cone shall be
provided for maximum performance and efficiency. Motor shall be heavy
duty type with permanently lubricated sealed bearings and furnished at
the specified voltage, phase and enclosure. Backdraft damper. Units as
scheduled shall have Vari-Green Constant Pressure Control option.
Greenheck.
PART 2 - EXECUTION
3.1 PIPING INSTALLATION
A. General:
1. Piping Layout: Piping shall be concealed in walls, above the ceilings, or
below grade unless otherwise noted. Exposed piping shall run parallel to
room surfaces; location to be approved by Engineer. No structural
member shall be weakened by cutting, notching, boring or otherwise,
unless specifically allowed by structural drawings and/or specifications.
Where such cutting is required, reinforcement shall be provided as
specified or detailed. All piping shall be installed in a manner to ensure
unrestricted flow, eliminate air pockets, prevent any unusual noise, and
permit complete drainage of the system. All piping shall be installed to
permit expansion and contraction without strain on piping or equipment.
Vertical lines shall be installed to allow for building settlement without
damage to piping. Lines shall be adequately braced against vertical and
lateral movement. For piping connected to equipment mounted on
springs, provide flex connections. Pipe sizes indicated on the drawings
are nominal sizes unless otherwise noted. Pipe sizes shall not decrease
in direction of flow, unless otherwise noted.
2. Joints:
a. Threaded: Pipe shall be cut square, and reamed to full size.
Threads shall be in accordance with ANSI B2.1. Joint compound
or tape suitable for conveyed fluid shall be applied to male thread
only. Joints shall be made with three threads exposed.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 16
b. Brazed: Welding and brazing shall conform to American Welding
Society (AWS) standards. Filler rod shall be of suitable or the
same alloy as pipe. Brazing filler metal shall have a minimum
melting point of 11001F. Brazing shall be performed by a Certified
Brazer as certified by an organization/institution that uses
standards recognized by the AWS and meets the requirements of
the ASME Boiler and Pressure Vessels Code, Section 9. The
Contractor shall submit welding procedures per AWS for project
welds for testing lab review.
C. Open Ends: Open ends of piping shall be capped during progress
of work to preclude foreign matter.
3. Fittings and Valves:
a. Standard Fittings: All joints and changes in direction shall be
made with standard fittings. Close nipples shall not be used.
b. Reducers: Pipe size reduction shall be made with bell reducer
fittings. Bushings shall not be used.
4. Pipe Support:
a. General: Hangers shall be placed to support piping without strain
on joints or fittings. Maximum spacing between supports shall be
as specified below (based on straight lengths of pipe with
couplings only). Provide additional supports for equipment, valves
or other fittings. Seismic requirements may reduce maximum
spacing. Actual spacing requirements will depend on structural
system. Refer to drawings for additional requirements and
attachment to structure. Side beam clamps shall be provided with
retaining straps to secure the clamp to the opposite side of the
beam. Vertical piping shall be supported with riser clamp at 20' on
center (maximum). Support pipe within 12" of all changes in
direction.
b. Refrigerant Piping: Support insulated refrigerant line with
construction channel and sheet metal support saddle or Cooper B-
Line Armafix clamps. 5' spacing. Use isolation shield for
uninsulated pipe. When using pre-charged tubing, all changes of
direction shall be made with bending tools producing neat uniform
bends. Free hand bends will not be accepted.
C. Trapeze: Trapeze hangers of construction channel and pipe
clamps may be used. Submit design to Engineer for review.
5. Miscellaneous:
a. Escutcheons: Provide chrome plated metal escutcheons where
piping penetrates walls, ceilings, or floors in finished areas.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 17
b. Pipe Sleeves: All piping passing through concrete shall be
provided with pipe sleeves. Allow 1" (nominal) clearance between
sleeve and pipe or pipe insulation.
C. Pipes Passing through Fire Rated Surfaces: Pipes passing
through fire rated walls, floors, ceilings, partitions, etc. shall have
the annular space surrounding the pipe or pipe insulation sealed
with fire rated materials in accordance with the requirements of
2022 CBC Section 714.
B. Refrigerant Piping: Pipe shall be cut square. Joint surfaces shall be thoroughly
cleaned, fitted and erected before brazing. After installation, evacuate to 29
inches of mercury, ambient temperature during evacuation shall not be less than
70°F. After evacuation, fill with dry nitrogen to 250 psi and maintain for two hour
period without additional charge. After nitrogen test, purge with refrigerant
charged through dryer and maintain holding charge in system and equipment.
Refrigerant piping below grade shall be run in 4" (min.) PVC conduit with long
radius ells. Seal ends of conduit watertight. VRF system fittings shall be as
recommended by manufacturer. Installers shall have successfully completed
manufacturer's installation training within 6 months of installation. Provide
training certificate or letter from manufacturer's rep stating such.
3.2 PIPING INSULATION INSTALLATION
A. Refrigerant Piping: Cover piping with foamed plastic insulation. Longitudinal and
end seams shall be thoroughly cemented with adhesive in accordance with
manufacturer's recommendations. Cover all fittings, unions, valves and
connections. Piping exposed to view shall be covered with PVC jacketing. Piping
exposed to weather shall be covered with aluminum jacketing, install all joints
and seams to prevent water entry, seal with 1/8" bead of gray metal jacketing
sealant.
3.3 DUCTWORK INSTALLATION:
A. General:
1. Standards: Unless otherwise noted, all ductwork shall be constructed and
installed in accordance with current SMACNA Standards. Ductwork shall
be built to a pressure classification equal to or greater than the maximum
operating pressure at that point in the ductwork. A copy of these
standards shall be maintained at the job site at all times. Duct work and
accessories shall be installed in a manner to prevent vibration and
rattling.
2. Access: Provide duct access doors as required to adjust equipment and
dampers. Provide wall or ceiling access panels, or remote actuators as
required where equipment and dampers are not otherwise accessible.
Ventlok 666 concealed remote actuator with zinc finish on cover.
3. Flanges and Escutcheon: Where ductwork penetrates walls, ceilings, or
floors, furnish and install flange or escutcheon of same material as duct.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 18
B. Low Velocity-Low Pressure (up to 2,000 ft/min and up to 2.0 in water):
1. Sheet Metal Ductwork:
a. Ells: Ells with less than standard radius and square ells shall be
fitted with turning vanes.
b. Tees: Tees in supply ductwork shall be straight tap-in with
extractor or 45 degree take-off as shown on drawings. Grilles or
branches in supply ductwork shall be a minimum of 8 duct
diameters downstream of tees.
C. Duct Joints and Seams: All joints and seams which are not
exposed to weather shall be sealed airtight with duct sealant. All
joints and seams exposed to weather shall be sealed air and
water tight with silicone sealant. (See Part 2 of this Specification).
All joints on spiral wound metal ductwork not exposed to weather
shall be sealed air tight with grey duct sealant.
d. Dampers: Install volume control damper and damper regulator in
all branch ducts.
3.4 AIR TERMINALS AND DUCT FITTINGS INSTALLATION:
A. General: Unless otherwise noted, all air terminals and duct fittings shall be
installed in accordance with current SMACNA Standards. Terminals and fittings
shall be installed in a manner to prevent vibration and rattling. Metal surfaces
exposed to view behind grilles and registers shall be painted flat black.
3.5 DUCTWORK INSULATION INSTALLATION:
A. General: Insulate all sheet metal supply, return and outside air intake ductwork
except as noted below. Insulation shall be continuous through walls and floors
except at fire dampers.
B. Where Insulation Is Not Required: Do not insulate factory-insulated ducts or
casings, acoustic lined ducts, fibrous glass ducts, underground ductwork, supply
or return ductwork exposed to view in the space that it serves, or exhaust
ductwork.
C. Acoustic Lining: Unless otherwise indicated, all supply and return ductwork in
equipment rooms, all ductwork exposed to weather and other ducts as indicated
on drawings, shall have acoustic lining. Do not acoustic line outside air intakes.
Where acoustic lining is installed, increase each sheet metal dimension to
accommodate lining and maintain clear inside duct dimensions shown on
drawings. Apply lining with bonding adhesive in accordance with manufacturer's
recommendations and also secure with mechanical fasteners in accordance with
SMACNA Standards. Seal exposed edges of lining with bonding adhesive.
3.6 EQUIPMENT INSTALLATION
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 19
A. General: The equipment installer shall ensure that no work done under other
specification sections will in any way block or hinder the equipment. All
equipment shall be securely anchored in place. Provide factory start-up for all
equipment in the Central Plant.
B. Connections to Equipment: Where size changes are required for connections to
equipment, they shall be made immediately adjacent to the equipment and, if
possible, inside the equipment cabinet.
3.7 TESTS AND ADJUSTMENTS
A. General: Unless otherwise directed, tests shall be witnessed by a representative
of the Engineer. Work to be concealed shall not be enclosed until prescribed
tests are made. Should any work be enclosed before such tests, the Contractor
shall, at his expense, uncover, test and repair all work to original conditions.
Leaks and defects shown by tests shall be repaired and entire work retested.
3.8 SYSTEM ENERGY BALANCE
A. Scope: Provide the services of an independent test and balance agency to test,
adjust and balance, retest and record performance of the system to obtain design
quantities as specified. The agency must prove that they have no affiliation with
any equipment manufacturer, design engineer, installing contractor, or any other
party which might lead to a conflict of interest, in order to provide an unbiased,
third party system balance and report.
B. Qualifications: Prior to commencing work, the agency shall be reviewed by the
Engineer and shall be certified by the Associated Air Balance Council or National
Environmental Balancing Bureau. The agency shall provide documentation of
having successfully completed at least five projects of similar size and scope.
The Contractor must have sufficient personnel to respond to a trouble call at the
site within two hours.
C. Instruments: All instruments shall be accurately calibrated; calibration histories
shall be available for examination. Application of instrumentation shall be in
accordance with AABC or NEBB standards.
D. Submittals: Include in shop drawings copies of forms to be used for testing and
balancing showing all data which is to be recorded. Three copies of completed
balance report shall be submitted for review.
E. Procedure - General: Procedure shall be in accordance with Associated Air
Balance Council's "National Standards for Field Measurements and
Instrumentation - Total System Balance", Volume Two, No. 12173, or equivalent
NEBB standards. System shall be in full, continuous operation during test.
Balanced quantities shall be plus 10%, minus 0% of design quantities. All
nameplate data, manufacturer, model and serial numbers shall be recorded for
each item tested.
F. Extended Warranty: The test and balance agency shall include an extended
warranty of 90 days after completion of test and balance work, during which time
the Engineer, at his discretion, may request a recheck or resetting of any item or
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 20
items in test report. The agency shall provide technicians to assist the Engineer
in making any tests he may require during this period of time.
G. Air Balance Procedure (For Each Air Handling System):
1. All air filters shall be clean when air balance is performed.
2. Provide a sketch of the equipment showing exactly where all pressure
readings were taken.
3. Adjust blower RPM to design requirements.
4. Record motor full load amperes.
5. Make pitot tube traverse of main supply and return ducts and obtain
design CFM at fans.
6. Record system static pressures, inlet and discharge.
7. Record filter quantity, size(s) and pressure drop across filter(s) at each
filter bank.
8. Adjust system for design CFM recirculated air.
9. Adjust system for design CFM outside air.
10. Record entering air temperatures. (DB heating, DB and WB cooling.)
11. Record leaving air temperatures. (DB heating, DB and WB cooling.)
12. Adjust all main supply and return air ducts to design CFM.
13. Adjust all zones to design CFM, supply and return.
14. Adjust all diffusers, grilles and registers to plus 10%, minus 0% of design
requirements.
15. Adjust CFM at all exhaust fans, make-up units, etc. (high and low speed,
where applicable). Record applicable data from items 1 through 11
above.
16. Each grille, diffuser and register shall be identified as to location.
17. Verify proper diffusion pattern for all ceiling grilles and that all sidewall
grilles are set for 5 degrees upward deflection unless otherwise noted.
Make a notation of any that are not set properly.
18. Size, type and manufacturer of diffusers, grilles, registers and all tested
items shall be identified and listed. Manufacturer's ratings shall be used to
make required calculations on all items.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HVAC
REEDLEY, CA. SECTION 230800 - 21
19. Readings and tests of diffusers, grilles, and registers shall include
required FPM velocity and test resultant velocity, required CFM and test
resultant CFM after adjustments.
20. In cooperation with the control manufacturer's representative, set
adjustments of automatically operated dampers to operate as specified.
Testing agency shall check all controls for proper calibrations and list all
controls requiring adjustment by control installers.
21. All diffusers, grilles and registers shall be adjusted for required air
patterns and to minimize drafts.
22. As a part of the work of this contract, THE AIR CONDITIONING
CONTRACTOR shall make any changes in pulleys, belts and dampers or
the addition of dampers required for correct balance as recommended by
air balance agency, at no additional cost to Owner.
23. Set, test and adjust packaged heating/cooling unit economizer operation
in cooperation with controls contractor. Record minimum and maximum
outside and exhaust airflows.
END OF SECTION 23 08 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 1
SECTION 250900— DIRECT DIGITAL CONTROL SYSTEM
PART 1 - GENERAL
1.1 GENERAL MECHANICAL PROVISIONS
A. The General Mechanical Provisions, Section 20 01 00, shall form a part of this
Section with the same force and effect as though repeated here.
1.2 SCOPE
Included: Provide all labor, materials and services necessary for a complete, lawful and
operating direct digital control (DDC) system as shown or noted on the drawings or as
specified here. The work includes, but is not necessarily limited to, the following:
1. Control panels, control devices, line and low voltage wiring, conduit and
related equipment as required for proper operation of all controlled
systems.
2. Power wiring required for control devices such as actuators, controllers,
sensors and power supplies. Power wiring for these devices shall be fed
from circuits dedicated to the DDC system.
B. Work Specified Elsewhere:
1. Line voltage dedicated power circuits for stand-alone building controllers
are included in the Electrical Divisions unless otherwise noted.
1.3 CONTRACTOR QUALIFICATIONS
A. All controls shall be furnished and installed by a Contractor who is licensed, certified
or contracted by the controls and VRV manufacturer for design, installation, start-up
and service of their product. The Contractor must have factory supplied training and
support. The Contractor shall have sufficient personnel to respond to a trouble call at
the site within four hours. The Contractor's local manager shall have a minimum of
five years' experience in the design, installation, start-up and service of similar
systems. The Contractor shall submit a list of at least five projects which are similar
in size, scope and contract value to this project. This list shall include the Owner's
contact person, phone number and controls contract value.
B. Quality Assurance
1. General
i. The Building Management System (BMS) Contractor shall be Authorized
Building Controls Specialist contractor that is regularly engaged in the
engineering, programming, installation and service of total integrated Building
Management Systems. Bids from wholesalers, distributors or contractors who
do not purchase directly from Johnson Controls are not allowed.
ii. The BMS Contractor shall have a branch facility within a 25-mile radius of the
job site supplying complete maintenance and support services on a 24 hour,
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 2
7-day-a-week basis. The BMS Contractor shall have at this facility at least
eight (8) factory trained, directly employed and full time technical staff, spare
parts inventory, and all necessary test and diagnostic equipment.
iii. As evidence and assurance of the BMS contractor's ability to support the
Owner's system with service and parts, the BMS contractor must have been
in the BMS business for at least the last ten (10) years and have successfully
completed total projects of at least 10 times the value of this contract in each
of the preceding five years.
iv. The BMS architecture shall consist of the products of a manufacturer
regularly engaged in the production of Building Management Systems, and
shall be the manufacturer's latest standard of design at the time of bid.
2. Workplace Safety and Hazardous Materials
a. Provide a safety program in compliance with the Contract Documents.
b. The BMS Contractor shall have a corporately certified comprehensive Safety
Certification Manual and a designated Safety Supervisor for the Project.
c. The BMS Contractor and its employees and subtrades shall comply with
federal, state and local safety regulations.
d. The BMS Contractor shall ensure that all subcontractors and employees have
written safety programs in place that covers their scope of work, and that their
employees receive the training required by the OSHA rules that have
jurisdiction for at least each topic listed in the Safety Certification Manual.
e. Hazards created by the BMS Contractor or its subcontractors shall be
eliminated before any further work proceeds.
f. Hazards observed but not created by the BMS Contractor or its
subcontractors shall be reported to either the General Contractor or the
Owner within the same day. The BMS Contractor shall be required to avoid
the hazard area until the hazard has been eliminated.
g. The BMS Contractor shall sign and date a safety certification form prior to
any work being performed, stating that the Contractors' company is in full
compliance with the Project safety requirements.
h. The BMS Contractor's safety program shall include written policy and
arrangements for the handling, storage and management of all hazardous
materials to be used in the work in compliance with the requirements of the
AHJ at the Project site.
i. The BMS Contractor's employees and subcontractor's staff shall have
received training as applicable in the use of hazardous materials and shall
govern their actions accordingly.
3. Quality Management Program
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 3
a. Designate a competent and experienced employee to provide BMS Project
Management. The designated Project Manager shall be empowered to make
technical, scheduling and related decisions on behalf of the BMS Contractor.
At minimum, the Project Manager shall:
0 Manage the scheduling of the work to ensure that adequate materials,
labor and other resources are available as needed.
0 Manage the financial aspects of the BMS Contract.
0 Coordinate as necessary with other trades.
0 Be responsible for the work and actions of the BMS workforce on site.
1.4 BASIS OF DESIGN
A. The system shall be Johnson Metasys Building Systems, without substitution, to
match County of Fresno Standard.
1.5 SUBMITTALS AND OPERATION AND MAINTENANCE MANUALS
A. Submittals shall be in accordance with Section 20 01 00 and shall include the
following:
1. Contractor qualifications. Manufacturer licenses, contracts or certifications
for the installer shall be submitted on manufacturer's letterhead.
2. Manufacturer's data for all devices.
3. Manufacturer's data for all software.
4. Diagrams showing control schematics. Diagrams shall include all
sensors, terminal strips, panels and control devices. Locations of all
devices shall be indicated.
5. Sequence of operation.
6. Site plan showing conduit trench and pullbox locations. This plan shall
also show the conduit termination points inside the buildings.
B. Operation and Maintenance Manuals: Furnish Operation and Maintenance
Manuals for all components. These manuals shall contain full documentation
which shall include, without being limited to, the following:
1. General description and specifications.
2. Installation and initial checkout procedures.
3. Complete trouble-shooting procedures and diagrams.
4. Complete alignment and calibration procedures for all components.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 4
5. Preventative maintenance requirements.
6. Detailed schematics and assembly drawings.
1.6 SYSTEM ARCHITECTURE
A. The direct digital control system shall employ a multi-level distributed processing
architecture. A web based front end controller shall act as the host and shall
communicate with both the system operator and the stand-alone controllers. The
stand-alone controllers shall be microprocessor based and perform the specified
data acquisition and control functions. They shall connect to and supervise
multiple application specific controllers (ASC). The stand-alone controllers shall
perform stand-alone control functions whether in communications with the web
based front end controller or not. All independent control loops shall be
processed and controlled by the stand-alone controllers. Each stand-alone
controller shall store historical data for all connected points for a minimum of 24
hours. Historical data shall include total run-time for each digital point. For analog
data, periodic samples shall be stored at the frequency of once per minute. The
physical connection and interface with the actual field points shall be
accomplished through the ASC's. The ASC's shall be located throughout the
data environment, communicate with, and be controlled by the stand-alone
controllers. The stand-alone controllers shall be accessible by laptop computer
with proper software via cable connection. Access to the system shall also be
available through connection at selected space sensors.
PART 2 - PRODUCTS
2.1 SENSORS
A. Space Temperature Sensor: Room sensor with solid-state electronic,
interchangeable with housing appropriate for application occupant and adjustable
set point. Occupant adjustable set point shall be limited by software. Wall
mounted temperature sensors shall be mounted with bottom of sensor at 48"
above finish floor.
B. Outside Air Temperature Sensor: Provide one outside air sensor per stand-alone
building controller. Install on north wall of building.
C. Duct Sensor: Averaging sensor shall be used at ducts with greater than 9 square
feet of cross sectional area. Sensor shall extend across 75% of the duct. Sensor
shall be housed in a NEMA 3R enclosure with proper extension at insulated
ducts. Provide access door.
D. Photocell: Wattstopper EM-24 A 2.
E. Status Sensor: Current sensing status sensor with sensitivity adjustment.
F. Smoke Detector: Photoelectric type, 115 VAC. The detector shall operate at air
velocities from 300 FPM to 4000 FPM. The detector head shall not require
additional filters or screens. Mounted in a sheet metal housing with a removable
cover. A visual indication of alarm and power shall be provided on detector front.
Manual test and reset switch on front of detector. Power supervisory relay.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 5
Minimum of two sets of alarm contacts. UL listed. California State Fire Marshal
listed. Air Products and Controls, SM-501 Series.
2.2 SYSTEM COMPONENTS
A. Electric Actuators:
1. General: Fully modulating, UL listed. Visual position indicator, manual
override, spring return. Factory weatherproof enclosure where exposed to
weather. Belimo.
2. Valve Actuators: Provide with factory mounting brackets and linkage to the
control valve. Capable of shutting off against a 50 psi differential.
3. Damper Actuators: Actuators shall be direct mounted onto the damper
control shaft without linkage. Damper actuators shall be sized to provide a
minimum of 5 inch-pounds of torque per square foot of damper face area.
B. Lighting Contactors: Contactor with metal enclosure. Square D. Provide low
voltage relays to complete the lighting control. For low voltage (120 volt) outside
lighting, provide status relay for lighting status. For 277 volt outside lighting,
provide current sensor for lighting status.
C. Web Based Front End Controller with Graphical Interface: Provide color graphics
accessible through the Owner's system (with security protocol) which will allow
the user to override on/off and temperature set points directly. Real time data
shall be continuously updated. The minimum graphic screens shall include the
following:
1. Site lay-out locations of all equipment being controlled, control component
locations and spaces served. Provide multiple screens— minimum of one
screen per building, plus site and others as needed for clarity. By
selecting the desired equipment item, a flow diagram shall be displayed
for the related equipment (as described below). By selecting a
conditioned space, a graphic display of the zone conditions shall be
displayed (as described below).
2. Flow diagrams shall be provided for each HVAC system, such as air-
handling system, chilled water system, hot water system, condenser
water system, package unit system with all inputs and outputs
dynamically displayed.
3. Each temperature control zone shall have a screen providing set points,
temperatures, and related HVAC system status data.
4. Scheduling screens allowing on/off times shall be set for all the following:
a. Pre-determined individual days
b. Pre-determined blocks of days (from/to)
c. Schedules for"Routine" days
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 6
d. Schedules for"Special" days
D. Enclosures: Hinged, lockable front panel. The panel shall be identified with a
label as specified. No conduit or other penetration of any kind shall be made on
top of the enclosure. If any such entry is made, a plug is not acceptable; replace
the enclosure. Hoffman with metal back panel. NEMA 1 for indoor; NEMA 3R for
outdoor, NEMA 12 for hazardous locations.
E. Wiring: Sensor and communication cable shall be shielded cable, wire gage and
number of wires as recommended by the system manufacturer. Install per
manufacturer's recommendations. No splices will be allowed. Identify both ends
at terminal blocks. All wiring that is routed below grade shall have a PVC jacket,
CL2-0552. All other wiring shall be plenum-rated, CL3P-0552.
F. Conduit: Size conduit per the California Electrical Code and then increase by one
size, except that the minimum conduit size for low voltage shall be 1" and the
minimum conduit size for 120 volt power shall be 114". For underground conduit,
provide 100% spare capacity by installing a second conduit (empty) along all
conduit routes.
G. Labels: All labels, signs, etc. shall be engraved, laminated plastic, white on black
background, 1/8" high lettering, minimum.
H. Mitsubishi Controller. CITY MULTI Controls Network (CMCN) controller with on-
site LCD and internet IP accessibility with Factory BACnet Interface Card.
I. Mitsubishi Room Sensor/Controller: Shall be wall mounted "in-room"wired
remote controller.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General: A dedicated ASC shall be provided for every item of new equipment
and for every item of existing equipment. All electrical work shall be in
accordance with the California Electrical Code and the Electrical Specification
Sections. Wiring shall be concealed in walls, above the ceilings, or below grade
unless otherwise noted. Exposed wiring shall run in conduit parallel to room
surfaces; location shall be approved by the Engineer. Wiring in walls or in
mechanical rooms, janitor rooms, or storage rooms shall be in conduit. Conduit
above roofs shall be rigid conduit. Low voltage wiring in accessible attics may be
run without conduit. This wiring shall be strapped to structure at 48" on center,
and shall not lay on the ceiling. No structural member shall be weakened by
cutting, notching, boring or otherwise. Provide power wiring for each device
requiring external power. Dedicated circuits shall be provided for devices as
required by the manufacturer. Devices or wiring exposed to the weather shall be
protected in NEMA 3R enclosures and weatherproof conduit. All conduit shall
include a pull wire. Set, test, and adjust the system for proper operation. Provide
connection to the Owner's network for web-based access to stand-alone
controllers.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 7
B. Programming: The Contractor shall be responsible for programming the system
and shall coordinate the scheduling (on/off times) with the Owner. All point lists
and programming blocks shall be provided by the Contractor. For upgrades or
additions to existing systems, all existing programming and existing sequences of
operation shall be incorporated into the new system and equipment. The project
will not be considered complete until all programming and graphics have been
completed and all systems are operational from the location of the web based
front end controller.
C. Control Panels/Enclosures:
1. ASC's, transformers, relays, etc. shall be housed in enclosures.
Enclosures shall be installed as shown on plans. Wherever practical, do
not locate enclosures above ceilings. Maintain access to enclosures that
are located above ceilings (e.g. at VAV boxes).
2. For all enclosures, provide a disconnect switch and an in-line fuse. All
wiring shall be terminated at terminal strips — no wire nuts. Provide a
plastic covered wiring diagram in each enclosure. All wiring (field and
inside enclosures) shall be labeled at both ends with machine printed
markers — black on white tape. At packaged equipment, locate the
enclosure on the side of the unit without obstructing access or service
clearance.
3. Separate 120 volt circuits from low voltage circuits horizontally. A physical
barrier is not required. Enclose wiring within the enclosure in 2"x2"
Panduit.
3.2 TRAINING
A. Prior to final acceptance, the Contractor shall provide operational training to the
Owner's personnel. The training sessions shall include a complete demonstration
of the system. Dates and times of the training sessions shall be coordinated
through the Owner not less than one week prior to session. A total of 40 hours of
instruction shall be provided - 20 hours initially, and 20 hours to be spread
throughout the first year of operation. The Contractor shall maintain a log of
training sessions including dates, times and names/titles of those attending. The
Contractor shall submit a copy of this log on request.
3.3 TESTING AND ACCEPTANCE
A. The Contractor shall verify, in the presence of the Owner, the system accuracy
and proper function of each controlled device and sensor. The following items
shall be successfully demonstrated prior to acceptance by the Owner:
1. All system outputs including controllers, relays, and other control devices
shall be addressed and start/stop functions demonstrated.
2. All inputs shall be displayed and all event-initiated functions shall be
demonstrated.
3. Demonstrate program integrity and power restore sequence during and
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 8
after a power failure and restoration.
4. Deliver all record drawings, wiring diagrams, equipment specifications,
operation and maintenance manuals and other documentation as
required to describe the system.
5. Complete operator training in the use, programming, and operation of the
system.
3.4 SERVICE WORK
A. Service work shall be performed by service personnel in the direct employ of the
controls contractor. The service technicians shall be factory trained and certified
by the manufacturer to be competent in all aspects of the installed system. The
technician shall have a working knowledge of calibration techniques, preventive
maintenance, troubleshooting, software diagnostics and microprocessor repair.
Precaution shall be taken to minimize disruption of facility operations by service
work.
3.5 SEQUENCE OF OPERATION
A. System Operation Schedule: The systems shall operate at the following schedule
(adjustable by Owner) except as noted:
Systems shall operate continuously 24 hrs/day.
B. Alarm Condition Display: On any alarm, the Central Workstation shall display the
equipment mark number and the specific alarm condition. Upon highlighting the
alarming equipment, the program shall have a graphic display function that
displays the plan of the building floor with the location of the alarming equipment
indicated.
C. System Report: The DDC/EMS shall prepare a system report on demand. The
report shall include the following items in the report:
Date and time of the current report.
Date and time of the previously reviewed report.
List of any alarms that have occurred the since the last report. The list shall include
the time of the alarm, unit that had the alarm, and the type of alarm.
List of any still active run time notices. The list shall include the time of the initial
notice, unit that had the notice, and the type of notice.
List of any still active filter change notices. The list shall include the time of the
initial notice, unit that had the notice, and the type of notice.
List of any off-hours operations that have occurred since the last report. The list
shall include the date and time of the off-hours operation, the unit identification
number, the physical /service location of the unit, and the duration of the off-
hours operation.
D. Variable Refrigerant Volume Air Conditioner (ODU / IDU):
DDC/EMS Interface: Provide a DDC/EMS panel and connect to the existing WAN
DDC/EMS. Connect to the DDC/EMS interface on the VRV Central Controller.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DIRECT DIGITAL CONTROL SYSTEM
REEDLEY, CA. SECTION 250900 - 9
Provide programming to allow the DDC/EMS to monitor the room temperatures
from the Indoor Units, reset the room temperature setpoints, display alarm
conditions from the VRV system.
Central Controller: Locate the Central Controller per plans. Wire the central
controller to each Outdoor Unit (ODU) system controller as the system is
installed. Program the controller to operate the system on the schedule noted
above. Alarm conditions of any component on the connected systems shall be
able to be reviewed through the Central Controller.
Outdoor Unit (ODU): Wire each Indoor Unit (IDU) controller to its respective ODU
controller. The IDU shall coordinate its total heating /cooling requirements with
its connected ODU.
Indoor Unit (IDU): (Heating setpoint 72°F, Cooling setpoint 75°F) The Indoor Unit
(IDU) operation shall be controlled by a factory furnished controller to be
mounted on the wall. The wall-mounted controller shall operate the IDU to
maintain the heating or cooling setpoint. Wire each IDU controller to the ODU
controller it serves.
Areas that are required to operate continuously by the Owner shall have the IDU
controller set to operate the IDU continuously maintaining setpoint.
E. A wall mounted temperature sensor shall monitor room temperature. If the room
temperature rises above 85°F (adj.), the DDC/EMS shall signal a high room
temperature alarm.
F. Exhaust Fans:
EF-1. Shall be started/stopped on a signal from factory thermostat (90F
adjustable) or the hydrogen sensor provided with the battery charging system.
When the hydrogen level in the space exceeds the set point, the fan shall run
until shut down by the battery charging system. When the fan is cycled on, the
operated dampers in the wall louver and fan inlet shall open and when the fan is
not in operation the dampers shall be in the closed position.
EF-2: Shall be started/stopped manually or by the energy management system.
The fan shall run continuously. The two position dampers in the louver and at
the fan shall be open when the fan is in operation and closed when the fan is off.
The fan shall be turned off on a signal from the fire alarm system.
END OF SECTION 25 09 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL ELECTRICAL PROVISIONS
REEDLEY, CA. SECTION 260100 - 1
SECTION 26 01 00 - GENERAL ELECTRICAL PROVISIONS
PART 1 GENERAL
1.1 RELATED DOCUMENTS:
A. Contract Requirements: The foregoing GENERAL CONDITIONS, SPECIFIC
CONDITIONS, and supplements thereto and all requirements of Division 1 of these
Specifications shall form a part of this Section with the same force and effect as
though repeated herein. The provisions of this Section shall apply to all of the
following Sections of Division 26 of these Specifications. All applicable portions of the
work under Division 26 and Division 25 (Electrical Work) shall conform fully to all
provisions of all other Division 26 sections along with other Sections of these
Specifications including, but not limited to the following:
GENERAL - STANDARDS, SUBMITTALS, SHOP DRAWINGS, REVIEW,
INSPECTION Sections
EXCAVATING, FILLING, GRADING: DIVISION 2 - SITEWORK
CONCRETE: DIVISION 3
MECHANICAL: DIVISION 25 - MECHANICAL
B. Codes and Regulations: All electrical equipment and material and its installation shall
conform to the current requirements of the following authorities.
1. California Code of Regulations, Title 8-Industrial Safety.
2. California Code of Regulations, Title 19-Public Safety.
3. California Code of Regulations, Title 24, Part 1, Administrative Regulations.
4. California Building Code, California Code of Regulations, Title 24-Part 2, 2013
edition.
5. California Electrical Code, California Code of Regulations, Title 24-Part 3, 2013
edition.
6. California Mechanical Code, California Code of Regulations, Title 24-Part 4.
7. California Plumbing Code, California Code of Regulations, Title 24-Part 5.
8. California Fire Code (based on the National Fire Code - NFPA).
9. Regulations of the Division of the State Architect of the State of California, Office of
Regulation Services.
10. Pacific Gas and Electric Service Requirements.
NOTE: Where two or more codes conflict, the most restrictive shall apply. Nothing in
these Plans and Specifications shall be construed to permit work not conforming to
applicable codes.
C. Test and Standards: The tests, standards, or recommended procedures of the
following agencies shall relate to all parts of these Specifications and shall be
considered a minimum:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL ELECTRICAL PROVISIONS
REEDLEY, CA. SECTION 260100 - 2
1. American National Standards Institute (ANSI).
2. Underwriters Laboratories, Inc. (UL).
3. National Electrical Manufacturers Association (NEMA).
4. Electrical Testing Laboratories (ETL).
5. National Fire Protection Association (NFPA)
6. Insulated Power Cable Engineers Association (IPCEA).
7. Institute of Electrical and Electronic Engineers (IEEE).
8. Illumination Engineering Society (IES).
9. National Electrical Testing Association, Inc. (NETA)
1.2 SUMMARY OF WORK:
The Electrical Contractor shall provide all materials, tools, equipment, labor and
services necessary to furnish and install complete working electrical systems as shown
on the Plans and described within these Specifications. The Electrical Contractor shall
furnish all power supplies, disconnects, controls, and any other work as called for in the
Division 25 specifications and plans as well as all Electrical and Electrical related work
as called for in the Division 26 specifications and plans. In addition, all conduit required
by Divisions 27 and 28 and the associated drawings. All systems, at project completion
and before final acceptance, shall be demonstrated to have a complete and working
functional operation. The work includes but is not specifically limited to items indicated
below.
A. Demolition and Phasing:
1. De-energize, disconnect and remove electrical feeds to equipment being removed
or relocated.
2. Remove or modify electrical installation in areas of remodel and demolition.
3. Make temporary feeds and connections to areas and equipment to allow phased
construction and operation.
B. Electrical Distribution:
1. New panelboards and related equipment.
2. Conduits and feeders for electrical power and control.
C. Building and Mechanical Systems:
1. Complete lighting and power systems.
2. Electrical work associated with mechanical equipment.
3. Conduit and support system for installed telephone and computer signal systems
by others.
D. Communications Distribution:
1. Conduit and support system for Video Surveillance, Security, Fire Alarm, Public
Address, and Clock Systems by others.
E. Permits and fees relating to electrical work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL ELECTRICAL PROVISIONS
REEDLEY, CA. SECTION 260100 - 3
END OF SECTION 26 01 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 1
SECTION 26 10 00 - BASIC ELECTRICAL REQUIREMENTS
PART 1 GENERAL
1.1 DESCRIPTION AND INSTALLATION OF SYSTEMS:
A. The electrical drawings are diagrammatic and do not necessarily show all raceways,
wiring, number or types of fittings, offsets, bends or exact locations of items required by
the electrical systems. Items not shown or indicted, which are clearly necessary for
proper operation or installation of systems shown, shall be provided at no increase in
contract price.
B. The exact routing of systems and location of devices and equipment shall be governed
by coordination with other trades, and structural and architectural conditions. The
Architect or Electrical Engineer reserves the right, at no increase in contract price, to
make reasonable changes in location of electrical equipment or wiring system so as to
coordinate with other systems, to group them into orderly relationships, or to increase
their utility. Electrical Contractor shall verify requirements in this regard prior to
roughing in.
C. Install electrical work in cooperation with other trades, make proper provisions to avoid
interferences, and coordinate with structural and architectural feature in a manner
approved by the Architect or Electrical Engineer. All changes caused by neglect to
make such provisions shall be at Electrical Contractor's expense. Provide offsets and
special fittings, as required to facilitate installation of the work.
D. When a particular product or type of product is specified with a manufacturer's
designation, the latest published specifications, installation, and construction
information of the manufacturer shall constitute the minimum acceptable standard. Any
substitutions shall be made in accordance with Paragraph 1.6 SUBSTITUTIONS.
1.2 EXAMINATION OF DOCUMENTS AND SITE:
A. Before submitting a proposal each bidder shall carefully examine the electrical,
mechanical, architectural, and structural drawings and specifications. He shall also visit
the sites and fully inform himself as to all existing conditions and limitations applying to
the work. If, after such examination and study, it appears that any change from the
drawings and specifications should be allowed, the bidder shall so state in writing
together with any change in cost involved.
B. By the act of submitting a proposal, each bidder shall be deemed to have made such
examinations of the drawings and specifications and premises, and it will be assumed
that he is therefore familiar with the entire scope of the project and has based his
proposal upon the work described in the plans and specifications and upon all existing
conditions and limitations applying to his work.
1.3 EXECUTION:
A. Workmanship: The work shall be performed by competent licensed electrician, skilled
in the particular phase of the work entailed. The work shall be first class throughout,
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 2
neat, accurate and in full accordance with the intent of these specifications, and to the
satisfaction of the Architect or Electrical Engineer.
B. Safety: All standard safety procedures as set forth by OSHA, CCR, and California
Division of Industrial Safety shall be strictly adhered to.
C. Coordination: The Electrical Contractor shall familiarize himself with the work of other
crafts so as to be able to provide electrical service of correct size, voltage, and other
requirements to any equipment to be installed. The installations shall coordinate as to
location and time, and interference causing delays and non-acceptable construction
shall be avoided.
1. Prior to commencing construction the Electrical Contractor shall arrange a
conference with the Mechanical and Plumbing Contractors and sub-contractors as
well as equipment suppliers, and shall verify types, sizes, locations, requirements,
controls, and diagrams of all equipment furnished by them. Prior to roughing in, he
shall inform the Architect and Electrical Engineer, in writing, that all phases of
coordination of this equipment have been covered.
2. Exact equipment rough-in locations shall be verified from shop drawings.
D. Cutting and Repairing: The Electrical Contractor shall do all cutting necessary for the
proper installation of his work, repair any damage done by himself or his workmen, and
coordinate his work with that of others. No cutting or patching shall be done without
approval of the Architect or Electrical Engineer. Round holes through concrete slabs or
walls shall be core drilled with a diamond drill, rectangular openings shall be cut with a
diamond saw. In no case shall any concrete beam or column be cut.
E. Sleeves and Openings: The Electrical Contractor shall be responsible for all sleeves
and openings through walls and floors required by electrical work. All openings around
conduits in sleeves shall be sealed with a material of equal fire rating as the surface
penetrated. Openings not utilized shall be temporarily sealed in a similar manner. All
required sleeves shall be furnished to and coordinated with the General Contractor.
F. Access to Equipment:
1. Access Doors: All concealed equipment, controls, etc., shall be provided with
access doors as called for in the Specifications which shall be furnished by the
Electrical Contractor of this section for work of this section. Installation shall be the
responsibility of the trades in whose surfaces they will be installed. Access doors
are not required in removable ceilings.
2. Equipment shall be installed in readily accessible locations, or means of access
provided. Equipment will be deemed to be accessible only if all normal
maintenance and operation can be performed with ease by an average sized
person.
G. Cleaning and Painting: All exposed work shall be thoroughly cleaned upon completion
of work. Panelboard enclosures, fixtures and equipment, where finish has been marred
in shipment or installation, shall be completely refinished. Minor finish damage shall be
rectified as indicated by the Architect or Electrical Engineer. Electrical Contractor shall
remove from the site all waste and rubbish resulting from his work.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 3
H. Permits and Fees: For work of this Specification Division, Electrical Contractor shall
secure necessary permits and licenses, pay fees and deposits, and arrange for
inspection, as required by applicable governmental rules, regulations, codes, and
ordinances.
1.4 QUALITY CONTROL:
A. Supervision: The Electrical Contractor shall personally, or through a competent
representative, constantly supervise the work from beginning to completion and final
acceptance. He shall cooperate fully with the inspection authorities in the provision of
information and access to the work. He shall, to the best of his ability, maintain the
same job foreman throughout the life of the project unless a replacement is requested
or authorized by the Architect or Electrical Engineer.
B. Inspection and Tests: The Electrical Contractor shall furnish all labor and test
equipment required to fully test and adjust the equipment installed under this
specification and demonstrate its proper operation, in accordance with the General
Conditions, and the following:
1. Arrange for all tests and inspections and provide minimum one (1) week prior
notice to the Architect or Electrical Engineer.
2. A test must demonstrate that each piece of equipment, outlet, fixture, device, and
appurtenance is in sound operating condition and in proper cooperative relation to
associated equipment.
3. All tests shall be conducted under supervision of the Owner or his designated
representative, and any defects of any nature which are apparent as a result of
such test shall be made correct to the satisfaction of the Architect or Electrical
Engineer before final acceptance is made.
4. No equipment shall be tested, or operated for any other purpose, such as checking
motor rotation, until it has been fully checked in accordance with the
manufacturer's instructions.
5. Check and tighten nuts, bolts, lugs, and similar elements of equipment;
switchboards, motor control centers, busways, panels, etc. Final torquing shall be
done in the presence of the Owner's inspecting representative.
6. Submit complete test reports with maintenance manual submission.
C. Work Correction: Any portion of the work that does not perform satisfactorily or any
defects that are disclosed by testing shall be corrected by Electrical Contractor at his
expense before work will be accepted.
1.5 GROUNDING:
A. The conduit system supports, cabinets, switchboards, etc., and neutral conductors
must be permanently and effectively grounded by means of approved ground clamp, in
accordance with the electrical safety orders of the Department of Industrial Relations of
the State of California.
B. The Electrical Contractor shall exercise every precaution to obtain good contacts at all
panel boxes, pull boxes, etc. Where it is not possible to obtain good contacts, the
conduit shall be bonded around the boxes with a #6 B&S gauge, rubber covered,
double braided wire with ground clamps.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 4
C. Equipment and raceway bonding procedures shall be rigidly maintained and meet all
jurisdictional requirements of codes and regulations.
1.6 SUBSTITUTIONS:
A. Those products, or types of products, listed and specified are intended to set the
standard for quality, design, and installation procedure required for the project. The
Electrical Contractor shall not substitute other materials, products or systems without
the written approval of the Architect or Electrical Engineer. All substitution requests
must be submitted prior to bid.
1. Electrical Contractor's Options:
a. Product specified only by reference standards: Select any product meeting
standards.
b. Product specified by naming several products and/or manufacturers: Select
any product and/or manufacturer named.
C. Product specified by naming several products and/or manufacturers and
reference standards: Select any product meeting standards. Product
and/or manufacturer names indicate products and/or manufacturers that
meet standards.
d. Product specified by naming only product: Select product specified.
e. Product specified by naming one of more products and stating "or
equivalent" in front of specified product: Select any product named or
submit request for substitution for any product not specifically named in
accordance with Paragraph 1.06.
B. All requests for substitution shall be made in accordance with Division 1 and the
General Conditions.
C. Cost to Electrical Contractor or Bidder for review of Substitution Request:
1. Each review of a Substitution Request by the Engineer will be billed to the
submitter (Electrical Contractor or Bidder) at an hourly rate of$200.00 an hour, two
hour minimum for each review, whether approved or rejected.
a. The Engineer may waive the review cost if in his sole opinion the submittal
was complete and the time involved in the review was not substantial, and
it was in the best interest of the Owner.
D. All requests for substitution shall be in writing and shall indicate all information required
thereon, including an itemized comparison of proposed substitution with specified
product(s). Representative samples may be required for determination of equality.
E. All proposed substitution shall be a standard product of the firm, under current
manufacture and be a catalog item at time of bid.
F. In making request for substitution, Electrical Contractor can attest that:
1. He personally investigated proposed product or method, and determined that it is
equal or superior in all respects to that specified.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 5
2. He will provide the same guarantee or warranty for substitution as for product or
method specified.
3. He will coordinate installation of accepted substitution into Work, making such
changes as may be required for Work to be complete in all respects.
4. He waives all claims for additional costs related to substitution which subsequently
become apparent.
G. Submit three (3) copies of substitution request prior to submittals required in
accordance with Paragraph 1.6.
1.7 SUBMITTALS:
A. Make submittals for all material to be used on the project, whether as specified or
substitutions, within thirty (30) days after award of Contract by the Owner. Reference
the General Conditions and Division 1 Section 01 31 13 for procedures and
administration of submittals for this project in addition to the following:
1. All submittals shall be organized in an electronic folder, identified by Project Title
and Section.
2. Identify each item by manufacturer, brand, trade name, number, size rating, and
whatever other data is necessary to properly identify and check materials and
equipment. Words "as specified" are not sufficient identification.
3. Identify each submittal item by reference to specifications section paragraph in
which item is specified, or Drawing or Detail number.
4. All submittals shall be submitted in complete groups, e.g., all light fixtures at one
time. No partial or incomplete submittals will be accepted.
5. Organize submittal in the same sequence as they appear in specification sections,
articles, or paragraphs.
6. Provide detailed index listing for all submittals.
B. Product Data: See Prolog/Converge per Division 1 Section 01 31 13 for
submittals for this project. Submit separated in groups, as follows:
1. Basic Site Components
a. Conduits and raceway types required, including fittings
b. Concrete pull-boxes, vaults, and manholes
C. Electrical Identification items
d. Concrete coloring
2. Basic Materials
a. Conduits and raceway types required, including fittings
b. Electric wire, cable and connectors
C. Electrical boxes and fittings
d. Wiring devices
e. Each type of support, anchor, sleeve, and seal
f. Fire stopping Material
g. Electrical Identification items
h. Junction Boxes
i. Time Clocks
j. Terminal Cabinets
3. Distribution Equipment
a. Switchboards
b. Transformers
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 6
C. Transfer switches
d. Panelboards
e. Disconnects and Starters
f. Terminal Cabinets
4. Lighting
a. Fixtures
b. Lighting Controls
5. Any Additional System
C. Shop Drawings: Upon product review, submit shop drawings showing physical
arrangement, wiring diagrams, construction details, finishes, materials used in
fabrication, provisions for conduit entrance, access requirements for installation and
maintenance, physical size, electrical characteristics, foundation and support details,
weight, power sources, circuit numbers. Shop drawings shall be compatible with the
Contract Drawings and Specifications.
Show wiring as actually installed, connected, and identified for this specific project.
Include identification of cables and cable conductors.
Shop and instruction drawings shall cover the equipment or device to be installed and
not merely the general class of such equipment or device.
Submit four prints and one reproducible as follows:
1. Panelboards
2. Special Manholes and Vaults
D. Samples: Submit single, factory boxed production run samples identical to equipment
to be supplied, as follows. Samples will be retained for analysis and comparison
purposes.
1. Receptacles
2. SPST and 3-way switches
3. Base cover plates
1.8 DOCUMENTATION:
A. Construction Record Drawings: The Electrical Contractor shall furnish to the Engineer,
in accordance with the GENERAL REQUIREMENTS, a complete set of "as
constructed" drawings which clearly indicate all deviations from the basic contract
drawings, including exact dimensioned locations and depths for all stubbed conduits,
location and size of spare conduits and conductors, all new and uncovered existing
work outside the buildings, power feeder runs, and communications "primary" conduit
runs. Corrections and changes shall be kept up-to-date at all times.
B. All submittals and shop drawings shall be resubmitted with record drawings showing all
revisions and changes made, clearly marked with field termination wire so as to reflect
actual construction record conditions. Revision and changes will be enumerated and
new dates of drawings shown. Grouped submittals shall be combined into loose leaf
binders.
C. Structural Conditions:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 7
1. Location as indicated on the drawings show the arrangements desired for the
principal apparatus, fixtures, etc., and shall be followed as closely as possible.
Proper judgment shall be exercised in carrying on the work to secure a neat
arrangement of the electrical systems and to overcome local difficulties and
interferences of structural conditions wherever encountered.
2. Notching and boring of structural members must be held to an absolute minimum.
Electrical Contractor shall lay out his work and obtain the approval of the Owner's
Representative for necessary holes and notches before proceeding with the work.
Where notches and holes are approved, they shall be carefully held to the
minimum sizes actually required.
D. Cutting and Patching: The Electrical Contractor shall be responsible for the cutting and
patching of rough or finish work required by his installation. Patching shall be of the
same material, finish and workmanship as the original work, and when required by the
Owner's Representative, done by mechanics of the original trade.
1.9 SEISMIC RESTRAINT AND ANCHORAGE:
A. Provide complete seismic anchorage and bracing for the lateral and vertical support of
conduit and electrical equipment in accordance with latest edition CBC, Chapter 16 and
Table 16A-0, and all provisions of this Section.
B. Submit calculations prepared and signed by a Structural Engineer licensed in the State
of California, showing compliance with the above for all electrical equipment weighing
more than 50 pounds, excepting items corresponding exactly in configuration and
weight to those specified and detailed. Where anchorage details are not shown on
drawings, the field installation shall be subject to the approval of the Architect and
Electrical Engineer.
C. All equipment mounted on concrete shall be secured with steel stud expansion anchors
requiring a drilled hole. Power driven anchors are not acceptable. Minimum spacing
shall be ten (10) diameters center to center and five (5) diameters center to edge of
concrete. Maximum allowable stresses for tension and shear shall be 80% of the ICBO
test report values. Hilti, Phillips.
1.10 EXISTING SUB-SURFACE STRUCTURES
The Electrical Contractor shall examine all record drawings made available by the
Owner to locate existing underground systems, utilities, conduits, and pipes prior to
installing the electrical distribution system. The Electrical Contractor shall also examine
the site for possible locations of sprinkler pipes. Any damage done to the existing
systems during the course of the electrical work, whose locations could be reasonably
determined, shall be repaired to the satisfaction of the Owner and the utility or agency
involved, at the expense of the Electrical Contractor.
1.11 PORTABLE OR DETACHABLE PARTS:
The Electrical Contractor shall retain in his possession and shall be responsible for, all
portable and detachable parts or portions of the installation, such as fuses, keys, locks,
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 8
adapters, locking clips, and inserts, until final completion of his work. These parts shall
be itemized and delivered to the Owner at Project Closeout.
1.12 OPERATION AND SERVICE MANUALS:
A. The Electrical Contractor shall prepare manuals describing the operations, service, and
maintenance requirements of, and complete parts lists for all electrical equipment.
B. Equipment: Equipment described in the manual shall include all equipment listed under
"Submittals", and all other auxiliary miscellaneous systems.
C. Information contained in the manual shall consist of 8'/2" x 11" size catalog data on
each item, together with parts lists, description of operation, maintenance information,
shop drawings, wiring and riser diagrams, and test reports as installed. Catalogs and
data in the manuals shall be neat, clean copies. Drawing shall be accordion folded to
letter size and installed in an envelope within the manual. An index shall be provided,
which shall list all contents in an orderly manner with the respective equipment
supplier's name, address and telephone number, and the manufacturer's
recommended servicing instructions. Diagrams shall be complete for each system
installed. Provide divider sheets with identifying tabs between each category.
1.13 INDEPENDENT TESTING AND CERTIFICATION:
A. General: The Electrical Contractor shall provide the services of an independent testing
and certification company acceptable to the Owner to inspect, test, and certify the
electrical equipment and installation as indicated by Division 26 Specification Sections
and as generally summarized as follows.
1. The testing firm shall provide all material, equipment, labor, and technical
supervision to perform such tests and certifications.
2. It is the purpose of these tests to assure that all tested electrical equipment is
operational and within industry and manufacturer's tolerances and is installed in
accordance with design specifications.
3. The tests and shall determine suitability for energization.
B. Qualifications of Testing Firm:
1. The testing firm shall be a corporately-and financially independent testing
organization that can function as an unbiased testing authority, professionally
independent of the manufacturers, suppliers, and installers of equipment or
systems evaluated by the testing firm.
2. The testing firm shall be regularly engaged in testing of electrical equipment
devices, installations, and systems.
3. The testing firm shall meet OSHA criteria for accreditation of testing laboratories,
or be a Full Member Company of the International Electrical Testing Association
(NETA).
4. The lead, on-site, technical person shall be currently certified by the International
Electrical Testing Association (NETA) or National Institute for Certification in
Engineering Technologies (NICET) in electrical power distribution system testing.
5. The testing firm shall utilize engineers and technicians who are regularly employed
by the firm for testing services.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 9
6. The terms used here within, such as Testing Company, shall be construed to
mean the testing firm.
C. Methods: Testing methods and equipment utilized by the Testing Firm shall be in
accordance with applicable sections of the NETA "Acceptance Testing Specifications
for Electrical Power Distribution Equipment and Systems".
D. Testing shall be performed and certification approved before energy is applied to items
tested.
E. All test equipment will be noted with factory calibration certification and date.
F. Any item dismounted or reconnected by the Electrical Contractor after test and
certification will be retested and recertified before energy is applied.
G. Any items not meeting the Manufacturer's tolerances or performance criteria shall be
corrected by the Electrical Contractor and retested and recertified before energy is
applied.
H. Tests and certification report shall be submitted in accordance with the applicable
sections of these specifications. Tests shall be presented in an organized binder with
subheadings for all line ups and tests performed with results therein.
I. Items not passing Manufacturer's recommended tolerances will be enumerated on a
separate set of sheets before each section.
J. Coordination: The Electrical Contractor shall notify Architect or Engineer of testing
schedule a minimum of one (1)week in advance of performance of any test.
K. Testing Firm Test and Certification Summary:
1. Main Switchboards
2. Solid State Circuit Breakers
3. Ground Fault Protected (GFI) circuit breakers
4. Isolation Panelboards
1.14 PENETRATIONS:
A. Fire Rated Surfaces: Conduits or cables passing through fire rated walls, floors,
ceilings, partitions, etc., of greater than one (1) hour construction shall be sleeved.
Conduits shall be centered in the sleeve and the annular space around the conduit or
cable shall be sealed with fire rated materials in accordance with California State Fire
Marshal requirement and approvals and as called for in the specifications.
B. Concrete and Masonry: All conduits passing through concrete or unit masonry walls,
floors, or foundations shall be sleeved to allow seismic movement of the building
structure without overstressing of the conduit and its connections.
1.15 PRELIMINARY OPERATION:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC ELECTRICAL REQUIREMENTS
REEDLEY, CA. SECTION 261000 - 10
The Owner reserves the right to operate portions of the electrical system on a
preliminary basis without voiding the guarantee or relieving the Electrical Contractor of
his responsibilities.
1.16 GUARANTEES:
All material furnished and installed under this Contract shall be new and free from all
defects and shall be guaranteed for a minimum period of one (1) year from date of
acceptance of the work. Should any trouble develop during this period, due to
defective material or faulty workmanship, this Electrical Contractor shall furnish all
necessary materials and labor to correct the trouble without any cost to the Owner.
Any defective material or inferior workmanship noticed at the time of installation shall
be corrected immediately to the entire satisfaction of the Owner or his representative.
1.17 DEMOLITION:
A. Demolition: The Electrical Contractor shall modify or remove the existing electrical
installation as required by the building alterations within the area of alteration work. All
removed material not to be reused or retained by the Owner shall become the property
of the Electrical Contractor and shall be removed from the site. Electrical Contractor
shall be responsible for de-energizing electrical circuits in demolition area so as to
ensure safe working conditions.
In walls, and ceilings to be removed, do circuit check to determine if areas beyond work
will be affected and provide temporary feeds to them; disconnect and remove all
electrical devices, fixtures and other devices. Cut off and seal all unused floor
penetrations for existing wire not utilized. Remove conduit in exposed location.
Abandon in place unused conduit in concealed locations after removing wire.
B. Continuity of Service:
1. The Electrical Contractor shall permanently reroute or relocate existing wiring
and/or equipment which is required, while maintaining existing systems in use.
2. Utility Work Approval: The Electrical Contractor shall give required notice and
obtain approval from the utility company prior to commencing work.
3. Service outages shall be kept to an absolute minimum. There shall not be any
interruption of power to any building or portion of a building that is not agreed upon
by the Owner and Engineer in writing. Any outages shall occur only at times
convenient to the Owner, predominately between the hours of midnight and 6:00
a.m. The Electrical Contractor's necessary work associated with outages shall
commence upon de-energization and shall continue uninterrupted until normal
power is restored. Electrical Contractor shall maintain optimal crew size to keep
outage time to a minimum.
4. Premium Pay: Any overtime work required to comply with the above paragraph
shall be included as part of this contract. No additional payments will be
authorized for work performed on weekends, holidays or other than normal
working hours, as required to schedule outages at Owner's convenience.
END OF SECTION 26 10 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL RELATED WORK
REEDLEY, CA. SECTION 261110 - 1
SECTION 26 11 00 - ELECTRICAL RELATED WORK
PART 1 GENERAL
1.1 SCOPE:
A. Provide all related work required for installation of electrical systems.
B. Types of electrical related work specified in this section include the following:
1. Excavating for Electrical Work:
Underground electrical wiring and service tunnels.
Independent (isolated)foundations.
Underground electrical vaults.
2. Concrete for Electrical Work:
Equipment and pole fixture bases, conduit caps.
Lean concrete backfill to support electrical work.
Encasement of electrical work.
Underground structural concrete to accommodate electrical work.
Vaults for electrical work.
Electrical equipment foundations and mounting pads.
Rough grouting in and around electrical work.
Patching concrete which has been cut to accommodate electrical work.
1.2 PROJECT CONDITIONS:
A. Existing Utilities: Locate and protect existing utilities and other underground work in
manner which will ensure that no damage or service interruption will result from
excavating and backfilling.
B. Protect property from damages which might result from excavating and backfilling.
C. Protect persons from injury at excavations by barricades, warnings, and illumination.
D. Coordinate excavations with weather conditions to minimize possibility of washouts,
settlements and other damages and hazards.
E. Keep the work site clean and free from rubbish and debris. The Electrical Contractor
shall also abate dust nuisance by cleaning, sweeping, and sprinkling with water, or
other means as necessary.
F. Materials and equipment shall be removed from the site as soon as they are no longer
necessary; and, upon completion of the work and before final inspection, the entire
work site shall be cleared of equipment, unused materials, and rubbish so as to present
a satisfactory clean and neat appearance. All cleanup, dust control, and project site
maintenance costs shall be included in the Electrical Contractor's bid.
1.3 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS:
A. Unless otherwise provided, the Electrical Contractor shall repair or replace all existing
improvements (e.g., curbs, sidewalks, driveways, fences, signs, utilities, street
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL RELATED WORK
REEDLEY, CA. SECTION 261110 - 2
surfaces, structures, etc.) damages or removed as a result of his operations. Repairs
and replacements shall be at least equal to existing improvements and shall match
them in finish and dimension.
B. Trees, lawns and shrubbery not designed for removal shall be protected from damage
or injury. If damaged or removed because of the Electrical Contractor's operations,
they shall be restored or replaced in as nearly the original condition and location as is
reasonably possible. Lawns shall be reseeded and covered with suitable mulch.
PART2 PRODUCTS
2.1 BACKFILL ELECTRICAL WORK:
A. Bottom of Trench to 6" above Conduit Material: Well graded sand.
B. Backfill Material: Sandy or silty loam, free of lumps, laid in 6" layers, uniformly mixed to
proper moisture and compacted to required density.
2.2 CONCRETE WORK:
A. Equipment Bases: 2500 psi concrete and reinforcing in accordance with Division 03
concrete.
B. Pole Fixture Bases: 3000 psi concrete and reinforcing in accordance with Division 03
concrete.
C. Conduit Cap/Encasement: 2000 psi concrete slurry.
PART 3 EXECUTION
3.1 EXCAVATING FOR ELECTRICAL WORK:
A. General: Do not excavate for electrical work until work is ready to proceed without
delay, so that total elapsed time from excavation to completion of backfilling will be
minimal.
B. Excavate with vertical-sided excavations to greatest extent possible, except where
otherwise indicated. Where necessary, provide sheeting and cross-bracing to sustain
sides of excavations. Remove sheeting and cross bracing during backfilling wherever
such removal would not endanger the work or other property. Where not removed, cut
sheeting off at sufficient distance below finished grade to not interfere with other work.
C. Width and Cover: Unless otherwise noted, minimum earth cover above conduit shall
be 36". Excavate for conduit with 6" to 9" clearance at both sides of conduit, except
where otherwise shown or required for proper installation of joints and fittings.
Excavate for other electrical work to provide minimum practical but adequate working
clearances.
D. Depth for Subbase Support: Where installation of subbase material is indicated,
excavate for installation of subbase material in depth indicated or, if not otherwise
indicated, 6" below bottom of work to be supported.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL RELATED WORK
REEDLEY, CA. SECTION 261110 - 3
E. Excavate near large trees (within drip line) by hand, and protect the root system from
damage or dry out to greatest extent possible. Verify trench locations with Architect or
Engineer prior to trenching. Maintain moist condition for root system and cover
exposed roots with burlap.
F. Store excavated material (temporarily) near excavation, in manner which will not
interfere with or damage excavation or other work. Do not store under trees (within drip
line).
1. Retain excavated material which complies with requirements for backfill material.
2. Dispose of excavated material that is either in excess of quantity needed for
backfilling or does not comply with requirements for backfill material. Remove
unused material from project site, and dispose of in lawful manner.
3.2 DEWATERING:
Maintain dry excavations for electrical work by removing water. Project excavations
from inflow of surface water. Pump minor inflow of ground water from excavations.
3.3 BACKFILLING:
A. General: Except as otherwise indicated, backfill with properly qualified backfill material.
B. Backfill with well graded sand to 6" above conduits.
C. Condition backfill material by either drying or adding water uniformly, to whatever extent
may be necessary to facilitate compaction to required densities. Do not backfill with
frozen soil materials.
D. Backfill simultaneously on opposite sides of electrical work, and compact
simultaneously. Do not dislocate the work from installed positions.
E. Backfill excavations in 6" high courses of backfill material uniformly compacted to the
following densities (% of minimum density, ASTM D 1557), using power-driven hand-
operated compaction equipment. If backfill is determined to be suitable and required
compaction is demonstrated by laboratory test, water compaction in 6" layers may be
used, subject to review by Engineer.
Lawn/Landscaped Areas: 85%
Paved Areas, Other Than Roadways: 90%
Roadways: 95%
F. Backfill to elevations matching adjacent grades, at time of backfilling excavations for
electrical work.
G. Compaction Test: Demonstrate proper compaction by testing at one-half of the trench
depth. Perform three (3)tests per 100' of trench.
H. Encase all underground conduits with concrete to 6" above conduit material before
backfilling. PG&E conduits shall be capped with 3" concrete and the top the capping
colored red.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL RELATED WORK
REEDLEY, CA. SECTION 261110 - 4
3.4 BORING AND CUTTING:
A. Where trench crosses concrete walks or paved areas bore or saw cut and patch as
required for conduit installation. Boring shall be by screw auger or dry ramming.
Where soil conditions warrant, (water boring may be allowed on a case by case basis
upon approval of the Engineer). No water jetting shall be allowed.
B. Bore and saw cut as indicated on the plans, or where not indicated; bore under
concrete, paved, tiled or permanent surface 20'-0" wide or less. Saw cut permanent
surfaces wider than 20'-0" with Engineer's approval.
C. Depth of saw cutting shall be no greater than '/4" below slab thickness.
3.5 PERFORMANCE AND MAINTENANCE, EXCAVATION WORK:
A. Subsidence: Where subsidence is measurable or observable at electrical work
excavations during general project warranty period, remove surface (pavement, lawn,
or other finish), add backfill material, compact, and replace surface treatment.
B. Restore appearance, quality and condition of the surface or finish to match adjacent
work, and eliminate evidence of restoration to greatest extent possible.
3.6 INSTALLATION OF CONCRETE WORK:
A. Install concrete for electrical work in accordance with Division 03 and the drawings.
B. Exposed fixture bases and enclosures shall be Architectural Grade Concrete in
accordance with Division 03.
END OF SECTION 26 11 10
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 1
SECTION 26 20 00 - BASIC MATERIALS AND METHODS
PART 1 GENERAL
1.1 SCOPE:
Furnish and install material and equipment as indicated on drawings and as specified.
1.2 MATERIALS AND EQUIPMENT:
Shall be new and of the best quality used for the purpose in good commercial practice.
1.3 UL APPROVAL:
All material and equipment within the scope of the UL reexamination service shall be
approved by the Underwriters Laboratories for the purpose for which they are used and
shall bear their label.
1.4 STORAGE:
All material and equipment shall be stored in a manner to prevent damage or corrosion.
Equipment with components which can be damaged by moisture shall be placed in
special heated storage facilities.
1.5 DRAWINGS:
Drawings for all equipment are intended to be diagrammatic only. Any location not
actually dimensioned is not to be considered as necessarily final or accurate. Exact
locations must be determined in the field from the requirements of the equipment that is
to be installed.
1.6 COORDINATION:
Before rough-in of any utility lines, services, and feeders, or of any equipment, the
Electrical Contractor must coordinate his work with that of other crafts and trades so
that these services shall be installed in their proper locations and without interference to
the equipment or building structure. This will require cooperation among all crafts and
trades, the Inspector, and General Contractor, along with study of shop drawings and
the building plans.
1.7 ELECTRICAL WORK EXPOSED TO WEATHER:
A. All electrical devices and equipment installed in exposed locations shall be protected by
suitable NEMA type 3R enclosures, cast steel boxes with gasketed steel covers, or
other Engineer approved methods.
B. All ferrous metal portions of electrical work exposed to weather including conduits,
clamps, supports, etc. shall be hot-dipped galvanized.
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-1
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 2
1.8 SUBMITTALS:
A. Product Data: Submit manufacturer's data including specifications, installation
instructions, and general recommendations for each item submitted under submittals,
Section 261000, Paragraph 1.7. Submit calculations in accordance with Paragraph 1.9.
Reference Division 01, Section 01 31 13 for the procedures and administration of
submittals.
PART2 PRODUCTS
2.1 CONDUIT MATERIALS AND COMPONENTS:
A. Rigid Metal Conduit-Type RMC: All locations as follows excepting those specifically
indicated for EMT and PVC. All exterior locations above grade, in concrete walls and
slabs, or elsewhere shown on plans. Runs within, passing through or above hazardous
areas shall be rigid. RMC shall be new galvanized threaded, conforming to UL 6. All
couplings and connectors shall be threaded. RMC shall be specifically used on roofs or
on all surfaces of corridor and walkway coverings. Threadless fittings are not allowed.
B. Electrical Metallic Tubing-Type EMT: Interior dry locations above ground,
exposed only above 60" above floor in non-finished areas where not subject to
physical abuse or damage, and exterior walls and underside of eaves above 96"
above grade. EMT shall be new galvanized, conforming to UL 797, furnished in
10 foot lengths. In interior locations, EMT shall be coupled with steel setscrew
type connectors. In exterior locations EMT shall be coupled with steel
compression type couplings requiring the tightening of a nut in all locations.
Crimp type or die cast connectors or couplings are not acceptable. Connectors
to have nylon insulated throats.
C. Flexible Metal Conduit-Type FMC: Connections from junction boxes to lay-in
fluorescent fixtures in accessible ceilings only, 6' maximum. FMC shall be
flexible interlocking single strip zinc coated steel with an insulated copper
ground wire pulled with the conductors, conforming to UL
1. Aluminum FMC shall not be used. Minimum size 3/4". Fittings shall be steel
clamp type utilizing two (2) screws, galvanized steel with
nylon insulated throat type. FMC is not to be used for
connection to permanently fixed equipment.
D. Liquidtight Flexible Metal Conduit-Type LFMC: Connections to machinery and
equipment only. LFMC shall be flexible interlocking single strip steel conduit with liquid
tight exterior cover, with all connections made using galvanized steel liquid tight
connectors with "O" ring gaskets and nylon insulated throat and with copper ground
wire, American Brass Sealtight or equivalent, conforming to UL 1. LFMC maximum
length allowed is 36". LFMC is not to be used for connection to permanently fixed
equipment.
E. Rigid Polyvinyl chloride Conduit-Type PVC.: Underground locations and below vapor
barrier of slabs. No PVC shall be installed in slab floors or in exposed locations. PVC
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-2
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 3
conduit shall be schedule 40, Underwriters' Laboratories tested, furnished in 10'
lengths, conforming to UL 651-77.
F. Surface Metal Raceway: Type and locations as noted on the drawings. Provide
concealed connections. Paint to match adjacent surface unless noted otherwise.
2.2 OUTLET AND SWITCH BOXES:
A. Boxes shall be one piece die formed galvanized steel of shape and with fittings
necessary to suit location and use. Boxes shall be of sufficient size to contain all wires,
devices, and connection fittings required without crowding, minimum 2 gang for
receptacles. Ceiling and surface mounted boxes shall be minimum 4" square by 1'/2" or
octagonal. Plaster rings shall be provided where required. Boxes shall be used
wherever possible. Where voltages are mixed in the same box (120V/277V), install
welded partition barriers to separate the systems.
B. Exposed boxes shall be cast steel provided with steel gasketed weatherproof covers
and utilize only cast metal threaded hub type fittings.
2.3 WIRING DEVICES:
A. Wall Switches:
1. 120/277 Volt Switches: Quiet slow make, slow break design, toggle handle, with
totally enclosed case, rated 20 ampere, heavy duty specification grade conforming
to Federal Specification WS896. Provide matching two pole, 3-way, 4-way, and
key switches as required. Hubbell or ArrowHart 1221 series.
2. Switch and Pilot Light: Push action type with red handle, integral long-life neon
pilot light, rated at 15 ampere, 120 volts.
3. Color: Normal Lighting Circuits; provide ivory, gray, white, and brown colored
switches dependent upon room wall finish as directed by Architect. Emergency
power circuits; provide red colored switches.
4. Thermal switches where designated on plans or in specifications shall be
equivalent to Square D, Type "F", Class 2510. Thermal switch heater elements
shall be rated for overload protection of loads controlled. Switches for special
purposes, such as exhaust fans, boiler control, heaters, etc., shall be engraved
with 1/8" high letters on plates. Adhesive labels are not acceptable.
B. Receptacles:
1. Duplex Receptacles: Full gang size, polarized duplex, parallel blade, U-grounding
slot, specification grade conforming to Federal Specification WC596, rated at 20
amperes, 125 volts, designed for split feed service. Hubbell or ArrowHart 5352
series or equal.
2. Duplex Receptacle - Ground Fault Interrupting: Hubbell or ArrowHart #GF-5362
series or equal. Ground fault interrupting receptacles shall be required within six
(6)feet of all sinks and in exterior locations.
3. Nameplates: Provide engraved or embossed plastic for receptacles other than
standard duplex receptacles, indicating voltage, phase and amperes.
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-3
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 4
4. Color: Normal Power Circuits; Provide ivory, gray, white, and brown colored
receptacles dependent upon room wall finish as directed by Architect. Emergency
Power Circuits, provide red colored receptacles.
2.4 WALL PLATES:
A. Provide plate for each wiring device, or as required to protect or cover-up existing
conditions left exposed due to the removal of existing devices, conduits, or equipment.
B. Interior Flush: All locations unless noted otherwise, stainless steel (0.35") satin finish,
Sierra "S" series.
C. Weatherproof Plates: Steel, gasketed, for receptacles, provide spring loaded gasketed
doors. Provide at all weatherproof locations.
D. Where two gang boxes are required for single gang devices, provide special plates with
device opening in one gang and second gang blank.
E. Receptacle Plates: Each receptacle plate shall be identified with the panel number and
the circuit number. This identification shall be with engraved phenolic labels applied to
plate with permanent contact cement. Labels shall be 5/16" high, gray phenolic plastic,
with 1/8" high white engraved lettering. Special receptacles shall also indicate voltage,
phase, and amps.
F. Multi-Gang Switch Plates: Where three or more switches occur at a common location,
provide engraved labeling, '/4' high (black), on the switch plate(s) indicating areas or
fixtures served by each switch. Submit schedule to Engineer for approval.
G. Blank bushed or special outlet plates shall be provided for all signal systems outlets as
required.
2.5 FLOOR BOXES:
A. Floor Boxes: Concrete tight fully adjustable type with round brass faceplate, deep fill
type. Walker 886 series, Hubbell or Steel City equivalent.
B. Receptacle Floor Fitting: Brass, duplex flap Walker 895 series or equivalent.
C. Telephone Floor Fitting: Brass round opening, combination 2'/4" x 1", Walker 866 CK-1
series or equivalent.
2.6 WIRE:
A. Low Voltage - (Under 600 Volt):
1. Feeder and Branch Circuit Wire: Copper type THWN/THHN, 600 volt, from new
fresh stock, bearing UL label, delivered to site in unbroken packages; minimum
size 12 AWG. All 20/1 home runs over 180 feet from panel for 277 volt circuits,
and 100 feet from panel for 120 volt shall be increased to next larger size. All
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-4
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 5
conductors shall be stranded copper. All control, signal, and communication wires
shall be stranded. Fire alarm wire shall be solid.
2. High Temperature Wire: NEMA type AF or SFF-2 stranded, for fixture wires and
circuit runs within fixtures.
2.7 TERMINAL CABINETS:
A. Telephone and Signal System Cabinets:
1. Telephone and signal system cabinets for collection of individual device or outlet
homeruns, or mounting of equipment shall be 24" wide x 36" high x 6" deep unless
otherwise noted. Cabinets shall be provided with V fire treated plywood
backboard "Dricon", conforming with CBC Section 207, one piece per cabinet,
sized to maximum dimension of cabinet.
2. Cabinets shall be provided with vertical barriers as required separate conduits of
different signal systems, one partitioned area per system type; i.e. fire alarm, clock,
etc.
3. Cabinets located in finished areas; classrooms, corridors, storage rooms, etc. shall
be flush mounted, constructed to match lighting panelboards, with concealed flush
door hinges and concealed face panel trim clamps. Provide with flush lock keyed
to match panelboard locks.
4. Cabinets located in electrical rooms or electrical closets may be screw cover type
with continuous hinged door, surface or flush to match adjacent panels.
PART 3 EXECUTION
3.1 INSTALLATION OF CONDUIT RACEWAYS:
A. General: Install conduits in a neat manner, concealed except as noted. Mount conduits
directly to building structure with clamps or two hole straps where possible. Secure
straps with cadmium plated wood screws into wood, and machine screws into metal or
inserts preset in concrete. Where impractical to secure directly to structure, suspended
on conduit hangers. Wherever possible, group and rack multiple conduit runs.
1. Conduit Size: All branch circuit homeruns, and conduit runs containing more than
two (2) circuits shall be a minimum of V diameter.
B. Installation and Cleaning: Install free from dents, kinks and bruises. Plug ends at time
of installation to prevent entry of dirt or moisture. Thoroughly clean out conduits before
installing conductors. Thoroughly clean all exposed conduit exteriors.
C. Provide tagged pullwire in all empty conduits. Pullwire shall be 1/4" Kevlar high
strength measuring tape #39243 with a minimum breaking strength of 1250 pounds.
Leave 36" free coiled each end. Tagging all runs shall include the source and
destination locations.
D. Plastic conduit shall be installed in accordance with manufacturer's recommendations
and accepted trade practice. Where plastic conduit runs rise above ground in exposed
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-5
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 6
locations, the riser bend and riser shall be of 40 Mil PVC coated galvanized rigid metal
conduit installed according to rigid metal portion of this specification section.
E. All plastic, flexible, feeder and receptacle branch conduits shall carry a grounding bond
wire with the size as shown, or where not shown, as determined by applicable codes
for the ampacity of the circuit being carried.
F. Protective Coating: All metallic conduits installed in contact with earth, or in concrete in
contact with earth, shall be coated with a minimum 40 Mil PVC coating on all conduit
lengths and fittings. The coating shall correspond to ATSM D638-68, D1706, D140-64,
and D746-64T specifications and Federal Test Standard 141, Method 615z. Coating
shall be continuous without flaws showing exposed metal. Coating shall extend to the
device conduit is terminated to in exposed locations and 12" above grade in unexposed
locations. Tape wrapped conduit is not acceptable.
G. Conduits which stub-up from or through floor slabs shall be installed so that none of the
curved portion of the elbow is exposed. Conduits stubbed up shall be rigid type with
coupling installed flush floor to permit future conduit removal. Seal unused conduit with
a flush threaded pipe plug.
H. Conduit Routing: Route exposed conduits parallel or perpendicular to walls or floors.
Install conduits in masonry walls at time of wall construction. No conduits shall be run
under heavy equipment, footing or other structural elements. Where runs must cross
footings, install in sleeves per structural details.
I. Conduit Runs in Ceiling Areas: Conduits running above accessible ceiling shall be
routed parallel or perpendicular to ceiling system and structural members. All conduit
runs shall be coordinated to avoid conflicts with mechanical and structural systems,
lighting fixtures and ceiling support system. Conduits shall be installed as close to the
structure above as possible to avoid conflict with removal of ceiling panels. It is
specifically not permitted to attach or support conduit from ceiling system suspension
wire. Exposed cables shall be strapped to the structure above the accessible ceiling.
J. Conduits Penetrating Membranes: Where conduits penetrate wall or slab membrane
moisture barriers, penetration shall be sealed in accordance with the requirements of
applicable sections of these Specifications for"Thermal and Moisture Protection."
K. Conduits Penetrating Roof: Provide flashing and counter flashing making watertight
joints where conduits pass through roof or waterproofing membranes.
L. Escutcheons: Conduits penetrating wall, floors, or ceiling in exposed locations shall be
installed with appropriate escutcheon plates.
M. Separations: Coordinate with all other crafts to allow minimum of 12" running and 6"
crossing clearance at flues, hot water pipes, steam pipes, and heat sources. Keep
electrical conduits free from contact with all other piping runs of other systems or of
dissimilar metals.
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-6
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 7
N. Concrete Encased Conduits: All conduits installed underground shall be encased with
2,000 psi concrete to a minimum of 6" above the conduit. The top of concrete
encasements for feeds greater than 600 volts shall be colored red.
O. Conduits Crossing Building Joints: Conduits shall not be run in concrete slab or wall
construction where passing through an earthquake or expansion joint. At such
condition, conduit shall be run exposed or in furred ceiling space with 24" length of
flexible conduit crossing joints.
P. Conduits Penetrating Floors and Walls: Provide grouting around raceways where
penetrating floor slabs, concrete or masonry walls. At fire separation walls or floors,
use Engineer and CSFM approved expanding type intumescent foam, to maintain the
fire rating of the surface penetrated.
Q. Conduit Support: Support of conduit and tubing in steel stud walls shall be by #18
gauge steel wire, secured to steel bars or straps attached to steel studs. Conduits
rising vertically between wall studs shall be tied to a horizontal cross support attached
tightly to eliminate any movement.
R. Conduits Installed Below Floor Slabs: Conduits 1" diameter and smaller may be
installed below concrete slab vapor barriers or sand fill by shallow scraping and
recovering with earth as required to bury just below surface. Install to minimize
disruption to engineered fill. Conduits larger than 1" shall be trenched to a minimum
depth of 12" below slab and backfilled and compacted in accordance with Section
26110.
S. Conduits Installed in Area of Footings: Conduits installed in the area of footings shall
be installed per the applicable structural details and the electrical details for installing
conduits in the vicinity of footings.
T. Conduit Hangers:
1. Conduit hangers spaced at 8'-0" on center maximum with one hanger adjacent to
each outlet box, shall be installed wherever conduit cannot be directly attached to
structure. Hangers shall be secured to wood structures with steel brackets and
wood screws; to steel structures with appropriate clamps complete with positive
attachment restraining strap or hook rod to prevent slippage; and to concrete
structures with preset imbedded inserts or machine screws with expansion shields.
Preset inserts are preferred to provide a secure anchorage with greatest location
flexibility. Power or velocity driven type attachments will not be allowed. Complete
hanger installation shall provide a safety factor of five (5) based upon maximum
CEC allowed conduit fill.
2. Hangers for rigid conduit and EMT 2" and smaller in concealed spaces shall be
galvanized perforated type strap wrapped around raceway and bolted; then
fastened to structure as described above.
3. Hangers for exposed conduit and tubing suspended below ceilings shall be steel
rods '/4" size for up to 2" and 3/8" for larger size conduits, with adjustable pipe ring;
Steel City#C-149, Fee and Mason #199 or#201, or approved equivalent.
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-7
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 8
4. Trapeze type supports shall be used where conduits are run grouped together.
Such hangers shall consist of 3/8" minimum steel rods, structural steel channels,
and clamps of Kindorf, Unistrut, or approved equivalent manufacture.
5. Electrical Contractor shall furnish concrete inserts to General Contractor, and
coordinate location.
3.2 INSTALLATION OF JUNCTION BOXES AND INTERIOR PULL BOXES:
Locate pull boxes and junction boxes above removable ceilings or in electrical rooms,
utility rooms, or storage areas. No junction box shall be installed in an inaccessible
area. Exposed boxes shall be cast with gasketed weatherproof covers.
3.3 INSTALLATION OF EXTERIOR PULL BOXES AND MANHOLES:
A. Where pull boxes are used without bottoms, they shall be set on 3/4' crushed rock of a
volume equal to that of the pull box used.
B. Where pre-cast units are used, all joints are to be tongue and groove, sealed with a
suitable sealer.
C. Where conduits enter, they shall be properly bushed and extended a minimum 1/2" from
inside of wall into pull box.
D. All conduits entering pull boxes and manholes shall be sealed watertight with suitable
duct sealing compound.
3.4 INSTALLATION OF OUTLET AND SWITCH BOXES:
A. Mounting: Mount outlet boxes flush in finished areas other than mechanical rooms,
electrical rooms, and above removable ceilings. Boxes shall be set true and flush with
all necessary and correct adapters and/or plaster rings. All boxes set deeper than code
allowable shall be corrected by use of factory made extension rings such as Raco#976
or equivalent. Boxes in wood construction shall be mounted to support with wood
screws.
B. Device Locations: Locations of devices on plans are approximate only. Electrical
Contractor shall study the architectural and structural plans and locate the outlets so
that his work is coordinated with the work of others and the fixtures and devices present
a pleasing and symmetrical appearance when installed. The location of outlets
centered on any architectural feature shall be exact. Outlet locations may be moved a
maximum of ten (10) feet from the location shown on the plans before roughing-in
without cost to Owner. Switches in relation to door swings and cabinets must be
coordinated with architectural drawings. This Electrical Contractor shall coordinate with
Mechanical Contractor regarding thermostat outlets and other equipment locations.
C. Device Height: The following dimensions for locating wall outlets represent the distance
from the finished floor to the center of the outlet, unless noted otherwise.
OUTLET INCHES
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-8
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 9
Telephone 15
Convenience receptacle 15
Lighting switch 48
Clock outlet 84
Wall mount telephone 54
Adjust outlet mounting height to agree with required location for equipment served.
D. Boxes Located in Stud Walls: Securely mount with screws to studs or blocking so that
box face is straight and true with finish wall alignment. Install backing to align box
where studs are twisted or crooked, and as required to meet dimensioned or detailed
device spacings. Blocking material shall be same as wall studs and shall be attached to
two adjacent studs.
E. Boxes in Counterbacks or Casework: Install in accordance with architectural details.
Where not indicated in details, the Architect or Engineer shall be consulted prior to
installation.
F. Boxes Above Accessible Suspended Ceilings: Mount to horizontal trapeze hangers,
secured to rod attached to structure above. It is specifically not permitted to attach or
support boxes from ceiling system suspension wire. Conduit and boxes shall be
located a minimum of 12" above ceiling where suspended depth permits. Conduit and
boxes shall not be installed prior to ceiling unless system is attached or braced to
structure as to prevent horizontal movement of conduit.
G. Boxes Located in Masonry Walls: Coordinate cutting of masonry walls to achieve neat
openings for boxes. Use rotary cutting equipment to cut masonry work for installation.
Where furring occurs, install extension rings to bring box flush to furred surface. Where
masonry is the finished surface, locate boxes uniformly for each height at either the top
or bottom of a block course and install so that device plate will fit tight to block wall
without extending over mortar joints.
H. Outlets in Acoustical Tile Ceilings: Locate either centered on the joint between tiles, or
in the center of a tile. All such outlet locations shall be carefully planned and verified
with the Architect or Engineer.
I. Exterior Wall Outlets: Conduits shall enter boxes or exterior wall mounted devices at
the sides or top only. No conduit shall enter the bottom of such boxes.
J. Common Boxes and Alignment: Devices shown adjacent to each other at the same
mounting location shall be gang under a common plate, except for outlets of different
voltages such as telephone and duplex receptacles. Outlets mounted one over the
other, or side by side, shall be in exact alignment, centered on one another.
K. Sound Control: Boxes and conduit shall be installed in a manner that minimizes sound
transmission between rooms. Boxes mounted in a common wall shall be offset
horizontally a minimum of 12" and mounted in different stud spaces wherever possible.
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-9
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 10
No boxes shall be mounted back to back. No through boxes shall be used. Offset
boxes may be connected with flexible conduit not to exceed 18" length.
L. Sealing: All unused holes or openings in boxes shall be slugged or sealed by an
acceptable means.
3.5 INSTALLATION OF WIRING DEVICES:
A. Devices shall be securely fastened to outlet box with face flush with plate.
B. Mount receptacles vertically in appropriate boxes with grounding pin towards floor,
except where noted for horizontal installation.
3.6 INSTALLATION OF WALL PLATES:
Install coverplates on wiring devices. Plates shall be set plumb and flush with finish
wall surface. Plates located adjacent to one another shall be exactly the same height.
3.7 INSTALLATION OF WIRE:
A. Scope: Provide all wiring for complete electrical work, installed in code conforming
raceway. Branch circuit wiring shall be#12 AWG minimum, unless noted otherwise.
B. Home Runs: Branch circuit conductors shall home run to panelboards or motor control
centers in groupings shown on the drawings. Combining branch circuit home run
conductors in single conduits other than that shown shall not be permitted.
C. Color Coding shall be strictly adhered to and shall be as indicated in Section 26210
ELECTRICAL IDENTIFICATION:
1. Color coding utilized shall be noted on electrical "as constructed" drawings and
shop drawings.
2. The color coding for control circuit wires will be as noted on the plans or as agreed
upon with the Architect or Electrical Engineer and will be of a color other than that
designated for the phase wires. Where control wires are installed and various
colors are used, they shall be noted on them "as constructed" drawings and shop
drawings turned in at the completion of the job.
D. Pulling: Use approved wire pulling lubricant for pulling #4 AWG and larger wire. Oil or
grease is prohibited as a conductor pulling lubricant. All conductors #8 and smaller
shall only be pulled by hand. Pulling lubricant for conductors over 600 volt shall be
approved by the conductor manufacturer and the Architect or Electrical Engineer.
E. Splices & Terminations: Join the conductors securely, both mechanically and
electrically using crimp, compression, or Scotch Lok type connectors, except that
screw-on type connectors shall not be used for conductors larger than #6 AWG. Splices
and terminations of conductors larger than #10 AWG shall be made using an oxide
inhibitor (NoAlox or equal). The splice area shall be taped to provide equal or greater
insulation than the original. Tape run-back over the original insulation shall extend 3 to
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-10
REEDLEY RADIO TOWER & EQUIPMENT SHELTER BASIC MATERIALS AND METHODS
REEDLEY, CA. SECTION 262000 - 11
5 overall diameters of the insulated conductor. Type of connectors used shall be
submitted to the Engineer for approval.
No splices in conductors over 600 volt or feeders over#6 AWG permitted.
F. Splice only in accessible junction or outlet boxes.
G. Wiring in panelboards, switchboards, cabinets, and junction boxes shall be neatly
installed. Wiring shall be grouped, laced or clipped, and fanned out to wiring terminals.
H. Identification and Markings: Provide identification and markings as indicated in Section
26210 ELECTRICAL IDENTIFICATION.
I. Cable Testing:
1. All wires under 600 volt potential, #6 or larger shall be tested as follows:
a. Continuity test to insure proper cable connection.
b. Insulation resistance test on each conductor with respect to ground and
adjacent conductors. Applied potential shall be 1000 Volts do for 1 minute.
C. Readings shall be recorded and handed in with the record drawings at the
completion of the project.
2. Test Values: Minimum insulation resistance values shall be not less than 5
megohms.
3.8 INSTALLATION OF TERMINAL CABINETS
A. Install cabinets flush, straight and true, with top aligned with any adjacent panelboards.
B. Terminate conduits in cabinet with lock nut and bushing or lock nut and grounding
bushing. Conduits shall be located in front of plywood backboard, minimum 1" from
rear of terminal cabinet (measured from edge of conduit).
C. Install a minimum of two (2) %" and two (2) 1" conduits from each cabinet stubbed to
accessible attic or ceiling space for future connections.
D. Terminate wiring on terminal blocks or strips. All wiring shall be neatly cabled or
fanned. Label conductors and cables, including spares with plastic Panduit MP series
labels, and corresponding location on terminal or punch block with permanent black
marker.
E. Identify all conduits terminating in terminal cabinets, new and existing, with waterproof
permanent black marker on conduit surfaces close to terminal cabinet; or inside
terminal cabinet adjacent to conduits. Electrical Contractor shall furnish a supplemental
diagrammatic layout of conduits inside each terminal cabinet at Project Closeout.
END OF SECTION 26 20 00
County Contract No.: D-22-456 BASIC MATERIALS AND METHODS
3/12/2024 26 20 00-11
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL IDENTIFICATION
REEDLEY, CA. SECTION 262100 - 1
SECTION 26 21 00 - ELECTRICAL IDENTIFICATION
PART GENERAL
1.1 SCOPE:
A. Furnish and install identification of electrical materials, equipment, and installations,
including but not limited to the following:
Buried electrical line warnings
Identification labeling for raceways, cables, and conductors.
Warning and caution signs.
Equipment labels and signs.
B. Refer to other Division 26 sections for additional specific electrical identification
associated with specific items.
1.2 SUBMITTALS:
A. Product Data: Submit manufacturer's data for each type of product specified.
See Prolog/Converge per Division 1 Section 01 31 13 for submittals for this
project.
PART2 PRODUCTS
2.1 GENERAL:
A. Underground Line Marking Tape: Permanent, bright colored, continuous-printed,
plastic tape compounded for direct-burial service not less that 4" wide by 4 mils thick.
Printed legend indicative of general type of underground line below.
B. Wire/Cable Designation Tape Markers: Vinyl, self-adhesive, wraparound,
cable/conductor markers with preprinted numbers and letter.
C. Plastic Write-on Tags: 0.015" thick, all-nylon, accepts waterproof ink labeling, Panduit
MP series or Engineer approved equivalent; 1/4" x 31/2" for panelboard and switchboard
circuits, 1/4" x 1 S/,,"for signal, communication, and fire alarm circuits.
D. Brass or Aluminum Tags: Metal tags with stamped legend, punched for fasteners.
Dimensions: 2" x 4" (19 gauge).
E. Engraved, Plastic-Laminated Labels, Signs, and Instruction Plates: Engraving stock
melamine plastic laminate, 1/16" minimum thick for signs up to 20 square inches, or 8"
in length; 1/8" thick for large sizes. Engraved legend and color as indicated.
F. Baked-Enamel Warning and Caution Signs for Interior Use: Preprinted aluminum
signs, punched for fasteners, with colors, legend, and size appropriate to the location.
G. Exterior Metal-Backed Butyrate Warning and Caution Signs: Weather-resistant,
nonfading, preprinted cellulose acetate butyrate signs with 20-gage, galvanized steel
backing, with colors, legend, and size appropriate to the location. Provide '/4'
grommets in corners for mounting.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL IDENTIFICATION
REEDLEY, CA. SECTION 262100 - 2
H. Fasteners for Plastic-Laminated Labels and Metal Signs: Self-tapping stainless steel
screws or number 10/32 stainless steel machine screws with nuts and flat and lock
washers.
I. Cable Ties: Fungus-inert, self-extinguishing, one-piece, self-locking nylon cable ties,
0.18" minimum width, 50-lb minimum tensile strength, and suitable for a temperature
range from minimum 50°F to 350°F. Provide ties in specified colors when used for
color coding.
PART 3 EXECUTION
3.1 GENERAL:
A. Lettering and Graphics: Coordinate names, abbreviations, colors, and other
designations used in electrical identification work with corresponding designations
specified or indicated. Install numbers, lettering, and colors as approved in submittals
and as required by code.
B. Install identification devices in accordance with manufacturer's written instructions and
requirements of CEC.
C. Sequence of Work: Where identification is to be applied to surfaces that require finish,
install identification after completion of finish work.
3.2 CONDUIT IDENTIFICATION:
A. High-Voltage Feeder Conduits: Identify feeder conduits (over 600v) by words
"DANGER-HIGH VOLTAGE" in black letters 2" high, stenciled at 10-foot intervals over
continuous painted orange background on entire surface of exposed conduits.
B. Underground Electrical Line Identification: During trench backfilling, for exterior
underground power, signal, and communications service lines, install continuous
underground plastic line marker, located directly above line at 12" below finished grade.
Where multiple lines installed in a common trench or concrete envelope do not exceed
an overall width of 16", install a single line marker.
3.3 CONDUCTOR COLOR CODING:
A. Color Coding: Provide color coding for secondary service, feeder, and branch circuit
conductors throughout the project secondary electrical system as follows:
208/120 Volts Phase 480/277 Volts
Black A Brown
Red B Orange
Blue C Yellow
White Neutral Gray
Green Ground Green
B. Color:
1. Use conductors with factory-applied color for wire sizes No. 10 AWG and smaller.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER ELECTRICAL IDENTIFICATION
REEDLEY, CA. SECTION 262100 - 3
2. For conductors larger than No. 10 AWG, apply colored, pressure-sensitive plastic
tape in half-lapped turns for a distance of six (6) inches from terminal points and in
boxes where splices or taps are made. Apply the last two laps of tape with tension
to prevent possible unwinding. Use 1" wide tape in colors as specified. Do not
obliterate cable identification markings by taping. Tape locations may be adjusted
slightly to prevent such obliteration.
3. For conductors 10 AWG and smaller being fed from sources identified as
emergency, use appropriately colored conductors with black and white tracer color
for all conductors of the circuit.
3.4 CIRCUIT IDENTIFICATION:
A. Conductor Labeling: Tag or label conductors as follows:
1. Future: Identify conductors indicated to be for future connection or connection
under another contract with identification indicating source and circuit number.
2. Switchboards, Panelboards, MCC's, Starters and Similar Equipment: Identify
incoming feed circuit at lugs with write-on tag indicating point of origination, circuit
number, phase, and voltage. Identify all distribution and branch circuit wires with
write-on tags indicating circuit number, destination area or equipment, and load
description; i.e., "A-13 / Room #14/ North wall plugs".
3. Junction and Wiring Boxes: Identify each wire passing through or terminating in
junction or wiring boxes with write-on tag indicating panel and circuit #, voltage,
and phase. Phase and voltage of branch circuit wiring may be indicated by means
of coded color of conductor insulation. Three circuit, four-wire branch circuit home
runs may be identified by a common tag.
4. Control Circuits: All control circuits shall be marked at each control panel
termination point as to their function and where they terminate. Where control
wires terminate into relays or enclosures or terminal cans remote from the main
point of control the incoming wires shall be identified with write-on tags as to their
function and where they originate. All associated wiring integral within a control
cabinet shall be marked with the printed circular wire wrapping at each end
corresponding to circuiting diagrams.
B. Raceway System Labeling: Label raceway system conduits and boxes as follows:
1. The interior of all junction and pull boxes shall be marked with permanent ink
marker indicating the panel and circuit numbers of the wires passing through,
originating, or terminating in the box. In attic spaces, the cover shall be marked
with the same information.
2. The conduits and/or raceways entering and leaving boxes shall be marked with
permanent ink marker to indicate respective points of origination and destination;
i.e., "Panel A" / "Room 16".
3. All junction boxes in attic spaces terminating or serving as gathering points for
emergency power or lighting circuits shall have the cover and first six (6) inches of
entering and leaving conduits painted red.
END OF SECTION 26 21 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 1
SECTION 26 30 00 -SERVICE, DISTRIBUTION AND GROUNDING
PART 1 GENERAL
1.1 SCOPE:
A. Work Included: Furnishing and installation of a complete electrical service, distribution,
and grounding system. Conditions of this section apply to all other 26000 series
sections included.
1.2 QUALITY ASSURANCE:
A. Codes and Regulations, Reference Standards: See Section 26100.
1.3 SUBMITTALS:
A. Product Data: Submit manufacturer's data on service entrance equipment
switchboards, motor control centers and/or individual starters, transformers,
panelboards, disconnect switches and grounding components.
B. Trip Curves: Submit trip timing curves for all circuit interrupting devices.
C. Nameplate Schedule: Submit nameplate schedule for approval.
1.4 COMPONENT COORDINATION:
A. In order to maintain close control and coordinate the various components of the
distribution systems, the number of manufacturers shall be kept to a minimum.
Equipment manufacturer shall be General Electric, Eaton, or Square D. It shall be the
manufacturer's responsibility through the Electrical Contractor to coordinate all
components of the system in order to ensure systems that will provide maximum
protection of equipment and reliable safe operation.
1.5 NAMEPLATES:
A. General: Engraved plastic-laminated, color coded red for 277/480 volt equipment,
black for 120/208 volt equipment, with white letters. Provide for identification of each
piece of electrical equipment, switchboards, transformers, panelboards, disconnects,
and enclosed breakers. A schedule of nameplates shall be included with the shop
drawings for approval. Nameplates shall be secured with permanent adhesive and two
(2) stainless steel self-tapping screws.
B. Each piece of electrical equipment shall be provided with a 2" x 3'/2" nameplate on the
front of the door or on the trim, indicating designation, voltage, and distribution panel
and circuit feeding the panel.
C. Switchboards, distribution panelboards, and all starters and disconnects shall have sub
feeders and main breakers marked with 1"x 3" nameplates indicating load served.
D. All weatherproof disconnects shall be marked with 1" x 3" nameplates indicating
voltage and the panelboard or switchboard from which it is fed from.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 2
E. Provide identification for emergency system boxes and enclosures by labeling the
boxes and enclosures and painting the conduits entering with red paint at a length of
six (6) inches.
1.6 FEEDER CONNECTIONS:
A. Provide cast saddle type bolted lugs, or hydraulically set compression lugs, for all bus
connections. Manufacturer shall be Thomas and Betts, Burndy, O-Z Gedney or
approved equivalent.
1.7 MISCELLANEOUS:
A. Equipment Bases: Provide appropriately sized concrete housekeeping bases for all
floor-mounted equipment.
B. Hoisting Lifting Lugs: Provide on all heavy equipment as required to ensure safe
hoisting.
C. Space for Future Protective Device: Provide as indicated on drawings, shall be
completely equipped for the future addition of a circuit breaker or fused switch,
including all connections.
D. Keys: All equipment enclosures shall be keyed alike.
PART2 PRODUCTS
2.1 GROUNDING:
A. Clamps, bonds, etc., suitable and as necessary to provide continuous ground system.
B. Ground Rods: "Copperweld" %" diameter, 10' long.
C. All grounding conductors shall be copper, sizes not less than that required under CEC
requirements.
2.2 MOLDED CASE CIRCUIT BREAKERS:
A. General: Provide factory-assembled, molded case circuit breakers of frame sizes,
characteristics, and ratings indicated. Circuit breakers shall be UL listed and meet
NEMA Standards Publication AB1. Breakers covered under this specification may be
applied in switchboards, panelboards, motor control centers, combination motor
starters, and individual enclosures. Circuit breakers shall be manufactured by General
Electric, Eaton, or Square D.
B. Construction: Construct with overcenter, trip-free, toggle-type operating mechanisms
with quick-make, quick-break action and positive handle trip indication. Construct
breakers for reverse connection capability, mounting and operating in any physical
position, and operating in an ambient temperature of 40°C. Two and three-pole
breakers shall be common trip. Provide breakers with mechanical screw type
removable connector lugs, AL/CU rated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 3
C. Operation: Automatic operation of the circuit breaker shall be obtained by means of
thermal and magnetic tripping devices located in each pole of the breaker. The thermal
device shall provide time-delay tripping on overloads, and the magnetic device shall
provide instantaneous tripping on short circuits. The instantaneous magnetic trip shall
be adjustable and accessible from the front of the breaker on frame sizes above 100
amperes.
D. Lighting and Appliance Panelboard Breakers: Bolt on construction, Square D QOB,
General Electric, or Eaton equivalent.
1. All single pole 15 and 20 amps shall be UL listed as "Switching Breakers" and
carry the SWD marking.
2. Breakers indicated as "GFI" (Ground Fault Interruptive) shall provide UL Class AC
5-milliampere sensitivity ground fault protection integral within the breaker. Single
pole GFI breakers shall take no more panel space than a conventional breaker.
E. Current Limiting Breakers: Provide breakers with current limiting capability as indicated
or required to meet system short circuit requirements. Square D I-Limited, General
Electric, or Eaton equivalent.
1. On high level fault currents, the circuit breaker shall limit peak current and let-thru
energy and provide a voltage transient-free interruption at near unity power factor.
On fault currents below the threshold of limitation, the circuit breaker shall provide
conventional overload and short circuit protection.
2. The unit shall not contain replaceable elements and the limiter automatically reset
after circuit interruption.
F. Series Connected Ratings: Where utilized to meet short circuit requirements,
combinations for series interrupting ratings shall be recognized by Underwriters
Laboratories and shall appear in the Recognized Component Directory under the
"Circuit Breakers - Series Connected" product category DKSY2. Current limiting circuit
breakers shall allow the use of branch circuit breakers with lower interrupting capacities
on systems capable of delivering fault currents up to 200,000 rms symmetrical amperes
at 480V, ac and 100,000 rms symmetrical amperes at 600V, ac.
G. Solid State Trip Breakers: Main and feeder breakers indicated "SS" shall be solid state
trip type with ampere setting adjustment knobs for changing current carrying capability
of units, and with ground-fault protection components with external neutral current
transformer(CT). Construct with current carrying components isolated from the trip unit
and field installed accessories, and with integral trip unit independent of any external
power source. Square D ME/NE/PE/SE, GE or Eaton equivalent.
1. Provide with Long Time, Short Time, Instantaneous, and Ground Fault Pick up and
delay (LSIG) unless indicated otherwise.
H. Ground Fault Protection: All 1,000 amp or greater 480 volt and "GFI" indicated service
breakers shall be furnished with ground fault protection. Protection may be provided by
a zero sequence/shunt trip system or solid state breaker with integral GFI. System
shall be complete with all required CTs, power supplies, etc., required.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 4
2.3 PANELBOARDS:
A. Power and Lighting Panelboards shall be Air Circuit Breaker bolted type, UL rated for
75°C. connections, with voltage, phase, breakers, and NEMA rating as specified in
panelboard schedules. Panelboards shall be installed flush or surface as indicated.
Panelboards shall be installed in code gauge rust proof steel cabinets with flush doors
having flush lock(s), all keyed alike, and with trim cut square and true; NEMA 3R steel
cabinets with gasketed doors having 3-point vault locks, all keyed alike, and two (2)
spring loaded trunk catches.
120/208 Volt Panelboards: Square D type NQOD, Eaton or General Electric
equivalent.
277/480 Volt Lighting Panelboards: Square D type NEHB, Eaton, or General Electric
equivalent.
B. Power Distribution Panelboards shall be Molded Case Circuit Breaker type, UL rated
for 75°C connections, with voltage, phase, breakers, and NEMA rating as specified in
panelboard schedules. Panelboards shall be installed flush or surface as indicated.
Panelboards shall be installed in code gauge rust proof steel cabinets with flush doors
having flush lock(s), all keyed alike, and with trim cut square and true; NEMA 3R steel
cabinets with gasketed doors having 3-point vault locks, all keyed alike, and two (2)
spring loaded trunk catches.
277/480 Volt Power Distribution Panelboards: Square D I-Line, Eaton or General
Electric equivalent.
1. Spaces indicated on panelboard schedules are a minimum. Specifically sized
spaces shall be provided. When schedules do not designate space frame size, the
panelboard shall be supplied with spaces for one (1) three-pole breaker of the
largest frame size which can be accommodated, and two (2) three-pole breakers
of the next largest frame size which can be accommodated in the scheduled
panelboard.
2. All spaces shall include all required circuit breaker mounting hardware. Any
breaker mounting area available after allotment to scheduled or required spaces
shall be filled out with all required hardware to mount three-pole breakers up to 225
amp frame size.
C. Short Circuit Rating: Panelboard and breakers shall have short circuit rating equal to or
exceeding that indicated. Rating shall be for each panelboard as a complete integrated
unit, tested in accordance with UL Standard UL 67. Panelboards shall be marked with
their maximum short circuit current rating.
D. All interiors shall be completely factory assembled. They shall be so designed that
switching and protective devices can be replaced without disturbing adjacent units and
without removing the main bus connectors, so that circuits may be changed without
machining, drilling, or tapping.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 5
E. Branch circuits shall be arranged using double row construction except when narrow
column panels are indicated. A nameplate shall be provided listing panel type and
ratings.
F. Unless otherwise noted, full size insulated neutral bars shall be included. Bus bar taps
for panels with single pole branches shall be arranged for sequence phasing of the
branch circuit devices. Neutral bussing shall have a suitable lug for each outgoing
feeder requiring a neutral connection. A ground bus will be included in all panels.
G. Boxes shall be at least 20" wide unless otherwise indicated and made from galvanized
steel. Provide minimum gutter space in accordance with the California Electric Code.
At least four (4) interior mounting studs with adjustable nuts shall be provided.
H. Door hinges shall be concealed. All locks shall be flush, stainless steel, cylinder
tumbler type locks with catches and spring loaded door pulls, keyed alike. Directory
frame and card having a transparent cover shall be furnished with each door.
I. All exterior and interior steel surfaces of the trim shall be properly cleaned, primed with
a rust inhibiting phosphatized coating, and finished with a gray ANSI 61 paint. Trims for
flush panels shall overlap the box for at least 3/4" all around. Surface trims shall have
the same width and height as the box. Trims shall be mountable by a screwdriver
without the need for special tools. After installation, trim clamps shall not be accessible
when the panel door is closed and locked.
J. All bus bars shall be copper, sized in accordance with UL standards to limit the
temperature rise on any current carrying part to a maximum of 50°C above an ambient
of 40°C maximum.
2.4 SWITCHBOARDS:
A. Manufacturers: Subject to compliance with requirements, provide switchboards of one
of the following:
General Electric
Eaton
Square D
B. General: Except as otherwise indicated, provide switchboards of types, sizes,
characteristics, and ratings indicated, which comply with manufacturer's standard
design, materials, components, and construction in accordance with published product
information.
C. Auxiliary Components: Where indicated or specified, auxiliary components such as
transformers, meters, contactors, controllers, etc. shall be incorporated at the factory.
Miscellaneous components such as current transformers, instrument transformers, etc.
shall be included as required to form complete and functional systems, whether
specifically specified or not.
D. AC Dead-Front Distribution Switchboards: Provide factory assembled, dead-front,
metal enclosed, self-supporting secondary power switchboards, of types, sizes and
electrical ratings and characteristics indicated; consisting of panel (vertical) units, and
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 6
containing circuit breakers of quantities, ratings and types indicated. Provide copper
main bus and connections to switching devices of sufficient capacity to limit rated
continuous operating temperature rise to 54°F and 90°F for circuit breaker branches;
with main bus and tap connections silver-surfaced and tightly bolted for maximum
conductivity. Brace bus for short circuit stresses up to maximum interrupting capacity.
Prime and paint switchboard with manufacturer's finish and color.
E. Enclosures: Construct dead-front switchboards, suitable for floor mounting, with front
cable/wire and conduit accessibility. Provide welded steel channel framework, hinge
wireway front covers to permit ready access to branch circuit breaker load side
terminals. Coat enclosures with manufacturer's standard corrosive resistant finish.
NEMA Type 3R construction, unless otherwise noted.
F. Short Circuit Rating: Switchboards shall have integrated short circuit rating meeting the
serving Utility Company available, 42,000 AIC minimum; or as indicated on plans.
G. Service Switchboards: Switchboards to be utilized as service boards shall be
constructed in accordance with serving Utility Company requirements; pull section,
lugs, meter provisions, etc.
1. Provide with specific grounding provisions as indicated on plans.
H. Spaces: All switchboards shall include all required circuit breaker mounting hardware
for designated frame size. Any breaker mounting area available after allotment to
scheduled or required spaces shall be filled out with all required hardware to mount
three-pole breakers up to 225 amp frame size.
2.5 DISCONNECTS:
A. Motor and circuit disconnects shall have an Underwriters' Laboratory label.
B. Disconnect switches shall be suitable for area where they are installed, i.e.,
weatherproof, and shall be rated heavy duty. Use only 600 volt class with proper
number of poles. Switches shall be fused unless indicated on plans. Fuses shall be
dual element time delay UL Class RK5 or of type specified on plans. Weatherproof
switches shall be in a NEMA 3R/12 enclosure.
C. All fuses shall be of a type to coordinate with the equipment be protected; i.e. dual
element fuses for motors and HVAC compressor motors.
D. When the disconnect is not clearly visible from the control location, provide it with an
operating handle which is lockable in the open and closed positions.
2.6 AC COMBINATION STARTERS:
A. General: Individual motor starters shall be circuit breaker combination magnetic
starters unless noted otherwise. Units shall be housed with an enclosure for the area in
which starter is installed. Starter size, voltage, and horsepower rating shall be
determined by motor being served. All starters shall be rated 600 volt.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 7
B. Combination starter shall be manufactured in accordance with the latest NEMA
Standards, sizes, and horsepower ratings, and shall be UL listed. Disconnect device
and starter shall be mounted in one enclosure. Handle shall have provisions for
padlocking in the "OFF" and "ON" positions with up to three padlocks.
C. Starters: Shall be gravity dropout type with double break silver alloy contacts, molded
coil, and melting alloy type overload relays. Thermal units shall be one-piece
interchangeable. Provide with 2 N.O. and 2 N.C. contact, unless noted otherwise.
D. Accessories: Provide starters with "Hand-Off-Auto" (HOA) selector switch - and red
pilot light, mounted in cover; unless noted otherwise.
E. Manufacturer: Combination starters shall be Square D Class 8539, General Electric, or
Eaton equivalent.
PART 3 EXECUTION
3.1 INSTALLATION OF GROUNDING:
A. Scope: Provide grounding system complying with the codes and ordinances specified.
Grounding system shall provide continuity through the entire electrical system
including:
1. Panelboard ground buses.
2. All conduit or other raceways.
3. All motors.
4. All lighting fixtures.
5. Grounding terminals of all receptacles.
6. Miscellaneous grounds required by code.
B. Equipment and raceway bonding procedures shall be rigidly maintained and meet all
jurisdictional requirements of codes and regulations.
C. Grounding conductors shall be terminated using a bolted crimped lug connection.
D. Good, electrically continuous, metal to metal contacts shall be made wherever possible
at all panel boxes, pull boxes, etc. Where it is not possible to obtain good contacts, the
conduit shall be bonded around the boxes with a #6 B&S gauge, rubber covered,
double braided wire with ground clamps.
E. A separate grounding conductor shall be run in all conduit runs from distribution,
lighting, and power, etc., panelboards, motor control outlets, etc., back to their
respective service or distribution panelboards.
F. Flexible Conduit Grounding: Provide a separate grounding conductor in all flexible
conduit runs to include watertight flexible conduit with integral grounding straps. Install
ground conductors inside conduit with ungrounded conductors. Extend from nearest
panel to device being connected.
G. A separate insulated (green colored) copper grounding conductor shall be run in all
branch circuit conduits.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 8
H. Ground Rods: All new service installations shall be grounded in accordance to code
requirements and per plans. Isolated transformers, including mini power zones, shall
be grounded on the secondary to a ground rod.
1. Check resistance to ground at all locations (new services and transformers) and
other grounded locations. If resistance exceeds 25 OHMS, install additional ground
rods separated at least 6-0" until resistance is reduced to 25 OHMS or less (CEC
250-84). Submit results to Engineer.
3.2 INSTALLATION OF PANELBOARDS:
A. Provide mounting brackets, busbar drillings, and filler pieces for unused spaces.
B. Branch circuits shall be connected as shown in line diagrams and/or panelboard
schedules, with wires neatly tie wrapped in panel.
C. Branch circuit panelboards shall have a plastic covered circuit directory card on the
inside of each door complete with all circuit destinations neatly typed. Provide also
project name and date of installation on card.
D. The Electrical Contractor shall check and tighten all factory made wire or lug
connections. Tighten connectors and terminals, including screws and bolts, in
accordance with equipment manufacturers published torque tightening values for
equipment connectors. Where manufacturer's torquing requirements are not indicated,
tighten connectors and terminals to comply with tightening torques specified in UL
Standard 486A.
E. Install four(4) spare %" conduits from all panelboards to accessible ceiling space.
3.3 INSTALLATION OF SWITCHBOARDS:
A. Install switchboards as indicated, in accordance with manufacturer's written instruction,
and with recognized industry practices to ensure that switchboards comply with
requirements of NEMA and CEC standards, and applicable portions of NECA's
"Standard of Installation."
B. Prior to energization of circuitry, check all accessible connections to manufacturer's
torque specifications. Subsequent to wire and cable hook-ups, energize switchboards
and demonstrate functioning in accordance with requirements.
C. Testing: All G.F.I. breakers shall be tested and shown to comply with CEC Section
230-95 in accordance with International Electrical Testing Association, Inc. (NETA)
standards by a NETA certified independent testing company.
D. Switchboards shall have a plastic covered circuit directory card on the inside of each
door with all circuit destinations neatly typed. Provide also project name and date of
installation.
3.4 INSTALLATION OF DISCONNECTS:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER SERVICE, DISTRIBUTION AND
REEDLEY, CA. GROUNDING
SECTION 263000 - 9
A. Install disconnects for all equipment and motors of the size required and as
recommended by manufacturer.
B. Fuses installed for all mechanical furnished equipment shall be sized and coordinated
with Mechanical Contractor for specific motor or equipment requirements.
3.5 INSTALLATION OF MOTOR STARTERS:
A. In finished areas, mount motor protection switches flush and install suitable cover
plates.
B. Install heaters correlated with full load current of motors provided.
C. Set overload devices to suit motors provided.
END OF SECTION 26 30 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DRY TYPE TRANSFORMERS
REEDLEY, CA. SECTION 263100 - 1
SECTION 26 31 00 - DRY TYPE TRANSFORMERS
PART GENERAL
1.1 SCOPE:
Furnish and install floor, shelf, or wall mounted style, dry type transformer as indicated
on drawings and as specified. All dry type transformers shall comply to 2016 energy
efficiency standards for transformers.
1.2 SUBMITTALS:
A. Product Data: Submit manufacturer's technical product data including rated KVA,
frequency, primary and secondary voltages, percent taps, polarity, and impedance.
B. Shop Drawings: Submit manufacturer's drawings indicating dimensions, and weight
loadings for transformer installations, showing layout, mountings and supports, spatial
relationship to associated equipment and panelboards, and transformer connection to
electrical equipment.
PART2 PRODUCTS
2.1 MANUFACTURER:
Subject to compliance with the requirements, provide transformer of one of the
following:
Square D
General Electric
Eaton
2.2 POWER/DISTRIBUTION TRANSFORMERS:
A. General: Except as otherwise indicated, provide manufacturer's standard materials
and components as indicated by published product information, designed and
constructed as recommended by manufacturer and as required for complete
installation.
B. Transformer: Dead front, single phase or three phase, two winding, 60 Hz., 150°C.
rise, self-cooled type, KVA capacity as shown on plans. Primary shall be 480 volts
delta and secondary shall be 208/120 volts wye for three phase transformers and 480
volts delta primary and 240/120 volts delta secondary for single phase transformers, or
as otherwise noted on plans. Impedance shall be manufacturer's standard. The
maximum temperature of the top of the enclosure shall not exceed 35°C rise above a
40°C ambient. All insulating materials used to be in accordance with NEMA ST20 or
NEMA TR27 standards for a 220°C. insulating system. The core of the transformer
shall be visibly grounded to the enclosure by means of a flexible grounding conductor
sized in accordance with applicable NEMA, IEEE, and ANSI standards.
C. Enclosure: Transformers 25 KVA and larger shall be in a heavy gauge, sheet steel,
ventilated enclosure. Provide wire fabric rodent guard over ventilated openings and
designed to prevent accidental access to live parts in accordance with UL, NEMA, and
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER DRY TYPE TRANSFORMERS
REEDLEY, CA. SECTION 263100 - 2
California Electric Code standards for ventilated enclosures. Transformers 25 KVA
through 75 KVA shall be designed so they can be either floor or wall mounted. Above
75 KVA they shall be floor mounted.
D. Sound: Sound levels shall be guaranteed by the manufacturer not to exceed the
following:
15 - 50 KVA 45 dB
51 - 150 KVA 50 dB
151 - 300 KVA 55 dB
301 - 500 KVA 60 dB
PART 3 EXECUTION
3.1 INSTALLATION OF TRANSFORMERS:
A. Install transformers as indicated, complying with manufacturer's written instructions,
applicable requirements of CEC, NEMA, ANSI, and IEEE standards, and in accordance
with recognized industry practices to ensure that products fulfill requirements.
B. Floor and roof mounted transformers shall be mounted on captive steel insert neoprene
mountings, Vibrex Model F.U. vibration isolators, seismic rated or equivalent. Conduit
entering transformers shall be isolated from case with oversize hole, ground wire, and
rubber grommet.
3.2 GROUNDING:
Provide equipment grounding connections, sufficiently tight to assure permanent and
effective ground, for transformers as indicated.
3.3 TESTING:
Upon completion of installation of transformers, energize primary circuit at rated voltage
and frequency from normal power source and test transformers, including, but not
limited to, audible sound levels, to demonstrate capability and compliance with
requirements. Where possible, correct malfunctioning units at the site, then retest to
demonstrate compliance; otherwise, remove and replace with new units and proceed
with retesting.
END OF SECTION 26 31 00
CONTRACT 24-S-04
REEDLEY RADIOTOWER & EQUIPMENT SHELTER TRANSIENT VOLTAGE SURGE
REEDLEY, CA. SUPPRESSION
SECTION 264300 - 1
SECTION 26 43 00 -TRANSIENT VOLTAGE SURGE SUPPRESSION
PART 1 — GENERAL
1.1 SUMMARY:
A. Transient voltage surge suppression shall be provided on all main services (Class C),
all MCC's, and the secondary main bus of station step-down transformer. Minimum
240KA/PH rating for all 480 volt MCC's. TVSS installation to include fused or circuit
breaker disconnect.
1.2 RELATED SECTIONS:
A. Section 26320 Motor Control Centers
1.3 SUBMITTALS:
A. The Electrical Contractor shall furnish submittals for all products identified in this
Section.
1.4 MANUFACTURER QUALIFICATIONS:
A. The manufacturer of transient voltage surge suppression equipment must have
engaged in the design and manufacture of similar equipment for a minimum of five (5)
years.
PART2 PRODUCTS
2.1 TRANSIENT VOLTAGE SURGE SUPPRESSION:
A. Provide transient voltage surge suppressors suitable for the circuit voltage rating,
service equipment, and connected loads.
2.2 SOURCE QUALITY CONTROL:
A. The specified system shall be tested to meet ANSI/IEEE C62.41-1991, tested per
ANSI/IEEE C62.45-1992.
B. The system shall be tested to 1,000 sequential ANSI/IEEE C62.41 Category C
waveforms.
2.3 MANUFACTURER:
A. Manufacturer shall be Eaton SPD Max, Square D EMA or equal.
PART 3 EXECUTION
3.1 INSTALLATION:
A. Transient voltage surge suppression equipment shall be installed in accordance with
manufacturer's instructions and all applicable codes and standards.
CONTRACT 24-S-04
REEDLEY RADIOTOWER & EQUIPMENT SHELTER TRANSIENT VOLTAGE SURGE
REEDLEY, CA. SUPPRESSION
SECTION 264300 - 2
END OF SECTION 26 43 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER HEAVY DUTY SAFETY SWITCHES
REEDLEY, CA. SECTION 264950 - 1
SECTION 26 49 50 - HEAVY DUTY SAFETY SWITCHES
PART 1 — GENERAL
1.1 SUMMARY:
A. This section includes equipment used for local disconnects at motors.
1.2 RELATED SECTIONS:
A. Division 26 Electrical
1.3 REFERENCES:
A. National Electrical Manufacturer's Association (NEMA)
B. National Electrical Code
C. American National Standards Institute (ANSI)
D. Underwriter Laboratories (UL)
1.4 SUBMITTALS:
The Electrical Contractor shall furnish submittals for all products identified in this
Section.
PART 2 PRODUCT DESCRIPTION
A. Switches to be Heavy Duty Safety switches, 600 volt, single throw, 3 pole, fusible.
B. Enclosure to be rated NEMA 4 dust tight, water tight, and corrosion resistant with
lockable access door. All current carrying parts to be copper.
C. Switch to be rated full load break.
D. Short circuit withstand rating to be 200,000 RMS symmetrical amperes.
E. Switch to be equipped with a cover viewing window showing the position of the stabs.
PART 3 EXECUTION
3.1 INSTALLATION:
A. All safety switches shall be installed and calibrated in accordance with manufacturer's
instructions.
END OF SECTION 26 49 50
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EQUIPMENT CONNECTIONS
REEDLEY, CA. SECTION 265000 - 1
SECTION 26 50 00 - EQUIPMENT CONNECTIONS
PART GENERAL
1.1 SCOPE:
A. Make all connections of power to all equipment along with installation of required
disconnecting means.
B. Furnish all electrical disconnects, power supplies, and controls as noted within the
electrical plans for equipment, compressors, fans, etc.
PART2 PRODUCTS
2.1 MATERIALS:
Conduits, boxes, cover plates, disconnects, etc., per applicable related sections.
PART 3 EXECUTION
3.1 INSTALLATION OF MECHANICAL EQUIPMENT WIRING:
A. Furnish all electrical disconnects, power supplies, and controls as noted within the
Division 15 and Division 26 plans for Division 15 equipment as shown on the
mechanical plans.
B. Make all connections of power to all mechanical equipment along with installation of
required disconnection means. The work is generally as noted, but not specifically
limited to the following:
1. Air-cooled chillers
2. Pumps
3. Air conditioning units
4. Exhaust fans
5. Fan coils
6. Temperature control panels
7. Boilers
8. Air compressors and air dryers
9. Air handlers
C. Supply all electrical junction boxes for mechanical equipment.
3.2 INSTALLATION OF OWNER-FURNISHED EQUIPMENT WIRING:
A. Make all connections of power to all Owner-furnished equipment along with installation
of required disconnection means. The work is generally as noted, and also as shown
on the architectural plans, but not specifically limited to the those.
B. Supply all electrical junction boxes for Owner-furnished equipment.
3.3 MOTOR CONNECTIONS:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EQUIPMENT CONNECTIONS
REEDLEY, CA. SECTION 265000 - 2
A. The Electrical Contractor shall make all line connections for each motor sized as shown
on the plans. Electrical Contractor shall be responsible for proper phasing and rotation
of all connected motors.
B. The Electrical Contractor shall supply those starters indicated on the plans, install these
and Mechanical furnished starters, and make motor-starter connections for all indicated
motors.
C. The Electrical Contractor shall verify motor characteristics prior to installing wiring.
Exact location of motor and motor connections shall be ascertained prior to installing
conduits.
D. A Liquidtight Flexible Metal (LFMC) conduit connection, in lengths not to exceed 36",
shall be provided at each motor. Lengths exceeding 36" are to be submitted to the
Engineer for approval.
3.4 TESTING:
After all wiring to each unit is complete, the Electrical Contractor shall cooperate with
Mechanical or Equipment Contractors in testing equipment for proper operation and
shall correct wiring as required for proper operation.
END OF SECTION 26 50 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 1
SECTION 26 51 00 —TIER 4 EMERGENCY GENERATOR AND AUTOMATIC TRANSFER
SWITCH
PART 1 GENERAL
1.1 SCOPE:
A. The Electrical Contractor shall furnish and install an indoor emergency standby
generation unit. Supplier shall verify/guarantee generator will start and run all
connected loads and provide simulation data with the submittal. The generator set shall
be rated per plans standby with 0.8 power factor at 60 hertz with ratings calculated at
50°C using #2 Diesel Fuel. The ratings will be with the radiator fan included, for
continuous electrical service during interruption of the normal utility service. Supplier to
submit verification the emergency generator meets all Regional Air Quality Board
requirements and provide the required Authority to Construct/Authority to operate
application with all technical data completed. The emergency generator shall meet all
fire marshal requirements.
B. The generator set shall have an output voltage of 120/208 volt, three phase, four wire.
C. The generating unit shall be furnished ready for operation as soon as the required
connections have been made to the unit's wiring.
1.2 SUBMITTALS:
A. Product Data: Submit manufacturer's data on engine-driven electric generator systems
and components. Include manufacturer's product warranty statement showing single
source responsibility by the engine manufacturer, for replacement of materials and
equipment used in standby engine driven generator system.
B. Shop Drawings: Submit dimensioned drawings of engine-driven generator units and
accessories including, but not limited to, automatic transfer switches, fuel line piping,
remote start/stop stations, and instruments, showing accurately scaled generator set
layout and its spatial relationship to associated equipment, and connections to remote
equipment.
C. Other: Supplier shall verify/guarantee generator will start and run all connected loads
and provide simulation data with the submittal. Supplier to submit verification the
emergency generator meets all Regional Sir Quality Board requirements and provide
the required Authority to Construct/Authority to operate application with all technical
data completed.
1.3 MATERIAL AND WORKMANSHIP:
The engine generator set shall be a factory fabricated and assembled package of new
and quality grade components. Only those products currently being manufactured for
the purpose of power generation will be considered. All work shall be congruent with
the highest quality standards.
1.4 DESIGN:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 2
The unit shall be designed and fabricated to meet all applicable codes and standards
associated with the area and application for which it is intended. Routine maintenance
and adjustments shall be able to be performed without the use of special tools or
instruments.
1.5 WARRANTY:
Equipment furnished under this section shall be guaranteed by the manufacturer and
administered by the selling dealer against defects in materials or workmanship for a
period of five (5) years from date of acceptance. It shall cover full parts and repair labor
expenses plus travel time and mileage.
PART2 PRODUCTS
2.1 MANUFACTURER:
Subject to compliance with requirements, provide engine/generator set of one (1) of the
following: Caterpillar, Cummins, or Generac.
2.2 GENERAL:
Furnish and install a complete and working packaged generator set including all engine
and generator components, standard engine mounted control panel, radiator and fan,
all engine oil and engine filters, and 50% Ethel glycol solution in the radiator and water
cooling system. To qualify as manufacturer, the engine must be the principal item
manufactured and the completed engine generator shall be supplied by that
manufacturer's authorized representative.
2.3 ENGINE:
A. Construction: The engine shall run on natural gas or#2 diesel, be fully water cooled, of
four stroke cycle design, compression ignited, rated for continuous standby application.
It shall produce sufficient horsepower to achieve ratings indicated while driving all
accessories and parasitic loads such as fans or alternators.
B. Governor: The engine shall be equipped with mechanical governor with a 3% speed
regulation from no load to full load.
C. Safety Devices: The generator set shall have installed and be warranted by the engine
manufacturer the following alarm and shutdown features:
1. Low oil pressure pre-alarm
2. High water temperature pre-alarm
3. Low water temperature alarm
4. Low oil pressure shutdown
5. High water temperature shutdown
6. Overspeed set for 118% rated speed. It shall allow the unit to be tested at 75% of
the actual trip point.
D. Cooling System: The engine shall be equipped with either a gear or belt driven
centrifugal water pump. The engine shall be cooled through a base mounted radiator
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 3
sized to continuously maintain safe operation at full load and at 1150OF ambient air at
the radiator core. A blower type fan will be furnished. The fan and all rotating
members and drive belts shall be guarded and meet OSHA standards.
E. Block Heater: A jacket water heater will be provided to maintain engine coolant
temperature between 90°-120°F. in an ambient of 30°F. The heaters shall be
thermostatically controlled. Voltage shall be 120 volt, single phase unless indicated
otherwise on plans.
2.4 EXHAUST SYSTEM:
The engine shall have a single exhaust outlet for installation ease. A critical grade
silencer and stainless steel bellows type flexible section shall be furnished complete
with all gaskets and hardware. The silencer shall be mounted as a complete system to
the weather protective enclosure.
2.5 FUEL SYSTEM:
Provide an integral sub-base fuel tank with high , low, and shutdown level switches and
a pre-wired tank control panel with alarms lights and contacts and on off emergency
switch hose MO Rt fuel taRkcomplying with NFPA 37 requirements, and UL Listed rated
48 hours of run time dual contained sub-bas with low level and leak detector switches,
5 gallon overfill/spill basin, 2" lockable fill capvent caps for norma and emergency
venting extended as required per local code.
2.6 MOUNTING:
The engine and generator shall be soft mounted to the base, minimizing transmission
of vibration to the package.
2.7 GENERATOR AND CONTROLS:
A. Construction: The generator shall be manufactured and packaged by the engine
manufacturer to insure proper performance and effect a single source of responsibility.
The generator shall be rated as per drawings, and conform to NEMA standards for
temperature rise and construction. Total harmonic content in the generator shall be
less than 5% measured line-to-line at rated voltage on an open circuit. No single
harmonic shall exceed 3%.
B. Voltage Regulator: The voltage regulator shall be solid-state, volts per hertz type. It
shall be mounted in the generator providing +/-1% no load to full load regulation.
Adjustable controls for voltage droop, level and gain shall be provided. Voltage level
adjustment shall be -25% to +10%. The regulator shall incorporate built-in under
voltage and an under frequency protection for the voltage regulator and generator. It
shall have parallel capability, TIF less than 50, and EMI/RFI suppression to commercial
standards.
C. Circuit Breaker: A main line circuit breaker shall be installed in a generator mounted
NEMA 1 cabinet that can be easily accessed by removing one (1) of the lockable
weather protective doors of the generator enclosure. The rating shall be as shown of
the drawing. The circuit breaker shall be UL listed and conform to NEMA and NEC
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 -4
standards. Load lugs shall be provided to accept conducted size and quantity as
shown on the drawings. A fully rated, isolated neutral and ground lug shall be provided.
D. Control Panel: The control panel shall be designed and built by the engine/generator
set manufacturer and shall incorporate 100% solid state circuitry, microprocessor
control, sealed dust tight, watertight modular components, and digital instrumentation.
The panel shall be shock mounted to the generator and labeled with ISO symbols. The
panel shall include the following equipment:
1. Safety Devices:
One (1) ISO red emergency stop pushbutton.
2. Generator AC Output Metering Devices:
Three (3) backlit LCD displays for volts, hertz and amperes in one (1)
environmentally sealed module. Numeral height shall be 0.5% accuracy for
voltage and current and 0.3% accuracy for a frequency throughout a temperature
range of-40°C to +70°C.
3. Silenceable alarm horn to annunciate shutdowns for overspeed, low oil pressure,
high water temperature and overcrank.
E. Excitation: Permanent magnet excitation.
2.8 STARTING SYSTEM:
A. Starter: The unit shall be equipped with a 24V DC staring motor, a starter relay and an
automatic reset circuit breaker in case of butt engagement.
B. Battery System: The starting batteries shall be the lead acid type, rubber cased with
removable fill caps. The batteries shall be mounted to the generator set base and
provide with seismic rated anchorage. Required cables and lugs shall be furnished of
the proper size.
C. Battery Charger: A solid state battery charger of current limiting design shall be
provided with DC voltmeter and ammeter. The charger shall maintain batteries by
automatically tapering output amperage as dictated by battery condition. Input shall be
120 VAC, single phase, with output of 5 ampere minimum at 24 volts DC. The battery
charger shall have an undervoltage alarm and contacts. The input power shall be
fused or circuit breaker protected. The battery charger shall be mounted in the
generator set enclosure.
2.9 OPERATION:
Upon power outage the transfer switch shall signal the engine-generator to start. When
generator output reaches approximately 90% rated voltage and speed, load shall be
transferred from the normal to the emergency source. Maximum time for generator on-
line shall be ten (10) seconds. Upon return of normal power, the transfer switch shall
transfer load to the utility bus and engine shall start into a cool down period. This
period shall be automatically overridden in the event of an additional utility failure. The
cool down shall last five (5) minutes.
2.10 OPERATING SYSTEMS:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 5
Filtering systems shall be adequate for a minimum of 200 hours of engine operation
under normal conditions. Furnish any special tools required for routine maintenance.
Provide sufficient lube oil and air cleaner elements for first change. Exposed parts
which are subject to high operating temperatures or which are electrically energized,
and moving parts which man constitute a hazard to operating personnel shall be
insulated, enclosed or guarded. Provide the unit with the initial fill of lubricating oil
together with 50% solution of ethylene glycol antifreeze for cooling system. Enclosure
will be pre-wired for jacket water heater, generator space heater, battery charger, and
LED enclosure lights to an interior load panel with circuit breakers.
2.11 ENCLOSURE:
The engine/generator assembly and components shall be equipped with a weather
protective sound attenuated enclosure constructed of steel sheet metal. It shall be
designed, manufactured and assembled by the engine manufacturer and carry the
same warranty as the engine. It shall be properly primed and finished for extended
wear. The doors shall be able to be locked. The doors shall be easily removable. The
enclosure shall provide a Level II 76dB(A) maximum sound attenuation.
2.12 AUTOMATIC TRANSFER SWITCH:
Furnish and install freestanding automatic transfer switch, of size indicated on
drawings. Switch shall be enclosed in a code gauge steel housing of NEMA 1
construction. Provide transfer switch that is fully compatible with Emergency
Generator, as manufactured by Eaton, Cummins, ASCO, Russelectric, or approved
equivalent.
A. The automatic transfer switch shall consist of a power transfer module and a control
module interconnected to provide complete automatic operation. The automatic
transfer switch shall be mechanically held and electrically operated by a single-solenoid
mechanism energized from the source to which the load is to be transferred. The switch
shall be rated for continuous duty and be inherently double throw. The switch shall be
mechanically interlocked to ensure only one of two possible operations - normal or
emergency. The automatic transfer switch shall be suitable for use with emergency
sources such as an engine or turbine generator source or another utility source.
B. All main contacts shall be of silver composition. They shall be protected by arcing
contacts in sizes 400 amperes and over. They shall be of the blow-on configuration
and of segmented construction in ratings 600 amperes and over. The operating
transfer time in either direction shall not exceed one-sixth (1/6) of a second.
C. All contacts, coils, springs, and control elements shall be conveniently removable from
the front of the transfer switch without major disassembly or disconnection of power
conductors.
D. The control module shall be supplied with a protective cover and be mounted
separately from the transfer switch for ease of maintenance. Sensing and control logic
shall be solid state and mounted on plug-in printed circuit boards. Printed circuit boards
shall be keyed to prevent incorrect installation. Interfacing relays shall be industrial
control grade plug-in type with dust covers.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 6
E. Automatic transfer switches utilizing components of molded case circuit breakers,
contactors, or parts thereof which have not been intended for continuous duty or
repetitive load transfer switching are not acceptable.
F. The automatic transfer switch shall conform to the requirements of NEMA Standard
ICS 2-447 and Underwriters' Laboratories UL-1008 and shall be UL listed as follows:
1. For use in emergency systems in accordance with Articles 517 and 700 of the
California Electrical Code.
2. Rated in amperes for total system transfer including control of motors, electric-
discharge lamps, electric-heating and tungsten-filament lamp loads as referred to
in Paragraph 30.9 of UL 1008.
3. Transfer switch rated 400 amperes and less shall be suitable for 100% tungsten-
filament lamp load. Switches rated above 400 amperes shall be suitable for 30%
or 400 amperes tungsten-filament lamp load, whichever is higher.
G. The automatic transfer switch shall be rated to withstand the RMS symmetrical short
circuit current available at the automatic transfer switch terminals with the type of
overcurrent protection, voltage and X-R ratio shown on the plans.
H. Operation:
1. Two pole switches shall be used for single phase service and three pole switches
for three phase service. Neutral conductor terminal lugs shall be provided as
required for the power system.
2. The automatic transfer switch control panel for single phase and for three phase
shall utilize solid state sensing on normal and emergency for automatic, positive
operation. The following shall be provided:
a. For single phase switches, the normal source voltage across live lines shall
be monitored, and for three phase switches all phases of the normal shall
be monitored line-to-line. Close differential voltage sensing shall be
provided. The pickup voltage shall be adjustable from 85% to 100% of
nominal and the dropout voltage shall be adjustable from 75% to 98% of
the pickup value. The transfer of emergency will be initiated upon
reduction of normal source to 85% of nominal voltage and retransfer to
normal shall occur when normal source restores to 95% of nominal.
b. A time delay to override momentary normal source outages to delay all
transfer switches and engine starting signals. The time delay shall be field
adjustable from 0.5 to 6 seconds and factory set at 1 second.
C. A time delay on retransfer to normal source. The time delay shall be
automatically bypassed if the emergency source fails and normal source is
available. The time delay shall be field adjustable from 0 to 30 minutes and
factory set at 30 minutes.
d. An unloaded running time delay for emergency generator cool down. The
time delay shall be field adjustable from 0 to 5 minutes and factory set at
five (5) minutes.
e. A time delay on transfer to emergency. Initially set at zero but field
adjustable up to five (5) minutes for controlling timing of load transfer to
emergency, where indicated.
f. Independent single phase voltage and frequency sensing of the emergency
source. The pickup voltage shall be adjustable from 85% to 100% of
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 7
nominal. Pickup frequency shall be adjustable from 90% to 100% of
nominal. Transfer to emergency upon normal source failure when
emergency source voltage is 90% or more of nominal frequency is 95% or
more of nominal.
g. A contact that closes when normal source fails for initiating engine starting,
rated 10 amps, 32 VDC. Contacts to be gold plated for low voltage service.
h. A contact that opens when normal source fails for initiating engine starting,
rated 10 amps, 32 VDC. Contacts to be gold plated for low voltage service.
i. A white signal light to indicate when the automatic transfer switch is
connected to the normal source. A yellow signal light to indicate when the
automatic transfer switch is connected to the emergency source.
j. One (1) auxiliary contact that is closed when automatic transfer switch is
connected to normal, and one (1) auxiliary contact that is closed when
automatic transfer switch is connected to emergency. Rated 10 amps, 480
volts, 60 Hz AC.
k. A test switch to momentarily simulate normal source failure.
I. Harnessing between transfer switch and control panel shall have built-in
disconnect for routine maintenance.
PART 3 EXECUTION
3.1 TESTING:
A. Manufacturer's Shop Tests: The generator set shall be tested for proper operation prior
to delivery. Standard factory full load tests shall be performed. The supplier shall
submit standard test reports with operation and maintenance materials.
B. Jobsite Testing: The equipment supplier shall test the installed generator set with
resistive load bank. The unit shall be tested at 50% load for one (1) hour, and 100%
rated load for one-half ('/2) hour. All starting and shutdown systems will be
demonstrated. The suppliers' standard test form shall be used with readings made and
recorded every fifteen (15) minutes. A copy of the test report along with the operation
guide and wiring diagrams shall be submitted within ten (10) days after performance of
the job site test.
1. In presence of the Engineer or Owner's Representatives, test emergency systems,
by means of simulated power outage, utilizing full load sized resistive load banks,
automatic start-up by remote-automatic starting, transfer of load, and automatic
shutdown. Prior to these tests, adjust transfer switch timers for proper system
coordination.
3.2 ANCHORAGE:
A. Units shall be anchored to a concrete equipment pad per structural engineer.with
vibration isolators.
3.3 MOUNTING:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 8
All components other than the automatic transfer switch will be either engine/generator
mounted . All batteries will be in earthquake racks.
3.4 INSTALLATION OF TRANSFER SWITCHES:
A. Install transfer switches, including associated control devices as indicated, in
accordance with equipment manufacturer's written instructions, and with recognized
industry practices, to ensure that transfer switches comply with requirements. Comply
with applicable requirements of NEC and NFPA pertaining to wiring practices and
installation of electrical power transfer switches.
B. Tighten electrical connectors and terminals, including screws and bolts, in accordance
with equipment manufacturer's published torque tightening values for equipment
connectors. Where manufacturer's torquing requirements are not indicated, tighten
connectors and terminals to comply with tightening torques specified in UL Standards
486A and B.
C. Provide equipment grounding connections for transfer switch units as indicated. Tighten
connectors to comply with tightening torques specified in UL Std 486A to assure
permanent and effective grounding.
3.5 FIELD QUALITY CONTROL:
A. Testing Company Tests: Prior to energization, provide independent testing company
test and certification of the indicated components of the Generator System in
accordance with the following NETA Acceptance Testing Specifications Sections:
1. Section 7.22.1 Visual and Mechanical Inspection
2. Section 7.22.2 Protective Relays
3. Section 7.22.4.1 Automatic Transfer Switch Visual and Mechanical Inspection
B. Supplier Tests: Prior to energization, perform the following tests:
1. Furnish and install test equipment and materials and perform load bank test in
accordance with the following schedule:
25% rated for 30 minutes
50% rated for 30 minutes
75% rated for 30 minutes
100% rated for 3 hours
Record voltage, frequency, load current, oil pressure, and coolant temperature at
periodic intervals during test.
2. Perform automatic transfer tests to:
a. Simulate loss of normal power
b. Return to normal power
C. Simulate loss of emergency power
d. Simulate all forms of single-phase conditions.
3. Monitor and verify correct operation and timing of following simulations:
a. Normal voltage sensing relays
b. Engine start sequence
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER EMERGENCY GENERATOR AND
REEDLEY, CA. AUTOMATIC TRANSFER SWITCH
SECTION 265100 - 9
C. Time delay upon transfer
d. Automatic transfer operation
e. Interlocks and limit switch function
f. Time delay and retransfer upon normal power restoration.
g. Engine cool down and shutdown feature.
END OF SECTION 26 51 00
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 1
SECTION 26 96 09 — ELECTRICAL COMMISSIONING AND FIELD TESTING AND NFPA 70E
REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
A. General
1. Related Sections — 01 81 00 Project Commissioning
2. The publications listed below form a part of this specification to the extent
referenced.
3. Where a date is given for reference standards, the edition of that date shall be
used. Where no date is given for reference standards, the latest edition available
on the date of the Notice Inviting Bids shall be used.
4. "Engineer" and FOR (Engineer of Record) = same designation.
B. American National Standards Institute (ANSI)
C. Institute of Electrical and Electronics Engineers, Inc. (IEEE)
1. IEEE 400, Guide for Making High-Direct-Voltage Test on Power Cable Systems
in the Field
2. IEEE 519, Guide for Harmonics Control in Electrical Power Systems
D. National Electrical Testing Association (NETA)
E. National Fire Protection Association (NFPA)
1. NFPA 70, National Electrical Code (NEC)
F. Electronics Industry Alliance/Telecommunications Industry Association (EIA/TIA)
1. TIA/EIA-568-B.1, B.2, B-2-1, B.3 - Commercial Building Telecommunications
Cabling Standard
2. TIA/EIA-569-B - Commercial Building Standard for Telecommunications Pathways
and Spaces
3. TIA/EIA 606A-Administration Standard for the Telecommunications Infrastructure
of Commercial Buildings
4. EIA/TIA 607A- Commercial Building Grounding and Bonding Requirements for
Telecommunications
5. EIA-310-D - Cabinets, Racks, Panels, and Associated Equipment
G. Federal Communications Commission (FCC) part 15, part 68 and part 76
H. Rural Electrification Association (REA), Bulletin 345-63, REA Standards for
Acceptance Tests and Measurements of Telephone Plant
1.2 SUBMITTALS
A. Submit in accordance with Section 26100 1.7. Submittals will include
completed test reports.
B. Test procedures will adhere to NETA (National Electrical Testing Associations),
NEMA, IEEE, other applicable industry standards, and/or specific requirements added by
the EOR. It will be the contractor's responsibility to provide personnel to carry out and/or
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 2
assist with these procedures and rectify issues as they are discovered. Test procedures
shall include but not be limited to:
1. Detailed procedures in sufficient detail to verify conformance with these
Specifications.
2. Incorporation of the Test Record Sheets included at the end of this Section. Use
of pre-formatted test forms and/or test results by manufacturers instrumentation software
is not permitted unless pre-approved by the EOR.
3. Detailed comprehensive testing schedule including:
a. Electrical testing of each major process area.
b. Each major piece of electrical distribution equipment.
c. Each major electrical subsystem.
d. Duration of each test.
e. Milestone test completion date.
f. Coordination with the master construction schedule.
g. Date of test results submittals following completion of the tests.
h. Names and qualifications of the individual(s) responsible for performing the
testing.
4. Submit six (6) like complete lists(s) of Procedures and Test Results. Tab in
logical order per Voltage/Phase (descending), cables (identified "from and to"), panels
with relays descending order), and all other miscellaneous equipment and systems.
Submit in punched individual sheets in three-ring binders with spline identification and
title sheet, index, references, and tabbed data.
C. Following completion of the test submit the completed test results to the FOR for
review. The results shall include a dedicated section with the "as-left" settings of all devices,
relays, circuit breakers, system software, relay program software with PDF copy on thumb
drive (one (1) per each of six (6) packages), etc.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 GENERAL
A. Upon completion of various phases of the project all new electrical equipment, wiring
and cabling systems shall be tested in accordance with these specifications.
B. The Engineer reserves the right to witness all tests and shall be notified at least 5
days prior to testing.
C. All test results shall be recorded on the attached Test Record Sheets or Contractor-
equivalent that are acceptable to the Engineer (see Section 269609, 1.2
SUBMITTALS). Test records shall be submitted to the Engineer.
D. High potential tests shall not be repeated without authorization by the Engineer.
E. The tests shall be documented on the Test Record Sheets. The checks and tests
that are required shall include, but not be limited to the following:
1. Visually check all wire and cable connections
2. Check all AC and DC control circuits for short circuits and extraneous grounds
3. Functional test of power, control, and lighting circuits
4. Functional test of electrical signal and alarm systems
5. Continuity tests of all 600-volt power and control circuits
6. Check grounding system
7. Check current transformer ratios and continuity of the secondary circuits by
passing current through the primary windings and taking readings of the primary current
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 3
and of the current flowing through the meter, relay, and instrument coils in the
secondary circuits.
8. Checks shall be performed to determine the proper functioning of all switches,
circuit breakers, relays, starters, and other items including control interlock and
sequence circuits. All necessary adjustments shall be made on apparatus in
accordance with the manufacturer's instructions and design requirements. Alarm
systems and circuits shall be tested by manually operating the initiating devices. Relays
and control components that may prove to be sluggish or otherwise unreliable shall be
repaired and replaced as necessary.
9. Special tests will be required on equipment if they are recommended by
manufacturers.
F. All safety rules and precautions shall be followed.
3.2 TESTS ON POWER, CONTROL, INSTRUMENTATION, AND LIGHTING CIRCUITS
A. Perform continuity checks of all power, control, and instrumentation cables including
each conductor of multiconductor and multipair cables.
B. Verify wire numbers. Verify that actual wiring conforms to the construction drawings.
C. Conductor ends shall be clean, dry, and guarded for personnel safety during testing.
Circuits in the immediate vicinity that are not under test shall be grounded.
D. Perform insulation resistance tests on 600-volt power cables. Testing shall be for
one minute using 1,000 VDC.
E. Perform insulation resistance test on medium voltage power cable. Testing shall be
1 minute using 2,500 VDC for 5 kV cables, 5,000 VDC for 15 kV cables, 7,500 VDC for 21-
25 kV cables.
F. Each conductor in a multiconductor or multipair cable or conduit shall be tested
against ground with the conduit and conductor to conductor.
G. Circuit testing shall be as follows:
1. Motor control circuits tested and verified for proper operation with control stations
and overcurrent devices connected.
H. Prior to performing insulation resistance tests on cables, verify that they are not
connected to a solid state device or any other connection not rated for test voltage.
I. The Engineer shall be consulted if minimum insulation values per IEEE and/or
NEMA cannot be obtained.
J. Alarm conditions shall be simulated for each alarm point, and alarm indicators shall
be checked for proper operation.
K. Metering and indication lights for motors and other devices shall be tested for proper
operation.
L. All control circuits such as bus paralleling, motor, interlock and remote shall be
tested for proper operation.
3.3 PROTECTIVE RELAYS INSPECTION AND TEST PROCEDURES
A. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect relays and cases for physical damage. Remove shipping restraint
material.
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 4
3. Tighten case connections. Inspect cover for correct gasket seal. Clean cover
glass. Inspect shorting hardware, connection paddles, and/or knife switches. Remove
any foreign material from the case. Verify target reset.
4. Set relays in accordance with Relay settings sheets.
B. Electrical Tests
1. Perform insulation-resistance test on each circuit-to-frame. Determine from the
manufacturer's instructions the allowable procedures for this test for solid-state
and microprocessor-based relays.
2. Inspect targets and indicators.
a. Determine pickup and dropout of relay targets.
b. Verify operation of all light-emitting diode indicators.
c. Set contrast for liquid-crystal display readouts.
d. Test and record for minimum trip on all taps and leave on tap to be used.
Submit recorded test data to Engineer.
e. The minimum trip accuracy for protective relays is +/-5% and the time curve
calibration is +/-% from manufacture's rating and curves for the particular
relay.
f. Primary overall test for each phase and from each source.
C. Functional Operation
1. 27 - Undervoltage Relay or Element in Multifunction Relays
59 - Overvoltage
a. Determine dropout voltage.
b. Determine time delay.
c. Determine the time delay at a second point on the timing curve for inverse
time relays.
2. 32 - Reverse Power Relay or Element in Multifunction Relays
a. Determine minimum pickup at maximum torque angle.
b. Determine closing zone
c. Determine maximum torque angle
d. Determine time delay
e. Verify the time delay at a second point on the timing curve for inverse time
delay
3. 46 - Current Balance Relay or Element in Multifunction Relays
a. Determine pickup of each unit.
b. Determine percent slope.
c. Determine time delay.
4. 47 - Phase Sequence or Phase Balance Voltage Relay or Element in
Multifunction Relays
a. Determine positive sequence voltage to close the normally open contact.
b. Determine positive sequence voltage to open the normally closed contact
(undervoltage trip).
c. Verify negative sequence trip.
d. Determine time delay to close the normally open contact with sudden
application of 120 percent of pickup.
e. Determine time delay to close the normally closed contact upon removal of
voltage when previously set to rated system voltage.
5. 49T - Temperature (RTD) Relay or Element in Multifunction Relays
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 5
a. Determine trip resistance.
b. Determine reset resistance.
6. 50 - Instantaneous Overcurrent Relay or Element in Multifunction Relays
a. Determine pickup.
b. Determine dropout.
c. Determine time delay.
7. 51 - Time Overcurrent (51 C, 51 V) or Element in Multifunction Relays
a. Determine minimum pickup.
b. Determine time delays at two points on the time current curve.
8. 81 - Frequency Relay (Over and Under) or Element in Multifunction Relays
a. Determine overfrequency pickup.
b. Determine overfrequency time delay.
c. Determine underfrequency pickup.
d. Determine underfrequency time delay.
9. XX— other relays or functions as noted in plans and specifications.
D. Control Verification
1. Verify that each of the relay contacts performs its intended function in the control
scheme including breaker trip tests, close inhibit tests, 86 lockout tests, and alarm
functions.
E. System Tests
1. After the equipment is initially energized, measure magnitude and phase angle of
all inputs and compare to expected values.
2. Test critical logic and controls including source transfer logic, tie breaker
interlocks, generator starting and stopping, etc.
F. Test Values
1. Use manufacturer's recommended tolerances when other tolerances are not
specified.
2. When critical test points are specified, the relay shall be calibrated to those
points even though other test points may be out of tolerance.
3.4 GROUNDED SYSTEMS
A. Relays and alarms for ground protection and system neutrals shall be tested and
calibrated.
B. Earth resistance measurements shall be made by using "Megger" ground-tester in
accordance with the manufacturer's instructions.
C. All ground rods and switchgear communication panels or boards, panel, motor
control centers, switchboards, etc. with neutral bus disconnects.
D. All neutral busses with protective devices in "OFF" and ground bus disconnected.
E. Submit a complete NFPA 70E Flash Hazard Analysis from point of electrical
connection (normal utility derived power and/or on or off site self-generated power) to
end of run last device being distribution panel, motor disconnect, motor combination
starter or any device where Maintenance and Operation personnel have access of any
kind to energized or switching ports or devices. (Use IEEE 1584, NFPA 70E 2015 Annex
DA as standard.)
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609 - 6
1. Prepare and apply approved sunlight and ultra-violet resistant weatherproof tags
to all equipment as applicable with all approach, minimum distance, clothing, class to be
used, eye/face protection to be used and tag identification corresponding to identification
number on study.
END OF SECTION 26 96 09
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
TEST RECORD SHEETS
The test record sheets listed below shall be used to record testing of electrical equipment and of
the electrical installation as required by these specifications. Sample copies of each sheet are
attached.
Sheet Title
No.
1 Insulation Resistance (Power, Control Wire, and Cable) Test Record.
2 Insulation Resistance (Instrument Wire and Cable) Test Record
3 DC High Potential (Medium Voltage Cable) Test Record
4 Ground Electrode Testing Test Record
5 Neutral Grounding Resistor Test Record WHEN USED.
6 Bonding Resistance Readings (Nonelectrical Equipment/Structures) Test Record
7 Bonding Resistance Readings (Electrical Equipment) Test Record
8 Insulation Resistance (Transformer) Test Record
9 Insulation Resistance (Equipment) Test Record
10 Insulation Resistance (Rotating Equipment) Test Record
11 Equipment Absorption Ratio and Polarization Index Test Record.
12 Record Feeder Breaker Test Record
13 Breaker/Contactor Test Record
14 Motor Circuit Test Record
15 Medium Voltage Motor Circuit Test Record
16 Electric Motor Run-In Test Record with all VFD or Soft Start Programming As-left,
Minimum, Mid-Range, or Maximum Amps, Volts, Power Factor, Kilowatts, Kilo-Volt
Amperes, and Input Harmonic Analysis at each Rang
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 1
INSULATION RESISTANCE
(POWER, CONTROL WIRE, AND CABLE)
TEST RECORD
TEST EQUIPMENT: TEST VOLTAGE:
TEST EQUIPMENT: TEST VOLTAGE:
AMBIENT TEMPERATURE: °C OF DATE:
NOTES: 1. Perform Insulation Resistance Test(megger) between each conductor and all other
conductors and metallic sheath for cables with nonshielded conductors. Test between each
conductor and shield for multiconductor cables with shielded conductors. Record lowest
reading for each cable.
2. Use 1,000-V test set for cable rated 600 volts and 2,500-V test set for cable rated over 600
volts.
3. Readings will vary inversely with temperature and cable length. When the use of
temperature correction factors is specified, attach a second sheet with computed values.
Indicate on each sheet"measured" or"temperature corrected."
Panel No. Cable Wire or Cable Insulation
Circuit No. Wire Rated Resistance
Feeder No. Tagging Voltage Quantity Size From To me ohms * Initials
*Minimum acceptable values:
Cable/Wire Size Resistance When Cable
Cable Rated Test Resistance for or Amperage Connected to Equipment
Voltage Duration Cable Only (megohms) (ohms)
--------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 2
INSULATION RESISTANCE
(INSTRUMENT WIRE AND CABLE)
TEST RECORD
TEST EQUIPMENT: TEST VOLTAGE:
TEST EQUIPMENT: TEST VOLTAGE:
AMBIENT TEMPERATURE: °C OF DATE:
NOTES: 1. Record only the lowest value.
2. MP- Multi-pair cable. SP - Single pair cable.
3. Megger with instruments disconnected.
4. Use 250 volt (or lower voltage, when specified) range on DC test set.
5. Readings will vary with temperature and cable length.*
Conductor Shield to Overall Lead and Shield to
Cable Indicate to Conduit Conductor Conductor Shield to Armor Conduit
Number MP or (Single Pair to to Shield Shield
or SP Type Non- Conductor (Multipair (Multipair (Single Pair
Instrume Shielded (megohms Cables Cables Only Cables
nt (2) Cables) (megohms ) Only) (megohms) Only) Initials
Number (megohms) ) (1) (megohms) (megohms)
1 1
--------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 3
DC HIGH POTENTIAL (MEDIUM VOLTAGE CABLE)
TEST RECORD
CIRCUIT NUMBER: REF. DWG.:
CABLE SIZE: (SQ.MM.) (MCM) FROM: TO:
NUMBER OF CONDUCTORS: NO. OF SPLICES:
CABLELENGTH: MANUFACTURER:
INSULATION TYPE: THICKNESS:
JACKET MATERIAL:
WEATHER: TEMP.: °C OF % HUMIDITY: DATE:
TEST EQUIPMENT USED:
NOTES: 1. The test voltage shown below shall be reached in 10 equal voltage increments.
2. After each voltage increase, the leakage current shall be allowed to stabilize during a 1-
minute interval. If 1-minute intervals are insufficient to stabilize the current, the cable shall
be discharged, and the test repeated with new time intervals of greater, but still equal
duration.
3. Record the stabilized leakage current, in microamps, at the end of each time interval.
4. Allow the voltage to remain constant at the full test voltage and record the leakage current
for 5 minutes for unshielded cables and 15 minutes for shielded cables.
5. Read test equipment instruction manual prior to testing cable.
6. When the plotting of test results is specified, attach the second sheet with separate plot for
each phase. Note leakage current, in microamps, on "y" axis. Note step-voltage increase
on "x" axis, followed by time, in minutes, for the dielectric absorption portion of the test.
7. All other phases and shields to be grounded.
Voltage hold time
at each step k k k k k k k k k k
sec. V V V V V V V V V V
OA7
OB7
OC7
RECORD LEAKAGE CURRENT IN MICROAMPS
Time at SE MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN MIN
Kv C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
30
CABLE-RATED VOLTAGE TEST VOLTAGE
(kilovolts) (kilovolts)
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 4
GROUND ELECTRODE TESTING
TEST RECORD
TEST EQUIPMENT:
(Note 1) (Note 2)
REFERENCE DRAWING:
NOTES: 1. Record resistance-to-earth for each electrode with all other conductors disconnected.
Resistance not to exceed 25 ohms for any single anode.
2. Check continuity from each electrode to any test bar or other electrode such that the
complete ground loop is tested.
Resistance to Ambient
Rod Number Earth Temperature Weather Taps Initials/Date
(ohms) (°C/°F) (4)
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 5
NEUTRAL GROUNDING RESISTOR
TEST RECORD
TEST EQUIPMENT: TEST VOLTAGE:
TEST EQUIPMENT: TEST VOLTAGE:
NOTES: 1. Use 1,000-volt test set for 600-volt equipment and below, 2,500-volt test set for equipment
rated over 600 volts.
2. Resistor must be disconnected from ground and neutral during Insulation Resistance
(megger) and DC Overpotential Tests.
3. Resistor must be disconnected from neutral during Cold Resistance Test.
4. Apply DC Overpotential Test between terminals and ground for the complete device. (The
voltage applied between the terminals of each assembly and its grounded enclosure shall be
twice the rated AC voltage plus 1000 V when rated 600 V or less, or 2.25 times the rated AC
voltage plus 2000 V when rated over 600 V for 1 minute. This test is a Pass/Fail test based
purely on withstand alone.
5. Inspect assembly for damage and missing parts.
6. Check to assure that the center tap ratio is correct, when CT is supplied with resistor.
Verify resistor reterminated.
Tag. Cold Res. Insul. Res. Overpot. CT Ratio Reterm
No. (ohms) Fm
egohms)* 4 Pri-Sec 4 Initials/Date
*Minimum acceptable values:
VOLTAGE CLASS INSULATION RESISTANCE
(megohms)
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 6
BONDING RESISTANCE READINGS
(NONELECTRICAL EQUIPMENT/STRUCTURES)
TEST RECORD
TEST EQUIPMENT USED: WEATHER:
NOTES: 1. Vessels, tanks, and structural steel bonded to the main grounding system, dedicated ground
rod or foundation, as indicated on drawings listed below.
2. Measure resistance from ground wire tap (or anchor bolt)to tagged equipment frame or
structural steel.
EQUIPMENT TAG NO. MEASURED
OR DRAWING RESISTANCE INITIALS/DATE
STRUCTURE (ohms)
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 7
BONDING RESISTANCE READINGS
(ELECTRICAL EQUIPMENT)
TEST RECORD
TEST EQUIPMENT USED: WEATHER:
NOTES: 1. Electrical equipment bonded to the main grounding system or dedicated ground rod, as
indicated on drawings listed below.
2. Measure resistance from ground wire tap to tagged equipment bus bars, tagged equipment
enclosures, and any other points indicated on the drawings.
EQUIPMENT TAG NO. MEASURED
OR DRAWING RESISTANCE INITIALS/DATE
STRUCTURE (ohms)
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 8
INSULATION RESISTANCE
(TRANSFORMER)
TEST RECORD
SUBSTATION NO.: TEST EQUIPMENT:
NOTES: 1. Use 1,000-V test set for 600-volt equipment and below, 2,500-V test set for equipment rated
601 - 5,000 volts, and 5,000-V test set for equipment rated over 5,000 volts.
2. Test voltage to be applied for 1-minute duration, and reading taken.
3. Neutral must be disconnected from ground during test.
4. Record temperature of surrounding air temperature for dry-type transformers.
5. Readings will vary inversely with temperature. When the use of temperature correction
factors is specified, attach second sheet with computed values. Indicate on each sheet
"measured" or"temperature corrected."
RESISTANCE IN me ahoms Pri Voltage Pri-Sec Liquid
Equipment Primary Secondary to Rating or Temp.
Tag No. OA to OB to C to G QUA to G OB to G OC to G Se (kV) Air (°C/°F)
G c
*Minimum acceptable values:
VOLTAGE CLASS RESISTANCE (megohms)
TESTER'S INITIALS/DATE
---------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 9
INSULATION RESISTANCE (EQUIPMENT)
TEST RECORD
TEST EQUIPMENT: SUBSTATION:
AMBIENT TEMPERATURE: °C OF DATE:
REFERENCE DRAWING: REF. SEC.:
NOTES: 1. Use 1,000-V test set for equipment rated 600 volts and below, 2,500/5,000-V test set for
equipment rated over 600 volts.
2. For equipment with solid state control circuits, consult manufacturer's literature for maximum
test voltages.
Switchgea Test Rated Initials/
r INSULATION RESISTANCE (megohms) * Voltage Voltag Date
MCC e
(other) OA to G OB to G OC to QUA to OB OB to OC OC to OA (kV) (kV)
G
*Minimum acceptable values:
EQUIPMENT VOLTAGE CLASS RESISTANCE
(megohms)
TESTER'S INITIALS/DATE
------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 10
INSULATION RESISTANCE (ROTATING EQUIPMENT)
TEST RECORD
TEST EQUIPMENT: TEST VOLTAGE:
AMBIENT TEMPERATURE: °C OF DATE:
EQUIP. TEMP., IF KNOWN: °C OF HOW KNOWN:
NOTES: 1. Use 1,000-V test set for equipment 600-volt and below, 2,500/5,000-V test set for equipment
rated over 600 volts.
2. Test duration shall be 1 minute, note if otherwise:
3. Isolate all motor leads from one another and from frame, test phase separately, wherever
practical.
4. Document testing of low voltage and medium voltage equipment on separate sheets.
5. Readings will vary inversely with temperature. When the use of temperature correction
factors is specified, attach second sheet with computed values. Indicate on each sheet
"measured" or"temperature corrected."
Equipment Rated Equipmen
Tag No. INSULATION RESISTANCE (megohms) * Voltage t
Initial/Dat
e
OA to G OB to G OC to OA to OB to OC to
G � 013 0C � OA
*Minimum acceptable values:
VOLTAGE CLASS RESISTANCE (megohms)
------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 11
EQUIPMENT ABSORPTION RATIO
AND POLARIZATION INDEX
TEST RECORD
TEST EQUIPMENT: TEST VOLTAGE:
AMBIENT TEMPERATURE: °C OF DATE:
EQUIP. TEMP., IF KNOWN: °C OF REL. HUMIDITY:
NOTES: 1. Perform test as indicated on Test Records for each individual equipment type. Reference
the following sheets:
Transformers 8
Equipment 9
Motors and Generators 10
2. Absorption Ratio = 1-Minute Resistance Value
30-Second Resistance Value
3. Polarization Index = 10-Minute Resistance Value
1-Minute Resistance Value
OHMS TO OHMS TO OHMS TO DIELECTRIC
GROUND GROUND GROUND ABSORPTION POLARIZATION
30-SECOND 1-MINUTE 10-MINUTE RATIO INDEX
READING READING READING
OA TO GROUND OA TO GROUND OA TO GROUND
OHMS TO OHMS TO OHMS TO DIELECTRIC
GROUND GROUND GROUND ABSORPTION POLARIZATION
30-SECOND 1-MINUTE 10-MINUTE RATIO INDEX
READING READING READING
OB TO GROUND OB TO GROUND OB TO GROUND
OHMS TO OHMS TO OHMS TO DIELECTRIC
GROUND GROUND GROUND ABSORPTION POLARIZATION
30-SECOND 1-MINUTE 10-MINUTE RATIO INDEX
READING READING READING
OC TO GROUND OC TO GROUND OC TO GROUND
TESTER'S INITIALS/DATE
-------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 12
FEEDER BREAKER (480 V MCC)
TEST RECORD
EQUIPMENT DESIGNATION
LOAD (kW/kVA) VOLTAGE F.L.A.
CIRCUIT BREAKER MFG. RATING SETTING
CONDUCTOR SIZE POWER GROUND
1. Check nameplate data of breaker against approved vendor drawings.
2. Check breaker components for cleanliness.
3. Check mechanical function of breaker.
4. Check wiring for proper identification.
5. Check conduits/cables for tagging.
6. Check components for identification.
7. Check equipment for conformance of area classification.
8. Check installation for seals, breathers, and drains.
9. Verify power conductor continuity.
10. Check that power cable insulation resistance test(megger) is completed.
--------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 13
BREAKER/CONTACTOR(480 V MCC)
TEST RECORD
EQUIPMENT DESIGNATION
LOAD (kW/kVA) VOLTAGE F.L.A.
CIRCUIT BREAKER MFG. RATING SETTING
CONTACTOR MFG. SIZE
CONDUCTOR SIZE POWER CONTROL GROUND
1. Check nameplate data of breaker, contactor fuses and relays against
approved vendor drawings.
2. Check main and auxiliary contacts.
3. Check contactor/breaker components for cleanliness.
4. Check control fuses, CPT rating, and coil voltage.
5. Check mechanical function of contactor and breaker.
6. Check wiring for proper identification.
7. Check conduits/cables for tagging.
8. Check components for identification.
9. Check equipment for conformance to area classification.
10. Check installation for seals, breathers, and drains.
11. Verify continuity of all power and control leads.
12. Check that power and control cable Insulation Resistance Test(megger) is
completed.
13. Complete functional operation check of the control circuit using contract
drawings and approved vendor drawings. Close and open the contactor
using all control devices.
-------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 14
460 V MOTOR CIRCUIT (480 V MCC)
TEST RECORD
EQUIPMENT DESIGNATION
MOTOR TAG NO. VOLTAGE F.L.A.
KW/HP RPM S.F.
CIRCUIT BREAKER MFG. RATING SETTING
STARTER MFG. SIZE O/L HTR. SIZE
C.T. RATIO O/L RELAY SETTING
CONDUCTOR SIZE POWER GROUND
1. Check motor starter for cleanliness.
2. Check nameplate data and tagging of motor starter components for
conformance to approved vendor drawings.
3. Check conduits and/or cables for correct tagging.
4. Check equipment and installation for conformance to area classification.
5. Check main and auxiliary contacts of breaker and contactors.
6. Manually check mechanical operation of breaker, contactor, O/L relay, and
O/L reset device.
7. Check continuity of power and control cables.
8. Complete functional operation check of the motor control circuit using the
contract drawings and approved vendor drawings. Close and open the
starter using all control devices.
9. Verify proper operation of motor winding space heater unit.
--------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 15
MEDIUM VOLTAGE MOTOR CIRCUIT
TEST RECORD
EQUIPMENT DESIGNATION
MOTOR DESCRIPTION
TAG NO. SERIAL NUMBER.
MANUFACTURER SERVICE FACTOR.
KW/HP RATED VOLTAGE.
FLA
STARTER DESCRIPTION
MANUFACTURER C.T. RATIO
CONTACTOR RATING TYPE
RATED CURRENT RATED VOLTAGE
O/L RELAY SETTING
FUSE SIZE.
CONDUCTOR SIZE POWER CONTROL GROUND
1. Check motor starter for cleanliness.
2. Check nameplate data and tagging of motor starter components for
conformance to approved vendor drawings.
3. Check conduits and/or cables for correct tagging.
4. Check equipment and installation for conformance to area classification.
5. Check installation for seals, breathers, and drains.
6. Check main and auxiliary contacts of breaker and contactors.
7. Check mechanical operation of breakers, contactors, and relay and O/L
reset devices.
8. Check continuity of power and control cables.
9. Verify calibration and setting of protective relays.
10. Check wiring to surge arrestors, capacitors, stator RTDs and current
transformers.
11. Complete functional operation check of the motor control circuit using the
contract drawings and approved vendor drawings. Close and open the
starter using all control devices.
GENERAL COMMENTS
------------------------------------------------------------------------------------------
DISTRI BUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER ELECTRICAL COMMISIONING
REEDLEY, CA. SECTION 269609
Sheet 16
ELECTRIC MOTOR RUN-IN
TEST RECORD
TEST EQUIPMENT: REFERENCE DRAWING:
NOTES: 1. Duration of tests to comply with specifications.
TEST REMARKS INITIALS/DATE
RESISTANCE:
Bonding resistance measured from motor frame to
main ground/earth system tap.
ohms
VOLTAGE:
Actual voltage measured at Motor Control Center.
volts
ROTATION CHECK:
Bump motor to verify rotation. Motor to be
uncoupled.
NO LOAD CURRENT:
At beginning of test amps
At end of test amps
TEMPERATURE OF BEARING:
Check bearing for high temperature:
Before start:
15 minutes after start
30 minutes after start
1 hour after start
2 hours after start
3 hours after start
VIBRATION:
Make visual inspection during run-test. Record any
unusual vibration in remarks column.
NOISE:
Record any unusual noise in remarks column.
-------------------------------------------------------------------------------------------
DISTRIBUTION:
CONTRACTOR/Date
Contract 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER GENERAL COMMUNICATIONS
REEDLEY, CA. SECTION 265100 - 1
SECTION 270000 — GENERAL COMMUNICATIONS
PART 1 - GENERAL
1.1 RELATED SECTIONS
A. Drawings and General Provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
B. This specification section provides general conditions for all division 27
specifications. All contractors working with in the Division 27 specification shall
adhere to this specification and these related specifications:
Section 270528 Communication Infrastructure
Systems Section 271000 Structured Cabling
System
Section 272010 Uninterruptable Power
Supply
Division 26 : Electrical
Division 27 : Mechanical
1.2 REGULATORY REFERENCES
A. Contractor will comply will all Federal, State, Local Codes/Regulations and
Industries Standards.
1. Federal:
• California Electric Code(CEC) 2013 or latest approved Chapter 8:
"Communications Systems" Article 250: "Grounding"
• NFPA 70 - National Electric Code(NEC)
• FCC - Part 15, Part 68
• ADA—Americans with Disabilities Act
2. State of California:
• CCR Part 2 - California Building Code.
• CCR Part 3 - California Electrical Code
• Occupational Safety and Health Act (OSHA).
• Title 24, Building Standards, State of California.
• Title 19, California Code of Regulations.
• Title 8, Electrical Safety, State of California
3. ANSI Standards
• ANSI C2-2001 National Electrical Safety Code.
• ANSI C80.3 Specification for Zinc-coated Electrical Metallic Tubing.
• ANSI/UL 797 Electrical Metallic Tubing.
• ANSI/ICEA S-83-596-2001 - Fiber Optic Premises Distribution
Cable Technical Requirements.
4. Industry Standards:
• Telecommunications Industry Associations/Electronics Industry
Association (TIA/EIA)
TIA/EIA-568.0-D Commercial Building Telecommunications Cabling
Standard
TIA/EIA-568-1.D General Requirements
TIA/EIA-568-C.2 Balanced Twisted Pair Cabling Components Standard
CONTRACT 24-S-04
REEDLEY TOWER & EQUIPMENT SHELTER GENERAL COMMUNICATIONS
REEDLEY, CA. SECTION 265100 - 2
TIA/EIA-568-3-D Optical Fiber Cabling Components Standard
TIA/EIA-569-A Commercial Building Standard for Telecom Pathways
and Spaces
TIA/EIA-606 Administration Standard for the Telecommunications
Infrastructure of Commercial Grounding/Bonding
Requirements
TIA/EIA-758 Customer-Owned Outside Plant Telecommunications
Cabling Standard
TIA/EIA-758-1 Addendum No. 1 to TIA/EIA-758, Customer-
Owned Outside Plant Telecommunications Cabling
Standard
• National Electrical Manufacturer's Association (NEMA)
• Institute of Electrical and Electronic Engineers (IEEE)
802.3 (Ethernet)
802.3ab (Gigabit Ethernet over 4-pair Category 5e, 6 & 6A or
higher) 802.3Z (Gigabit Ethernet over optical fiber)
802.11 ac (Wireless LAN Specfications)
• Underwriters Laboratories Inc. (UL)
• International Organization for Standardization/International
Electromagnetic Commission (ISO/IEC) ISO 11801 Generic Cabling
for Customer Premises
• Building Industry Consulting Services International (BICSI)
Telecommunications Distribution Methods Manual (TDMM 13th
Edition or latest).
• ASCII - American Standard Code for information Interchange
• ASTM -American Society for Testing and Materials
B. If there is a conflict between applicable documents, then the more
stringent requirement shall apply. All documents listed are believed to be
the most current releases of the documents. The Contractor has the
responsibility to determine and adhere to the most recent release when
developing the proposal for installation.
C. This document does not replace any code, either partially or wholly. The
contractor must be aware of and comply with all local codes that may
impact this project.
1.3 SUMMARY OF WORK :
The Contractor shall provide all materials, tools, labor and services necessary to furnish
and install equipment and accessories associated with communication systems as
shown on the Plans and described within these Specifications. The Contractor shall
furnish all power supplies, disconnects, controls, and any other work as called for in all
Electrical and Electrical related work as called for in the Division 26 specifications and
plans. In addition, all conduit required by Divisions 27 and 28 and the associated
drawings. All systems, at project completion and before final acceptance, shall be
demonstrated to have a complete and working functional operation.
END OF SECTION 270000
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 1
SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Related Requirements:
1. Section 260536 "Cable Trays for Electrical Systems" for cable trays and accessories
serving electrical systems.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of cable tray.
1. Include data indicating dimensions and finishes for each type of cable tray indicated.
B. Shop Drawings: For each type of cable tray.
1. Show fabrication and installation details of cable trays, including plans, elevations, and
sections of components and attachments to other construction elements. Designate
components and accessories, including clamps, brackets, hanger rods, splice-plate
connectors, expansion-joint assemblies, straight lengths, and fittings.
C. Delegated-Design Submittal: For seismic restraints.
1. Seismic-Restraint Details: Signed and sealed by a qualified professional engineer,
licensed in the state where Project is located, who is responsible for their preparation.
2. Design Calculations: Calculate requirements for selecting seismic restraints.
3. Detail fabrication, including anchorages and attachments to structure and to supported
cable trays.
1.4 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Floor plans and sections, drawn to scale, on which the following items
are shown and coordinated with each other, using input from installers of the items involved:
1. Include scaled cable tray layout and relationships between components and adjacent
structural, electrical, and mechanical elements.
2. Vertical and horizontal offsets and transitions.
3. Clearances for access above and to side of cable trays.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 2
4. Vertical elevation of cable trays above the floor or below bottom of ceiling structure.
B. Seismic Qualification Certificates: For cable trays, accessories, and components, from
manufacturer.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
C. Field quality-control reports.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000
"Quality Requirements," to design cable tray supports and seismic bracing.
B. Seismic Performance: Cable trays and supports shall withstand the effects of earthquake
motions determined according to ASCE/SEI 7.
1. The term "withstand" means "the cable trays will remain in place without separation of
any parts when subjected to the seismic forces specified."
2. Component Importance Factor: 1.0
C. Thermal Movements: Allow for thermal movements from ambient and surface temperature
changes in cable tray installed outdoors.
2.2 GENERAL REQUIREMENTS FOR CABLE TRAYS
A. Cable Trays and Accessories: Identified as defined in NFPA 70 and marked for intended
location, application, and grounding.
1. Source Limitations: Obtain cable trays and components from single manufacturer.
B. Sizes and Configurations: See the Cable Tray Schedule on Drawings for specific requirements
for types, materials, sizes, and configurations.
C. Structural Performance: See articles for individual cable tray types for specific values for the
following parameters:
1. Uniform Load Distribution: Capable of supporting a uniformly distributed load on the
indicated support span when supported as a simple span and tested according to
NEMA VE 1.
2. Concentrated Load: A load applied at midpoint of span and centerline of tray.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 3
3. Load and Safety Factors: Applicable to both side rails and rung capacities.
2.3 MATERIALS AND FINISHES
A. Steel:
1. Straight Section and Fitting Side Rails and Rungs: Steel complies with the minimum
mechanical properties of ASTM A 1011/A 1011M, SS, Grade 33]
ASTM A 1008/A 1008M, Grade 33, Type 2.
2. Steel Tray Splice Plates: ASTM A 1011/A 1011M, HSLAS, Grade 50, Class 1.
3. Fasteners: Steel complies with the minimum mechanical properties of
ASTM A 510/A 510M, Grade 1008.
4. Finish: Mill galvanized before fabrication.
a. Standard: Comply with ASTM A 653/A 653M, G90.
b. Hardware: Galvanized, ASTM B 633.
5. Finish: Electroga Ivan ized before fabrication.
a. Standard: Comply with ASTM B 633.
b. Hardware: Galvanized, ASTM B 633.
6. Finish: Hot-dip galvanized after fabrication.
a. Standard: Comply with ASTM A 123/A 123M, Class B2.
b. Hardware: Chromium-zinc plated, ASTM F 1136.
7. Finish: Epoxy-resin paint.
a. Powder-Coat Enamel: Cable tray manufacturer's recommended primer and
corrosion-inhibiting treatment, with factory-applied powder-coat paint.
b. Epoxy-Resin Prime Coat: Cold-curing epoxy primer, MPI# 101.
C. Epoxy-Resin Topcoat: Epoxy, cold-cured, gloss, MPI# 77.
d. Hardware: Chromium-zinc plated, ASTM F 1136.
8. Finish: Factory-standard primer, ready for field painting, with chromium-zinc-plated
hardware according to ASTM F 1136.
9. Finish: Black oxide finish for support accessories and miscellaneous hardware according
to ASTM D 769.
B. Aluminum:
1. Materials: Alloy 6063-T6 according to ANSI H 35.1/H 35.1M for extruded components
and Alloy 5052-H32 or Alloy 6061-T6 according to ANSI H 35.1/H 35.1M for fabricated
parts.
2. Hardware: Chromium-zinc-plated steel, ASTM F 1136.
3. Hardware for Aluminum Cable Tray Used Outdoors: Stainless steel, Type 316,
ASTM F 593 and ASTM F 594.
C. Stainless Steel:
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 -4
1. Materials: Low-carbon, passivated, stainless steel, Type 304L or Type 316L,
ASTM F 593 and ASTM F 594.
2. Hardware for Stainless-Steel Cable Tray Used Outdoors: Stainless steel, Type 316,
ASTM F 593 and ASTM F 594.
2.4 CABLE TRAY ACCESSORIES
A. Fittings: Tees, crosses, risers, elbows, and other fittings as indicated, of same materials and
finishes as cable tray.
B. Covers: Made of same materials and with same finishes as cable tray.
C. Barrier Strips: Same materials and finishes as for cable tray.
D. Cable tray supports and connectors, including bonding jumpers, as recommended by cable
tray manufacturer.
2.5 WARNING SIGNS
A. Lettering: 1-1/2-inch high, black letters on yellow background with legend "Warning! Not To Be
Used as Walkway, Ladder, or Support for Ladders or Personnel."
B. Comply with requirements for fasteners in Section 260553 "Identification for Electrical
Systems."
2.6 SOURCE QUALITY CONTROL
A. Testing: Test and inspect cable trays according to NEMA FG 1 NEMA VE 1.
PART 3 - EXECUTION
3.1 CABLE TRAY INSTALLATION
A. Install cable trays according to NEMA FG 1 NEMA VE 2.
B. Install cable trays as a complete system, including fasteners, hold-down clips, support
systems, barrier strips, adjustable horizontal and vertical splice plates, elbows, reducers, tees,
crosses, cable dropouts, adapters, covers, and bonding.
C. Install cable trays so that the tray is accessible for cable installation and all splices are
accessible for inspection and adjustment.
D. Remove burrs and sharp edges from cable trays.
E. Join aluminum cable tray with splice plates; use four square neck-carriage bolts and locknuts.
F. Fasten cable tray supports to building structure and install seismic restraints.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 5
G. Design fasteners and supports to carry cable tray, the cables, and a concentrated load of 200
lb (90 kg). Comply with requirements in Section 260529 "Hangers and Supports for Electrical
Systems." Comply with seismic-restraint details according to Section 260548.16 "Seismic
Controls for Electrical Systems."
H. Place supports so that spans do not exceed maximum spans on schedules and provide
clearances shown on Drawings. Install intermediate supports when cable weight exceeds the
load-carrying capacity of the tray rungs.
I. Construct supports from channel members, threaded rods, and other appurtenances furnished
by cable tray manufacturer. Arrange supports in trapeze or wall-bracket form as required by
application.
J. Support bus assembly to prevent twisting from eccentric loading.
K. Install center-hung supports for single-rail trays designed for 60 versus 40 percent eccentric
loading condition, with a safety factor of 3.
L. Locate and install supports according to NEMA FG 1 NEMA VE 2. Do not install more than
one cable tray splice between supports.
M. Make connections to equipment with flanged fittings fastened to cable trays and to equipment.
Support cable trays independent of fittings. Do not carry weight of cable trays on equipment
enclosure.
N. Install expansion connectors where cable trays cross building expansion joints and in cable
tray runs that exceed dimensions recommended in NEMA FG 1 NEMA VE 2. Space
connectors and set gaps according to applicable standard.
O. Make changes in direction and elevation using manufacturer's recommended fittings.
P. Make cable tray connections using manufacturer's recommended fittings.
Q. Seal penetrations through fire and smoke barriers. Comply with requirements in
Section 078413 "Penetration Firestopping."
R. Install capped metal sleeves for future cables through firestop-sealed cable tray penetrations
of fire and smoke barriers.
S. Install cable trays with enough workspace to permit access for installing cables.
T. Install barriers to separate cables of different systems, such as power, communications, and
data processing; or of different insulation levels, such as 600, 5000, and 15 000 V.
U. Install permanent covers, if used, after installing cable. Install cover clamps according to
NEMA VE 2.
V. Clamp covers on cable trays installed outdoors with heavy-duty clamps.
W. Install warning signs in visible locations on or near cable trays after cable tray installation.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 6
3.2 CABLE TRAY GROUNDING
A. Ground cable trays according to NFPA 70 unless additional grounding is specified. Comply
with requirements in Section 270526 "Grounding and Bonding for Communications Systems."
B. Cable trays with communications cable shall be bonded together with splice plates listed for
grounding purposes or with listed bonding jumpers.
C. Cable trays with control conductors shall be bonded together with splice plates listed for
grounding purposes or with listed bonding jumpers.
D. When using epoxy- or powder-coat painted cable trays as a grounding conductor, completely
remove coating at all splice contact points or ground connector attachment. After completing
splice-to-grounding bolt attachment, repair the coated surfaces with coating materials
recommended by cable tray manufacturer.
E. Bond cable trays to power source for cables contained within with bonding conductors sized
according to NFPA 70, Article 250.122, "Size of Equipment Grounding Conductors."
3.3 CABLE INSTALLATION
A. Install cables only when each cable tray run has been completed and inspected.
B. Fasten cables on horizontal runs with cable clamps or cable ties according to NEMA VE 2.
Tighten clamps only enough to secure the cable, without indenting the cable jacket. Install
cable ties with a tool that includes an automatic pressure-limiting device.
C. Fasten cables on vertical runs to cable trays every 18 inches.
D. Fasten and support cables that pass from one cable tray to another or drop from cable trays to
equipment enclosures. Fasten cables to the cable tray at the point of exit and support cables
independent of the enclosure. The cable length between cable trays or between cable tray and
enclosure shall be no more than 72 inches.
3.4 CONNECTIONS
A. Remove paint from all connection points before making connections. Repair paint after the
connections are completed.
B. Connect pathways to cable trays according to requirements in NEMA VE 2 and NEMA FG 1.
3.5 FIELD QUALITY CONTROL
A. Perform the following tests and inspections:
1. After installing cable trays and after electrical circuitry has been energized, survey for
compliance with requirements.
CONTRACT 24-S-04
REEDLEY RADIO TOWER & EQUIPMENT SHELTER CABLE TRAYS
REEDLEY, CA. SECTION 270536 - 7
2. Visually inspect cable insulation for damage. Correct sharp corners, protuberances in
cable trays, vibrations, and thermal expansion and contraction conditions, which may
cause or have caused damage.
3. Verify that the number, size, and voltage of cables in cable trays do not exceed that
permitted by NFPA 70. Verify that communications or data-processing circuits are
separated from power circuits by barriers or are installed in separate cable trays.
4. Verify that there are no intruding items such as pipes, hangers, or other equipment in the
cable tray.
5. Remove dust deposits, industrial process materials, trash of any description, and any
blockage of tray ventilation.
6. Visually inspect each cable tray joint and each ground connection for mechanical
continuity. Check bolted connections between sections for corrosion. Clean and retorque
in suspect areas.
7. Check for improperly sized or installed bonding jumpers.
8. Check for missing, incorrect, or damaged bolts, bolt heads, or nuts. When found, replace
with specified hardware.
9. Perform visual and mechanical checks for adequacy of cable tray grounding; verify that
all takeoff raceways are bonded to cable trays. Test entire cable tray system for
continuity. Maximum allowable resistance is 1 ohm.
B. Prepare test and inspection reports.
3.6 PROTECTION
A. Protect installed cable trays and cables.
1. Install temporary protection for cables in open trays to safeguard exposed cables against
falling objects or debris during construction. Temporary protection for cables and cable
tray can be constructed of wood or metal materials and shall remain in place until the
risk of damage is over.
2. Repair damage to galvanized finishes with zinc-rich paint recommended by cable tray
manufacturer.
3. Repair damage to paint finishes with matching touchup coating recommended by cable
tray manufacturer.
END OF SECTION 270536
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SLEEVES
REEDLEY, CA. SECTION 270544 - 1
SECTION 270544 - SLEEVES AND SLEEVE SEALS FOR COMMUNICATIONS PATHWAYS
AND CABLING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Sleeves for pathway and cable penetration of non-fire-rated construction walls
and floors.
2. Sleeve-seal systems.
3. Sleeve-seal fittings.
4. Grout.
5. Silicone sealants.
B. Related Requirements:
1. Section 078413 "Penetration Firestopping" for penetration firestopping installed
in fire-resistance-rated walls, horizontal assemblies, and smoke barriers, with
and without penetrating items.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
PART 2 - PRODUCTS
2.1 SLEEVES
A. Wall Sleeves:
1. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc
coated, plain ends.
2. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron
pressure pipe, with plain ends and integral waterstop unless otherwise indicated.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SLEEVES
REEDLEY, CA. SECTION 270544 - 2
B. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies:
Galvanized-steel sheet; 0.0239-inch minimum thickness; round tube closed with
welded longitudinal joint, with tabs for screw-fastening the sleeve to the board.
C. PVC-Pipe Sleeves: ASTM D 1785, Schedule 40.
D. Molded-PVC Sleeves: With nailing flange for attaching to wooden forms.
E. Molded-PE or -PP Sleeves: Removable, tapered-cup shaped, and smooth outer
surface with nailing flange for attaching to wooden forms.
F. Sleeves for Rectangular Openings:
1. Material: Galvanized-steel sheet.
2. Minimum Metal Thickness:
a. For sleeve cross-section rectangle perimeter less than 50 inches and with
no side larger than 16 inches, thickness shall be 0.052 inch .
b. For sleeve cross-section rectangle perimeter 50 inches or more and one or
more sides larger than 16 inches , thickness shall be 0.138 inch .
2.2 SLEEVE-SEAL SYSTEMS
A. Description: Modular sealing device, designed for field assembly, to fill annular space
between sleeve and pathway or cable.
2.3 SLEEVE-SEAL FITTINGS
A. Description: Manufactured plastic, sleeve-type, waterstop assembly made for
embedding in concrete slab or wall. Unit shall have plastic or rubber waterstop collar
with center opening to match piping OD.
2.4 GROUT
A. Description: Nonshrink; recommended for interior and exterior sealing openings in non-
fire-rated walls or floors.
B. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting,
dry, hydraulic-cement grout.
C. Design Mix: 5000-psi , 28-day compressive strength.
D. Packaging: Premixed and factory packaged.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SLEEVES
REEDLEY, CA. SECTION 270544 - 3
2.5 SILICONE SEALANTS
A. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric
sealants of grade indicated below.
1. Grade: Pourable (self-leveling) formulation for openings in floors and other
horizontal surfaces that are not fire rated.
B. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed,
expand and cure in place to produce a flexible, nonshrinking foam.
PART 3 - EXECUTION
3.1 SLEEVE INSTALLATION FOR NON-FIRE-RATED ELECTRICAL PENETRATIONS
A. Comply with NECA 1.
B. Comply with NEMA VE 2 for cable tray and cable penetrations.
C. Sleeves for Conduits Penetrating Above-Grade Non-Fire-Rated Concrete and
Masonry-Unit Floors and Walls:
1. Interior Penetrations of Non-Fire-Rated Walls and Floors:
a. Seal annular space between sleeve and pathway or cable, using joint
sealant appropriate for size, depth, and location of joint. Comply with
requirements in Section 079200 "Joint Sealants."
b. Seal space outside of sleeves with mortar or grout. Pack sealing material
solidly between sleeve and wall so no voids remain. Tool exposed surfaces
smooth; protect material while curing.
2. Use pipe sleeves unless penetration arrangement requires rectangular sleeved
opening.
3. Size pipe sleeves to provide 1/4-inch annular clear space between sleeve and
pathway or cable unless sleeve seal is to be installed or unless seismic criteria
require different clearance.
4. Install sleeves for wall penetrations unless core-drilled holes or formed openings
are used. Install sleeves during erection of walls. Cut sleeves to length for
mounting flush with both surfaces of walls. Deburr after cutting.
5. Install sleeves for floor penetrations. Extend sleeves installed in floors 2 inches
above finished floor level. Install sleeves during erection of floors.
D. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies:
1. Use circular metal sleeves unless penetration arrangement requires rectangular
sleeved opening.
2. Seal space outside of sleeves with approved joint compound for gypsum board
assemblies.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SLEEVES
REEDLEY, CA. SECTION 270544 -4
E. Roof-Penetration Sleeves: Seal penetration of individual pathways and cables with
flexible boot-type flashing units applied in coordination with roofing work.
F. Aboveground, Exterior-Wall Penetrations: Seal penetrations using steel pipe sleeves
and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear
space between pipe and sleeve for installing mechanical sleeve seals.
G. Underground, Exterior-Wall and Floor Penetrations: Install cast-iron pipe sleeves. Size
sleeves to allow for 1-inch annular clear space between pathway or cable and sleeve
for installing sleeve-seal system.
3.2 SLEEVE-SEAL-SYSTEM INSTALLATION
A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at
pathway entries into building.
B. Install type and number of sealing elements recommended by manufacturer for
pathway or cable material and size. Position pathway or cable in center of sleeve.
Assemble mechanical sleeve seals and install in annular space between pathway or
cable and sleeve. Tighten bolts against pressure plates that cause sealing elements to
expand and make watertight seal.
3.3 SLEEVE-SEAL-FITTING INSTALLATION
A. Install sleeve-seal fittings in new walls and slabs as they are constructed.
B. Assemble fitting components of length to be flush with both surfaces of concrete slabs
and walls. Position waterstop flange to be centered in concrete slab or wall.
C. Secure nailing flanges to concrete forms.
D. Using grout, seal the space around outside of sleeve-seal fittings.
END OF SECTION 270544
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER COMMUNICATIONS ROOM
REEDLEY, CA. FITTINGS
SECTION 271100 - 1
SECTION 271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Telecommunications mounting elements.
2. Backboards.
3. Telecommunications equipment racks and cabinets.
4. Grounding.
B. Related Requirements:
1. Section 270536 "Cable Trays for Communications Systems" for cable trays and
accessories.
2. Section 271300 "Communications Backbone Cabling" for voice and data cabling
associated with system panels and devices.
3. Section 271500 "Communications Horizontal Cabling" for voice and data cabling
associated with system panels and devices.
4. Section 280513 "Conductors and Cables for Electronic Safety and Security" for
voice and data cabling associated with system panels and devices.
1.3 DEFINITIONS
A. BICSI: Building Industry Consulting Service International.
B. LAN: Local area network.
C. RCDD: Registered Communications Distribution Designer.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual
components and profiles, and finishes for equipment racks and cabinets.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER COMMUNICATIONS ROOM
REEDLEY, CA. FITTINGS
SECTION 271100 - 2
2. Include rated capacities, operating characteristics, electrical characteristics, and
furnished specialties and accessories.
B. Shop Drawings: For communications equipment room fittings. Include plans,
elevations, sections, details, and attachments to other work.
1. Detail equipment assemblies and indicate dimensions, weights, loads, required
clearances, method of field assembly, components, and location and size of each
field connection.
2. Equipment Racks and Cabinets: Include workspace requirements and access for
cable connections.
3. Grounding: Indicate location of grounding bus bar and its mounting detail
showing standoff insulators and wall mounting brackets.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For installation supervisor, and field inspector.
B. Seismic Qualification Certificates: For equipment frames from manufacturer.
1. Basis for Certification: Indicate whether withstand certification is based on actual
test of assembled components or on calculation.
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and
locate and describe mounting and anchorage provisions. Base certification on
the maximum number of components capable of being mounted in each rack
type. Identify components on which certification is based.
3. Detailed description of equipment anchorage devices on which the certification is
based and their installation requirements.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: Cabling Installer must have personnel certified by BICSI on
staff.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Seismic Performance: Equipment frames shall withstand the effects of earthquake
motions determined according to ASCE/SEI 7.
1. The term "withstand" means "the unit will remain in place without separation of
any parts from the device when subjected to the seismic forces specified and the
unit will be fully operational after the seismic event."
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER COMMUNICATIONS ROOM
REEDLEY, CA. FITTINGS
SECTION 271100 - 3
2.2 BACKBOARDS
A. Backboards: Plywood, fire-retardant treated, 3/4 by 48 by 96 inches. Comply with
requirements for plywood backing panels specified in Section 061000 "Rough
Carpentry."
2.3 EQUIPMENT FRAMES
A. General Frame Requirements:
1. Distribution Frames: Freestanding and wall-mounting, modular-steel units
designed for telecommunications terminal support and coordinated with
dimensions of units to be supported.
2. Module Dimension: Width compatible with EIA 310-D standard, 19-inch
panel mounting.
3. Finish: Manufacturer's standard, baked-polyester powder coat.
B. Floor-Mounted Racks: Modular-type,steel or aluminum construction.
1. Vertical and horizontal cable management channels, top and bottom cable
troughs, grounding lug, and a power strip.
2. Baked-polyester powder coat finish.
C. Cable Management for Equipment Frames:
1. Metal, with integral wire retaining fingers.
2. Baked-polyester powder coat finish.
3. Vertical cable management panels shall have front and rear channels, with
covers.
4. Provide horizontal crossover cable manager at the top of each relay rack, with a
minimum height of two rack units each.
2.4 LABELING
A. Comply with TIA/EIA-606-A and UL 969 for a system of labeling materials, including
label stocks, laminating adhesives, and inks used by label printers.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Comply with NECA 1.
B. Comply with BICSI TDMM for layout and installation of communications equipment
rooms.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER COMMUNICATIONS ROOM
REEDLEY, CA. FITTINGS
SECTION 271100 - 4
C. Bundle, lace, and train conductors and cables to terminal points without exceeding
manufacturer's limitations on bending radii. Install lacing bars and distribution spools.
D. Coordinate layout and installation of communications equipment with Owner's
telecommunications and LAN equipment and service suppliers. Coordinate service
entrance arrangement with local exchange carrier.
1. Meet jointly with telecommunications and LAN equipment suppliers, local
exchange carrier representatives, and Owner to exchange information and agree
on details of equipment arrangements and installation interfaces.
2. Record agreements reached in meetings and distribute them to other
participants.
3. Adjust arrangements and locations of distribution frames, cross-connects, and
patch panels in equipment rooms to accommodate and optimize arrangement
and space requirements of telephone switch and LAN equipment.
4. Adjust arrangements and locations of equipment with distribution frames, cross-
connects, and patch panels of cabling systems of other communications,
electronic safety and security, and related systems that share space in the
equipment room.
E. Coordinate location of power raceways and receptacles with locations of
communications equipment requiring electrical power to operate.
3.2 SLEEVE AND SLEEVE SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS
A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies.
Comply with requirements in Section 270544 "Sleeves and Sleeve Seals for
Communications Pathways and Cabling."
3.3 FIRESTOPPING
A. Comply with requirements in Section 078413 "Penetration Firestopping."
B. Comply with TIA-569-B, Annex A, "Firestopping."
C. Comply with BICSI TDMM, "Firestopping Systems" Article.
3.4 GROUNDING
A. Install grounding according to BICSI TDMM, "Grounding, Bonding, and Electrical
Protection" Chapter.
B. Comply with J-STD-607-A.
C. Locate grounding bus bar to minimize the length of bonding conductors. Fasten to wall
allowing at least 2-inch clearance behind the grounding bus bar. Connect grounding
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER COMMUNICATIONS ROOM
REEDLEY, CA. FITTINGS
SECTION 271100 - 5
bus bar with a minimum No. 4 AWG grounding electrode conductor from grounding bus
bar to suitable electrical building ground.
D. Bond metallic equipment to the grounding bus bar, using not smaller than No. 6 AWG
equipment grounding conductor.
1. Bond the shield of shielded cable to the grounding bus bar in communications
rooms and spaces.
3.5 IDENTIFICATION
A. Identify system components, wiring, and cabling complying with TIA/EIA-606-A.
Comply with requirements in Section 260553 "Identification for Electrical Systems."
B. Comply with requirements in Section 099123 "Interior Painting" for painting
backboards. For fire-resistant plywood, do not paint over manufacturer's label.
C. Paint and label colors for equipment identification shall comply with TIA/EIA-606-A for
Class 2 level of administration including optional identification requirements of this
standard.
D. Labels shall be preprinted or computer-printed type.
END OF SECTION 271100
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 - 1
SECTION 311000 - SITE CLEARING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Protecting existing vegetation to remain.
2. Removing existing vegetation.
3. Clearing and grubbing.
4. Stripping and stockpiling topsoil.
5. Stripping and stockpiling rock.
6. Removing above- and below-grade site improvements.
7. Disconnecting, capping or sealing, and removing or abandoning site utilities in
place.
8. Temporary erosion and sedimentation control.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for temporary erosion- and
sedimentation-control measures.
C. Related Requirements:
1. Section 01500 "Temporary Facilities and Controls" for temporary erosion- and
sedimentation-control measures.
1.3 DEFINITIONS
A. Subsoil: Soil beneath the level of subgrade; soil beneath the topsoil layers of a
naturally occurring soil profile, typified by less than 1 percent organic matter and few
soil organisms.
B. Surface Soil: Soil that is present at the top layer of the existing soil profile. In
undisturbed areas, surface soil is typically called "topsoil," but in disturbed areas such
as urban environments, the surface soil can be subsoil.
C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or
existing in-place surface soil; the zone where plant roots grow.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 - 2
D. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or
existing in-place surface soil; the zone where plant roots grow. Its appearance is
generally friable, pervious, and black or a darker shade of brown, gray, or red than
underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects
larger than 2 inches in diameter; and free of weeds, roots, toxic materials, or other
nonsoil materials.
E. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.4 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.5 MATERIAL OWNERSHIP
A. Except for materials indicated to be stockpiled or otherwise remain Owner's property,
cleared materials shall become Contractor's property and shall be removed from
Project site.
1.6 INFORMATIONAL SUBMITTALS
A. Existing Conditions: Documentation of existing trees and plantings, adjoining
construction, and site improvements that establishes preconstruction conditions that
might be misconstrued as damage caused by site clearing.
1. Use sufficiently detailed photographs or video recordings.
B. Topsoil stripping and stockpiling program.
C. Rock stockpiling program.
D. Record Drawings: Identifying and accurately showing locations of capped utilities and
other subsurface structural, electrical, and mechanical conditions.
1.7 QUALITY ASSURANCE
A. Topsoil Stripping and Stockpiling Program: Prepare a written program to systematically
demonstrate the ability of personnel to properly follow procedures and handle materials
and equipment during the Work. Include dimensioned diagrams for placement and
protection of stockpiles.
B. Rock Stockpiling Program: Prepare a written program to systematically demonstrate
the ability of personnel to properly follow procedures and handle materials and
equipment during the Work. Include dimensioned diagrams for placement and
protection of stockpiles.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 - 3
1.8 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent
occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used
facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed trafficways if required by
Owner or authorities having jurisdiction.
B. Improvements on Adjoining Property: Authority for performing site clearing indicated on
property adjoining Owner's property will be obtained by Owner before award of
Contract.
1. Do not proceed with work on adjoining property until directed by Architect.
C. Salvageable Improvements: Carefully remove items indicated to be salvaged and store
on Owner's premises where indicated.
D. Utility Locator Service: Notify utility locator service for area where Project is located
before site clearing.
E. Do not commence site clearing operations until temporary erosion- and sedimentation-
control measures are in place.
F. Soil Stripping, Handling, and Stockpiling: Perform only when the soil is dry or slightly
moist.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Satisfactory Soil Material: Requirements for satisfactory soil material are specified in
Section 312000 "Earth Moving."
1. Obtain approved borrow soil material off-site when satisfactory soil material is not
available on-site.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during
construction.
B. Protect existing site improvements to remain from damage during construction.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 -4
1. Restore damaged improvements to their original condition, as acceptable to
Owner.
3.2 TEMPORARY EROSION AND SEDIMENTATION CONTROL
A. Provide temporary erosion- and sedimentation-control measures to prevent soil erosion
and discharge of soil-bearing water runoff or airborne dust to adjacent properties and
walkways, according to requirements of authorities having jurisdiction.
B. Verify that flows of water redirected from construction areas or generated by
construction activity do not enter or cross protection zones.
C. Inspect, maintain, and repair erosion- and sedimentation-control measures during
construction until permanent vegetation has been established.
D. Remove erosion and sedimentation controls, and restore and stabilize areas disturbed
during removal.
3.3 EXISTING UTILITIES
A. Owner will arrange for disconnecting and sealing indicated utilities that serve existing
structures before site clearing, when requested by Contractor.
1. Verify that utilities have been disconnected and capped before proceeding with
site clearing.
B. Locate, identify, disconnect, and seal or cap utilities indicated to be removed or
abandoned in place.
1. Arrange with utility companies to shut off indicated utilities.
2. Owner will arrange to shut off indicated utilities when requested by Contractor.
C. Locate, identify, and disconnect utilities indicated to be abandoned in place.
D. Interrupting Existing Utilities: Do not interrupt utilities serving facilities occupied by
Owner or others, unless permitted under the following conditions and then only after
arranging to provide temporary utility services according to requirements indicated:
1. Notify Resident Engineer not less than two days in advance of proposed utility
interruptions.
2. Do not proceed with utility interruptions without Architect's written permission.
E. Excavate for and remove underground utilities indicated to be removed.
F. Removal of underground utilities is included in earthwork sections; in applicable fire
suppression, plumbing, HVAC, electrical, communications, electronic safety and
security, and utilities sections; and in Section 024116 "Structure Demolition" and
Section 024119 "Selective Demolition."
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 - 5
3.4 CLEARING AND GRUBBING
A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new
construction.
1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be
relocated.
2. Grind down stumps and remove roots larger than 2 inches in diameter,
obstructions, and debris to a depth of 18 inches below exposed subgrade.
3. Use only hand methods or air spade for grubbing within protection zones.
4. Chip removed tree branches and dispose of off-site.
B. Fill depressions caused by clearing and grubbing operations with satisfactory soil
material unless further excavation or earthwork is indicated.
1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches,
and compact each layer to a density equal to adjacent original ground.
3.5 TOPSOIL STRIPPING
A. Remove sod and grass before stripping topsoil.
B. Strip topsoil to depth indicated on Drawings in a manner to prevent intermingling with
underlying subsoil or other waste materials.
1. Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel,
and other objects larger than 2 inches in diameter; trash, debris, weeds, roots,
and other waste materials.
C. Stockpile topsoil away from edge of excavations without intermixing with subsoil or
other materials. Grade and shape stockpiles to drain surface water. Cover to prevent
windblown dust and erosion by water.
1. Limit height of topsoil stockpiles to72 inches .
2. Do not stockpile topsoil within protection zones.
3. Dispose of surplus topsoil. Surplus topsoil is that which exceeds quantity
indicated to be stockpiled or reused.
4. Stockpile surplus topsoil to allow for respreading deeper topsoil.
3.6 STOCKPILING ROCK
A. Remove from area indicated on Drawings naturally formed rocks that measure more
than 1 foot across in least dimension. Do not include excavated or crushed rock.
1. Separate or wash off non-rock materials from rocks, including soil, clay lumps,
gravel, and other objects larger than 2 inches in diameter; trash, debris, weeds,
roots, and other waste materials.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER SITE CLEARING
REEDLEY, CA. SECTION 311000 - 6
B. Stockpile rock where indicated on Drawings away from edge of excavations without
intermixing with other materials. Cover to prevent windblown debris from accumulating
among rocks.
1. Limit height of rock stockpiles to 36 inches .
2. Do not stockpile rock within protection zones.
3. Dispose of surplus rock. Surplus rock is that which exceeds quantity indicated to
be stockpiled or reused.
4. Stockpile surplus rock to allow later use by the Owner.
3.7 SITE IMPROVEMENTS
A. Remove existing above- and below-grade improvements as indicated and necessary to
facilitate new construction.
3.8 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials,
and waste materials including trash and debris, and legally dispose of them off Owner's
property.
B. Burning tree, shrub, and other vegetation waste is permitted according to burning
requirements and permitting of authorities having jurisdiction. Control such burning to
produce the least smoke or air pollutants and minimum annoyance to surrounding
properties. Burning of other waste and debris is prohibited.
C. Separate recyclable materials produced during site clearing from other nonrecyclable
materials. Store or stockpile without intermixing with other materials and transport them
to recycling facilities. Do not interfere with other Project work.
END OF SECTION 311000
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 1
SECTION 312000 - EARTH MOVING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Section Includes:
1. Excavating and filling for rough grading the Site.
2. Preparing subgrades for slabs-on-grade
3. Excavating and backfilling for buildings and structures.
4. Drainage course for concrete slabs-on-grade.
5. Subsurface drainage backfill for walls and trenches.
6. Excavating and backfilling trenches for utilities and pits for buried utility
structures.
B. Related Requirements:
1. Section 033000 "Cast-in-Place Concrete" for granular course if placed over vapor
retarder and beneath the slab-on-grade.
2. Section 311000 "Site Clearing" for site stripping, grubbing, stripping and
stockpiling topsoil, and removal of above- and below-grade improvements and
utilities.
1.3 UNIT PRICES
A. Work of this Section is affected by unit prices for earth moving specified in
Section 012200 "Unit Prices."
B. Quantity allowances for earth moving are included in Section 012100 "Allowances."
1.4 DEFINITIONS
A. Backfill: Soil material or controlled low-strength material used to fill an excavation.
1. Initial Backfill: Backfill placed beside and over pipe in a trench, including
haunches to support sides of pipe.
2. Final Backfill: Backfill placed over initial backfill to fill a trench.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 2
B. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench
before laying pipe.
C. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.
D. Drainage Course: Aggregate layer supporting the slab-on-grade that also minimizes
upward capillary flow of pore water.
E. Excavation: Removal of material encountered above subgrade elevations and to lines
and dimensions indicated.
1. Authorized Additional Excavation: Excavation below subgrade elevations or
beyond indicated lines and dimensions as directed by the Engineer. Authorized
additional excavation and replacement material will be paid for according to
Contract provisions for unit prices.
2. Bulk Excavation: Excavation more than 10 fee in width and more than 30 feet in
length.
3. Unauthorized Excavation: Excavation below subgrade elevations or beyond
indicated lines and dimensions without direction by Engineer. Unauthorized
excavation, as well as remedial work directed by Engineer, shall be without
additional compensation.
F. Fill: Soil materials used to raise existing grades.
G. Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and
boulders of rock material that exceed 1 cu. yd. for bulk excavation or[3/4 cu. yd. for
footing, trench, and pit excavation that cannot be removed by rock-excavating
equipment equivalent to the following in size and performance ratings, without
systematic drilling, ram hammering, ripping, or blasting, when permitted:
1. Equipment for Footing, Trench, and Pit Excavation: Late-model, track-mounted
hydraulic excavator; equipped with a 42-inch maximum-width, short-tip-radius
rock bucket; rated at not less than 138-hp flywheel power with bucket-curling
force of not less than 28,700 Ibf and stick-crowd force of not less than 18,400 Ibf
with extra-long reach boom.
2. Equipment for Bulk Excavation: Late-model, track-mounted loader; rated at not
less than 230-hp flywheel power and developing a minimum of 47,992-Ibf
breakout force with a general-purpose bare bucket.
H. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs,
mechanical and electrical appurtenances, or other man-made stationary features
constructed above or below the ground surface.
I. Subbase Course: Aggregate layer placed between the subgrade and base course for
hot-mix asphalt pavement, or aggregate layer placed between the subgrade and a
cement concrete pavement or a cement concrete or hot-mix asphalt walk.
J. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill
immediately below subbase, drainage fill, drainage course, or topsoil materials.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 3
K. Utilities: On-site underground pipes, conduits, ducts, and cables as well as
underground services within buildings.
1.5 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct preexcavation conference at Project site.
1. Review methods and procedures related to earthmoving, including, but not
limited to, the following:
a. Personnel and equipment needed to make progress and avoid delays.
b. Coordination of Work with utility locator service.
C. Coordination of Work and equipment movement with the locations of tree-
and plant-protection zones.
d. Extent of trenching by hand or with air spade.
e. Field quality control.
1.6 ACTION SUBMITTALS
A. Product Data: For each type of the following manufactured products required:
1. Geotextiles.
2. Controlled low-strength material, including design mixture.
3. Warning tapes.
B. Samples for Verification: For the following products, in sizes indicated below:
1. Geotextile: 12 by 12 inches.
1.7 INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified testing agency.
B. Material Test Reports: For each on-site and borrow soil material proposed for fill and
backfill as follows:
1. Classification according to ASTM D 2487.
2. Laboratory compaction curve according to ASTM D 698.
C. Preexcavation Photographs or Videotape: Show existing conditions of adjoining
construction and site improvements, including finish surfaces that might be
misconstrued as damage caused by earth-moving operations. Submit before earth
moving begins.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 4
1.8 QUALITY ASSURANCE
A. Geotechnical Testing Agency Qualifications: Qualified according to ASTM E 329 and
ASTM D 3740 for testing indicated.
1.9 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent
occupied or used facilities during earth-moving operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used
facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed traffic ways if required by
Owner or authorities having jurisdiction.
B. Improvements on Adjoining Property: Authority for performing earth moving indicated
on property adjoining Owner's property will be obtained by Owner before award of
Contract.
1. Do not proceed with work on adjoining property until directed by Engineer.
C. Utility Locator Service: Notify utility locator service for area where Project is located
before beginning earth-moving operations.
D. Do not commence earth-moving operations until temporary site fencing and erosion-
and sedimentation-control measures specified in Section 015000 "Temporary Facilities
and Controls"and Section 311000 "Site Clearing" are in place.
E. Do not commence earth-moving operations until plant-protection measures specified in
Section 015639 "Temporary Tree and Plant Protection" are in place.
F. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Erection of sheds or structures.
5. Impoundment of water.
6. Excavation or other digging unless otherwise indicated.
7. Attachment of signs to or wrapping materials around trees or plants unless
otherwise indicated.
G. Do not direct vehicle or equipment exhaust towards protection zones.
H. Prohibit heat sources, flames, ignition sources, and smoking within or near protection
zones.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 5
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are
not available from excavations.
B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according
to ASTM D 2487, or a combination of these groups; free of rock or gravel larger than 3
inches in any dimension, debris, waste, frozen materials, vegetation, and other
deleterious matter.
C. Unsatisfactory Soils: Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and
PT according to ASTM D 2487, or a combination of these groups.
1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent
of optimum moisture content at time of compaction.
D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel,
crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90
percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200
sieve.
E. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel,
crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent
passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
F. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel,
crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; except with 100
percent passing a 1-inch sieve and not more than 8 percent passing a No. 200 sieve.
G. Drainage Course: Narrowly graded mixture of washed crushed stone or crushed or
uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent
passing a 1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.
H. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone
and natural sand; ASTM D 448; coarse-aggregate grading Size 67; with 100 percent
passing a 1-inch sieve and zero to 5 percent passing a No. 4 sieve.
I. Sand: ASTM C 33/C 33M; fine aggregate.
J. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense
state.
1. UV Stability: 50 percent after 500 hours' exposure; ASTM D 4355.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 6
2.2 ACCESSORIES
A. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured
for marking and identifying underground utilities, 6 inches wide and 4 mils thick,
continuously inscribed with a description of the utility; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
B. Detectable Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape
manufactured for marking and identifying underground utilities, a minimum of 6 inches
wide and 4 mils thick, continuously inscribed with a description of the utility, with
metallic core encased in a protective jacket for corrosion protection, detectable by
metal detector when tape is buried up to 30 inches deep; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage
caused by settlement, lateral movement, undermining, washout, and other hazards
created by earth-moving operations.
B. Protect and maintain erosion and sedimentation controls during earth-moving
operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove
temporary protection before placing subsequent materials.
3.2 DEWATERING
A. Prevent surface water and ground water from entering excavations, from ponding on
prepared subgrades, and from flooding Project site and surrounding area.
B. Protect subgrades from softening, undermining, washout, and damage by rain or water
accumulation.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 7
1. Reroute surface water runoff away from excavated areas. Do not allow water to
accumulate in excavations. Do not use excavated trenches as temporary
drainage ditches.
3.3 EXCAVATION FOR STRUCTURES
A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1
inch. If applicable, extend excavations a sufficient distance from structures for placing
and removing concrete formwork, for installing services and other construction, and for
inspections.
1. Excavations for Footings and Foundations: Do not disturb bottom of excavation.
Excavate by hand to final grade just before placing concrete reinforcement. Trim
bottoms to required lines and grades to leave solid base to receive other work.
2. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility
Structures: Excavate to elevations and dimensions indicated within a tolerance of
plus or minus 1 inch. Do not disturb bottom of excavations intended as bearing
surfaces.
3.4 EXCAVATION FOR UTILITY TRENCHES
A. Excavate trenches to indicated gradients, lines, depths, and elevations.
1. Beyond building perimeter, excavate trenches to allow installation of top of pipe
below frost line.
B. Excavate trenches to uniform widths to provide the following clearance on each side of
pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches
higher than top of pipe or conduit unless otherwise indicated.
1. Clearance: 12 inches each side of pipe or conduit.
C. Trench Bottoms: Excavate trenches 4 inches deeper than bottom of pipe and conduit
elevations to allow for bedding course. Hand-excavate deeper for bells of pipe.
1. Excavate trenches 6 inches deeper than elevation required in rock or other
unyielding bearing material to allow for bedding course.
3.5 SUBGRADE INSPECTION
A. Notify Engineer when excavations have reached required subgrade.
B. If Engineer determines that unsatisfactory soil is present, continue excavation and
replace with compacted backfill or fill material as directed.
C. Proof-roll subgrade below the building slabs and pavements with a pneumatic-tired and
loaded 10-wheel, tandem-axle dump truck weighing not less than 15 tons to identify
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 8
soft pockets and areas of excess yielding. Do not proof-roll wet or saturated
subgrades.
1. Completely proof-roll subgrade in one direction repeating proof-rolling in direction
perpendicular to first direction. Limit vehicle speed to 3 mph.
2. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or
rutting, as determined by Engineer, and replace with compacted backfill or fill as
directed.
D. Authorized additional excavation and replacement material will be paid for according to
Contract provisions for unit prices.
E. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated
water, or construction activities, as directed by Engineer, without additional
compensation.
3.6 UNAUTHORIZED EXCAVATION
A. Fill unauthorized excavation under foundations or wall footings by extending bottom
elevation of concrete foundation or footing to excavation bottom, without altering top
elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi, may be
used when approved by Engineer.
1. Fill unauthorized excavations under other construction, pipe, or conduit as
directed by Engineer.
3.7 STORAGE OF SOIL MATERIALS
A. Stockpiles borrow soil materials and excavate satisfactory soil materials without
intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to
prevent windblown dust.
1. Stockpile soil materials away from edge of excavations. Do not store within drip
line of remaining trees.
3.8 BACKFILL
A. Place and compact backfill in excavations promptly, but not before completing the
following:
1. Construction below finish grade including, where applicable, subdrainage,
dampproofing, waterproofing, and perimeter insulation.
2. Surveying locations of underground utilities for Record Documents.
3. Testing and inspecting underground utilities.
4. Removing concrete formwork.
5. Removing trash and debris.
6. Removing temporary shoring, bracing, and sheeting.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 9
7. Installing permanent or temporary horizontal bracing on horizontally supported
walls.
B. Place backfill on subgrades free of mud, frost, snow, or ice.
3.9 UTILITY TRENCH BACKFILL
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. Place and compact bedding course on trench bottoms and where indicated. Shape
bedding course to provide continuous support for bells, joints, and barrels of pipes and
for joints, fittings, and bodies of conduits.
C. Trenches under Footings: Backfill trenches excavated under footings and within 18
inches of bottom of footings with satisfactory soil; fill with concrete to elevation of
bottom of footings. Concrete is specified in Section 033000 "Cast-in-Place Concrete.
D. Backfill voids with satisfactory soil while removing shoring and bracing.
E. Initial Backfill:
1. Soil Backfill: Place and compact initial backfill of satisfactory soil, free of particles
larger than 1 inch in any dimension, to a height of 12 inches over the pipe or
conduit.
a. Carefully compact initial backfill under pipe haunches and compact evenly
up on both sides and along the full length of piping or conduit to avoid
damage or displacement of piping or conduit. Coordinate backfilling with
utilities testing.
2. Controlled Low-Strength Material: Place initial backfill of controlled low-strength
material to a height of 12 inches over the pipe or conduit. Coordinate backfilling
with utilities testing.
F. Final Backfill:
1. Soil Backfill: Place and compact final backfill of satisfactory soil to final subgrade
elevation.
2. Controlled Low-Strength Material: Place final backfill of controlled low-strength
material to final subgrade elevation.
G. Warning Tape: Install warning tape directly above utilities, 12 inches below finished
grade, except 6 inches below subgrade under pavements and slabs.
3.10 SOIL MOISTURE CONTROL
A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer
before compaction to within 2 percent of optimum moisture content.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 10
1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or
contain frost or ice.
2. Remove and replace, or scarify and air dry, otherwise satisfactory soil material
that exceeds optimum moisture content by 2 percent and is too wet to compact to
specified dry unit weight.
3.11 COMPACTION OF SOIL BACKFILLS AND FILLS
A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for
material compacted by heavy compaction equipment and not more than 4 inches in
loose depth for material compacted by hand-operated tampers.
B. Place backfill and fill soil materials evenly on all sides of structures to required
elevations and uniformly along the full length of each structure.
C. Compact soil materials to not less than the following percentages of maximum dry unit
weight according to ASTM D 1557:
1. Under structures, building slabs, steps, and pavements, scarify and recompact
top 12 inches of existing subgrade and each layer of backfill or fill soil material at
95 percent.
2. For utility trenches, compact each layer of initial and final backfill soil material at
85 percent.
3.12 GRADING
A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes.
Comply with compaction requirements and grade to cross sections, lines, and
elevations indicated.
1. Provide a smooth transition between adjacent existing grades and new grades.
2. Cut out soft spots, fill low spots, and trim high spots to comply with required
surface tolerances.
B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent
ponding. Finish subgrades to elevations required to achieve indicated finish elevations,
within the following subgrade tolerances:
1. Turf or Unpaved Areas: Plus or minus 1 inch .
2. Walks: Plus or minus 1 inch .
3. Pavements: Plus or minus 1/2 inch.
C. Grading inside Building Lines: Finish subgrade to a tolerance of 1/2 inch when tested
with a 10-foot straightedge.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 11
3.13 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a qualified special inspector to perform the
following special inspections:
1. Determine prior to placement of fill that site has been prepared in compliance
with requirements.
2. Determine that fill material classification and maximum lift thickness comply with
requirements.
3. Determine, during placement and compaction, that in-place density of compacted
fill complies with requirements.
B. Testing Agency: Owner will engage a qualified geotechnical engineering testing
agency to perform tests and inspections.
C. Footing Subgrade: At footing subgrades, at least one test of each soil stratum will be
performed to verify design bearing capacities. Subsequent verification and approval of
other footing subgrades may be based on a visual comparison of subgrade with tested
subgrade when approved by Engineer.
D. Testing agency will test compaction of soils in place according to ASTM D 1556,
ASTM D 2167, ASTM D 2937, and ASTM D 6938, as applicable. Tests will be
performed at the following locations and frequencies:
1. Paved and Building Slab Areas: At subgrade and at each compacted fill and
backfill layer, at least one test for every 2000 sq. ft. or less of paved area or
building slab but in no case fewer than three tests.
2. Foundation Wall Backfill: At each compacted backfill layer, at least one test for
every 100 feet or less of wall length but no fewer than two tests.
3. Trench Backfill: At each compacted initial and final backfill layer, at least one test
for every 150 feet or less of trench length but no fewer than two tests.
E. When testing agency reports that subgrades, fills, or backfills have not achieved
degree of compaction specified, scarify and moisten or aerate, or remove and replace
soil materials to depth required; recompact and retest until specified compaction is
obtained.
3.14 PROTECTION
A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and
erosion. Keep free of trash and debris.
B. Repair and reestablish grades to specified tolerances where completed or partially
completed surfaces become eroded, rutted, settled, or where they lose compaction due
to subsequent construction operations or weather conditions.
1. Scarify or remove and replace soil material to depth as directed by Engineer;
reshape and recompact.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER EARTH MOVING
REEDLEY, CA. SECTION 311000 - 12
C. Where settling occurs before Project correction period elapses, remove finished
surfacing, backfill with additional soil material, compact, and reconstruct surfacing.
1. Restore appearance, quality, and condition of finished surfacing to match
adjacent work, and eliminate evidence of restoration to greatest extent possible.
3.15 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil,
trash, and debris, and legally dispose of them off Owner's property.
B. Transport surplus satisfactory soil to designated storage areas on Owner's property.
Stockpile or spread soil as directed by Engineer.
1. Remove waste materials, including unsatisfactory soil, trash, and debris, and
legally dispose of them off Owner's property.
END OF SECTION 312000
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 1
SECTION 323113 - CHAIN LINK FENCES AND GATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this
Section.
1.2 SUMMARY
A. Related Requirements:
1. Section 033000 "Cast-in-Place Concrete" for cast-in-place concrete and post
footings.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual
components and profiles, and finishes for the following:
a. Fence and gate posts, rails, and fittings.
b. Chain-link fabric, reinforcements, and attachments.
C. Gates and hardware.
B. Shop Drawings: For each type of fence and gate assembly.
1. Include plans, elevations, sections, details, and attachments to other work.
2. Include accessories, hardware, gate operation, and operational clearances.
1.4 INFORMATIONAL SUBMITTALS
A. Product Certificates: For each type of chain-link fence and gate.
B. Product Test Reports: For framework strength according to ASTM F 1043, for tests
performed by manufacturer.
C. Field quality-control reports.
D. Sample Warranty: For special warranty.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 2
1.5 FIELD CONDITIONS
A. Field Measurements: Verify layout information for chain-link fences and gates shown
on Drawings in relation to property survey and existing structures. Verify dimensions by
field measurements.
1.6 WARRANTY
A. Special Warranty: Installer agrees to repair or replace components of chain-link fences
and gates that fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Failure to comply with performance requirements.
b. Deterioration of metals, metal finishes, and other materials beyond normal
weathering.
C. Faulty operation of gate operators and controls.
2. Warranty Period: Five years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Structural Performance: Chain-link fence and gate frameworks shall withstand the
design wind loads and stresses for fence height(s) and under exposure conditions
indicated according to ASCE/SEI 7.
B. Lightning Protection System: Maximum resistance-to-ground value of 25 ohms at each
grounding location along fence under normal dry conditions.
2.2 CHAIN-LINK FENCE FABRIC
A. General: Provide fabric in one-piece heights measured between top and bottom of
outer edge of selvage knuckle or twist according to "CLFMI Product Manual" and
requirements indicated below:
2.3 FENCE FRAMEWORK
A. Posts and Rails ASTM F 1043 for framework, including rails, braces, and line;
terminal; and corner posts. Provide members with minimum dimensions and wall
thickness according to ASTM F 1043 based on the following:
1. Fence Height: As indicated on Drawings.
2. Light-Industrial-Strength Material: Group IC-L, round steel pipe, electric-
resistance-welded pipe.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 3
3. Heavy-Industrial-Strength Material: Group IA, round steel pipe, Schedule 40
Group IC, round steel pipe, electric-resistance-welded pipe.
4. Horizontal Framework Members: Intermediate, top, and bottom rails according to
ASTM F 1043.
5. Brace Rails: ASTM F 1043.
6. Metallic Coating for Steel Framework:
a. Type A: Not less than minimum 2.0-oz./sq. ft. average zinc coating
according to ASTM A 123/A 123M or 4.0-oz./sq.ft.zinc coating according to
ASTM A 653/A 653M.
2.4 TENSION WIRE
A. Metallic-Coated Steel Wire: 0.177-inch- diameter, marcelled tension wire according to
ASTM A 817 or ASTM A 824
2.5 SWING GATES
A. General: ASTM F 900 for gate posts and single swing gate types.
1. Gate Leaf Width: As indicated.
2. Framework Member Sizes and Strength: Based on gate fabric height of 72
inches.
B. Pipe and Tubing:
1. Zinc-Coated Steel: ASTM F 1043 and ASTM F 1083;
2. Gate Posts: Round tubular steel
3. Gate Frames and Bracing: Round tubular steel
C. Frame Corner Construction: Welded or assembled with corner fittings
D. Hardware:
1. Hinges 360-degree inward and outward swing.
2. Latch: Permitting operation from both sides of gate with provision for padlocking
accessible from both sides of gate.
3. Lock: Manufacturer's standard internal device.
4. Padlock and Chain:
5. Closer: Manufacturer's standard
2.6 FITTINGS
A. Provide fittings according to ASTM F 626.
B. Post Caps: Provide for each post.
1. Provide line post caps with loop to receive tension wire or top rail.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 -4
C. Rail and Brace Ends: For each gate, corner, pull, and end post.
D. Rail Fittings: Provide the following:
1. Top Rail Sleeves: Pressed-steel or round-steel tubing not less than 6 inches
long.
2. Rail Clamps: Line and corner boulevard clamps for connecting intermediate and
bottom rails to posts.
E. Tension and Brace Bands: Pressed steel
F. Tension Bars: Steel, length not less than 2 inches shorter than full height of chain-link
fabric. Provide one bar for each gate and end post, and two for each corner and pull
post, unless fabric is integrally woven into post.
G. Truss Rod Assemblies: Steel, hot-dip galvanized after threading rod and turnbuckle or
other means of adjustment.
H. Tie Wires, Clips, and Fasteners: According to ASTM F 626.
1. Standard Round Wire Ties: For attaching chain-link fabric to posts, rails, and
frames, according to the following:
a. Hot-Dip Galvanized Steel:0.106-inch-diameter wire galvanized coating
thickness matching coating thickness of chain-link fence fabric.
I. Finish:
1. Metallic Coating for Pressed Steel or Cast Iron: Not less than 1.2 oz./sq. ft. of
zinc.
a. Polymer coating over metallic coating.
2.7 GROUT AND ANCHORING CEMENT
A. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive,
nongaseous grout complying with ASTM C 1107/C 1107M. Provide grout,
recommended in writing by manufacturer, for exterior applications.
B. Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled
expansion cement formulation for mixing with water at Project site to create pourable
anchoring, patching, and grouting compound. Provide formulation that is resistant to
erosion from water exposure without needing protection by a sealer or waterproof
coating, and that is recommended in writing by manufacturer for exterior applications.
2.8 GROUNDING MATERIALS
A. Comply with requirements in Section 260526 "Grounding and Bonding for Electrical
Systems."
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 5
B. Connectors and Grounding Rods: Listed and labeled for complying with UL 467.
1. Connectors for Below-Grade Use: Exothermic welded type.
2. Grounding Rods: Copper-clad steel, 5/8 by 96 inches.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements
for site clearing, earthwork, pavement work, and other conditions affecting performance
of the Work.
1. Do not begin installation before final grading is completed unless otherwise
permitted by Engineer.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Stake locations of fence lines, gates, and terminal posts. Do not exceed intervals of
500 feet or line of sight between stakes. Indicate locations of utilities, lawn sprinkler
system, underground structures, benchmarks, and property monuments.
3.3 CHAIN-LINK FENCE INSTALLATION
A. Install chain-link fencing according to ASTM F 567 and more stringent requirements
specified.
1. Install fencing on established boundary lines inside property line.
B. Post Excavation: Drill or hand-excavate holes for posts to diameters and spacings
indicated, in firm, undisturbed soil.
C. Post Setting: Set posts in concrete at indicated spacing into firm, undisturbed soil.
1. Verify that posts are set plumb, aligned, and at correct height and spacing, and
hold in position during setting with concrete or mechanical devices.
2. Concrete Fill: Place concrete around posts to dimensions indicated and vibrate or
tamp for consolidation. Protect aboveground portion of posts from concrete
splatter.
a. Exposed Concrete: Extend 2 inches above grade; shape and smooth to
shed water.
b. Concealed Concrete: Place top of concrete 2 inches below grade as
indicated on Drawings to allow covering with surface material.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 6
D. Terminal Posts: Install terminal end, corner, and gate posts according to ASTM F 567
and terminal pull posts at changes in horizontal or vertical alignment of 15 degrees or
more. For runs exceeding 500 feet, space pull posts an equal distance between corner
or end posts.
E. Line Posts: Space line posts uniformly at 10 feet o.c.
F. Post Bracing and Intermediate Rails: Install according to ASTM F 567, maintaining
plumb position and alignment of fence posts. Diagonally brace terminal posts to
adjacent line posts with truss rods and turnbuckles. Install braces at end and gate
posts and at both sides of corner and pull posts.
1. Locate horizontal braces at midheight of fabric 72 inches or higher, on fences
with top rail, and at two-third fabric height on fences without top rail. Install so
posts are plumb when diagonal rod is under proper tension.
G. Tension Wire: Install according to ASTM F 567, maintaining plumb position and
alignment of fence posts. Pull wire taut, without sags. Fasten fabric to tension wire with
0.120-inch- diameter hog rings of same material and finish as fabric wire, spaced a
maximum of 24 inches o.c. Install tension wire in locations indicated before stretching
fabric. Provide horizontal tension wire at the following locations:
1. Extended along top and bottom of fence fabric. Install top tension wire through
post cap loops. Install bottom tension wire within 6 inches of bottom of fabric and
tie to each post with not less than same diameter and type of wire.
2. Extended along top of extended posts and top of fence fabric to support barbed
tape.
H. Top Rail: Install according to ASTM F 567, maintaining plumb position and alignment of
fence posts. Run rail continuously through line post caps, bending to radius for curved
runs and terminating into rail end attached to posts or post caps fabricated to receive
rail at terminal posts. Provide expansion couplings as recommended in writing by
fencing manufacturer.
I. Intermediate and Bottom Rails: Secure to posts with fittings.
J. Chain-Link Fabric: Apply fabric to outside of enclosing framework. Leave 1-inch bottom
clearance between finish grade or surface and bottom selvage unless otherwise
indicated. Pull fabric taut and tie to posts, rails, and tension wires. Anchor to framework
so fabric remains under tension after pulling force is released.
K. Tension or Stretcher Bars: Thread through fabric and secure to end, corner, pull, and
gate posts, with tension bands spaced not more than 15 inches o.c.
L. Tie Wires: Use wire of proper length to firmly secure fabric to line posts and rails.
Attach wire at one end to chain-link fabric, wrap wire around post a minimum of 180
degrees, and attach other end to chain-link fabric according to ASTM F 626. Bend
ends of wire to minimize hazard to individuals and clothing.
1. Maximum Spacing: Tie fabric to line posts at 12 inches o.c. and to braces at 24
inches o.c.
CONTRACT 24-S-04
REEDLEY RADIO TOWER AND EQUIPMENT SHELTER FENCES AND GATES
REEDLEY, CA. SECTION 323113 - 7
M. Fasteners: Install nuts for tension bands and carriage bolts on the side of fence
opposite the fabric side. Peen ends of bolts or score threads to prevent removal of
nuts.
3.4 GATE INSTALLATION
A. Install gates according to manufacturer's written instructions, level, plumb, and secure
for full opening without interference. Attach fabric as for fencing. Attach hardware using
tamper-resistant or concealed means. Install ground-set items in concrete for
anchorage. Adjust hardware for smooth operation.
3.5 ADJUSTING
A. Gates: Adjust gates to operate smoothly, easily, and quietly, free of binding, warp,
excessive deflection, distortion, nonalignment, misplacement, disruption, or
malfunction, throughout entire operational range. Confirm that latches and locks
engage accurately and securely without forcing or binding.
B. Lubricate hardware and other moving parts.
3.6 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance
personnel to adjust, operate, and maintain chain-link fences and gates.
END OF SECTION 323113
CONTRACT 24-S-04