HomeMy WebLinkAboutWAJ CO29 Bernard Bros signed.pdf LETTER OF TRANSMITTAL -C.C.O. No. 029 September 4, 2024
Page 1 of 6
TO: Steven White, Director West Annex Jail
Public Works and Planning
ATTN: Will Kettler
Division Manager CONTRACT NO. 16-S-04
FROM:
Jim Anderson, Sr. Project Manager
Kitchell CEM
STATUS OF FUNDS
Contract Items $ 81,756,000.00 Original Allotment $ 85,843,800.00
Co. Furnished Materials $ 0.00 *Supplemental Allotment $ 1,100,000.00
Previous CCO's $ 4,168,695.00 Total Allotment $ 86,943,800.00
This CCO $ 292,314.00 Obligated Funds $ 86,217,009.00
Total Obligated Fund $ 86,217,009.00 Unobligated Balance $ 726,791.00
Note: 1. Total allotment is the bid amount plus the Board Chairman's limit to authorize
Change Orders $4,087,800.00
*Note 2. *Board Action dated September 6, 2022 to increase the original contingency
$1,100,00 for a revised contingency of$5,187,800
DESCRIPTION (PCO 0613)
RFI 573.2— Level 3 Mezz Future Floor Electrical Feeders @ Elevator Machine Room
WHY:
Cores were drilled into the elevator machine room that required in-fill.
HOW:
Lump Sum
COST:
A $756.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 626)
RFI 700.03 — Fire Command Center Firestopping
WHY:
Spray applied fire proofing was required by the SFM to comply with UL details at the wall to deck
angles.
Letter Of Transmittal— C.C.O. No 029
Contract No. 16-S-04
September 4, 2024
Page 2 of 6
HOW:
Time and Material
COST:
A $14,843.00
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0580.2)
RFI 940.3 & 940.4—Fire Sprinkler head changes in Elevator Shafts
WHY:
The sprinkler heads within the elevator shafts were required to be changed from the approved
documents to a higher heat rating.
HOW:
Time and Material
COST:
A $4,323.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0602.1)
Stair#3 &4 handrail modifications to comply with ADA
WHY:
Handrail required modifications from the Contract Documents to comply with ADA requirements.
HOW:
Time and Material
COST:
A $8,318.00 In
crease
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0662.1)
Removal of Expandable Foam throughout the building
WHY:
Expandable foam was allowed for use by the A/E but is considered flammable by the SFIVI and was
required to be removed from the building.
Letter Of Transmittal—C.C.O. No 029
Contract No. 16-S-04
September 4, 2024
Page 3 of 6
HOW:
Time and Material
COST:
A$160,979.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0664)
RFI 1246, 1246.1 —Sealant at Non-Rated Walls
WHY:
Where foam was required to be removed as noted in PCO 662.1 above, sealant was required to be
installed for acoustics and odor.
HOW:
Lump Sum
COST:-
A 28,170.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0683)
RFI 1276—Water Barrier @ Exterior Roll-Up Door
WHY:
The northern most exterior roll-up door allows water to seep into the building. The A/E directed a
water barrier installed to mitigate this issue.
HOW:
Lump Sum
COST:
A $722.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0689)
RFI 1293—Adjust Dayroom Tables for ADA
WHY:
The layout of dayroom tables encroached into a door opening that did not comply with ADA.
Letter Of Transmittal — C.C.O. No 029
Contract No. 16-S-04
September 4, 2024
Page 4 of 6
HOW:
Time and Material
COST:
A$6,067.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0693)
RFI 1297 —Power to Water Solenoids
WHY:
The design showed a redundancy in the control of water to the dayrooms. Contractor was directed to
remove the power to the redundant valves
HOW:
Lump Sum
COST:
A$2,060.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0664.1)
Tarlton—ASI 113 (Stair#4) Design Assist
WHY:
Design assist and coordination from their internal engineers and staff to resolve questions associated
with stair#4 fire rated enclosure
HOW:
Lump Sum
COST:
A $21,322.00 Increase
TIME:
No time extension requested by contractor
Letter Of Transmittal—C.C.O. No 029
Contract No. 16-S-04
September 4, 2024
Page 5 of 6
DESCRIPTION (PCO 0697)
Non-Contact Visitation door numbering
WHY:
The door numbering noted on the Contract drawings showed the numbering on one side of the doors
opposite as the other side.
HOW.
Time and Material
COST:
A$789.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0699)
Added Knox Box @ Fire Pump House
WHY:
The City Fire Department requested a Key Knox Box added at the fire pump house.
HOW:
Lump Sum
COST:
A$845.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0704)
RFI 1241.1 —Credit for Thresholds
WHY:
Elimination of(5)thresholds at exterior doors
HOW:
Lump Sum
COST:
A$-375.00 Decrease
TIME:
No time extension requested by contractor
Letter Of Transmittal—C.C.O. No 029
Contract No. 16-S-04
September 4, 2024
Page 6 of 6
DESCRIPTION (PCO 0709)
RFI 1305—Wall Mounted Desks @ Interview Rooms
WHY:
Contract documents did not show (8) wall mounted desks as contractor resposible for providing and
installing.
HOW:
Lump Sum
COST:
A $43,495.00 Increase
TIME:
No time extension requested by contractor
NET COST THIS CCO : $292,314.00 INCREASE AND 0 CALENDAR DAY EXTENSION
aPrime Contract Change Order
Detailed
Date: 8/9/2024
To Contractor: Contract Number: 16-S-004
Bernards Change Order Number: 029
3633 E.Inland Empire Blvd,
Ontario,CA 91764
The Contract is hereby revised by the following items.
Contract Change Order#029
PCO Description Amount
0613 RFI 573.2-L3_Mezz-Future Floor Elec Feeders @ Elev Machine Rm 3204 $756.00
0626 RF10700.0003-L1_Fire Command Center 1172-Thermal Requirements $14,843.00
(EJ-054,EJ-055,&EJ-056)
0580.2 RFI 940.3,940A-FA VesdalHeat-Smoke DetectorlFS Head Changes $4,323.00
0602.0001 CASp-Stair 3&4 Handrail Modifications $8,318.00
0662.0001 Removal of All Expandalble Foam $160,979.00
0664 RFI 1246,1246.1-Sealant at Non-Rated Walls $28,170.00
0683 RFI 1276-Water Barrier @ Roll-Up Door $722.00
0689 RFI 1293-Adjust Dayroom Tables for ADA $6,067.00
0693 RFI 1297-Power to Water Solenoids S2,060.00
0654.0001 Tarlton-ASI 113 Design Assist Costs $21.322.00
0697 Non-Contact Visitation Door Numbering $789.00
0699 Added Knox Box @ Fire Pump House $845.00
0704 RFI 124�.1-Credit for Thresholds $(375.00)
0709 RFI 1305-Wall Mounted Desk @ Interview Rms $43,495.00
Theoriginal Contract Value was....................................................................................................................... $81,756,000.00
Sum of changes by prior Prime Contract Change Orders.............................................................................. $4,168,695.00
The Contract Value prior to this Prime Contract Change Order was................................................................ $85,924,695,00
The Contract Value will be changed by this Prime Contract Change Order in the amount of.................. $292,314,00
The new Contract Value including this Prime Contract Change Order will be.................................................. $06,217,009.00
The Contract duration will be changed by...................... 0 Days
The revised Completion date as of this Prime Contract Change Order is..................................................... September 16,2020
EJ FTOO.s.�..r - Prime Contract Change Order
Detailed
We the above-signed contractor,have given careful consideration to the change proposed and hereby agree,when this proposal Is approved,
that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work
above specified,and will accept as full payment therefor the prices shown above.
If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the Specifications as to proceeding with
the ordered work and filing a written protest within the time therein specified
By accepting a Change Order,Contractor agrees to the changes,If any,In the Contract Price specified for each item and to the specified
Extension of Time allowed,if any,for completion of the entire Work on account of such Change Order,and agrees to furnish all labor and
materials and perform all Work necessary to complete all additional Work specified therein for the price adjustment and within the time specified
therein. Contractor shall make no additional claim for adjustment to the Contract Price or Contract Time,nor for additional costs or damages,on
account of the work referenced in such Change Order. A Change Order duly issued by the Owner and accepted by the Contractor shall
constitute a complete accord and satisfaction as to the Work,Contract Price,and Contract Time changed thereby. Contractor shall defend and
indemnify the Owner,its officers,employees,agents and consultants,if any Subcontractor asserts any claim against the Ownerlhat contradicts,
or is inconsistent with a duly issued Change Order accepted by Contractor. Section 0126 00,1.9
r1 Prime Contract Change Order
Detailed
Approval Recommended
Bernards Kitchell CEM
CONTRACTOR / PROJECT MANAGER
By --Gene�Jemes— yCAll By Jim Anderson
SIGNATURE —t"y� SIGNATUR!!� •� , -
DATE � —f DATE
Approval Recommended Approved By
DLR Fresno County
PROJECT MANAGER DIRECTOR
BY Gregg Williams By Steven White
SIGNATURE _ :z:.;- SIGNATURE
DATE 08/30/24 DATE
Approved By
Fresno County Fresno County
COUNTY COUNSEL COUNTY ADMINISTRATIVE OFFICER
BY Danle.0 C der6org BY Paul Ne nd
SIGNATURE '' _ SIGNATURE
DATE DATE "! •��