HomeMy WebLinkAbout2323C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 2
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE NOVEMBER 4, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 1 OF 2
CONTRACT NO. 23-23-C
TO: EMMETT VALLEY CONSTRUCTION:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
COMPENSATE THE CONTRACTOR FOR THE CALIFORNIA STATEWIDE CRUDE OIL PRICE
INDEX FLUCTUATION
Compensate the contractor per the methods established in the State Standard Specifications Section 9-
1.07 for fluctuations greater than or less than five percent in the California Statewide Crude Oil Index
for the month the material was placed, when compared to the index published for the month of the bid
opening. The California Statewide Crude Oil Price index for the month of February 2024, was 423.9.
The index was 462.6 for the month of August 2024, which applies to the Pay Estimate No. 4 for the
quantity of asphalt in the hot mix asphalt(HMA) and emulsion (tack coat).
The asphalt content in the 3/4-inch HMA from Vulcan Ashlan plant was 4.30 percent. The asphalt
content was adjusted to 2.92 percent to account for the 25 percent reclaimed asphalt pavement(RAP)
in the mix. The adjustment applies to 5389.04 tons placed in Augst 2024. The asphalt content in the
1/2-inch HMA from Vulcan Ashlan was 4.60 percent. The asphalt content was adjusted to 3.27 percent
to account for the 25 percent reclaimed asphalt pavement(RAP) in the mix. The adjustment applies to
2289.3 tons material placed in August 2024. Also, Asphaltic emulsion (SS-1 h) was utilized on the
project where the minimum percent asphalt residue for the emulsion placed as tack was 57 percent. A
total of 8.46 tons of tack coat was used in August 2024.
The total compensation adjustment for price index fluctuation resulted in an increase of$4,252.60. This
amount is being paid under Bid Item No. 1, Supplemental Work (Payment Adjustments for Price Index
Fluctuations), with no net cost increase to the contract.
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that.we will provide all equipment,furnish all materials, except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ADAMS AVENUE SHOULDER IMPROVEMENT AND OVERLAY CHANGE ORDER NO. 2
CHERRY AVENUE TO 0.25 MILES EAST OF CLOVIS AVENUE NOVEMBER 4, 2024
FEDERAL PROJECT NUMBER CML-5942(253) PAGE 2 OF 2
CONTRACT NO. 23-23-C
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NOA)
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
Jason Ahumada, Resident Engineer
APPROVAL RECOMMENDED:
EMMET VALLEY CONSTRUCTION
Contractor Mandeep S. Sekhon, PE
��
Construction Engineer
By AlUs,n APPROVED BY:
} /� } Digitally signed by Steve
Title Vice president
Steve V V h I Le D tee2024.11.06
13:50:32-08'00'
Steven E. White, Director
Accepted Date:
Nov 5 2024 Public Works and Planning
,
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors therefore the prices shown above.
_Const.Management
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.