HomeMy WebLinkAbout2307M CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ROAD MAINTENANCE AND REHABILITATION CHANGE ORDER NO. 1
ACCOUNT (SB-1) ASPHALT CONCRETE OVERLAYS JUNE 3, 2024
VARIOUS LOCATIONS IN FRESNO COUNTY PAGE 1 OF 2
CONTRACT NO. 23-07-M
TO: YARBS GRADING AND PAVING, INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
PLACE GEOSYNTHETIC PAVEMENT INTERLAYER (PAVING MAT) ON LOCATION NO. 13A, WOODY
LANE (CSA-35AK)—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, place
Geosynthetic Pavement Interlayer (paving mat) on Location No. 13A, Wood Lane (CSA-35AK). Use
approved materials (paving mat and asphalt binder) per the approved Submittal No. 23 for this project.
Perform all work according to the Section 39-2.01 C(3)(g), "Geosynthetic Pavement Interlayer," of the
Special Provisions. The estimated quantity for the paving mat is 2,500 square yards and 3.50 tons for
the asphalt binder. Compensation for this work will be made at an agreed unit price of$3.92 per square
yard for the paving mat and $1.00 per ton for the asphalt binder, per Section 9-1.03, "Payment Scope,"
of the Special Provisions. Total estimated cost for this work is (2,500 square yards x $3.92 per square
yard + 3.50 tons x $1.00 per ton) $ $9,803.50. Actual cost will be determined in the field upon
completion of this work, and if necessary, adjustments will be made in a subsequent change order. This
agreed unit price includes compensation of all materials, labor, equipment, traffic control, overhead
costs, markups, profits, and incidentals for performing the work. The actual payable amount will be paid
as extra work.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
_Contractor We, the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
ROAD MAINTENANCE AND REHABILITATION CHANGE ORDER NO. 1
ACCOUNT (SB-1)ASPHALT CONCRETE OVERLAYS JUNE 3, 2024
VARIOUS LOCATIONS IN FRESNO COUNTY PAGE 2 OF 2
CONTRACT NO. 23-07-M
NET COST THIS CHANGE ORDER: A $9,803.60 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING & PAVING INC. 04�-�^
Contractor Mandeep S. Sekhon, PE
Construction Engineer
w0v w-bi-owh
By Troy Yar rough(Jun 6,2024)74:48 PDT) APPROVED BY:
/� } Digitally signed by Steve
WhitSteve V V h I Le Datee2024.06.10
Title President 17:05:19-07'00'
Steven E. White, Director
Public Works and Planning
Accepted Date: J U n 6, 2024
Date:
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
_Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.