Loading...
HomeMy WebLinkAbout2214C CCO 27.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO.27 AMERICAN AVENUE TO MISSION STREET JUNE 21, 2024 CONTRACT NO. 22-14-C PAGE 1 OF 2 TO: YARBS GRADING AND PAVING, INC.: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract timeline. PART 1: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES This change was proposed by the engineer. Quantities in the Bid Book are estimates only. This part adjusts items to the actual quantities used. Increased Items: Item Total TOTAL No. Description Unit Quantity Price Amount (0/0) (0/6) 18 Adjust Valve Box Frame and EA 4.00 $800.00 $3,200.00 7.55 (20.83) Cover to Grade 28 Slurry Seal TON 19.25 1,230.00 23,677.50 32.08 32.08 TOTAL INCREASES: $26,877.50 This change did not impact the critical path for the project,therefore, granting additional contract time was not warranted. TOTAL COST PART 1: $26,877.50 INCREASE TOTAL TIME EXTENSION PART 1: ZERO (0) -WORKING DAYS PART 11: ADJUST COMPENSATION FOR THE SURPLUS TREES/PLANTS DUE TO THE LANDSCAPE REVISIONS IN THE SELMA REGION This compensation adjustment was requested by the contractor. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, adjust compensation for the additional trees/plants which were not planted due to the landscape revisions in the Selma region. The surplus trees/plants were delivered to the City of Selma maintenance yard. This compensation adjustment will be made at an agreed lumpsum price of$3,060.59(a cost breakdown with standard mark-up was provided) according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in a $3,060.59 increase,this amount will be paid as extra work. —Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,If —Auditor Controller this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be —Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors Const,Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 27 AMERICAN AVENUE TO MISSION STREET JUNE 21, 2024 CONTRACT NO. 22-14-C PAGE 2 OF 2 This extra work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART II: $3,060.59 INCREASE TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS NET COST THIS CHANGE ORDER: A$29,938.09 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS A=ZZ4 � LARue Goossen(Jun 24,2024 07:51 PDT) LaRue Goossen, Resident Engineer APPROVAL RECOMMENDED: i YARBS GRADING AND PAVING INC. hlL� Contractor Mandeep S. Sekhon, PE TnV Yaybn h Construction Engineer By Troy Yar rough(Ju19,20241 AG PDT) APPROVED BY: Digitally signed by Steve President SWhitt} }eve WhlteDatee2024.07.10 Title 10:04:17-07'00' Steven E. White, Director Accepted Date: U[ 8, 2024 Public Works and Planning Date: Nathan Magsig, Chairman Board of Supervisors Date: _Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office_Board of Supervisors noted above,and perform all services necessary for the work above specified,and will accept as full payment _Const.Management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.