HomeMy WebLinkAbout2107SW CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 2
PHASE I WASTE RELOCATION NOVEMBER 28, 2023
18950 W AMERICAN AVE, KERMAN, CA 93630 PAGE 1 OF 4
CONTRACT NO. 21-07-SW
TO: SUKUT CONSTRUCTION, LLC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 78 -WORKING DAYS will be added to the contract timeline.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT PRICES
This change was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount (ON °(�
6 Clearing and Grubbing ACRE 9.00 $155.00 $1,395.00 9.89 9.89
8 Hydroseeding ACRE 14.00 5,200.00 72,800.00 15.56 15.56
14 Intermediate Soil Cover SY 65,361.00 5.50 359,485.50 16.63 16.63
22 Earthfill Embankment CY 5,217.00 3.75 19,563.75 7.90 7.90
TOTAL INCREASES: $453,244.25
Decreased Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount
1 Supplemental Work $ 607,021.44 $1.00 $607,021.44 (24.28) (24.28)
10 Phase I Groundwater Monitoring LF 12.50 145.00 1,812.50 (0.89) (0.89)
Well Decommissioning
12 Phase I Waste Excavation, CY 6,385.17 7.30 46,611.74 (0.43) (0.43)
Hauling, and Placement
15 Stormwater Diversion Berm LF 442.00 6.60 2,917.20 (3.45) (3.45)
16 Straw Wattles LF 16,086.70 3.50 56,303.45 (10.08) (10.08)
17 Erosion Control Mat SF 20,945.00 1.65 34,559.25 (9.93) (9.93)
18 Permanent Erosion Control Mat SF 1,902.00 10.00 19,020.00 (4.23) (4.23)
19 8-oz Non-Woven Geotextile SF 17,898.00 0.35 6,264.30 (10.00) (10.00)
20 Rock Slope Protection, D50 = 6" SF 2,584.00 6.00 15,504.00 (10.00) (10.00)
21 Rock Slope Protection, D50 = 8" SF 79.00 12.50 987.50 (10.00) (10.00)
24 Hot Mix Asphalt (HMA) TON 6.95 175.00 1,216.25 (0.29) (0.29)
Placement
26 Midwest Guardrail System LF 23.00 105.00 2,415.00 (1.87) (1.87)
27 HMA Dike LF 10.00 10.50 105.00 (0.94) (0.94)
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business Office noted above, and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 2
PHASE I WASTE RELOCATION NOVEMBER 28, 2023
18950 W AMERICAN AVE, KERMAN, CA 93630 PAGE 2 OF 4
CONTRACT NO. 21-07-SW
28 18" Corrugated Dual Walled LF 6.00 100.00 600.00 (2.50) (2.50)
HDPE Culvert
TOTAL DECREASES: $795,337.63
Eliminated Items:
Item Total TOTAL
No. Description Unit Quantity Price Amount % �°/�
2 Supplemental Work(Payment $ 20,000.00 $1.00 $20,000.00 (100.00) (100.00)
Adjustment Price Index
Fluctuation)
13 Off-Site Disposal of Non- TON 500.00 300.00 150,000.00 (100.00) (100.00)
Conforming or Hazardous
Materials
TOTAL ELIMINATIONS: $170,000.00
These revisions did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
TOTAL COST PART I: $512,093.38 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: REPLACE DAMAGED STRAW WATTLES AND EROSION CONTROL MATS THROUGHOUT
THE PROJECT SITE—EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace
the damaged straw wattles and erosion control mats throughout the project site as directed by the
engineer. Perform all work according to the applicable sections of the Standard Specifications and
Special Provisions. Payment for this work will be made as an agreed Iumpsum price of$37,000,
according to Section 9-1.03, "Payment Scope," of the Special Provisions.
This extra work did not impact the critical path for the project, therefore, granting additional contract time was
not warranted.
TOTAL COST PART II: A $37,000 INCREASE
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 2
PHASE I WASTE RELOCATION NOVEMBER 28, 2023
18950 W AMERICAN AVE, KERMAN, CA 93630 PAGE 3 OF 4
CONTRACT NO. 21-07-SW
PART III: GRANT A TIME EXTENSION
This change was requested by the contractor.
Grant the contractor a 78-working days' time extension according to Section 8-1.07B, "Time Adjustments," of
the Special Provisions. This time extension includes 58-working days for the unsuitable working conditions due
to the rain/wet surface conditions, and 20-working days due to contract suspension.
Weather Day Extension Summary/Reference
Weather Day September 19-21, 2022 3 Working Days
Weather Day November 2, 2022 1 Working Day
Weather Day November 7-9, 2022 3 Working Days
Weather Day December 1-13, 2022 9 Working Days
Weather Day December 16, 2023 1 Working Day
Weather Day December 23-30, 2022 5 Working Days
Weather Day January 3-24, 2023 15 Working Days
Weather Day January 30-31, 2023 2 Working Day
Weather Day February 1, 2023 1 Working Day
Weather Day February 24-28, 2023 3 Working Day
Weather Day March 1-3, 2023 3 Working Day
Weather Day March 10-24, 2023 11 Working Day
Weather Day March 29, 2023 1 Working Day
Total Weather Days 58 Working Days
TOTAL COST PART III: $0.00 (NO COST)
TOTAL TIME EXTENSION PART III: 78 -WORKING DAYS
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE DISPOSAL SITE CHANGE ORDER NO. 2
PHASE I WASTE RELOCATION NOVEMBER 28, 2023
18950 W AMERICAN AVE, KERMAN, CA 93630 PAGE 4 OF 4
CONTRACT NO. 21-07-SW
NET COST THIS CHANGE ORDER: A $475,093.38 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 78 -WORKING DAYS
Oe'� 5�
Oleg Savelyev, Resident Engineer
APPROVAL RECOMMENDED:
SUKUT CONSTRUCTION, LLC 0,—
- U
Contractor MANDEEP S. SEKHON, PE
Construction Engineer
By: Thomas Wadden(Dec 4,2023 13:14 PST) APPROVED BY:
Digitally signed by Steve White
Project Manager Steve White Date:2023.12.08 08:08:51
Title: -08'00'
STEVEN E. WHITE, Director
Accepted Date:
Dec 4 2023 Public Works and Planning
,
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials, except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.