Loading...
HomeMy WebLinkAbout2001C CCO 08.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 8 BRIDGE NO. 42CO697 MAY 4, 2023 FEDERAL PROJECT NUMBER: BRLO-5942(238) PAGE 1 OF 2 CONTRACT NO. 20-01-C TO: AGEE CONSTRUCTION CORPORATION: Make the following changes to the plans and specifications or do work not included in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time. The date of completion for the Third Order of Work is April 28, 2023. REPAIR SLOPE EROSION AREA & REMOVE STORM DEBRIS FROM ROADWAY— EXTRA WORK This extra work was requested by the engineer. In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, remove and reinstall fiber rolls approximately every 15', backfill and compact the native soil in the erosion areas northwest of the new bridge, and finish by placing straw on any area disturbed by the repair efforts. Remove excess dirt and silt from the roadway deposited from recent storms. Perform the work according to the applicable sections of the Standard Specifications and Special Provisions. Payment for this work will be made as extra work at force account according to Section 9-1.03, "Payment Scope," of the Special Provisions. Total compensation for this work resulted in $2,679.65. This extra work did not impact the critical path for the project, therefore, granting additional contract time was not warranted. Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment _Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 8 BRIDGE NO. 42CO697 MAY 4, 2023 FEDERAL PROJECT NUMBER: BRLO-5942(238) PAGE 2 OF 2 CONTRACT NO. 20-01-C NET COST THIS CHANGE ORDER: A $2,679.65 INCREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS James Drews, Resident Engineer APPROVAL RECOMMENDED: AGEE CONSTRUCTION CORPORATIONV Contractor Mandeep S. Sekhon, PE Construction Engineer By 4�' APPROVED BY: Steve , w h ite DigitDateally signed by Steve White Title Chief Estimator GVG VV G 0700?023.05.1113:34:00 Steven E. White, Director May 4 2023 Public Works and Planning Accepted Date: � Date: Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if _Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment Board of Supervisors _Const.Management therefore the prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.