Loading...
HomeMy WebLinkAboutD-21-278 2015C CCO 08 - Revised.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 08 3 MILES EAST OF COLORADO AVENUE NOVEMBER 3, 2022 FEDERAL AID NUMBER: BRLS-5942(233) PAGE 1 OF 4 CONTRACT NO. 20-15-C TO: VIKING CONSTRUCTION COMPANY, INC.: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ONE (1) -WORKING DAY will be added to the road closure contract timeline only. PART I: ADJUST REINFORCING STEEL CLEARANCES DUE TO BEARING SEAT ELEVATION REVISIONS AND REVISE BACK WALL REINFORCING STEEL TO CLEAR EXISTING STRUCTURE—EXTRA WORK This compensation adjustment was requested by the contractor. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, adjust the bearing seat rebar to clear the revised bearing seat elevations and supply revised back wall reinforcing steel to clear the existing structure as extra work. Perform all work according to the applicable sections of the project Special Provisions and/or Standard Specifications. Payment for this work will be made as extra work at Force Account according to Section 9-1.03, "Payment Scope," of the Special Provisions; total compensation for this work resulted in $2,599.30. A total of one working day time extension will be granted to the road closure timeline only (no impact to the overall critical path of the project) for performing this extra work in accordance with Section 8-1.07B, "Time Adjustment," of the project Special Provisions. TOTAL COST PART I: A $2,599.30 INCREASE TOTAL TIME EXTENSION PART I: ONE (1) -WORKING DAY(ROAD CLOSURE ONLY) PART If: ADJUST CONTRACT CHANGE ORDER NO. 5 This change was proposed by the engineer. Contract Change Order No. 5 was written with an estimated hot mix asphalt(HMA) quantity of 215 tons at agreed unit price of$220, for replacing the existing damaged asphalt concrete surfacing as extra work. However, this work required additional 25 tons of HMA, total HMA quantity of 240 tons. Compensation of the additional 25 tons of HMA quantity is being made at previously agreed unit price of$220 (in Contract Change Order No. 5), in accordance with Section 9-1.03, "Payment Scope," of the Special Provisions; resulting in an increase of$5,500. This change did not further impact the critical path of the project(two working days were previously granted in Contract Change Order No.5), so granting of additional time was not warranted. Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of supervisors _Const.management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 08 3 MILES EAST OF COLORADO AVENUE NOVEMBER 3, 2022 FEDERAL AID NUMBER: BRLS-5942(233) PAGE 2 OF 4 CONTRACT NO. 20-15-C TOTAL COST PART II: A $5,500 INCREASE TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS PART III: REMOVE SECTIONS OF THE 4-INCH HMA DIKE AND REPLACE WITH 2-INCH HMA DIKE— EXTRA WORK This change was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, remove approximately 25 lineal feet of the newly constructed 4-inch HMA dike in front of the terminal end treatment of the metal beam guard railing (at four locations, a total of approximately 100 lineal feet of dike) and replace with a 2-inch HMA dike as extra work. Perform all work according to the applicable sections of the project Special Provisions and/or Standard Specifications. Payment for this work will be made as extra work at an agreed lump sum price of$11,289.40, according to Section 9-1.03, "Payment Scope," of the Special Provisions. This price includes compensation of all labor, materials, equipment, overhead costs, markups, and incidentals for performing the work. This work did not impact the critical path for the project, so granting additional contract time was not warranted. TOTAL COST PART III: A $11,289.40 INCREASE TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS PART IV: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT PRICES These changes were proposed by the engineer. Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item quantities to the actual quantities used. Increased Items: Item Total No. Description Unit Quantity Price Amount 1 Supplemental Work(Payment $ 7,942.29 $1.00 $7,942.29 79.42 Adjustment for Price Index Fluctuations) 25 Temporary Sign EA 16.00 300.00 4,800.00 30.77 26 Temporary Railing (Type K) LF 10.00 25.00 250.00 00.95 27 Temporary Barricade (Type III) EA 18.00 150.00 2,700.00 180.00 32 Embankment CY 7.90 100.00 790.00 1.98 35 Cold Plane HMA SY 94.00 15.00 1,410.00 10.33 Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.Management therefore the prices Shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 08 3 MILES EAST OF COLORADO AVENUE NOVEMBER 3, 2022 FEDERAL AID NUMBER: BRLS-5942(233) PAGE 3 OF 4 CONTRACT NO. 20-15-C 36 Hot Mix Asphalt(Type A) TON 172.47 100.00 17,247.00 9.13 39 Place HMA Dike (Type F) LF 18.00 5.00 90.00 2.99 61 Joint Seal (Type A) LF 4.25 150.00 637.50 425.-091 6.44 TOTAL INCREASE: $ 35, 54.29, $35,866.79 Decreased Items: Item Total No. Description Unit Quanti Price Amount 12 Temporary Construction Entrance EA 2.00 $5,000.00 $10,000.00 50.00 19 Monitoring Bird Exclusion Devices EA 10.00 500.00 5,000.00 41.67 Week 24 Temporary Traffic Stripe (Tape) LF 21.00 2.00 42.00 0.41 28 Temporary Crash Cushion Module EA 18.00 350.00 6,300.00 32.14 29 Remove Metal Beam Guard Railing LF 1.00 25.00 25.00 0.39 34 Remove Asphalt Concrete Dike LF 70.00 2.00 140.00 2.94 37 Tack Coat TON 0.64 600.00 384.00 32.00 38 Place HMA Dike (Type A) LF 75.00 6.00 450.00 4.24 40 Flume Downdrain (With RSP) LF 5.50 145.00 797.50 3.77 49 4" Paint Traffic Stripe (2-Coat) LF 200.00 1.00 200.00 5.48 Yellow(Detail 27B) 50 4" Paint Traffic Stripe (2-Coat) White LF 45.00 1.00 45.00 2.54 (Detail 6) 52 Place Polyester Concrete Overlay SF 171.12 5.00 855.60 1.75 56 48" Cast-In-Drilled-Hole Piling LF 3.00 1,025.00 3,075.00 0.49 60 Joint Seal (MR=2") LF 19.00 175.00 3,325.00 5.62 TOTAL DECREASE: $30,639.10 Eliminated Items: Item Total No. Description Unit Quantity Unit Price Amount (0/0) 5 Water Quality Sampling and Analysis EA 20.00 $1,000.00 $20,000.00 100.00 Day 33 Rock Slope Protection (Class 2, CY 30.00 500.00 15,000.00 100.00 Method B) (Miscellaneous Areas) 44 Object Marker(Type P) EA 8.00 100.00 800.00 100.00 Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 08 3 MILES EAST OF COLORADO AVENUE NOVEMBER 3, 2022 FEDERAL AID NUMBER: BRLS-5942(233) PAGE 4 OF 4 CONTRACT NO. 20-15-C Since you did not incur any costs associated with these items, no payment will be made for these bid items. This work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. TOTAL DECREASE: $35,800.00 TOTAL COST PART IV: A $30,784.81 DECRE S $30,572.31 Decrease TOTAL TIME EXTENSION PART IV: ZERO (0) -WORKING DAYS NET COST THIS CHANGE ORDER: A $11,396.11 DEGREAS $11,183.61 Decrease NET TIME EXTENSION THIS CHANGE ORDER: ONE (1) -WORKING DAY(ROAD CLOSURE ONLY) Bch d Richard Stockwell(Nov 4,2022 07:47 PDT) Richard Stockwell, Resident Engineer APPROVAL RECOMMENDED: VIKING CONSTRUCTION COMPANY, INC_ Contractor Mandeep S. Sekhon, PE Construction Engineer 7��r/v CCey� By Troy Ciemons(Nov 4,2.02214:31PDT) APPROVED BY: Digitally signed by Steve White Vice President Steve White Date:2022.11.1608:39:29 Title -08'00' Steven E. White, Director Nov q 2022 Public Works and Planning Accepted Date: , Date: Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be _Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.management therefore the prices shown above. RE/Arch- -Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.