HomeMy WebLinkAbout2214C CCO 29.pdf COUNTY OFFRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
GOLDEN STATE BOULEVARD PHASE | CHANGE ORDER NO. 2S
AK8ER|CAN AVENUE TJ MISSION STREET GEPTEK8BER25. 2O24
CONTRACT NO. 22-14-C PAGE 1OF2
TO: YARBS GRADING AND PAVING, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(e). will bm added to the contract tinneUne.
RE-CONSTRUCT TEMPORARY CURB RAMPS IN THESELK0A REG|ON -EXTRA WORK
This extra work was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, na-
oonatruotbannponarycurbrampsotthofo||ovvinQ |onationoueingdeuornpomadQronite:
* NVV corner of Floral Avenue and Whitson Street
° NE corner, s/o Floral Avenue(by Circle KK8arkeU
° GVV corner of Stillman Street and Whitson Street
• 8E and NVV corners cf First Street and Whitson Street
* 8E corner of McCall Avenue and Whitson Street
° NVV corner(midexve{h) of Todd Street and Whitson Street
° SVV corner of Ross Street and Whitson Street
° NVV corner ofPark Street and Whitson Street
Decomposed granite shall comply with the requirements of Section 20-5.03D, "Decomposed Granite,"of the
Standards Specifications. Perform all work in accordance with Section 16-2.02. "Temporary Pedestrian
Facilities," of the Standard Specifications. Compensation for this work will be made as extra work at force
account according to Section 9-1.03, "Payment Scope,"of the Special Provisions.Total compensation for this
work resulted in $G.O41.43. this amount will be paid aa extra work.
This extra work did not impact the critical path for the project,tharefona. QrantinOoddiUonm|cuntnoctUrnevvoo
not warranted.
_m"*acm, We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
—Auditor Controller m�nmnosa/�ann�,eu'motwewmnmvmeanenv/nmen�mm/sxanm*�n*/sex'rotas may mher^/seue
--o",mo,pma no�uaou,eanupenmnmaosew/asne'�,sv�mrme=v,�aovv�sveuneoa���mvoentasmonavmant
mm��s.n°°/m� ' '
mn*.Managemen, therefore the prices shown above.
_RE/Arch.
_oes*o If the Contractor ones not sign acceptance of this ump,,his attention/s directed to the requirements mthe
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 29
AMERICAN AVENUE TO MISSION STREET SEPTEMBER 25, 2024
CONTRACT NO. 22-14-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: A $6,041.43 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
LaRue Goossen, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING AND PAVING, INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
TY Y bi-o Gt
By TrovYani(our;h(Sep26.202, 4:55PDT) APPROVED BY:
Digitally signed by Steve
Whit
President Steve WhlteDatee2024.10.02
Title 12:55:08-0T00'
Steven E. White, Director
Accepted Date:
Sep26 2024 Public Works and Planning
�
Date:
Nathan Magsig, Chairman
Board of Supervisors
Date:
contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, If
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention Is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.