HomeMy WebLinkAbout2205C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
DRY CREEK BRIDGE REPLACEMENT ON CHANGE ORDER NO. 2
BURROUGH VALLEY ROAD, BURROUGH VALLEY ROAD, SEPTEMBER 1, 2023
JUST EAST OF TOLLHOUSE ROAD PAGE 1 OF 3
FEDERAL PROJECT NUMBER: BRLS-5942(245)
CONTRACT NO. 22-05-C
TO: AGEE CONSTRUCTION CORPORATION:
Make the following changes to the plans and specifications or do work not included in the plans and
specifications for this contract. Because of the change(s), 19 -WORKING DAYS will be added to the contract
time for the First Order of Work is December 22, 2023.
PART I: INCREASE /DECREASE / ELIMINATE ITEMS AT UNIT PRICES:
This change was requested by the contractor.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total Total
No. Description Unit Quantity Price Amount (0/0) °�
45 30" Cast-In-Drilled-Hole Concrete LF 5.00 $1,215.00 $6,075.00 15.63 15.63
Piling (Rock Socket)
TOTAL INCREASE: $6,075
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount °(/o
43 30" Cast-In-Drilled-Hole Concrete LF 5.00 $667.00 $3,335.00 11.36 11.36
Piling
TOTAL DECREASE: $3,335
Eliminated Items:
Item Total Total
No. Description Unit Quantity Unit Price Amount °�/0) °l/VI
76 Cable Railing LF 98.00 $40.00 $3,920.00 100.00 100.00
Since you did not incur any costs associated with these items, no payment will be made for these bid items.
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
DRY CREEK BRIDGE REPLACEMENT ON CHANGE ORDER NO. 2
BURROUGH VALLEY ROAD, BURROUGH VALLEY ROAD, SEPTEMBER 1, 2023
JUST EAST OF TOLLHOUSE ROAD PAGE 2 OF 3
FEDERAL PROJECT NUMBER: BRLS-5942(245)
CONTRACT NO. 22-05-C
This work did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL DECREASE: $3,920
TOTAL COST PART I: $1,180.00 DECREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: GRANT A TIME EXTENSION:
This time extension was requested by the contractor.
Grant a time extension of 19 -working days to the "First Order of Work" due to suspension of project to
assess environmental concerns relating to active bird nests and a sighted western pond turtle within the
vicinity of the project limits. The time extensions shall apply according to Section 8-1.07B of the Special
Provisions.
TOTAL COST PART II: $0.00 (NO COST)
TOTAL TIME EXTENSION PART II: 19 -WORKING DAYS
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
DRY CREEK BRIDGE REPLACEMENT ON CHANGE ORDER NO. 2
BURROUGH VALLEY ROAD, BURROUGH VALLEY ROAD, SEPTEMBER 1, 2023
JUST EAST OF TOLLHOUSE ROAD PAGE 3 OF 3
FEDERAL PROJECT NUMBER: BRLS-5942(245)
CONTRACT NO. 22-05-C
NET COST THIS CHANGE ORDER: A $1,180 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: 19 -WORKING DAYS
James Drews, Resident Engineer
APPROVAL RECOMMENDED:
AGEE CONSTRUCTION CORPORATION
Contractor Mandeep S. Sekhon, PE
Construction Engineer
By � �• -- APPROVED BY:
Digitally signed by Steve White
Title
Chief Estimator Steve White ate:2023.09.0711:53:51
Steven E. White, Director
Accepted Date:
Sep 5, 2023 Public Works and Planning
Date:
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business Office noted above, and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.