Loading...
HomeMy WebLinkAbout2214C CCO 26.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 26 AMERICAN AVENUE TO MISSION STREET JUNE 6, 2024 CONTRACT NO. 22-14-C PAGE 1 OF 4 TO: YARBS GRADING AND PAVING, INC.: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0)-WORKING DAYS will be added to the contract timeline. PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES This change was proposed by the engineer. Quantities in the Bid Book are estimates only. This part adjusts items to the actual quantities used. Increased Items: Item Total TOTAL No. Description Unit Quantity Price Amount (0/0) o\/0) 25 Aggregate Base (Class II) (F) CY 13.00 $44.00 $572.00 0.10 5.17 32 Tack Coat TON 7.40 600.00 4,440.00 5.44 10.31 88 8" Yellow Thermoplastic Traffic LF 214.00 3.50 749.00 24.04 (75.96) Striping (Chevron Striping) 92 2 -Coat Paint Pavement Marking SF 647.00 4.00 2,588.00 101.09 101.09 158 City of Fresno Bollard EA 3.00 1,500.00 4,500.00 20.00 20.00 TOTAL INCREASES: $12,849.00 Decreased Items: Item Total TOTAL No. Description Unit Quantity Price Amount o� (°� 18 Adjust Valve Box Frame and EA 19.00 $800.00 $15,200.00 (26.39) (26.39) Cover to Grade 21 Remove Tree EA 22.00 500.00 11,000.00 (5.98) 297.70 26 Ful Depth Reclamation - SF 18,133.00 0.90 16,319.70 (6.74) (6.74) Cement (FDR-C) 29 Hot Mix Asphalt (Type A) TON 2,000.00 103.00 206,000.00 (1.79) 83.17 33 Place Hot Mix Asphalt Dike LF 255.00 9.00 2,295.00 (22.10) 45.00 (Type A) 36 Place Hot Mix Asphalt Dike LF 4.00 9.00 36.00 (2.11) (2.11) (Type F) 37 Remove HMA Dike LF 81.00 3.00 243.00 (13.06) (13.06) 39 Cold In-Place Recycling SY 5,094.93 11.00 56,044.23 (2.06) (2.54) _Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.Management therefore the prices shown above. _RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 26 AMERICAN AVENUE TO MISSION STREET JUNE 6, 2024 CONTRACT NO. 22-14-C PAGE 2 OF 4 45 12" Reinforced Concrete Pipe LF 11.00 470.00 5,170.00 (18.64) (18.64) 46 18" Reinforced Concrete Pipe LF 54.00 115.00 6,210.00 (9.18) (16.56) 47 24" Reinforced Concrete Pipe LF 20.00 136.00 2,720.00 (5.49) (20.00) 56 Adjust Manhole to Grade EA 17.00 1,300.00 22,100.00 (19.77) (19.77) 57 Rock Slope Protection (Class 11, CY 0.33 1,300.00 429.00 (4.71) (4.71) Method B) 58 Rock Slope Protection Fabric SY 1.33 20.00 26.60 (6.65) (6.65) (Class 8) 102 Street Lighting - Foundations - EA 2.0 1500.00 3,000.00 (4.44) (4.44) Ornamental Poles 114 Street Lighting - Poles- EA 2.0 10,000.00 20,000.00 (4.44) (4.44) Decorative Pole 116 Street Lighting - Signal EA 4.0 2,000.00 8,000.00 (4.44) (4.44) Hardware- Decorative Luminaires 128 Packet Fertilizer EA 5,769.00 1.00 5,769.00 (56.96) (71.18) 129 Plant (Group A) EA 73.00 17.00 1,241.00 (5.00) (44.85) 130 Plant (Group B) EA 21.00 32.00 672.00 (4.50) (41.93) 131 Plant (Group U) EA 36.00 120.00 4,320.00 (9.35) (19.77) 134 Root Barrier LF 77.00 9.00 693.00 (1.84) (2.77) 136 1" Remote Control Valve EA 1.00 600.00 600.00 (3.57) 50.00 137 2" Remote Control Valve EA 1.00 700.00 700.00 (20.00) 0.00 145 Tree Well Sprinkler Assembly EA 122.00 50.00 6,100.00 (14.66) (23.82) TOTAL DECREASES: $394,888.53 TOTAL COST PART I: A $382,039.53 DECREASE TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS PART II: ADJUST STORM DRAIN CLEANOUT ACCESS TO GRADE IN THE CENTER MEDIAN AT STA 356+20, SELMA REGION -EXTRA WORK This extra work was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, furnish and install a 30-inch by 48-inch Christy Box with a removable lid to adjust the storm drain cleanout access to grade in the center median at Sta. 356+20, in the Selma region. This work consists of chipping the existing access to fit the new box, grouting, backing filling, compacting and grading around the new Christy Box. Perform all work in accordance with Section 71, "Existing Drainage Facilities," of the Standard Specifications and/or the Project Specifications. Compensation for this work will be made Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 26 AMERICAN AVENUE TO MISSION STREET JUNE 6, 2024 CONTRACT NO. 22-14-C PAGE 3 OF 4 at an agreed lumpsum price of$5,009.92 according to Section 9-1.03, "Payment Scope," of the Special Provisions. This amount includes compensation for all labor, equipment, materials, traffic controls, incidental, markups and profit for the above referenced work, no additional compensation will be made. This amount will be paid as extra work. This extra work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART II: A $6,009.92 INCREASE TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS PART III: INSTALL "BORE GUARD" CONDUIT IN LIEU OF THE TYPICAL PVC CONDUIT AND INSTALL UPGRADED N9 PULL BOXES IN LIEU OF THE STANDARD PULL BOXES FOR THE STREETLIGHTS THROUGHOUT SELMA REGION PER PG&E REQUIREMENTS— EXTRA WORK This change was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install approximately 3,200 linear feet of 2-inch "Bore Guard" conduit in lieu of the typical PVC conduit, and install at total of 38 N9 pull boxes in lieu of the standard N30 pull boxes for the streetlights throughout Selma region per the PG&E requirements. Perform all work in accordance with the applicable sections of the Standard Specifications and Project Specifications. Compensation for this work will be made at an agreed lumpsum price of$65,000.00 according to Section 9-1.03, "Payment Scope," of the Special Provisions. This amount includes compensation for all labor, equipment, materials, traffic controls, incidentals, markups, and profit for the above referenced change, no additional compensation will be made. This amount will be paid as extra work. This extra work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL COST PART III: A $65,000 INCREASE TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER GOLDEN STATE BOULEVARD PHASE I CHANGE ORDER NO. 26 AMERICAN AVENUE T 0 MISSION STREET JUNE 6, 2024 CONTRACT NO. 22-14-C PAGE 4 OF 4 NET COST THIS CHANGE ORDER: A $312,029.61 DECREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS at__� LARue Goossen(Jun 6,2024 14:50 PDT) LaRue Goossen, Resident Engineer APPROVAL RECOMMENDED: YARBS GRADING AND PAVING, INC. Contractor Mandeep S. Sekhon, PE Construction Engineer TDt1 Y-bi-ow—h By TroyYar rough(Jun7,2024)76:09PDT) APPROVED BY: Digitally signed by Steve President St}eve WhlteDatlee2024.06.13 Title 14:24:06-07'00' Steven E. White, Director Accepted Date: Jun 7 2024 Public Works and Planning , Date: Contractor We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if _Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be —Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors_Const.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.