HomeMy WebLinkAbout2324SW CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 3
PHASE III - MODULES 9 & 10 OCTOBER 3, 2024
EXCAVATION AND LINER CONSTRUCTION PAGE 1 OF 2
18950 W AMERICAN AVENUE, KERMAN, CA 93630
CONTRACT NO. 23-24-SW
TO: YARBS GRADING AND PAVING, INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
PERFORM ADDITIONAL POTHOLING TO LOCATE EXISTING 2-INCH LEACHATE LINE—EXTRA WORK
This change was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, perform
additional potholing to locate the existing 2-inch leachate transmission line in the southwest corner of Module
10. Perform all work in accordance with the applicable sections of the Special Provisions and/or Standard
Specifications. Compensation for this work will be made as extra work at force account according to Section 9-
1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in $4,835.49.
This amount will be paid through Bid Item No. 1, Supplemental Work Allowance, with no net increase to
the contract.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 3
PHASE III - MODULES 9 & 10 OCTOBER 3, 2024
EXCAVATION AND LINER CONSTRUCTION PAGE 2 OF 2
18950 W AMERICAN AVENUE, KERMAN, CA 93630
CONTRACT NO. 23-24-SW
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NO. 1)
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
Oleg Savelyev, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING & PAVING, INC. 0'-Jy�."�—_
Contractor Mandeep S. Sekhon, PE
Construction Engineer
TYo� �a
B �b�or�Gc y Troy�YarYrough(Oct9.2024 :41PDT) APPROVED BY:
Digitally signed by Steve
Whit
President Steve WhlteD tee2024.10.10
Title 16:24:27-07'00'
Steven E. White, Director
Accepted Date:
Oct 9 2024 Public Works and Planning
5
Date:
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified, and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.