HomeMy WebLinkAbout2309SW CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SOUTHEAST REGIONAL DISPOSAL SITE CHANGE ORDER NO. 1
PERIMETER FENCE REPLACEMENT JULY 9, 2024
CONTRACT NO.: 23-09-SW PAGE 1 OF 3
TO: AJ EXCAVATION, INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 10 -WORKING DAYS will be added to the contract time.
PART I: REPAIR EROSION AREA —EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, repair
approximately 20-feet by 20-feet eroded slope area along Academy Avenue, approximately 1,800 feet
n/o Dinuba Avenue. This work includes grading and addressing the eroded area and placing
approximately 46 tons of 6-inch riprap and approximately 23 tons of Class 2 Aggregate Base. Perform
all work according to the applicable sections of the Standard Specifications and/or Special Provisions,
as directed by the Resident Engineer. Compensation for this work will be made at an agreed lumpsum
price of$11,415 according to Section 9-1.03, "Payment Scope," of the Special Provisions. This agreed
price includes compensation of all materials, labor, equipment, traffic control, overhead costs, markups,
profits, and incidentals for performing the work. This amount will be paid through Bid Item No. 1,
Supplemental Work, with no net increase to the contract.
Five additional working days will be granted for this work.
TOTAL COST PART I: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART I: FIVE (5) -WORKING DAYS
PART II: REMOVE AND DISPOSE IRRIGATION LINES, STEEL PIPE RISERS, AND SPRINKLERS—
EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, remove
and dispose approximately 6,025 linear feet of irrigation lines (3 to 8-inch in diameter), and
approximately 230 steel pipe risers (3/4-inch diameter) with sprinkler heads. Perform all work according
to Section 15, "Existing Facilities," of the Standard Specifications, as directed by the Resident Engineer.
Compensation for this work will be made at an agreed lumpsum price of$2,200 according to Section 9-
1.03, "Payment Scope," of the Special Provisions. This agreed price includes compensation of all
materials, labor, equipment, traffic control, overhead costs, markups, profits, and incidentals for
performing the work. This amount will be paid through Bid Item No. 1, Supplemental Work, with no net
increase to the contract.
Five additional working days will be granted for this work.
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices Shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SOUTHEAST REGIONAL DISPOSAL SITE CHANGE ORDER NO. 1
PERIMETER FENCE REPLACEMENT JULY 9, 2024
CONTRACT NO.: 23-09-SW PAGE 2 OF 3
TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART II: FIVE (5) -WORKING DAYS
PART III: INCREASE/ DECREASE/ ELIMINATE ITEMS AT UNIT PRICES
This payment adjustment was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount °1 N %
1 Supplemental Work $ 51,385.00 $1.00 $51,385.00 (79.05) (79.05)
TOTAL DECREASE: $51,385.00
TOTAL COST PART III: A $61,385.00 DECREASE
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
_Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SOUTHEAST REGIONAL DISPOSAL SITE CHANGE ORDER NO. 1
PERIMETER FENCE REPLACEMENT JULY 9, 2024
CONTRACT NO.: 23-09-SW PAGE 3 OF 3
NET COST THIS CHANGE ORDER: A $51,385.00 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 10 -WORKING DAYS
OPT-5
Oleg Savelyev, Resident Engineer
APPROVAL RECOMMENDED:
AJ EXCAVATION, INC.
Contractor Mandeep S. Sekhon, PE
By Al(fir/' _w Construction Engineer
APPROVED BY:
Digitally signed by Steve
President SWh
teve Whites Datee2024.07.17104113
Title _0700
Steven E. White, Director
Accepted Date.
J U[ 10 2024 Public Works and Planning
Date:
_Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.