HomeMy WebLinkAboutT80339 CCO 007.pdf COU
County of Fresno
Department of Public Works and Planning
O� 90 Development Services&Capital Projects Division
FRES Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Sheriff Substation Bid Package 2
Contract No.: 21-S-01
Date: 11/14/2024
Contractor: BMY Construction Group,Inc.
Architect: Roger Davidson
Change Order No.: CCO#7
Construction Contract Dollar Amount(as awarded on 5/17/2022) $2,465,000.00
Director's Change Order Limit: $135,750.00
Adjusted Change Order Allowance(per BAI 58 9/10/24) $446,500.00
Contract Time(Calendar Days): 60
Construction Start Date(NTP Issued 11/13/23): 11113123
Original Construction Completion Date: 1112124
Change Order Scope of Work:
PCO#11.1 Remove drywell and add 2"condensate piping
PCO#14.1 American Inc.change in scope
PCO#20.1 Concrete Work Correction
PCO#21 Electrical Correction(Option A)
PCO#22 Erect-A-Step Modular Platform(Option B)
PCO#23 Generator Terminations Correction
Attachment(s):
Contractors PCO,Change Order Summary
Net Change Order Dollar Amount: $142,322.85
Net Calendar Days: 31
Total Change Order Dollar Amount To Date $374,600.66
Adjusted Contract Dollar Amount: $2,839,600.66
Director's Change Order Limit Balance: $0.00
Change Order Allowance Balance: $71,899.34
Total Adjusted Calendar Days To Date: 130
Adjusted Construction Completion Date: 05/21/24
Reviewed: Keith M.Eckert ll Keith Frkart 1 1119124
Senior Engineering Technician-Project Manager
Reviewed: Mandeep Sekhon MandeeP S.Sekhon Digllally s igned by Mandeep S.Selhw
Dale:2024.11.19 10:15V-0900'
Construction Division Engineer-Construction Manager
Reviewed: William M.Kettler William M.Kettler Digitally William M.Netder
Date:2024.77 b 11:n:m-Oe•ot
Deputy Director of Planning
Bernard Jimenez Digitally signed by Bernard Jimenez
ernar mene
Reviewed: Bernard Jimenez Data:2024.11.2108:51:25-DB'W'
Planning&Resource Management Officer
Approved: Steven E. White Steve White DI911agysigned by Sieve Wbite
Dale:2024 naal b 09:2s:W hit.
Director of Public Works and Planning
Approved: Nathan Magsig
Board of Supervisors,Chairman
KKVan Digitally signed by Kay Vang
ay Acknowledged: Kay Vang y g Date:2024.12.10 15:28:59-08'00'
Principal Accountant
Scan and forward Director Approved Copy to: PWP Business Office Kay Vang
qe/ p'k-\� County of Fresno
Department of Public Works and Planning
Development Services&Capital Projects Division
Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: Sheriff Substation Bid Package 2
Contract No.: 21-S-01
Date: 9/16/2024
Contractor: BMY Construction Group,Inc.
2485 East Olive Avenue
Fresno,CA 93727
(559)243 4200
Change Order No.: CCO#7
Construction Contract Dollar Amount(as awarded on 5/17/2022) $2,465,000.00
Original Construction Completion Date: F 01/12/24
CCO#7 is hereby approved by the County.
Scope of Work:
PCO#11.1 Remove drywell and add 2"condensate piping
PCO#14.1 American Inc.change in scope
PCO#20.1 Concrete Work Correction
PCO#21 Electrical Correction(Option A)
PCO#22 Erect-A-Step Modular Platform(Option B)
PCO#23 Generator Terminations Correction
Attachment(s):
Contractors PCO,Change Order Summary
Net Change Order Dollar Amount: $142,322.85
Net Calendar Days: 31
Adjusted Contract Dollar Amount: $2,839,600.66
Total Change Order Dollar Amount To Date: $374,600.66
Total Adjusted Calendar Days To Date: 130
Adjusted Construction Completion Date: 11121/24 TBD
Keith M.Eckert 11 Keith Eckert
Project Manager
Date: 9/16/24
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractordoes not sign acceptance of this Change Order,Provisions underthe Agreement 16-S-05,Article VI shall apply.
Accepted By: BMY Construction Group,Inc. Lit 6�f
Authorized Signature Q
Date: l q
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Sheriff Substation Bid Packaqe 2
Cha
1 12/19/2023 $73,759.38 $0.00 32 Includes PCO#4,5
2 1/29/2024 $13,144.95 $0.00 10 Includes PCO#7
3 2/26/2024 $17,246.41 $0.00 3 Includes PCO#2,9
4 4/8/2024 $97,206.02 $0.00 40 Includes PCO#12.1,13,17
5 5/16/2024 $3,680.80 $0.00 3 Includes PCO#10.1
6 7/1/2024 $27,240.25 $0.00 11 Includes PCO#18,19
7 7/31/2024 $142,322.85 $0.00 31 Includes PCO#11,14.1,20.1,21,22,23
8
9
10
Totals $374,600.66 $0.00 130
Proposed Executed Add Credit Rejected Pending Adj.
Days DescriptionChange • •
1 Not Used
2 3 $15,269.48 0 Material&Labor Increase due to late start of project
3 $2,266.26 5 Room#SS113 clean and seal concrete
4 1 $10,551.27 7 D One Drywall Addendum 4(Extra Studs)
5 1 $63,208.11 25 Client request,see RFI#15
6 $56,930.36 7 American Inc.Added roof drains
7 2 $13,144.95 10 Generator Pad Relocation
8 $1,105.31 0 Glass&glazing material increase
9 3 $1,976.93 3 Missing Power R.1
10 $5,809.79 3 Power to mezzanine HVAC units
10.1 5 $3,680.80 3 Power to mezzanine HVAC units
11 $2,432.59 0 Remove drywell and add 2"condensate piping
11.1 7 $1,956.15 0 Remove drywell and add 2"condensate piping
12 $103,191.00 0 EPC
12.1 4 $61,380.00 36 EPC
13 4 $35,616.02 4 Nation-Added roof draings ASI 11-29-2023-01
14 $28,126.78 5 American Inc.Change of scope
14.1 7 $28,126.78 5 American Inc.Change of scope
15 $26,640.86 5 Equipment Yard-Added baserock
16 Not Used
17 4 $210.00 0 Reinstall Mail Box T&M
18 6 $13,768.17 0 Contra Costa Electric-Labor Escalation
19 6 $13,472.08 11 Contra Costa Electric-T&M
20 $60,231.37 15 Concrete Work Correction
20.1 7 $56,474.50 15 Concrete Work Correction
21 7 $31,582.04 5 Electrical Correction(Option A selected)
22 7 $21,529.00 5 Erect-A-Step Modular Platform(Option B selected)
23 7 $2,654.38 1 Generator Terminations Correction
24
25
26
27
28
29
30
31
32
33
34
35
Totals $374,600.66 $0.00 $258,988.15 $27,746.17
PCO #11 . 1
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group Incorporated Project:22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone: (559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #011 : CE #015 - Drywell
TO: The County of Fresno, Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 011 /0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 2/26/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $1,956.15
POTENTIAL CHANGE ORDER TITLE:CE#015-Drywell
CHANGE REASON:Correction
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#015-Drywell
Remove Drywell from Scope
Add 100'of 2"Condensate Piping to Run Along Warehouse Wall and Terminate at existing rain water leader at West Corner
ATTACHMENTS:
American Change Request#2.pdf
# Budget Code Description Amount
1 23-OOOO.PO HVAC/AMERI CAN.Purchase Order Remove Drywell from scope $(6,517.00)
2 23-OOOO.PO HVAC/AMERI CAN.Purchase Order Add 100'of 2"Condensate Piping $8,137.00
Subtotal: $1,620.00
Overhead(Subcontractor 15%): $243.00
Subcontractor Total: $1,863.00
Overhead(BMY): $93.15
Grand Total: $1,956.15
BMY Construction Group Incorporated Page 1 of 2 Printed On:2/26/2024 02:20 PM
PCO #011
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
P—,.ArchitectSign Here Pro—ArchitectSlg-dDate ProcoreOwnerSig,Here Pro co reOwnerSlgnedDate ProcoreGeneralC,—,torSig,Here P,coreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:2/26/2024 02:20 PM
American Incorporated
1345 N.American Street
Visalia, CA 93291
Ph :559-651-1776
Change Request
To: Derek Brawley Number: 2
BMY CONSTRUCTION Date: 1/31/24
5485 E. OLIVE AVE Job: 30-07789 BMY-FRESNO CO SHERIFF SUBSTATN
FRESNO, CA 93727 Phone:
Ph: (559)243-4200 Fax: (559)222-2380
Description: Condensate vs Drywell
Reason: Change in Scope
We are pleased to offer the following specifications and pricing to make the following changes:
Remove Drywell from Scope
Add 1 00'of 2" Condensate Piping to Run Along Warehouse Wall and Terminate at existing rain water leader at West Corner
Work performed by us:
Description Quantity Unit Unit Price Price
Remove Drywell from Scope Material&Labor $-6,517.00
Add 100'of 2"Condensate Labor $4,667.00
Add 100'of 2"Condensate Material $3,470.00
Subtotal: $1,620.00
Material List Subtotal: $1,620.00
OH & P $1,620.00 15.00% $243.00
CITY SIZE DESCRIPTION
Total: $1,863.00
100, 2" COPPER TUBE TYPE L
2 2" COPPER 90 ELL
5 2" COPPER COUPLING
2 2" COPPER TEE
2 2" COPPER FEMALE ADTR
2 2" THREADED PLUG
13 PIPE HANGER ASSYMBLIES
If you have any questions, please contact me at(559)651-1776.
Submitted by: JUSTIN BROU Approved by:
AMERICAN INCORPORATED Date:
Page 1 of 1
PCO #014
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group Incorporated Project: 22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone:(559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #014: CE #020 - American Inc. -
Change of Scope
TO: The County of Fresno,Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 014/0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 3/1/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 5 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $28,126.78
POTENTIAL CHANGE ORDER TITLE: CE#020-American Inc.-Change of Scope
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#020-American Inc.-Change of Scope
Change of Scope
ATTACHMENTS:
Change Request#4-Change in Scope(5).pdf
# Budget Code Description Amount
1 23-0000.PO HVAC/AMERICAN.Purchase Order Change of scope $26,286.70
Subtotal: $26,286.70
Overhead(BMY): $1,840.08
Grand Total: $28,126.78
BMY Construction Group Incorporated Page 1 of 2 Printed On: 3/1/2024 01:59 PM
PCO #014
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
P—,.ArchitectSign Here Pro—ArchitectSlg-dDate ProcoreOwnerSig,Here Pro co reOwnerSlgnedDate ProcoreGeneralC,—,torSig,Here P,coreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:3/1/2024 01:59 PM
American Incorporated
1345 N.American Street
Visalia,CA 93291
Ph:559-651-1776
Change Request
To: Carmen Manganaan Number: 4 Rev 1.
BMY CONSTRUCTION Date: 8/11/23
5485 E. OLIVE AVE Job: 12-07789 BMY-FRESNO CO SHERIFF SUBSTATN
FRESNO, CA 93727 Phone:
Ph: (559)243-4200 Fax: (559)222-2380
Description: Change In Scope
Reason: Change in Scope
We are pleased to offer the following specifications and pricing to make the following changes:
Supplier Increase : $90,010.00
Original Quote : $65,000.00
Price Difference : $25,010.00
5% Credit from being preffrered contractor ($1,113.00)
Change in Scope Price$23,897.00
Work performed by subcontractors:
Description Subcontractor Price
Change in Scope $23,897.00
Subtotal: $23,897.00
Subtotal: $23,897.00
OH&P $23,897.00 10.00% $2,389.70
Total: $26,286.70
If you have any questions, please contact me at.
Submitted by: Approved by:
Date:
Page 1 of 1
Sheriff Substation 7-30-23 Base Bid Summary 8/10/2023 3:55 PM
Bid Qualification List
Inclusions
No.1 Provide and Install New HVAC Equipment as Specified on Plans Dated 2/14/22
No.2 Provide and Install New Refrigerant Linesets Per Manufactures Specifications
No.3 Provide and Install New Duct and Air Distribution as Specified
No.4 Provide and Install New Low Voltage Controls as Specified by Bedard
No.S Provide Check,Test and Start Up of HVAC Equipment
No.6 Provide Air Balancing
No.7 Provide Crane and Rental Equipment
No.8 Provide and Install 3/4"Type L Copper at Crac Unitsl,2 and Connect at Location
Note 3 of M1.1 Existing Condensate
No.9 Provide and Install 1-1/2"Type L Copper at FC-1-4,Connect Together and
Terminate 2"Condensate at Drywell
No.10 Provide and Install New 2"x8"RCP Pipe with Grade Ring and Cover for Drywell
No.11 Prevailing Wages
Exclusions
No.1 Bond Cost
No.2 Permits and Fees
No.3 Commissioning Authority
No.4 Electrical Above Controls Voltage
No.S Framing of Openings/Penetrations
No.6 Roofing and/or Patching of Roof
No.7 Building Sheet Metal Other Than Mechanical
No.8 Concrete Slabs/Pads/Cutting/Coring
No.9 Painting and/or Patching of Walls,Ceilings and Floors
No.10 Painting of Ductwork
No.11 Connection of Smoke Detectors to Fire Alarm
ClaPirications
No.1 All Work to be Performed During Regular Business Hours.
No.2 Excludes All Other Work Not Listed in Inclusions
Addendums Noted: (3) Add. 1-3
Thom Sardinha, Estimator Base Bid Summary Page 2
AnNORMAN S. WRIGHT QUOTATION
&7TT,FIT,M111
' Mechanical Equipment Company, LLC
7595 N.Del Mar Ave.,Fresno CA 93711 778 Osos St.,#13,San Luis Obispo CA 93401
Tel 559.449.8701 i Fax 559.449.8734 Tel 805.773.2810 1 Fax 805.773.2812
To: All Bidders
Project: Fresno Co. Sheriff Area 2 Substation -Ph. 2
Location: Fresno, CA.
Bid Date: Plan Date: Addendum:3
Project: 6436 Plan #:
Engineer: Lawrence Engineering Group Proposal: 004776 Revision: 01
IKIN VRV SYSTEM
AIKIN Heat Pump Condensing Units - Marks: ODU-1 THRU 8
460/3 V
• del #: RXYQ144XAYDA
• E V400 AHU integration valve kit
• Rem ontroller, shipped loose
• Z-Contro x
• Crankcase ter, low ambient operation, high-low pressure switches integral to unit
NOT INCLUDED. mmissioning, mounting platforms, external vibration isolati , roof curbs, ball valves,
refrigerant trim, pi ,valves, R410a charge, starters, roofing, and any add! ' al accessories not
specifically listed ab
4 Indoor Air Handling Units arks: AH-1 THRU 4
• 460/60/3 V
• Double wall construction with foam insulation
• Mixing box with dampers and ME 13 filters
• 4" base formed channel
• Plenum supply fans with internal spring ation isolatio d PE ODP motors
• Factory mounted &wired VFD for supply
• UVC Light, shipped loose
• (2) DX VRV coil per unit and stainless steel dra' n
NOT INCLUDED: Platforms/curbs, smoke de or tart-up, commissioning, wiring, disconnects or
fusing, controls for actuators, controller tuators, ntrols, control enclosures or mounting of
controls, valves or valve packages, da r actuators, rity bars, seismic certification or calculations,
transformers, special coatings or co , piping, hanging nting hardware, owner training, and any
additional accessories not specifli y listed above.
1 DAIKIN Heat Pump Condens' Unit:
• Model #RXTQ60TAVJU
• 230/1 V
• Swing compressor
• Heating down t
• Compact de '
NOT INCLU : Mounting platform, refrigerant piping, interlocking of controls, r 'ng, mounting
hardware d any additional accessories not specifically listed above.
2 DAIKIN Ceiling Suspended Unit - Mark: FC-1 & FC-2
• Model #FXHQ
• Wired remote controller, field wired
• Integral condensate pump, with overflow alarm
NOT INCLUDED: Filters, line sets, smoke detectors, hanging/mounting hardware, wiring, piping,
refrigerant trim, seismic clips, and any additional accessories not specifically listed above.
VRV and Split System Subtotal
LIEBERT COMPUTER ROOM UNITS MARKS: CRAC-1&2, CR-1&2
2 Liebert PDX Air-Cooled System
• Model number: PX018UA
• Upflow, air-cooled, cooling only
• Nominal 5 ton
• 208 Voltage, 3 Phase, 60 Hz
System Details:
• Upflow with Front Air Return
• Liebert iCOM Control with High-Definition Display
• iCOM based communication
• Base Comms & Connectivity includes one Ethernet port and one RS-485 port on iCOM controller, dedicated to
supporting BACnet IP, Modbus TCP/IP, BACnet 485, Modbus 485 and SNMP v1/v2c/v3
• Variable speed EC plug fan
• Digital scroll, variable capacity compressor utilizing R-410A
• Crankcase Heater
• Thermal Expansion Valve
• Compressor Sound Jacket
• Evaporator Type: tilted- slab, copper tubes - aluminum fins with hydrophilic coating
• 65,000 Amp, rms Short Circuit Current Rating
• Locking Disconnect Switch
• Dual-float condensate pump factory-mounted internal to unit
• Filter Rating: MERV 8 per ASHRAE 52.2-2007
• Unit Color: RAL 7021 Black Gray Matte
• Supply Air Sensor
• Compressor Overload Sensor
• Remote Temperature and Humidity Sensors provided in a vented case with a 30' cable
• Three Remote Shut Down Contacts
• Four Alarm Contacts
• Main Fan Contact
• 4-Way Discharge Grille Plenum — Field installed
• Single Point Power- Heat rejection unit powered from the indoor unit
Liebert MC Air-Cooled Microchannel Condensers:
• Model number: MCM040E
• Outdoor design ambient: 105F
• Voltage: 208-230V/3ph /60hz
• Microchannel aluminum coil.
• Variable speed EC fans.
• Premium electronic control board providing communication with iCON using CANbus.
• Short Circuit rating of 65,000 Amps, rms.
• R-410A factory set points and single refrigerant circuit.
• Aluminum exterior panels and 18" aluminum legs.
• Domestic packaging.
Services Include:
Warranty inspection included (Includes Liebert PDX System)
Not included: Off-loading and handling, installation, piping, refrigerant charge, seismic restraints, reheat,
humidifier, owner training, special coatings, wiring, hanging/mounting hardware, and any additional
accessories not specifically listed above.
Liebert Subtotal $ 90,010.00
DISTRIBUTION MARK: A
8 r Outlets complete with:
• For a mounting as scheduled
• Standard white exterior finish
Note: Opposed b ampers, volume dampers, square to round dapters, gaskets, boots,
extractors, special fine or colors, mounting hardware, an other accessories not specifically
listed above are NOT inclu
BACKDRAFT DAMPERS MARK: B
2 Ruskin Gravity Backdraft Dampers co e with:
• Extruded aluminum frame a e construction
• Blade edge seals
• Counterbalance ed operation
Note: Insects s, duct transitions, access doors, special coating lors, mounting hardware, and
any oth essories not specifically listed above are NOT included.
ribution Subtotal
NORMAN S.WRIGHT QUOTATION
W11411111111TIn,
' Mechanical Equipment Company, LLC
7595 N.Del Mar Ave.,Fresno CA 93711 778 Osos St.,#B,San Luis Obispo CA 93401
Tel 559.449.8701 1 Fax 559.449.8734 Tel 805.773.2810 I Fax 805.439.2091
To: All Bidders
Project: Fresno Co. Sheriff Area 2 Substation -Ph. 2
Location: Fresno, CA.
Bid Date: Plan Date: Addendum:3
Project: 6436 Plan #:
Engineer: Lawrence Engineering Group Proposal: 004776 Revision: 02
LIEBERT COMPUTER ROOM UNITS MARKS: CRAC-1&2, CR-1&2
2 Liebert PDX Air-Cooled System
• Model number: PX018UA
• Upflow, air-cooled, cooling only
• Nominal 5 ton
• 208 Voltage, 3 Phase, 60 Hz
System Details:
• Upflow with Front Air Return
• Liebert iCOM Control with High-Definition Display
• iCOM based communication
• Base Comms & Connectivity includes one Ethernet port and one RS-485 port on iCOM controller, dedicated to
supporting BACnet IP, Modbus TCP/IP, BACnet 485, Modbus 485 and SNMP vl/v2c/v3
• Variable speed EC plug fan
• Digital scroll, variable capacity compressor utilizing R-410A
• Crankcase Heater
• Thermal Expansion Valve
• Compressor Sound Jacket
• Evaporator Type: tilted- slab, copper tubes - aluminum fins with hydrophilic coating
• 65,000 Amp, rms Short Circuit Current Rating
• Locking Disconnect Switch
• Dual-float condensate pump factory-mounted internal to unit
• Filter Rating: MERV 8 per ASHRAE 52.2-2007
• Unit Color: RAL 7021 Black Gray Matte
• Supply Air Sensor
• Compressor Overload Sensor
• Remote Temperature and Humidity Sensors provided in a vented case with a 30' cable
• Three Remote Shut Down Contacts
• Four Alarm Contacts
• Main Fan Contact
• 4-Way Discharge Grille Plenum — Field installed
• Single Point Power- Heat rejection unit powered from the indoor unit
Liebert MC Air-Cooled Microchannel Condensers:
• Model number: MCM040E
• Outdoor design ambient: 105F
• Voltage: 208-230V/3ph /60hz
• Microchannel aluminum coil.
• Variable speed EC fans.
• Premium electronic control board providing communication with iCON using CANbus.
• Short Circuit rating of 65,000 Amps, rms.
• R-410A factory set points and single refrigerant circuit.
• Aluminum exterior panels and 18" aluminum legs.
• Domestic packaging.
Services Include:
Warranty inspection included (Includes Liebert PDX System)
Not included: Off-loading and handling, installation, piping, refrigerant charge, seismic restraints, reheat,
humidifier, owner training, special coatings, wiring, hanging/mounting hardware, and any additional
accessories not specifically listed above.
Total Price, FOB Factory, Full Freight Allowed (No Taxes Included)... ....................... $ 65,000.00
Nick Hostetler
From: Carmen Manganaan
Sent: Monday, January 30, 2023 1:09 PM
To: Justin Brou
Subject: FW: Sheriff Substation Phase 2 1 Eliminate 2 Crack Units
Importance: High
Justin,
Spoke to Keith right after I got off the phone with you; the county is eliminating 2 units, see the e-mail below. Can you
release all the other units?
Carmen L. Manganaan, Project Manager
5485 E. Olive Avenue- Fresno, CA 93727
CSL#686178 A, B, C-8
P: (559) 243-4200
C: (559) 355-0426
www.bmyinc.com
CONSTRUCTION
L.r U A I-INC C[ F41-S)I«.I I L1
This communication may contain privileged and/or confidential information.It is intended solely for the use of the addressee.If you are not the intended recipient,you are
strictly prohibited from disclosing,copying,distributing,or using any of this information.If you received this communication in error,please contact the sender immediately
and destroy the material in its entirety,whether electronic or hard copy.This communication may contain nonpublic personal information about consumers subject to the
restrictions of the Gramm-Leach-Bliley Act.You may not directly or indirectly reuse or re-disclose such information for any purpose other than to provide the services for which
you are receiving the information.
From: Eckert, Keith <keckert@fresnocountyca.gov>
Sent: Monday,January 30, 2023 12:54 PM
To: Carmen Manganaan <cmanganaan@bmyinc.com>
Cc: Nick Wicks<nwicks@bmyinc.com>; Sekhon, Mandeep <msekhon@fresnocountyca.gov>
Subject: Sheriff Substation Phase 2
Carmen,
Per phone conversation today the Architect would like to eliminate Crack unit 1 and 2 from the data rack room. If you
have any questions let me know.
Thank you
UKeith M. Eckert III Senior Engineering Technician
Department of Public Works and Planning I Construction
2220 Tulare St. 7th Floor Fresno, CA 93721
Main Office: (559) 600-4154 Direct: (559) 862-5024 Email:keckert@fresnocountyCA.gov
1
IYour input matters!Customer Service Survey
2
PCO #020 A
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group, Inc. Project:22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone: (559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #020 A: CE #026 - ASI 5.3.2024
(Concrete Work)
TO: The County of Fresno, Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 020 A/0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 5/29/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 15 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $56,474.50
POTENTIAL CHANGE ORDER TITLE:CE#026-ASI 5.3.2024(Concrete Work)
CHANGE REASON:Correction
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#026-ASI 5.3.2024 Concrete Work Only
EPC
Remobilization 15 Days When we start concrete work through completion of that work.=$1,267xl5 CD's=$19,004.00
ATTACHMENTS:
EZ ACCESS LAYOUT.pdf, Estimate 1146 from Wicks Fabrication Inc.pdf, FORTRESS Brochure.pdf, 73111 -CO#08 Proposal.pdf, PCO
sheriff substation.pdf
# Budget Code Description Amount
1 1 01-0400.0 Direct Work Fee.Other Concrete $29,721.95
Subtotal: $29,721.95
Overhead(Subcontractor 15%): $5,245.05
Subcontractor Total: $34,967.00
Overhead: (BMY): $2,502.50
2 01-0300.0 BMY MARGIN Other EPC $19,005.00
Grand Total: $56,474.50
BMY Construction Group, Inc. Page 1 of 2 Printed On:7/18/2024 06:21 AM
PCO #020 A
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
P—,.ArchitectSign Here Pro—ArchitectSlg-dDate ProcoreOwnerSig,Here Pro co reOwnerSlgnedDate ProcoreGeneralC,—,torSig,Here P,coreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:7/18/2024 06:21 AM
BMY CONSTRUCTION GROUP INC.
Sheriff Station
BMY Job Number 1 22009.00
Demo 2 existing concrete pads that are 32"thick and back fill and compact.Add 2 concrete pads
around generator with rebar dowels and rebar. New 4"thick pad infront of PG&E transformer.
PCO Description:
PCO#: 1 Date:
MATERIAL
Description Units Unit Price Subtotal
Concrete 18.00 190.00 3,420.00
rebar 80.00 14.00 1,120.00
0.00
0.00
0.00
Subtotal 4540.00
Sales Tax(7.98%) 362.29
Shipping/Freight
Overhead &Profit 10% 343.16
Total Material $5,245.45
EQUIPMENT
Description Units Unit Price Subtotal
Mini EX 3.00 350.00 1050.00
Foreman truck 5.00 250.00 1250.00
Skid steer 5.00 250.00 1250.00
Subtotal 3550.00
Overhead&Profit 10% 532.50
Total Equipment $4,082.50
LABOR
Description M/Hr Cost/MH MD Labor Burden Subtotal
Cement Mason 160.00 70.56 20 25.32 15340.80
Laborer 56.00 63.91 7 23.62 4901.68
Carpenter 86.97 0 29.52 0.00
Operator 16.00 91.380 2 30.65 1952.48
0.00 0.00
22194.96
Overhead&Profit 10% 1553.65
Total Labor $23,748.61
Subcontractors
Subcontractors Description Units Unit Price Other Cost Subtotal
0.00
Demo/off haul dirt 2.00 300.00 600.00
pump 1.00 1,200.00 1,200.00
0.00
0.00
0.00
Subtotal Subs 1,800.00
Overhead &Profit 10% 90.00
Total Subcontractors $1,890.00
TOTAL
Subtotal 34,966.56
TOTAL $34,967
TIME EXTENSION REQUIREMENT= 0 Calendar Days
PCO #021 A
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group, Inc. Project:22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone: (559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #021 A: CE #027 - ASI 5.3.2024
Electrical (Option A 150 breaker)
TO: The County of Fresno, Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 021 A/0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 5/30/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 5 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $31,582.04
POTENTIAL CHANGE ORDER TITLE:CE#027-ASI 5.3.2024 Electrical(Option A 150 breaker)
CHANGE REASON:Correction
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#027-ASI 5.3.2024 Electrical(Option A 150 breaker)
A. In general,our quotation will include the following:
•Provide and install power from Panel 3LA to the generator sub panel.
•Provide and install conduit,wire,and(1)150A breaker.
•Provide and install new panel board to replace existing Panel 3LA in order to house
new breaker.
EPC
Remobilization 5 Days=$1,267x5 CD's=$6,335.00
ATTACHMENTS:
73111 -CO#08 Proposal(1).pdf
BMY Construction Group, Inc. Page 1 of 2 Printed On:5/31/2024 02:50 PM
PCO #021 A
CONSTRUCTION
GROUPINCORPORATED
# I Budget Code Description Amount
1 1 26-OOOO.PO Electrical.Purchase Order Electrical $20,056.07
Subtotal: $20,059.07
Overhead(Subcontractor 15%D): $3,539.30
Subcontractor Total: $23,595.37
Overhead(BMY):
$1,651.67
2 01-0300.0 BMY MARGIN.Other EPC $6,335.00
Grand Total: $31,582.04
BMY Construction Group, Inc. Page 1 of 2 Printed On:5/31/2024 02:50 PM
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
Pr.—ArchitectSign Here ProcoreArchitectSlg-dDate ProcoreOwnerSig,Here Procore0—rSlgnedDate ProcoreGeneralContractorSig,Here Pro—General CmtractorSig-dDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:5/31/2024 02:50 PM
Contra Costa Electric Contra Costa Electric,Inc.
4690 E Carmen Ave
An EMCOR Company Fresno,CA 93703
Ph:559.252.1114
Fax:559.452.1013
May 22nd, 2024
Attn: Derek Brawley
Subject: Fresno Sherriffs Substation Bid Package 2 -Added Generator Power
CCE CO#7
We are pleased to offer for your consideration our Lump Sum Quotation for the above
referenced project. Proposal is valid for 30 days.
Lump Sum $23,595.37
A. In general, our quotation will include the following:
• Provide and install power from Panel 3LA to the generator sub panel.
• Provide and install conduit,wire,and (1) 150A breaker.
• Provide and install new panel board to replace existing Panel 3LA in order to house
new breaker.
See attached summary.
B. We have excluded the following items from our scope of work:
• Providing performance and payment bond.
• Surveying or staking.
• Anything not specifically included is explicitly excluded.
C. The following clarifications and qualifications were made in the preparation of this
proposal:
1. Work hours to be 7:OOAM to 3:30PM Monday thru Friday.
2. CCE will require 5 additional days to perform the work described in this proposal.
We recognize that you have a choice when it comes to selecting contractors to work on your
projects and we thank you for giving Contra Costa Electric, Inc.the opportunity of bidding on
your work. If we can be of service to you on this or future projects,please feel free to contact me
at(559) 252-1114 or jfowler(@emcor.net
Sincerely,
���Gtl2 �alc�P1Z
Fresno Office
Contra Costa Electric,Inc.
An EMCOR Company
,p
d..._..'"'Rs
www.ccelectric.com
Page 1 of 1 D R#10000011625
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
1
Description Quantity Date Trade Price Unit Disc% Link Price Cost Adj% NetCost DB Labor Labor Unit
1 11/2"CONDUIT-EMT 6003/20/2024 1,295.84C 68.69 0.00 0.000 405.76 7.00 7.00C
2 11/2"CONNCOMPDC-EMT 406/08/2022 1,205.90C 0.00 0.00 0.000 1,205.90 45.00 45.00C
3 11/2"COUPLING COMP DC-EMT 1006/08/2022 1,663.78C 0.00 0.00 0.000 1,663.78 25.00 25.00C
4 2" TYPE C STD CONDUIT BODY-EMT-ALUM 110/05/2022 174.33E 0.001 0.00 0.0001 174.33 1.35 1.35E
5 12 TO 1 1/2"REDUCING WASHER 210/18/2023 769.09 C 0.00 0.00 0.000 769.09 11.45 11.45 C
6 11/2"FIELD BEND-EMT 611/12/2013 0.00E 0.00 0.00 0.000 0.00 0.80 0.80E
7 11/2"COUPLING-RMC-GALV 112/11/2023 2,776.00C 41.71 0.00 0.000 1,618.20 0.00 0.000
8 11/2"BUSHING-STEEL 110/18/2023 1,138.72C 0.00 0.00 0.000 1,138.72 8.50 8.50C
9 11/2"1-H STRAP-EMT-STEEL 1001/31/2024 2,081.75C 0.00 0.00 0.0001 2,081.75 4.25 4.25C
10 1 1/2"FLEX-LIQUIDTIGHT METALLIC-GRAY 1011/02/2022 897.20 C 59.37 0.00 0.000 364.57 15.00 15.00 C
11 11/2"CONN STRAIGHT-LIQUIDTIGHTDIECAST 203/30/2022 5,368.18C 0.00 0.00 0.000 5,368.18 36.00 36.00C
12 11/2"CONN90 DEG-LIQUIDTIGHTDIECAST 110/18/2023 11,015.89C 0.00 0.00 0.000 11,015.89 43.20 43.20C
13 1 1/2"ADAPTER FEM-PVC-UNDERGROUND 1 02/21/2024 424.06 C 64.531 0.00 0.000 150.41 25.00 25.00 C
14 #6THHNBLACK 15005/01/2024 8,718.20M 30.00 0.00 0.0001 6,102.76 11.00 11.00M
15 1/OTHHNBLACK 45005/01/2024 28,735.62M 30.00 0.00 0.000 20,114.93 22.00 22.00M
16 1600A3W CIRCUIT BKR PANEL BOARD 111/13/2013 0.00E 0.00 0.00 -100.000 0.00 14.00 14.00E
17 150A3PBREAKER-NEMA1 105/21/2024 0.00E 0.00 0.00 -100.000 0.00 5.00 5.00E
18 150A3PPANELBREAKERTERM 311/06/2013 0.00E 0.00 0.00 -100.000 0.00 1.60 1.60E
19 DEMO 400A DPB PANEL 1 111/08/2013 0.00E 0.00 0.00 0.0001 0.00 3.27 2.00E
Totals 715
Description Quantity Lab Adj% TotalMaterial TotalHours Material Condition LaborCondition Manufacturer Name Catalog Number
1 11/2"CONDUIT-EMT 60 0.000 243.46 4.20 Normal Normal CONDUITRIGID-EMT
2 11/2"CONNCOMPDC-EMT 4 0.000 48.24 1.80 Normal Normal CONDUIT&CBLFT
3 11/2"COUPLING COMP DC-EMT 10 0.000 166.38 2.50 Normal No Labor CONDUIT&CBLFT
4 2" TYPE STD CONDUIT BODY-EMT-ALUM 1 0.000 174.33 1.35 Normal Normal BRIDGEPORT C-36
5 2 TO11/2"REDUCING WASHER 21 0.000 15.38 0.23 Normal Normal CONDUIT&CBLFT
6 11/2"FIELD BEND-EMT 6 0.000 0.00 4.80 No Cost Normal
7 11/2"COUPLING-RMC-GALV 1 0.000 16.18 0.00 Normal No Labor CONDUITFTGSRIGI
8 11/2"BUSHING-STEEL 1 0.000 11.39 0.09 Normal Normal CONDUIT&CBLFT
9 11/2"1-H STRAP-EMT-STEEL 10 0.000 208.18 0.42 Normal Normal CONDUIT&CBLFT
10 11/2"FLEX-LIQUIDTIGHT METALLIC-GRAY 10 0.000 36.46 1.50 Normal Normal CONDUITFLEX
11 111/2"CONN STRAIGHT-LIQUIDTIGHTDIECAST 2 0.000 107.36 0.72 Normal Normal CONDUIT&CBLFT
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
2
Description Quantity Lab Adj% TotalMaterial TotalHours Material Condition LaborCondition Manufacturer Name Catalog Number
12 11/2"CONN90 DEG-LIQUIDTIGHTDIECAST 1 0.000 110.16 0.43 Normal Normal CONDUIT&CBLFT
13 1 1/2"ADAPTER FEM-PVC-UNDERGROUND 1 0.000 1.50 0.25 Normal Normal CONDUIT&FTGSP
14 46THHNBLACK 150 0.000 915.41 1.65 Normal Normal COPPERWIRE THHN-6-BLK-19
15 1/0THHNBLACK 450 0.000 9,051.721 9.90 Normal Normal COPPERWIRE THHN-1/0-BLK-1
16 600A3W CIRCUIT BKR PANEL BOARD 1 0.000 0.00 14.00 Quoted Normal
17 150A3PBREAKER-NEMA 1 1 0.000 0.00 5.00 Quoted Normal
18 150A 3P PANEL BREAKER TERM 3 0.000 0.00 4.80 Quoted Normal
19 DEMO400ADPBPANEL 11 0.000 0.00 2.001 No Cost Normal
Totals 715 11,106.14 55.64
Description Quantity Price Code Reference SupplierName SupplierCode Sort Code 1 Sort Code 2 Sort Code 3 Sort Code 4
1 11/2"CONDUIT-EMT 60980010020 101013 1000 120 100 0
2 11/2"CONNCOMPDC-EMT 4980070136 101073 1000 120 100 0
3 11/2"COUPLINGCOMPDC-EMT 10980070137 101358 1000 120 100 0
4 2" TYPE STD CONDUIT BODY-EMT-ALUM 1781747034 101490 1000 120 100 0
5 2 TO11/2"REDUCING WASHER 2980070125 101994 1000 110 100 0
6 11/2"FIELD BEND-EMT 6 102099 1000 120 100 0
7 11/2"COUPLING-RMC-GALV 1980020001 102351 1000 120 100 0
8 11/2"BUSHING-STEEL 1980070120 103593 1000 1201 100 0
9 11/2"1-H STRAP-EMT-STEEL 10980070140 101688 1000 120 100 0
10 11/2"FLEX-LIQUIDTIGHT METALLIC-GRAY 10980050023 107775 1000 120 100 0
11 11/2"CONN STRAIGHT-LIQUIDTIGHTDIECAST 2980070146 107808 1000 120 100 0
12 11/2"CONN90 DEG-LIQUIDTIGHTDIECAST 1980070147 107838 10001 120 100 0
13 11/2"ADAPTERFEM-PVC-UNDERGROUND 1980060062 106149 1000 125 100 0
14 r6THHNBLACK 150980100231 108834 2000 140 200 0
15 1/0THHNBLACK 450980100234 108849 2000 140 200 0
16 600A3W CIRCUIT BKR PANEL BOARD 1 12000 50 1004 1501
17 150A3P BREAKER-NEMA 1 1 148230 120001 501 300 0
18 150A3P PANEL BREAKERTERM 31 12000 50 1005 1501
19 DEMO 400A DPB PANEL 1 1 175305 20000 45 601 0
Totals 715
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
3
Description Quantity Sort Code 5 Sort Code 6 Sort Code 7 Sort Code 8 Quick Takeoff Code
1 11/2"CONDUIT-EMT 60100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
2 11/2"CONNCOMPDC-EMT 4100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
3 11/2"COUPLING COMP DC-EMT 10100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
4 2" TYPE STD CONDUIT BODY-EMT-ALUM 1 100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
5 12 TO11/2"REDUCING WASHER 2100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
6 11/2"FIELD BEND-EMT 6100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
7 11/2"COUPLING-RMC-GALV 1100011Cond 120021112002.11/4TO6RSC FEEDER CON D1001ICondui <NOCODE>
8 11/2"BUSHING-STEEL 1100011Cond 120021112002.11/4TO6RSC FEEDER CON D1001ICondui <NOCODE>
9 11/2"1-H STRAP-EMT-STEEL 10100011Cond 120011112001.11/4TO4 EMTCONDUITFEE 1001ICondui <NOCODE>
10 11/2"FLEX-LIQUIDTIGHT METALLIC-GRAY 10100011Cond 120311112031.11/4TO4 LIQUID TITEFLEX 1001ICondui <NOCODE>
11 11/2"CONN STRAIGHT-LIQUIDTIGHTDIECAST 2100011Cond 120311112031.11/4TO4LIQUIDTITEFLEX 10011Condui I<NOCODE>
12 11/2"CONN90 DEG-LIQUIDTIGHTDIECAST 1100011Cond 120311112031.11/4TO4 LIQUID TITEFLEX 1001ICondui <NOCODE>
13 1 1/2"ADAPTER FEM-PVC-UNDERGROUND 1100011Cond 125101112510.11/4TO6PVCSCHD40FEE 1001ICondui <NOCODE>
14 #6THHNBLACK 15012000 11 Wire 140011114001.8TO1000THHNFEEDER 200 Wire <NOCODE>
15 1/OTHHNBLACK 450 2000 11 Wire 140011114001.8TO1000THHNFEEDER 200 Wire <NOCODE>
16 160OA3WCIRCUITBKR PANEL BOARD 1 10000 11 Distr 05011050 EQUIPMENT-DISTRIBUTION 300 Distrib I<NOCODE>
17 150A3P BREAKER-NEMA 1 1 1000011 Distr 05011050 EQUIPMENT-DISTRIBUTION 300 Distrib <NOCODE>
18 150A3PPANELBREAKERTERM 3 10000 11 Distr 05011050 EQUIPMENT-DISTRIBUTION 300 Distrib <NOCODE>
19 DEMO 400ADPBPANEL I 1 200001I Dem 450011045.DEMOLITION 06011 Demolit<NOCODE>
Totals 715
Description Quantity Weight Unit Total Weight
1 11/2"CONDUIT-EMT 60 0.00E 0.00
2 11/2"CONNCOMPDC-EMT 4 0.00E 0.00
3 11/2"COUPLING COMP DC-EMT 10 0.00E 0.00
4 2" TYPE STD CONDUIT BODY-EMT-ALUM 1 0.00E 0.00
5 2 TO11/2"REDUCING WASHER 21 0.00E 0.00
6 11/2"FIELD BEND-EMT 6 0.00E 0.00
7 11/2"COUPLING-RMC-GALV 1 0.00E 0.00
8 11/2"BUSHING-STEEL 1 0.00E 0.00
9 11/2"1-H STRAP-EMT-STEEL 10 0.00E 0.00
10 11/2"FLEX-LIQUIDTIGHT METALLIC-GRAY 10 0.00E 0.00
11 111/2"CONN STRAIGHT-LIQUIDTIGHTDIECAST 2 0.00E 0.00
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
4
Description Quantity Weight Unit Total Weight
12 11/2"CONN90 DEG-LIQUIDTIGHTDIECAST 1 0.00E 0.00
13 1 1/2"ADAPTER FEM-PVC-UNDERGROUND 1 0.00E 0.00
14 46THHNBLACK 150 0.00E 0.00
15 1/0THHNBLACK 450 0.00E 0.00
16 600A3WCIRCUITBKR PANEL BOARD 1 0.00E 0.00
17 150A3PBREAKER-NEMA 1 1 0.00E 0.00
18 150A 3P PAN EL BREAKER TERM 3 0.00E 0.00
19 DEMO 400ADPB PANEL 1 0.00 E 0.00
Totals 715 1 0.00
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
5
Labor Type Crew Hours Rate$ SubTotal Brdn% Frng$ Brdn Tot. Frng Tot.
5 FOREMAN 1.00 27.82 92.70 2,578.91
6 JOURNEYMAN 1.00 27.82 84.31 2,345.50
Totals 2.00 55.64 88.50 4,924.41
Labor Type Total Full Rate Code Type
5 FOREMAN 2,578.91 92.70
6 JOURNEYMAN 2,345.50 84.31
Totals 4,924.41 88.50
Indirect Labor Lab% Hours Rate$ SubTotal Brdn% Frng$ Brdn Tot. Frng Tot. Total Full Rate Code
3 SUPERVISION-FOREMANELECT(NON-PROD) 5.000 2.78 89.22 248.03 248.03 89.22 002
11 IN-HOUSE PROJ MGMT ELECT 5.000 2.78 ####### 278.00 1 1 1 1 278.00 100.00 071
Totals 5.56 94.61 526.03 526.03 94.61
Indirect Labor JTpe3 SUPERVISION-FOREMANELECT(NON-PROD)11 IN-HOUSE PROJ MGMT ELECT
Totals
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
6
General Expenses Alarm Quantity Field Duration Cost/Unit Total Cost Tax(%) Overhead% Markup% Total
19 SAFETY/SMALLTOOLS/CONSUMABLES Off 1 4,924.41 DirLbTotal 1.00 0.04 196.98 8.350 213.43
20 PICK-UPTRUCK I Off I 55.64 DirLb Hours 1.00 5.25 292.11 1 1 1 292.11
Totals 489.09 16.45 505.54
General Expenses Notes Code Type
19 SAFETY/SMALLTOOLS/CONSUMABLES
20 PICK-UPTRUCK
Totals
Quoted Materials Alarm Cost Adjustment% Adjustment$ Adj Cost Vendor Notes Code Type
1+GEARQUOTE I Off 1 2,333.39 2,333.39 CED
Totals 2,333.39 2,333.39
Job Name-73111 BMY FRESNO SHERIFFS SUBSTATION 11 Job#-73111-CO#07ADDITIONAL POWER
05/22/202412:09:37 PM
7
Final Pricing Calculated(%) Calculated($) Variance (%) Modified($) Modified(%) Alarm Code %Final Price
Database Material(Extension) 11,106.14 11,106.14 47.069
Quoted Material 2,333.39 2,333.39 9.889
Material Tax 8.350 1,122.20 1,122.20 8.350 4.756
Material Total 14,561.73 14,561.73 61.714
Direct Labor 4,924.41 4,924.41 20.870
Indirect Labor 526.03 526.03 2.229
LaborTotal 5,450.44 5,450.44 23.100
General Expenses 505.54 505.54 2.143
Total Cost 20,517.71 20,517.71 86.957
Adjustment Markup 15.000 3,077.66 3,077.66 15.000 13.043
Total Markup 1 15.0001 3,077.66 13,077.66 15.0001 1 1 13.043
Selling Price 1 23,595.371 23,595.371 100.000
Final Price 23,595.37 23,595.37
PCO #022 B
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group, Inc. Project:22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone: (559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #022 B: CE #029 - ASI 5.3.2024 (Ez-
access fortress stair system)
TO: The County of Fresno, Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 022 B/0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 5/31/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 5 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $21,529.00
POTENTIAL CHANGE ORDER TITLE:CE#029-ASI 5.3.2024(Ez-access fortress stair system)
CHANGE REASON:Correction
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#029-ASI 5.3.2024(Ez-access fortress stair system)
Ez-access fortress stair system
Ref.modified layout plan
Supplied F.O.B.
EPC
Remobilization 5 Days=$1,267x5 CD's=$6,335.0
ATTACHMENTS:
EZ ACCESS LAYOUT.pdf
# Budget Code Description Amount
1 01-0400.0 Direct Work Fee.Other Staircases $7,437.50
BMY Construction Group, Inc. Page 1 of 2 Printed On:5/31/2024 03:36 PM
PCO #022 B
CONSTRUCTION
GROUPINCORPORATED
# I Budget Code Description Amount
3 1 01-0400.0 Direct Work Fee.Other Install $4,632.50
Subtotal: $12,070.00
Overhead(Subcontractor 15%): $2,130.00
Subcontractor Total: $14,200.00
Overhead(BMY): $994.00
2 01-0300.0 BMY MARGIN.Other EPC 6,335.00
Grand Total: $21,529.00
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
Pr.—ArchitectSign Here ProcoreArchitectSlg-dDate ProcoreOwnerSig,Here Procore0—rSlgnedDate ProcoreGeneralContractorSig,Here Pro—General CmtractorSig-dDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:5/31/2024 03:36 PM
BMY CONSTRUCTION GROUP INC.
_ Sheriff Station
BMY JOB#
Install and secure platform around generator
PCO Description:
PCO#: 000 Date:
MATERIAL
Description Units I Unit Price Subtotal
_ 0.00 0.00 ea 0.00
_ 0.00 0.00 ea 0.00
_ 0.00 0.00 ea 0.00
' Subtotal _ _ 0.00
Sales Tax(7.980/6) 0.00
Shipping/Freight
Overhead &Profit 15% 0.00
Total Material $0.00
EQUIPMENT
Descri tion I Units I Unit Price I Subtotal
Gradall 1.00 550.00 550.00
Foreman truck 2.00 250.00 500.00
Subtotal 1050.00
Overhead& Profit 15% 157.50
Total Equipment $1,207.50
LABOR
Description' I M/Hr I Cost/MH Labor Burden Subtotal
Cement Mason 0.00 70.56 25.32 0.00
Laborer 16.00 63.91 23.62 1400.48
Carpenter _ 86.97 29.52 0.00
Iron Worker 16.00 83.81 28.71 1800.32
Operator 4.00 _ 91.38` 30.65 488.12
Subtotal Labor 3688.92
Overhead &Profit 15% 553.34
Total Labor $4,242.26
OTHER
Description F Units I Unit Price I Other Cost I Subtotal
0.00
0.00
Subtotal 0.00
Overhead & Profit 15% 0.00
Total Other $0.00
TOTAL
f Subtotal 5,449.76
TOTAL $5,450
TIME EXTENSION REQUIREMENT= 0 Calendar Days
NOTES:
ESTIMATE
Wicks Fabrication,Inc. kwicksfab@gmail.com
11380 E.Sierra Ave. 559-392-1674
Clovis,CA 93619
Wicks Fabrication /nc_
BMY Construction
Bill to Ship to
BMY Construction BMY Construction
BMY Construction Group Inc. BMY Construction Group Inc.
5485 E.Olive Ave. 5485 E.Olive Ave.
Fresno,CA 93727 Fresno,CA 93727
Estimate details P.O.Number:Area 2 Sherriff Substation
Estimate no.:1146
Estimate date:05/29/2024
# Date Product or service Description Oty Rate Amount
1. Steel Erect-a-step modular platform system 1 $47,500.00 $47,500.00
per details
-ref.A1.6
-Supplied F.O.B.
2. Alum. Ez-access fortress stair system 1 $8,750.00 $8,750.00
-Ref.modified layout plan
-Supplied F.O.B.
3. Alum. Custom aluminum platform system to 1 $15,450.00 $15,450.00
match layout on A1.6
-2"sq.support members
-plank grating platform
-1"sq.railing
Total $71,700.00
4
-O\1 Q\I — xET TI— i-O\I j'O\I IMexssx,1 eENEaniaal NOasilPnD '-O\I I O 1 I-O 1 I O 1 I-O 1
e piu w
0
p d: d O /l
aucnons d o d \ Y / \
a am
d a
d ° O a OF cOxcftETE PAD
O �OMPorvExT YPICAL ° },
c o
`w
DIAeoNAL NATON ELEIML i
INDICATES PLATFORM o
� SY5TEM GSTOM INFILL � ___ _ ° - -
O
Y Exlsrirv5
/ TRnNSFORnER /-�- -, b � on coucaETe Pnv 1, 0
i
Ul
I I I I d ° I \ � \ /
- I dl ses srxucTuau d d I ° ° \
-
4 O\I D\I l O\1
O ° d IN FILL PANEL d C O d a EOL1T Z TrplcnLl
_ FO-ACRTRESSESS 4 HAI�DRAILING ExlsmPROT
d a d STAIRSYSTEM Q
T d
------ 1 a----��� ------¢-- J
a -----�--�� ra � r�---
I I d IncaS.zazam
\ \ d
-------------
CONTRACT#21-S-01
a /I IT II�A Q F irtcT
\ \ �oRAVEL vaauxv \ d II II all II L------ ------J ° dsSx Aechr6 r.� nww�iw
a covEa rrPi _ �__ I I I I I
�I���ill Id ii �di�ti § a ��
d a `� ----�J II II II I L- --- -
\ \ rvery LAxvscAP[xEADez ti °J ti 1�- d----�II \I II II I/ coxcasr pooTirvS T"'"°n6„^°"'s"''
d w L d ul � _a y �rPo�a>�f T
Project:
2 Sebstation Storage Bldg Data
Center&Elec Rm RavlslDns-Bld Package 2
IMITIT"
coMPox"IT""IL n4 RM R Erwn[reasse�ary
MPR Ix5 R TIDxS EE ALaD 5TR Taft D 5Tft DT ftAL Sheet Content:
PAD0EN rDa O ftErS l N EMERGENCY
GENERATOR
C' ENLARGED SITE PLAN AT EMERGENCY GENERATOR SERVICE PLATFORM DETAILS
Ai 6 SCALE 11Z-1'-.'
FRL`+
Sheet No.:
Al .6
PCO #023
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group, Inc. Project: 22009-Fresno County Sheriff Substation Bid Package Contract
5485 East Olive Avenue #21-S-01
Fresno,California 93727-2541 1129 N Armstrong Ave
Phone:(559)243-4200 Fresno,California 93727
Fax:null
Prime Contract Potential Change Order #023: CE #032 - Generator
Terminations
TO: The County of Fresno,Department of Public FROM: BMY Construction Group,Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 023/0 CONTRACT: 22009-Fresno County Sheriff Substation
Bid Package Contract#21-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Nick Hostetler(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 8/1/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO 30
WILL EXPIRE AFTER:
SCHEDULE IMPACT: 1 day PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $2,654.38
POTENTIAL CHANGE ORDER TITLE: CE#032-Generator Terminations
CHANGE REASON: Correction
ATTACHMENTS:
73111 -CO#09 Proposal.pdf
# Budget Code Description Amount
1 26-OOOO.PO Electrical.Purchase Order Generator Terminations $2,155.60
Subtotal: $2,155.60
Overhead(Subcontractor 15%): $380.40
Subcontractor Total: $2,536.00
Overhead(BMY): $118.38
Grand Total: $2,654.38
BMY Construction Group, Inc. Page 1 of 2 Printed On: 8/8/2024 07:24 AM
PCO #023
CONSTRUCTION
GROUPINCORPORATED
Keith Eckert(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
P—,.ArchitectSign Here Pro—ArchitectSlg-dDate ProcoreOwnerSig,Here Pro co reOwnerSlgnedDate ProcoreGeneralC,—,torSig,Here P,coreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group, Inc. Page 2 of 2 Printed On:8/8/2024 07:24 AM
Contra Costa Electric Contra Costa Electric,Inc.
4690 E Carmen Ave
An EMCOR Company Fresno,CA 93703
Ph:559.252.1114
Fax:559.452.1013
July 30th, 2024
Attn: Derek Brawley
Subject: Fresno Sherriffs Substation Bid Package 2 -Generator Terminations
CCE CO#9
We are pleased to offer for your consideration our Lump Sum Quotation for the above
referenced project. Proposal is valid for 30 days.
Lump Sum $2,536.00
A. In general, our quotation will include the following:
• Provide and install (16) 600mcm to 500mcm stepdown compression adapters.
• Provide and install (6) 500mcm to 350mcm stepdown compression adapters.
B. We have excluded the following items from our scope of work:
• Providing performance and payment bond.
• Surveying or staking.
• Anything not specifically included is explicitly excluded.
C. The following clarifications and qualifications were made in the preparation of this
proposal:
1. Work hours to be 7:OOAM to 3:30PM Monday thru Friday.
2. CCE will require 5 additional days to perform the work described in this proposal.
We recognize that you have a choice when it comes to selecting contractors to work on your
projects and we thank you for giving Contra Costa Electric, Inc.the opportunity of bidding on
your work. If we can be of service to you on this or future projects,please feel free to contact me
at(559) 252-1114 or jfowler@emcor.net
Sincerely,
�6� 74Gf&T
Fresno Office
Contra Costa Electric,Inc.
An EMCOR Company
,p
d..._..'"'Rs
www.ccelectric.com
Page 1 of 1 D R#10000011625
PAGE 29
G R EAVE S GREAVES EXCLUSIVE
COMPRESSION
Reducefl TM For copper cable
Class B
600V*
STEP-DOWN ADAPTERS SP. & 1050C
All-copper compression adapters C us LISTED
For reliable termination of Class B copper conductor
Use where oversized cable is used to reduce voltage drop on long runs
Use where neutrals are upsized for power quality
Narrow profile often allows use in place of offset adapters on multi-wire terminals
Fits into mechanical set-screw type connectors
Amperage rating is per the incoming conductor
Fabricated of wrought copper with pin of Class B stranded copper conductor
Insulating covers are included
L
E B�
Strip Length -o-j P
D** PIN SIZE
L :ft y
PT-R SERIES
NOMINAL U-TYPE DIE*
DIMENSIONS(IN) CABLE
NAED CATALOG CABLE PIN STRIP COLOR DIE # EST.SHIPPING
NUMBER NUMBER SIZE SIZE B P L D** LENGTH CODE INDEX CRIMPS WEIGHT(lbs) UNIT
54102 PT10R2 1/0 AWG 2 1.75 1.10 2.85 0.50 1 PINK 12/348 1 0.08 EA
54202 PT20R2 2/0AWG 2 1.81 1.10 2.93 0.56 1% BLACK 13 1 0.10 EA
54210 PT20R10 2/0 AWG 1/0 1.94 1.23 3.13 0.56 1'/4 BLACK 13 1 0.11 EA
54320 PT30R20 3/0 AWG 2/0 1.95 1.19 3.13 0.62 1'/4 ORANGE 14 1 0.13 EA
54420 PT40R20 4/0 AWG 2/0 1.93 1.19 3.15 0.67 1'/4 PURPLE 15 2 0.13 EA
54430 PT40R30 4/0 AWG 3/0 2.10 1.30 3.15 0.67 1'/4 PURPLE 15 2 0.16 EA
54254 PT25OR40 250 kcmil 4/0 2.13 1.31 3.50 0.74 1'/4 YELLOW 16 2 0.24 EA
54305 PT30OR250 300 kcmil 250 kcmil 2.38 1.40 3.75 0.80 1% WHITE 17/298 2 0.25 EA
54355 PT35OR250 350 kcmil 250 kcmil 2.40 1.40 3.85 0.85 1% RED 18/324 2 0.26 EA
54353 PT35OR300 350 kcmil 300 kcmil 2.40 1.45 3.85 0.87 1'A RED 18/324 2 0.32 EA
54435 PT40OR350 400 kcmil 350 kcmil 2.65 1.51 4.30 0.95 1'/2 BLUE 19/470 2 0.38 EA `
54535 PT50OR350 500 kcmil 350 kcmil 2.50 1.50 4.00 0.99 1% BLUE 19/470 2 0.40 EA
54540 PT50OR400 500 kcmil 400 kcmil 2.63 1.65 4.13 1.01 1'A BLUE 19/470 2 0.44 EA
54650 PT60OR500 600 kcmil 500 kcmil 2.90 1.75 4.72 1.13 1'/2 GREEN 22/472 2 0.64 EA
54750 PT75OR500 750 kcmil 500 kcmil 3.06 1.75 4.90 1.21 1% BLACK 24/473 2 0.65 EA
54760 PT750R600 750 kcmil 600 kcmil 3.15 1.90 5.00 1.27 1'/4 BLACK 24/473 2 0.89 EA
54107 PT1000R750 1000 kcmil 750 kcmil 3.00 2.01 5.00 1.44 1% YELLOW 936 2 1.09 EA 4
Consult factory for price and delivery of the following: n ,
Size combinations not shown 5
Custom pin lengths,diameters,and solid pins 9
Tin plating(when ordering,add the suffix"P"to Catalog Number)
For aluminum cable,use PT,PTA,PTO(aluminum barrel adapters).See page 41.
*UL Installation tool:Greenlee HKL 1232.
**Add%"for insulating cover. www.greaves-usa.com
Phone 860-664-4505•Fax 860-664-4546
TOLL FREE 1-800-243-1130(Outside CT)
Job Name-73111 11 Job#-73111-CO#09GENSET TERMINATIONS
07/30/202411:44:43 AM
1
Description Quantity Date Trade Price Unit Disc% Link Price Cost Adj% NetCost DB Labor Labor
1 GREAVESPT500R350500-350MCMSTEPDOWNCOMPADAPTER 1 607/30/2024 1 53.00E 0.00 0.00 0.000 53.00 63.82 63.82
2 GREAVESPT600R500600-500MCMSTEPDOWNCOMPADAPTER 1607/30/2024 1 58.00E 0.00 0.00 0.000 58.00 80.18 80.18
Totals 122
Description Quantity Unit Lab Adj% Total Material Total Hours Material Condition LaborCondition
1 GREAVESPT500R350500-350MCMSTEPDOWNCOMPADAPTER I 6C -50.000 318.00 1.91 Normal Normal
2 GREAVESPT600R500600-500MCMSTEPDOWNCOMPADAPTER I 16C -50.000 928.00 6.41 Normal Normal
Totals 22 1,246.00 8.33
Description Quantity Manufacturer Name Catalog Number Price Code Reference SupplierName Supplier Code Sort Code 1
1 GREAVESPT500R350500-350MCMSTEPDOWNCOMPADAPTER I 6BURNDY YP350 781810737 123006 1 000
2 GREAVESPT600R500600-500MCMSTEPDOWNCOMPADAPTER 16ILSCO CM-600 783669009 4000
Totals 22
Description Quantity Sort Code 2 Sort Code 3 Sort Code 4 Sort Code 5 Sort Code 6 Sort Code 7
1 GREAVESPT500R350500-350MCMSTEPDOWNCOMPADAPTER 1 6 190 350 0 0001JWire 190071119007.TERMINATION LUGS 35011Motors
2 GREAVESPT600R500600-500MCMSTEPDOWNCOMPADAPTER 16 190 350 0 000jjWire 190071119007.TERMINATION LUGS 35011Motors
Totals 122
Description Quantity Sort Code 8 Quick Takeoff Code Weight Unit rotalWeight
1 GREAVESPT500R350500-350MCMSTEPDOWNCOMPADAPTER I 6<NOCODE> I 0.00E 1 0.00
2 GREAVESPT600R500600-500MCMSTEPDOWNCOMPADAPTER 16<NOCODE> I 0.00E 1 0.00
Totals 122 0.00
Job Name-73111 Job#-73111-CO#09 GENSET TERMINATIONS
07/30/202411:44:43 AM
2
Labor Type Crew Hours Rate$ SubTotal Brdn% Frng$ Brdn Tot. Frng Tot.
6 JOURNEYMAN 11.00 8.33 84.31 702.30
Totals 1.00 8.33 84.31 702.30
Labor Type Total Full Rate Code Type
k6—JO—URNEYMAN 702.30 84.31
Totals 702.30 84.31
Indirect Labor Lab% Hours Rate$ 1 SubTotal Brdn% I Frng$ Brdn Tot. Frng Tot. Total Full Rate I Code
k3— SU—PERVISION-FOREMANELECT(NON-PROD) 5.000 0.42 89.22 37.47 37.47 89.21002
Totals 0.42 89.21 37.47 37.47 89.21
Indirect Labor Type
k3— SU—PERVISION-FOREMANELECT(NON-PROD) L
Totals
Job Name-73111 11 Job#-73111-CO#09GENSET TERMINATIONS
07/30/202411:44:43 AM
3
General Expenses Alarm Quantity Field Duration Cost/Unit Total Cost Tax(%) Overhead% Markup% Total
19 SAFETY/SMALLTOOLS/CONSUMABLES Off 702.30 DirLbTotal 1.00 0.04 28.09 8.350 30.44
20 PICK-UPTRUCK Off 8.33 DirLb Hours 1.00 5.25 43.73 43.73
25 IN-HOUSE PROJMGMTELECT Off 8.33 DirLb Hours 0.05 100.00 41.65 41.65
Totals 113.47 2.35 115.82
General Expenses Notes Code Type
19 SAFETY/SMALLTOOLS/CONSUMABLES
20 PICK-UPTRUCK
25 IN-HOUSE PROJ MGMT ELECT
Totals
Final Pricing Calculated(%) Calculated($) Variance (%) Modified($) Modified(%) Alarm Code %Final Price
Database Material(Extension) 1,246.00 1,246.00 49.123
Material Tax 8.350 104.04 104.04 8.350 4.102
Material Total 1,350.04 1,350.04 53.225
Direct Labor 702.30 702.30 27.688
Indirect Labor 37.47 37.47 1 1.477
LaborTotal 739.77 739.77 29.165
General Expenses 115.82 115.82 4.566
Total Cost 2,205.63 2,205.63 86.957
Adjustment Markup 15.000 330.84 330.84 15.000 13.043
Total Markup 1 15.000 330.84 1330.84 15.000 13.043
Selling Price 2,536.47 2,536.47 100.000
Final Price 2,536.47 2,536.47