Loading...
HomeMy WebLinkAbout2307M CCO 02 correction.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ROAD MAINTENANCE AND REHABILITATION CHANGE ORDER NO.,e Z ACCOUNT (SB-1)ASPHALT CONCRETE OVERLAYS JUNE 11, 2024 VARIOUS LOCATIONS IN FRESNO COUNTY PAGE 1 OF 2 CONTRACT NO. 23-07-M TO: YARBS GRADING AND PAVING, INC: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time. PART I: ADJUST STORM DRAIN MANHOLES TO GRADE—EXTRA WORK This change was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, lower 10 storm drain manholes prior to pavement cold planing operations, and then adjust to grade after paving operations at location No. 6,Ashlan Avenue. The adjustment rings for the manholes will be provided by the Fresno Metropolitan Flood Control District(FMFCD). Perform all work per the FMFCD Standards and Section 71-5, "Adjust Drainage Structures," of the Standard Specifications and Special Provisions. Payment for this work will be made as extra work at Force Account according to Section 9-1.03, "Payment Scope,"of the Special Provisions. Total compensation for this work resulted in $13,789.77. This work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART I: A $13,789.77 INCREASE TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS PART II: ADJUST WATER VALVE COVERS TO GRADE—EXTRA WORK This change was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, lower 30 water valve covers prior to pavement cold planing operations, and then adjust to grade after paving operations at location No. 6, Ashlan Avenue. Perform all work per the City of Clovis Standards and Section 71-5, "Adjust Drainage Structures," of the Standard Specifications and Special Provisions. Payment for this work will be made as extra work at Force Account according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in $40,790.87. This work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART li: A $40,790.87 INCREASE TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is _Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above, _Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the _Board of Supervisors _Const.Management prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER ROAD MAINTENANCE AND REHABILITATION CHANGE ORDER NO.X 2, ACCOUNT(SB-1)ASPHALT CONCRETE OVERLAYS JUNE 11, 2024 VARIOUS LOCATIONS IN FRESNO COUNTY PAGE 2 OF 2 CONTRACT NO. 23-07-M NET COST THIS CHANGE ORDER: A$54,580.64 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS A'4"--//ez�ae w Robert Hendrickson, Resident Engineer APPROVAL RECOMMENDED: � �( ,r YARBS GRADING & PAVING, INC. PI" - O 5. Contractor Mandeep S. Sekhon, PE Construction Engineer TI-n YaYbhowh By TroyYar rough(Jun12,2024 2:06PDT) APPROVED BY: Digitally signed by Steve President SWhilt}eve WhlteDatee2024.06.13 Title 1019:56-07'00' Steven E. White, Director Accepted Date: Jun 12 2024 Public Works and Planning , Date: Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above, _Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the _Board of Supervisors _Const.Management prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.