HomeMy WebLinkAboutECC - CCO 010 -Signed.pdf F Co County of Fresno
Department of Public Works and Planning
O� 50 Development Services&Capital Projects Division
FRE`' Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Environmental Compliance Center
Contract No.: 20-S-01
Date: 12/26/2023
Contractor: BMY Construction Group, Inc.
Architect: Roger Davidson
Change Order No.: CCO#10
Construction Contract Dollar Amount as awarded on 7/13/2021 $2,660,000.00
Director's Change Order Limit: $145,500.00
Contract Time(Calendar Days): 200
Construction Start Date: 09/13/21
Original Construction Completion Date: 3/31/22
Change Order Scope of Work:
PCO#28.1-Credit for Lift Gates
PC0#31.1-Time and Material Street Light to Tesco
Attachment(s):
CO Summary,CO Proposal,PCO estimate
Net Additive Change Order Dollar Amount: $26,046.12
Net Additive Calendar Days: 0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: 0
Total Change Order Dollar Amount To Date $157,977.26
Adjusted Contract Dollar Amount: $2,817,977.26
Total Adjusted Calendar Days To Date: 139
Director's Change Order Limit Balance: `ECC Phase 11 budgeted ($12,477.26)
Adjusted Construction Completion Date: 1 08/17/22
Reviewed: Roger Davidson 7-oww- 2023.12.26 08:42:26-08'00'
Supervising Architect
Reviewed: Keith Eckert Keith Eckert 12/27/23
Sr.Engineering Technician-Project Manager
Reviewed: Mandeep S. Sekhon
Mandee S.Sekhon Digitallysigned by Mandeep S.Sekhon
P Dale:2023,12.2713:45:28-08'00'
Construction Division Engineer-Construction Manager
William M.Kettler Digitallysigned by William M.Kettler
Reviewed: Will M.Kettler Data 2023 12 29 10:24'46-08'00'
Deputy Director of Planning
Reviewed: Bernard Jimenez Bernard Jimenez Digitallysigned by Bernard Jimenez
Date:2024.01.02 08:50:41-08'00'
Planning&Resource Management Officer
Reviewed: Steven E. White Steve White Dgitallysigned by Steve WMte
Data 2024 01.0210 21:16-08'00'
Director,Department of Public Works&Planning
Approved: Sal Quintero Not Applicable
Board of Supervisors Chairman
Acknowledged: Kay Vang Kaying Vang Dare 2—D1.12y1323.02 'DO'
Principal Accountant
Scan and forward Director Approved Copy to: CAD Paul Nerland
Resources Craig Nickel
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
c°al County of Fresno
r Department of Public Works and Planning
Development Services&Capital Projects Division
Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: Environmental Compliance Center
Contract No.: 20S-01
Date: 12/13/2023
Contractor: BMY Construction Group,Inc.
5485 E.Olive Ave.
Fresno,California 93727
(559)243-4200
Change Order No.: CCO#10
Construction Contract Dollar Amount as awarded on 7/13/2021 $2,660,000.00
Original Construction Completion Date: 03131/22
CCO#10 is hereby approved by the County.
Scope of Work:
PCO#28.1-Credit for Lift Gates
PCO#31.1-Time and Material Street Light to Tesco
Attachment:
CO Summary,CO Proposal,PCO estimate
Net Additive Change Order Dollar Amount: $26,046.12
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days:
Total Change Order Dollar Amount To Date: $167,977.26
Adjusted Contract Dollar Amount: $2,817,977.26
Total Adjusted Calendar Days To Date: 139
Adjusted Construction Completion Date: 08/17/22
Keith Eckert Keith Eckert
Project Manager
Date: 12/13/20
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order Provisions under the Agreement 20-S-01
Article VI shall apply.
Accepted By: BMY Construction Group,Inc.
Authoriz d Signa
2i5
Date:
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
jinda ueir,,?iie nucuunt�ca.:fov-
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Environmental Compliance Center
D. 1VW Days Description
Change Orders
1 11/9/2021 $0.00 -$14,820.00 0 Includes PCO#1
2 1/6/2022 $36,635.08 $0.00 0 Includes PCO#3,4.1
3 3/21/2022 $22,784.56 $0.00 4 Includes PCO#2
4 5/2/2022 $2,811.62 -$30,720.00 27 Includes PCO#5.1,6.2,8,and 11
5 6/24/2022 $5,131.09 $0.00 7 Includes PCO#10.1, 13
6 10/6/2022 $32,383.14 $0.00 91 Includes PCO#9, 14.1, 16, 17, 18
7 12/19/2022 $16,740.88 $0.00 10 Includes PCO#12.1,21,22,23,24,26
8 3/28/2023 $1,873.38 $0.00 0 Includes PCO#25
9 8/8/2023 $59,111.39 $0.00 0 Includes PCO#29,30
10 12/13/2023 $33,440.09 -$7,393.97 0 Includes PCO#28.1,31.1
Totals $210,911.23 1 -$52,933.97 139
Proposed
• • A.. Credit Rejected Pending � .
Change Orders
1 1 -$14,820.00 0 Omit 8'sidewalk on the north side of site
2 3 $22,784.56 4 Add fire system at PH1 -Shade Structure
3 2 $830.28 0 Storefront finish alteration
4 $37,711.89 0 Revised Fire Line per C4.0
4.1 2 $35,804.80 0 Revised Fire Line per C4.0-Alterations to site utility plan
5 $0.00 3.5 Rain Delays
5.1 4 $0.00 4 Rain Delays
6 -$28,000.00 0 Tire bark credit
6.1 Not used
6.2 4 -$30,720.00 0 Tire bark and labor credit
7 Not used
8 4 $0.00 23 Time extension for Metal Building Supply issues
9 6 $2,618.36 0 Flooring change PH2-ASI#3
9.1 $2,618.36 0 Flooring change PH2-ASI#3
10 $14,141.00 7 Refabricate Risers at Building 1 &2
10.1 5 $3,596.93 7 Refabricate Risers at Building 1 &2
11 4 $2,811.62 0 Frame Parapet PH2&Pony Walls PH3
12 $13,490.00 10 Time extension for Submittal#34
12.1 7 $0.00 10 Time extensions-Submittal#34-PH1 Shade structure
13 5 $1,534.16 0 Rebar add,credit move strip&PH1 footing sizes
14 $4,819.08 0 Emergency eyewash station cost increase
14.1 6 $2,158.00 0 Emergency eyewash station cost increase
15 Not used
16 6 $0.00 91 Time extension-MSB delays
17 6 $20,645.00 0 T&M for retaining wall at transformer pad
18 6 $6,961.78 0 Tie into existing Fire line
19 $63,029.00 0 HHS&purlin changes at shade structure
20 $51,103.42 0 Street light plan changes from bid to approved set
21 7 $5,478.48 0 Removal of dirt at Transformer Pad
22 7 $3,165.07 0 Electrical for PIV location change
23 7 $1,316.44 0 Lower DI due to drawing conflict
24 7 $2,467.60 0 Relocate 3"drain line due to footing conflict
25 8 $1,873.38 0 Drywall repairs for moving plug in restrooms
26 7 $4,313.29 0 Paint perimeter C-Channel PH1
27 Not used
28 -$750.00 0 Credit for Lift Gates
29 9 $7,348.10 1 0 ADA Concrete Walks
30 9 $51,763.29 0 T&M Tesco Panel feed
31 $38,988.69 0 Not used
M Street Light to Tesco
32 Not used
33 Not used
34 Not used
Totals $210,911.23 1 -$52,933.97 1 $197,151.44 $0.00
= PCO #028
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #028: CE #046 - Credit Lift Gates
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 028/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 1/4/2023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO
WILL EXPIRE AFTER:
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: ($7,393.97)
POTENTIAL CHANGE ORDER TITLE: CE#046-Credit Lift Gates
CHANGE REASON:Client Request
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#046-Credit Lift Gates
Credit for lift gates that were not installed at PH-1 Shade Structure
ATTACHMENTS:
# Budget Code Description Amount
1 32-3113.PO Fences and Gates/VALLEY Credit lift Gates $(5,000.00)
FENCE.Purchase Order
2 26-0500.PO Electrical/WESTECH.Purchase Order Credit for electric gates $(2,393.97)
Subtotal: $(7,393.97)
Project Manager(0.00%Applies to all line item types.): $0.00
General Liability(0.00%Applies to all line item types.): $0.00
Superintendent(0.00%Applies to all line item types.): $0.00
Project Engineer(0.00%Applies to all line item types.): $0.00
Overhead and Profit(0.00%Applies to all line item types.): $0.00
Health Insurance(0.00%Applies to all line item types.): $0.00
Bond(0.00%Applies to all line item types.): $0.00
Grand Total: $(7,393.97)
BMY Construction Group Incorporated Page 1 of 2 Printed On: 10/26/2023 09:14 AM
PCO #028
CONSTRUCTION
GROUPINCORPORATED
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On: 10/26/2023 09:14 AM
I =1 17A P3 PCO #031
CONSTRUCTION
GROUPINCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #031 : CE #049 - T&M Street Light to
Tesco
TO: The County of Fresno,Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBERIREVISION: 031/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 9/1/2023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
THE REFERENCED PCO
WILL EXPIRE AFTER:
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $33,440.09
POTENTIAL CHANGE ORDER TITLE:CE#049-T&M Street Light to Tesco
CHANGE REASON:Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#049-T&M Street Light to Tesco
County directed to proceed on T&M with all streetlight work. Site plan originally had 8'sidewalk,due to the elimination of this,galvanized ridged conduit
was required with slurry.Credit PVC from streetlight to tesco panel.
ATTACHMENTS:
CO-09.pdf, _CO-03R6.pdf
# I Budget Code Description Amount
1 26-0500.PO Electrical/WESTECH.Purchase Order Changed to GRC from SL to Tesco,added slurry $29,949.16
Subtotal: $29,949.16
Project Manager(2.90%Applies to all line item types.): $868.53
General Liability(0.10%Applies to all line item types.): $29.95
Superintendent(2.00%Applies to all line item types.): $598.98
Project Engineer(1.50%Applies to all line item types.): $449.24
Overhead and Profit(3.50%Applies to all line item types.): $1,048.22
Health Insurance(0.75%Applies to all line item types.): $247.08
Bond(0.75%Applies to all line item types.): $248.93
Grand Total: $33,440.09
BMY Construction Group Incorporated Page 1 of 2 Printed On: 11/6/2023 01:00 PM
I =1 01A la PCO ##031
CONSTRUCTION
GROUPINCORPORATED
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On: 111612023 01:00 PM
s
/ ELECTRICAL CONTRACTORS
CONT.ZIC.NO 1072735 C-10
11/2/2023
Project: 21132 - Fresno County Envirnmental Compliance Center
Change Order: 03116 RFI/RFP:
Description:Change conduit from PVC to GRC and additional Concrete incasemenst saw cut and patch
due to elimination of sidewalk
Material Items Quantity Unit Cost Material Labor Units Labor
Material/Labor 1 $ 14,865.00 $ 14,865.00 11510.00 $ 11,510.00
$ - $ -
Credit Items Quantity Unit Cost Material (Labor Units Labor
1 1/2" PVC $ (260.00) $ 3.50 $ (910.00) 1.50 $ (390.00)
Totals $ 13,955.00 1 $ 11,120.00
Sub Contractor Material Labor P/O
BMY- Patch Back 0 $ _
Totals $ _
Equipment Cost Delivery Fuel
Totals $ _
Material $ 13,955.00
Labor $ 11,120.00 (Inside Wireman=00.00 hours at 95.00 per hour)
Subcontractor $ -
Equipment $ - Time Extention days:0
Sub Total $25,075.00
Overhead @ 10% $ 2,507.50
Profit @ 5% $ 1,253.75 �°Ota I Cost:Tax @ 7.975% $ 1,112.91 1 $ 29,949.16
Notes:See attached material breakouts,T&M Sheets and Certified Payroll
Exclusion: NO PG&E R16 NO WORK FROM TESCO TO POC
827 Jefferson Ave Clovis Ca 93612
Lic#1072735 - Ph#559-455-1720
WESTECH SYSTEMS, LLC
ELECTRICAL CONTRACTORS CONT. LIC. NO. 1072735
827 JEFFERSON AVE. L O#03it5
CLOVIS, CA. 93612 -
TEL.: (559)455-1720 `,PAGE 2 OF 2
FAX.: (559)455-0952
PROJECT: 21132 -FRESNO COUNTY ENVIRONMENTAL COMPLIANCE CENTER -CHANGE IN CONDUIT TYPE
MATERIALILABOR BREAKDOWN
SITE-CONDUIT CHANGES FOR STREET LIGHTS
260 1 1/2"GRC 18.50 4810 0 0
2 1 1/2"SWEEP GRC 25.00 50 0 0
375 CONCRETE 7.50 2813 0 0
75 SAWCUT 20.00 1500 0 0
1 TESCO PANEL 5692.50 5693 0 0
134 LABOR 0.00 0 84 11256
2 LABOR-OT 0.00 0 127 254
0.00 0 0 0
14865 11510
-260 1 1/2" PVC 3.50 -910 1.5 -390