HomeMy WebLinkAbout2015C CCO 10-Revised.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING CHANGE ORDER NO. 10— REVISED
AVENUE, 3 MILES EAST OF COLORADO AVENUE JANUARY 4, 2024
FEDERAL AID NUMBER: BRLS-5942(233) PAGE 1 OF 2
CONTRACT NO. 20-15-C
TO: VIKING CONSTRUCTION COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 18 -WORKING DAYS will be added to the Third Order of Work-
Permanent Erosion Control Establishment.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT PRICES
This change was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Decreased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/0 (0/6)
10 Permanent Erosion Control EA 1.00 $3,000.00 $3,000.00 (8.33) (8.33)
Establishment Inspection Day
TOTAL DECREASE: $3,000.00
Eliminated Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (0/0) (
21 Treated Wood Waste LB 4,775.00 $1.00 $4,775.00 (100.00) (100.00)
(Guardrail)
TOTAL DECREASE: $4,775.00
This change did not impact the critical path for the project, so granting additional contract time was not
warranted.
TOTAL COST PART I: A $7,775.00 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: GRANT A TIME EXTENSION
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING CHANGE ORDER NO. 10—REVISED
AVENUE, 3 MILES EAST OF COLORADO AVENUE JANUARY 4, 2024
FEDERAL AID NUMBER: BRLS-5942(233) PAGE 2 OF 2
CONTRACT NO. 20-15-C
This change was requested by the contractor.
Grant the contractor an 18-working days' time extension to the Third Order of Work— Permanent
Erosion Control Establishment, according to Section 8-1.07B, "Time Adjustments," of the Special
Provisions.
TOTAL COST PART II: $0.00 (NO COST)
TOTAL TIME EXTENSION PART II: 18 -WORKING DAYS
NET COST THIS CHANGE ORDER: A $7,775.00 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 18 -WORKING DAYS
� s.C', -
Richard Stockwell, Resident Engineer
APPROVAL RECOMMENDED:
VIKING CONSTRUCTION COMPANY, INC.
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By Troy Clem s(Jan 11,202410:53 PST) APPROVED BY:
Digitally signed by Steve
Wh
Vice President Steve White D tle:2024.01.1113:09:57
Title -08'00'
Steven E. White, Director
Accepted Date:
Jan 11 2024 Public Works and Planning
,
Date:
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.