CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 2
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 31, 2024
CONTRACT NO. 23-04-C PAGE 1 OF 3
TO: AVISON CONSTRUCTION INC.:
Make the following change(s) to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the proposed change(s), THREE (3) -WORKING DAYS will be granted to the
allotted contract time. The revised date of completion for the Second Order of Work is December 9, 2024.
PART I: INCREASE / DECREASE / ELIMINATE ITEMS AT UNIT PRICES
These quantity adjustments were proposed by engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total Total
No. Description Unit Quantity Price Amount 0/0) of/6)
4 Portable Changeable Message EA 2.00 $4,000.00 $8,000.00 33.33 33.33
Sign
17 Remove & Dispose Barbed Wire LF 195.00 3.00 585.00 19.21 19.21
Fence
44 Survey Monument (Type D) EA 1.00 1,200.00 1,200.00 100.00 100.00
TOTAL INCREASE: $9,785.00
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount o� o�
13 Remove & Dispose Sign EA 3.00 $100.00 $300.00 (75.00) (75.00)
Structure
14 Remove & Dispose Concrete LF 7.00 130.00 910.00 (16.28) (16.28)
Pipe
TOTAL DECREASE: $1,210.00
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 2
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 31, 2024
CONTRACT NO. 23-04-C PAGE 2 OF 3
Eliminated Items:
Item Total Total
No. Description Unit Quantity Price Amount ° (0/-)
11 Remove & Dispose Light Fixtures LS 1.00 $800.00 $800.00 (100.00) (100.00)
12 Remove & Dispose Storage LS 1.00 3,500.00 3,500.00 (100.00) (100.00)
Sheds
16 Remove & Dispose Hog Wire LF 744.00 3.00 2,232.00 (100.00) (100.00)
Fence
TOTAL DECREASE: $6,532.00
Since you did not incur any costs associated with these items, no payment will be made for these bid items.
This work did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: $2,043.00 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: REMOVE & DISPOSE OF OLIVE TREES - EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, remove &
dispose approximately 40 olive trees on the road right-of-way line on the north side of Olive Avenue, from
approximately Sta. 92+00 to Sta. 98+00. Perform all work according to the applicable sections of the Standard
Specifications and the Special Provisions. Payment for this work will be made as extra work at Force Account
according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work
resulted in $34,452.02. This amount will be paid as extra work.
Three (3) working days will be added to the contract time for the above referenced extra work, in accordance
with Section 8-1.07B, "Time Adjustments," of the Project Specifications.
TOTAL COST PART IL $34,452.02 INCREASE
TOTAL TIME EXTENSION PART II: THREE (3) -WORKING DAYS
PART III: USE WHITE PAINT (2-COAT) FOR BID ITEM NOS. 53 & 59 IN-LEIU OF WHITE
THERMOPLASTIC STRIPE AND MARKINGS
This change was requested by the engineer.
Contractor We, the above signed contractor,have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of supervisors therefore the prices shown above.
_Const.Mgmt
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
FOWLER AVE & OLIVE AVE INTERSECTION IMPROVEMENTS CHANGE ORDER NO. 2
FEDERAL PROJECT NUMBER: CML-5942(293) OCTOBER 31, 2024
CONTRACT NO. 23-04-C PAGE 3 OF 3
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, use paint (2-
coat) in lieu of thermoplastic for Bid Item No. 53, Thermoplastic Traffic Stripe (Detail 39), and Bid Item No. 59,
Thermoplastic Pavement Markings (Bike Lane Symbol with Person and Bike Lane Arrow). Perform all work
according to the applicable Standard Specifications and the Special Provisions. This change is being made at
no additional cost.
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL COST PART III: $0.00 (NO COST)
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
NET COST THIS CHANGE ORDER: $36,495.02 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: THREE (3) -WORKING DAYS
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
AVISON CONSTRUCTION, INC. �A C--
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By APPROVED BY:
Digitally signed by Steve
Whit
Title Project Manager Steve W h lte 09:39:47-08'0D tee2024.11.18
0'
Steven E. White, Director
Accepted Date.
Nov 15, 2024 Public Works and Planning
Date:
Contractor We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Mgmt therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.