HomeMy WebLinkAbout2324SW CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 1
PHASE III - MODULES 9 & 10 JUNE 7, 2024
EXCAVATION AND LINER CONSTRUCTION PAGE 1 OF 2
18950 W AMERICAN AVENUE, KERMAN, CA 93630
CONTRACT NO. 23-24-SW
TO: YARBS GRADING AND PAVING, INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
REPLACE A DAMAGED PULL BOX—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace
an existing damaged electrical pull box near the southwest corner of Module 10, with a Christy (13-1/4" x
24", Caltrans No. 5 (T)) pull box with a 12-inch extension and a traffic rated lid. Perform all work in
accordance with Section 86-1.02C, "Pull Boxes," and Section 87-1.03C, "Installation of Pull Boxes," of
the Special Provisions. Compensation for this work will be made at an agreed lumpsum price of
$6,198.61 according to Section 9-1.03, "Payment Scope," of the Special Provisions. This agreed price
includes compensation of all materials, labor, equipment, traffic control, overhead costs, markups,
profits, and incidentals for performing the work. This amount will be paid through Bid Item No. 1,
Supplemental Work Allowance, with no net increase to the contract.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 1
PHASE III - MODULES 9 & 10 JUNE 7, 2024
EXCAVATION AND LINER CONSTRUCTION PAGE 2 OF 2
18950 W AMERICAN AVENUE, KERMAN, CA 93630
CONTRACT NO. 23-24-SW
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NO. 1)
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
Oleg Savelyev, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING & PAVING, INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
T1o� YybroKh
By Troy Yaar rough(Jun7,2024 :23PDT) APPROVED BY:
Digitally signed by Steve
Whit
President Steve WhlteD tee2024.06.10
Title 17:08:00-07'00'
Steven E. White, Director
Accepted Date:
J u n 7 2024 Public Works and Planning
,
Date:
_Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment, furnish all materials, except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices Shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.